Specifications Trout Creek Main Office Roof Replacement.pdf
PDF 219 KB Posted
- Attached to
- Trout Creek Ranger Station roof replacement
- Solicitation number
- 1240LU24Q0045
- Issued by
-
Department of Agriculture Forest Service
About this file
This document appears to be the specifications for the Trout Creek Main Office Roof Replacement project. The work consists of removing the existing asphalt shingled roof, replacing damaged roof decking, and installing a new asphalt shingle roofing system. The work also includes removal and replacement of rain gutters, fascia, soffits, and permanent fall protection anchors.
The project is located at the Trout Creek Ranger Station in Trout Creek, MT and is owned by the USDA Forest Service, Kootenai National Forest. The estimated start date is August 1, 2024 and all work must be completed by September 30, 2025, with a preference that the work be done in the summer/fall of 2024. There will be no pre-bid site visit, but prospective bidders are encouraged to visit the site prior to submitting a bid. The contractor shall submit a safety plan, work schedule, subcontractor list, materials list, and manufacturer's warranty at various points in the project. The Forest Service will perform asbestos testing and any necessary remediation prior to the start of work.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Wage determinations mt60.pdf | ||
| Experience Questionnaire.pdf | ||
| 1240LU24Q0045 Trout Creek roof replacement.pdf | ||
| Drawings Trout Creek Roof Replacement.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION 011000 - SUMMARY
PART 1 - GENERAL
1.1 PROJECT INFORMATION
A. Project Identification: Trout Creek Main Office Roof Replacement.
1. Project Location:
a. Trout Creek Ranger Station
2693 MT HWY 200
Trout Creek, MT 59874
B. Owner: USDA Forest Service, Kootenai National Forest.
C. The work consists of removing the existing asphalt shingled roof and all underlayment materials, replacing damaged roof decking, and installing a complete asphalt shingle roofing system. The work also includes the removal of the existing rain gutters, fascia and soffits, replacing damaged or improperly installed sub fascia, installing new metal facia, installing new metal soffits, and installing new gutters and downs spouts. All work will be performed on the main office located at the Trout Creek Ranger Station.
D. Work by Owner:
1. The Forest Service will conduct testing of the existing roofing materials for the presence of asbestos prior to the commencement of work under this contract. A complete report will be furnished to the contractor.
E. Work Under Separate Contracts:
1. None.
F. Owner-Furnished Products: The following products will be furnished by Owner and shall be installed by Contractor as part of the Work:
1. None.
A. G. Submittals:
1. The contractor shall submit the following along with the price quote:
a. Safety Plan, including a Fall Protection Plan
2. The contractor shall submit the following at the prework meeting:
a. A proposed day by day work schedule.
b. A list of all subcontractors, and their intended use.
c. Materials list and color options for all components of the roofing system that require a color choice (Shingles, Fascia, and Gutters).
d. Materials selected for each layer of the roofing system.
e. Description of flashing materials.
f. List of sealants to be used on the project.
3. The contractor shall submit the following at end of the project, before the final payment:
a. Manufacturer’s Warranty as described in Section 07311, Part 1.1 – C.
H. Building Details and Work Items:
1. Remove existing gutters and downspouts. Gutters will not be reused on this project.
2. Remove all existing roofing materials down to the roof sheathing.
3. Remove existing fascia and trim boards.
4. Install new sub-fascia where water damage is present, or the existing materials have been improperly installed. It appears that some of the sub-fascia may have been installed too high, creating an area that allows water to sit at the drip edge. The existing sub-fascia is made of a timber-strand material (like oriented strand board - OSB), replacement can be the same or structural select DFL framing material.
5. Remove and Replace any damaged roof decking. Existing decking is made from 5/8” OSB, new boards should match existing. Notify the Contracting Officer prior to exposure of the roof deck for inspection and concurrence on what roof decking needs to be replaced.
6. Install metal fascia. Metal should be formed to completely cover all exposed surfaces of the sub-fascia. Provide a profile with stiffening beads to minimize oil canning of the fascia material.
7. Place ice and water shield as shown on the drawings. Use synthetic underlayment for the rest of the roof deck.
8. Ridge: ensure decking and underlayment allow for a vented ridge as indicated by the shingle manufacturer’s instructions.
9. Install asphalt roofing shingles according to the specs and manufacturer’s installation instructions. Use appropriate starter strips, flashings, sealants and vented ridge system to meet warranty requirements.
10. Furnish and install permanent fall protection anchor points at the ridge at locations shown on the drawings. Provide OSHA approved fall protection anchors designed to be permanently installed under the ridge of a shingled roof.
11. Furnish and Install new seamless rain gutters. Tie rain gutter down-spouts into existing drainpipes where available.
1.2 WORK RESTRICTIONS
A. Contractor's Use of Premises: During construction, Contractor will have limited use of building indicated. Contractor's use of premises is limited only by Owner's right to perform work or employ other contractors on portions of Project.
1. Owner will occupy premises during construction. Clean up work areas and return to usable condition at the end of each work period.
2. Driveways, Walkways, and Entrances: Keep driveways and entrances serving premises clear and available to Owner, Owner's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials.
B. On-Site Work Hours: Limit work in the existing building to normal business working hours of 8 a.m. to 5 p.m., Monday through Friday, unless otherwise indicated.
1. Weekend Hours: Upon approval from the Contracting Officer.
2. Early Morning Hours: Upon approval from the Contracting Officer.
C. Nonsmoking Buildings: Smoking is not permitted within the building or within 25 feet of entrances, operable windows, or outdoor-air intakes.
1.3 PROSECUTION AND PROGRESS
A. The estimated start work date is August 1, 2024.
B. There will not be a pre-bid tour for this project. Prospective bidders are still encouraged to visit the site prior to submitting a bid.
1. Check in at the front desk of the main office prior to viewing the project site.
2. Any questions from the site visit should be directed to the contracting officer.
C. Prior to start work a prework conference will be held.
D. All work under this contract must be completed by September 30, 2025.
1. It is preferred that the work be done in the summer/fall of 2024. If the time of award does not provide adequate time for the contractor to complete the work this year, work can be completed next year.
2. No work is allowed between October 1, 2024, and May 01, 2025 due to the increased chances of unfavorable weather.
1.4 CODES, STANDARDS, AND PERMITS
A. Comply with these specifications, project drawings, and all applicable local, State, and National laws, codes, standards, and regulations. Comply with all health and safety codes for personnel and public.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 011000
SECTION 016000 - PRODUCT REQUIREMENTS
1.1 SECTION REQUIREMENTS
A. The term "product" includes the terms "material," "equipment," "system," and terms of similar intent.
B. Comparable Product Requests: Submit request for consideration of each comparable product.
Identify product or fabrication or installation method to be replaced.
1. Show compliance with requirements for comparable product requests.
2. Contracting Officer will review the proposed product and notify Contractor of its acceptance or rejection.
C. Basis-of-Design Product Specification Submittal: Show compliance with requirements.
D. Compatibility of Options: If Contractor is given option of selecting between two or more products, select product compatible with products previously selected.
E. Deliver, store, and handle products using means and methods that will prevent damage, deterioration, and loss, including theft. Comply with manufacturer's written instructions.
1. Schedule delivery to minimize long-term storage at Project site and to prevent overcrowding of construction spaces.
2. Deliver products to Project site in manufacturer's original sealed container or packaging, complete with labels and instructions for handling, storing, unpacking, protecting, and installing.
3. Inspect products on delivery to ensure compliance with the Contract Documents and to ensure that products are undamaged and properly protected.
4. Store materials in a manner that will not endanger Project structure.
5. Store products that are subject to damage by the elements, under cover in a weathertight enclosure above ground, with ventilation adequate to prevent condensation.
F. Warranties specified in other Sections shall be in addition to, and run concurrent with, other warranties required by the Contract Documents. Manufacturer's disclaimers and limitations on product warranties do not relieve Contractor of obligations under requirements of the Contract Documents.
PART 2 - PRODUCTS
2.1 PRODUCT SELECTION PROCEDURES
A. Provide products that comply with the Contract Documents, are undamaged, and, unless otherwise indicated, are new at the time of installation.
1. Provide products complete with accessories, trim, finish, and other devices and components needed for a complete installation and the intended use and effect.
2. Descriptive, performance, and reference standard requirements in the Specifications establish salient characteristics of products.
B. Where the following headings are used to list products or manufacturers, the Contractor's options for product selection are as follows:
1. Products:
a. Where requirements include "one of the following," provide one of the products listed that complies with requirements.
b. Where requirements do not include "one of the following," provide one of the products listed that complies with requirements or a comparable product.
2. Manufacturers:
a. Where requirements include "one of the following," provide a product that complies with requirements by one of the listed manufacturers.
b. Where requirements do not include "one of the following," provide a product that complies with requirements by one of the listed manufacturers or another manufacturer.
2.2 COMPARABLE PRODUCTS
A. Contracting Officer will consider Contractor's request for comparable product when the following conditions are satisfied:
1. Evidence that the proposed product does not require revisions to the Contract Documents, that it is consistent with the Contract Documents and will produce the indicated results, and that it is compatible with other portions of the Work.
2. Detailed comparison of significant qualities of proposed product with those named in the Specifications.
3. List of similar installations for completed projects, if requested.
4. Samples, if requested.
PART 3 - EXECUTION (Not Used)
END OF SECTION 016000
SECTION 024119 - SELECTIVE DEMOLITION
PART 2 - GENERAL
2.1 SECTION REQUIREMENTS
A. Selective Demolition refers to removal of the exiting roofing materials and any other building components required to install the new roofing materials.
B. Items indicated to be removed and salvaged remain Owner's property. Carefully detach from existing construction, in a manner to prevent damage.
1. Existing rain gutters and down spouts. These gutters will NOT be re-used on this project.
C. Forest Service will occupy the buildings immediately adjacent to selective demolition area.
Coordinate operations with the Contracting Officer in order to ensure public and employee safety during demolition and construction activities.
D. It is not expected that hazardous materials will be encountered in the Work. If hazardous materials are encountered, do not disturb; immediately notify the Contracting Officer. Hazardous materials will be removed by the Forest Service under a separate contract.
PART 3 - PRODUCTS
3.1 PERFORMANCE REQUIREMENTS
A. Regulatory Requirements: Comply with EPA regulations and with hauling and disposal regulations of authorities having jurisdiction.
B. Standards: Comply with ANSI/ASSE A10.6 and NFPA 241.
PART 4 - EXECUTION
4.1 DEMOLITION
A. Maintain services/systems indicated to remain and protect them against damage during selective demolition operations. Before proceeding with demolition, provide temporary services/systems that bypass area of selective demolition and that maintain continuity of services/systems to other parts of the building.
B. Locate, identify, shut off, disconnect, and seal or cap off indicated utility services and mechanical/electrical systems serving areas to be selectively demolished.
C. Provide temporary barricades and other protection required to prevent injury to people and damage to adjacent buildings and facilities to remain.
D. Provide temporary weather protection to prevent water leakage and damage to structure and interior areas.
E. Neatly cut openings and holes plumb, square, and true to dimensions required. Use cutting methods least likely to damage construction to remain or adjoining construction.
F. Remove demolition waste materials from Project site and legally dispose of them in an EPA-approved landfill or take them to a recycling facility. Do not burn demolished materials.
G. Clean adjacent structures and improvements of dust, dirt, and debris caused by selective demolition operations. Return adjacent areas to condition existing before selective demolition operations began.
END OF SECTION 024119
SECTION 061600 - SHEATHING
PART 5 - GENERAL
5.1 SECTION REQUIREMENTS
A. Submittals: None
B. If any of the existing roof sheathing has water damage it will need to be replaced with full (4’x8’) sheets of OSB that matches the existing sheathing. The contractor must notify the CO 48 hours prior to exposing the roof deck so the Forest Service can arrange for inspection to determine what, if any, materials need to be replaced.
PART 6 - PRODUCTS
6.1 WOOD PRODUCTS, GENERAL
A. Use No. 1/Select Structural Douglas Fir / Larch boards.
6.2 ROOF SHEATHING
A. 5/8” OSB, Exposure 1 sheathing.
6.3 MISCELLANEOUS PRODUCTS
A. Fasteners: Size and type indicated.
1. For roof sheathing, provide fasteners with hot-dip zinc coating complying with
ASTM A 153/A 153M.
2. Power-Driven Fasteners: CABO NER-272.
PART 7 - EXECUTION
7.1 INSTALLATION
A. Securely attach to substrates, complying with the following:
1. CABO NER-272 for power-driven fasteners.
B. Fastening Methods:
1. Wall and Roof Sheathing:
a. Nail to wood framing members (trusses and rafters).
END OF SECTION 061600
SECTION 07311 - ASPHALT SHINGLES
1.1 SECTION REQUIREMENTS
A. Submittals: Manufacturers Product Data and Installation Instructions.
B. Identify each bundle of shingles with appropriate markings of UL or another testing and inspecting agency acceptable to authorities having jurisdiction.
1. Exterior Fire-Test Exposure: ASTM E 108 or UL 790, Class A.
2. Wind-Resistance-Test Characteristics: ASTM D 3161 or UL 997, passed.
C. Warranties: Provide standard manufacturer's written warranty, signed by manufacturer agreeing to promptly repair or replace asphalt shingles that fail in materials or workmanship within 30 years from date of Substantial Completion, prorated, with first 5 years non-prorated.
PART 2 - PRODUCTS
2.1 ASPHALT SHINGLES
A. Fiberglass Shingles: ASTM D 3462 and as follows:
1. Laminated-Strip Asphalt Shingles: Laminated, multi-ply overlay construction, mineral-granule surfaced, and self-sealing. Straight cut butt edge.
B. Available Products:
1. Owens Corning Corp; Duration Shingles
2. CertainTeed; Landmark TL
3. GAF; Timberline
4. IKO; Cambridge
5. TAMKO; Heritage
C. Color: Dark Green or Gray selected by the Contracting Officer from the manufacturers standard color options for the line of shingles provided by the contractor.
2.2 ACCESSORIES
A. Synthetic Roofing Underlayment, mechanically attached, coated woven synthetic roofing underlayment. Apply according to manufactures written instructions.
1. Products: Subject to compliance with requirements, provide the following or submit a comparable product for approval as outlines in Section 16000.
a. Interwrap - UDL30
B. Self-Adhering Sheet Underlayment, High Temperature: Butyl or SBS-modified asphalt; slip-resisting-polyethylene surfaced; with release-paper backing; cold applied.
1. Products: Subject to compliance with requirements, provide one of the following or submit a comparable product for approval as outlines in Section 16000.
a. Carlisle Coatings & Waterproofing Inc. - WIP 100
b. Interwrap - PSU30
C. Ridge Vent: Rigid UV-stabilized plastic ridge vent for use under ridge shingles.
D. Asphalt Roofing Cement: ASTM D 4586, Type II, asbestos free.
E. Roofing Nails: Aluminum, stainless-steel, or hot-dip galvanized steel shingle nails, minimum 0.120-inch-diameter, of sufficient length to penetrate 3/4 inch into solid wood decking.
F. Sheet Metal Flashing and Trim: Comply with requirements in Division 7 Section "Sheet Metal Flashing and Trim."
1. Fabricate sheet metal flashing and trim to comply with recommendations in SMACNA's "Architectural Sheet Metal Manual."
2. Drip Edge: Brake-formed sheet metal with at least a 2-inch (50-mm) roof deck flange and a 1-1/2-inch fascia flange with a 3/8-inch drip at lower edge.
3. Open-Valley Flashing: Fabricate with 1-inch-high inverted-V profile at center of valley and equal flange widths required to meet the overlap noted in the drawings.
PART 3 - EXECUTION
3.1 INSTALLATION
A. Comply with recommendations in ARMA's "Residential Asphalt Roofing Manual" and asphalt shingle recommendations in NRCA's "The NRCA Roofing and Waterproofing Manual."
B. Apply self-adhering sheet underlayment at eaves and rakes from edges of roof to at least 36 inches inside exterior wall line.
C. Apply self-adhering sheet underlayment at valleys extending 18 inches on each side.
D. Install valleys complying with ARMA and NRCA instructions. Construct sheet metal open valleys.
E. Install metal flashings and other sheet metal to comply with recommendations in ARMA's "Residential Asphalt Roofing Manual," and asphalt shingle recommendations in NRCA's "The NRCA Roofing and Waterproofing Manual."
http://www.specagent.com/Lookup?ulid=11435 http://www.specagent.com/Lookup?ulid=11435 http://www.specagent.com/Lookup?uid=123456999453
F. Install first and remaining courses of asphalt shingles stair-stepping diagonally across roof deck with manufacturer's recommended offset pattern at succeeding courses, maintaining uniform exposure.
END OF SECTION 07311
SECTION 07710 - MANUFACTURED ROOF SPECIALTIES
1.1 SUMMARY
A. This Section includes the following:
1. Fascia.
2. Soffit.
3. Seamless Gutters and downspouts.
4. Permanently mounted fall protection anchors.
1.2 SUBMITTALS
A. Product Data: For each product indicated.
B. Shop Drawings or Manufacture’s Product Brochures: Include plans, elevations, sections, details, and attachments to other Work.
PART 2 - PRODUCTS
2.1 FASCIA
A. General: Of metal and in shapes and sizes required to fully cover and protect sub-fascia. Use compatible attachment devices, sealants, and touch up paint.
B. Color: Dark Green - or other standard color from supplier’s color selection.
C. Formed-Aluminum Fascia: Minimum 0.032 inch thick, unless otherwise indicated.
2.2 SOFFIT
A. General: Provide both vented and non-vented interlocking aluminum soffit panels.
B. Color: White - or other standard color from supplier’s color selection.
C. Provide all necessary support channels and accessories to install a complete soffit system.
D. Follow the soffit manufacturer’s instructions for installation.
2.3 GUTTERS AND DOWNSPOUTS
A. General: Of metal and in shapes and sizes required to adequately drain water from the areas of the roof served by each section of gutter. Include hangers or other attachment devices; end plates;
and trim and other accessories indicated or required for complete installation.
B. Color: Dark Green - or other color from supplier’s standard color selection.
C. Formed-Aluminum Seamless Gutters and Downspouts: Minimum 0.032 inch thick, unless otherwise indicated.
D. Secure gutters and downspouts to fascia in a manner typical of a commercial installation. The climate in this area leads to heavy snow and ice accumulations which will cause additional stress to the gutter mounting system.
2.4 PERMANENTLY INSTALLED FALL PROTECTION ANCHORS
A. Provide OSHA approved anchor devices designed for permanent installation under the ridge cap of an asphalt shingled roof. Install at locations identified on the drawings.
2.5 ACCESSORIES
A. Exposed Fasteners: Stainless steel, nonmagnetic, of manufacturer's standard type and size for product and application indicated. Match finish of exposed heads with material being fastened.
B. Concealed Fasteners: Same metal as item fastened or other noncorrosive metal as recommended by manufacturer.
C. Asphalt Mastic: SSPC-Paint 12, solvent-type asphalt mastic, nominally free of sulfur and containing no asbestos fibers, compounded for 15-mil (0.4-mm) dry film thickness per coat.
D. Mastic Sealant: Polyisobutylene; nonhardening, nonskinning, nondrying, nonmigrating sealant.
E. Foam-Rubber Seal: Manufacturer's standard foam.
PART 3 - EXECUTION
3.1 INSTALLATION
A. Coordinate installation of products with installation of roof deck and other substrates, vapor retarders, roofing insulation, roofing membrane, flashing, and wall construction, as required to ensure that combined elements are waterproof and weathertight. Anchor products securely to structural substrates to withstand lateral and thermal stresses and inward and outward loading pressures.
B. Isolation: Where metal surfaces of units contact dissimilar metal or corrosive substrates, including wood, apply bituminous coating on concealed metal surfaces or provide other permanent separation as recommended in writing by manufacturer.
C. Expansion Provisions: Install running lengths to allow controlled expansion for movement of metal components in relation not only to one another but also to adjoining dissimilar materials, including flashing and roofing membrane materials, in a manner sufficient to prevent water leakage, deformation, or damage.
D. Immediately after installation, clean exposed metal surfaces according to manufacturer's written instructions. Touch up damaged metal coatings.
END OF SECTION 07710
| PART 1 - GENERAL |
| 1.1 PROJECT INFORMATION |
| A. Project Identification: Trout Creek Main Office Roof Replacement. |
| 1. Project Location: |
| a. Trout Creek Ranger Station |
| 2693 MT HWY 200 |
| Trout Creek, MT 59874 |
| B. Owner: USDA Forest Service, Kootenai National Forest. |
| C. The work consists of removing the existing asphalt shingled roof and all underlayment materials, replacing damaged roof decking, and installing a complete asphalt shingle roofing system. The work also includes the removal of the existing rain gutt... |
| D. Work by Owner: |
| E. Work Under Separate Contracts: |
| 1. None. |
| F. Owner-Furnished Products: The following products will be furnished by Owner and shall be installed by Contractor as part of the Work: |
| 1. None. |
| A. G. Submittals: |
| 1. The contractor shall submit the following along with the price quote: |
| a. Safety Plan, including a Fall Protection Plan |
| 2. The contractor shall submit the following at the prework meeting: |
| a. A proposed day by day work schedule. |
| b. A list of all subcontractors, and their intended use. |
| c. Materials list and color options for all components of the roofing system that require a color choice (Shingles, Fascia, and Gutters). |
| d. Materials selected for each layer of the roofing system. |
| e. Description of flashing materials. |
| f. List of sealants to be used on the project. |
| 3. The contractor shall submit the following at end of the project, before the final payment: |
| a. Manufacturer’s Warranty as described in Section 07311, Part 1.1 – C. |
| H. Building Details and Work Items: |
| 1. Remove existing gutters and downspouts. Gutters will not be reused on this project. |
| 2. Remove all existing roofing materials down to the roof sheathing. |
| 3. Remove existing fascia and trim boards. |
| 4. Install new sub-fascia where water damage is present, or the existing materials have been improperly installed. It appears that some of the sub-fascia may have been installed too high, creating an area that allows water to sit at the drip edge. Th... |
| 5. Remove and Replace any damaged roof decking. Existing decking is made from 5/8” OSB, new boards should match existing. Notify the Contracting Officer prior to exposure of the roof deck for inspection and concurrence on what roof decking needs to b... |
| 6. Install metal fascia. Metal should be formed to completely cover all exposed surfaces of the sub-fascia. Provide a profile with stiffening beads to minimize oil canning of the fascia material. |
| 7. Place ice and water shield as shown on the drawings. Use synthetic underlayment for the rest of the roof deck. |
| 8. Ridge: ensure decking and underlayment allow for a vented ridge as indicated by the shingle manufacturer’s instructions. |
| 9. Install asphalt roofing shingles according to the specs and manufacturer’s installation instructions. Use appropriate starter strips, flashings, sealants and vented ridge system to meet warranty requirements. |
| 10. Furnish and install permanent fall protection anchor points at the ridge at locations shown on the drawings. Provide OSHA approved fall protection anchors designed to be permanently installed under the ridge of a shingled roof. |
| 11. Furnish and Install new seamless rain gutters. Tie rain gutter down-spouts into existing drainpipes where available. |
| 1.2 WORK RESTRICTIONS |
| A. Contractor's Use of Premises: During construction, Contractor will have limited use of building indicated. Contractor's use of premises is limited only by Owner's right to perform work or employ other contractors on portions of Project. |
| 1. Owner will occupy premises during construction. Clean up work areas and return to usable condition at the end of each work period. |
| 2. Driveways, Walkways, and Entrances: Keep driveways and entrances serving premises clear and available to Owner, Owner's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials. |
| B. On-Site Work Hours: Limit work in the existing building to normal business working hours of 8 a.m. to 5 p.m., Monday through Friday, unless otherwise indicated. |
| 1. Weekend Hours: Upon approval from the Contracting Officer. |
| 2. Early Morning Hours: Upon approval from the Contracting Officer. |
C. Nonsmoking Buildings: Smoking is not permitted within the building or within 25 feet of entrances, operable windows, or outdoor-air intakes.
| 1.3 PROSECUTION AND PROGRESS |
| A. The estimated start work date is August 1, 2024. |
| B. There will not be a pre-bid tour for this project. Prospective bidders are still encouraged to visit the site prior to submitting a bid. |
| 1. Check in at the front desk of the main office prior to viewing the project site. |
| 2. Any questions from the site visit should be directed to the contracting officer. |
| C. Prior to start work a prework conference will be held. |
| D. All work under this contract must be completed by September 30, 2025. |
| 1. It is preferred that the work be done in the summer/fall of 2024. If the time of award does not provide adequate time for the contractor to complete the work this year, work can be completed next year. |
| 2. No work is allowed between October 1, 2024, and May 01, 2025 due to the increased chances of unfavorable weather. |
| 1.4 CODES, STANDARDS, AND PERMITS |
| A. Comply with these specifications, project drawings, and all applicable local, State, and National laws, codes, standards, and regulations. Comply with all health and safety codes for personnel and public. |
| PART 2 - PRODUCTS (Not Used) |
| PART 3 - EXECUTION (Not Used) |
| PART 1 - GENERAL |
| 1.1 SECTION REQUIREMENTS |
| A. The term "product" includes the terms "material," "equipment," "system," and terms of similar intent. |
| B. Comparable Product Requests: Submit request for consideration of each comparable product. Identify product or fabrication or installation method to be replaced. |
| 1. Show compliance with requirements for comparable product requests. |
| 2. Contracting Officer will review the proposed product and notify Contractor of its acceptance or rejection. |
| C. Basis-of-Design Product Specification Submittal: Show compliance with requirements. |
| D. Compatibility of Options: If Contractor is given option of selecting between two or more products, select product compatible with products previously selected. |
| E. Deliver, store, and handle products using means and methods that will prevent damage, deterioration, and loss, including theft. Comply with manufacturer's written instructions. |
| 1. Schedule delivery to minimize long-term storage at Project site and to prevent overcrowding of construction spaces. |
| 2. Deliver products to Project site in manufacturer's original sealed container or packaging, complete with labels and instructions for handling, storing, unpacking, protecting, and installing. |
| 3. Inspect products on delivery to ensure compliance with the Contract Documents and to ensure that products are undamaged and properly protected. |
| 4. Store materials in a manner that will not endanger Project structure. |
| 5. Store products that are subject to damage by the elements, under cover in a weathertight enclosure above ground, with ventilation adequate to prevent condensation. |
F. Warranties specified in other Sections shall be in addition to, and run concurrent with, other warranties required by the Contract Documents. Manufacturer's disclaimers and limitations on product warranties do not relieve Contractor of obligations ...
| PART 2 - PRODUCTS |
| 2.1 PRODUCT SELECTION PROCEDURES |
| A. Provide products that comply with the Contract Documents, are undamaged, and, unless otherwise indicated, are new at the time of installation. |
| 1. Provide products complete with accessories, trim, finish, and other devices and components needed for a complete installation and the intended use and effect. |
| 2. Descriptive, performance, and reference standard requirements in the Specifications establish salient characteristics of products. |
| B. Where the following headings are used to list products or manufacturers, the Contractor's options for product selection are as follows: |
| 1. Products: |
| a. Where requirements include "one of the following," provide one of the products listed that complies with requirements. |
| b. Where requirements do not include "one of the following," provide one of the products listed that complies with requirements or a comparable product. |
| 2. Manufacturers: |
| a. Where requirements include "one of the following," provide a product that complies with requirements by one of the listed manufacturers. |
| b. Where requirements do not include "one of the following," provide a product that complies with requirements by one of the listed manufacturers or another manufacturer. |
| 2.2 COMPARABLE PRODUCTS |
| A. Contracting Officer will consider Contractor's request for comparable product when the following conditions are satisfied: |
| 1. Evidence that the proposed product does not require revisions to the Contract Documents, that it is consistent with the Contract Documents and will produce the indicated results, and that it is compatible with other portions of the Work. |
| 2. Detailed comparison of significant qualities of proposed product with those named in the Specifications. |
| 3. List of similar installations for completed projects, if requested. |
| 4. Samples, if requested. |
| PART 3 - EXECUTION (Not Used) |
| PART 2 - GENERAL |
| 2.1 SECTION REQUIREMENTS |
| A. Selective Demolition refers to removal of the exiting roofing materials and any other building components required to install the new roofing materials. |
| B. Items indicated to be removed and salvaged remain Owner's property. Carefully detach from existing construction, in a manner to prevent damage. |
| 1. Existing rain gutters and down spouts. These gutters will NOT be re-used on this project. |
| C. Forest Service will occupy the buildings immediately adjacent to selective demolition area. Coordinate operations with the Contracting Officer in order to ensure public and employee safety during demolition and construction activities. |
| D. It is not expected that hazardous materials will be encountered in the Work. If hazardous materials are encountered, do not disturb; immediately notify the Contracting Officer. Hazardous materials will be removed by the Forest Service under a separ... |
| PART 3 - PRODUCTS |
| 3.1 PERFORMANCE REQUIREMENTS |
| A. Regulatory Requirements: Comply with EPA regulations and with hauling and disposal regulations of authorities having jurisdiction. |
| B. Standards: Comply with ANSI/ASSE A10.6 and NFPA 241. |
| PART 4 - EXECUTION |
| 4.1 DEMOLITION |
| A. Maintain services/systems indicated to remain and protect them against damage during selective demolition operations. Before proceeding with demolition, provide temporary services/systems that bypass area of selective demolition and that maintain c... |
| B. Locate, identify, shut off, disconnect, and seal or cap off indicated utility services and mechanical/electrical systems serving areas to be selectively demolished. |
| C. Provide temporary barricades and other protection required to prevent injury to people and damage to adjacent buildings and facilities to remain. |
| D. Provide temporary weather protection to prevent water leakage and damage to structure and interior areas. |
| E. Neatly cut openings and holes plumb, square, and true to dimensions required. Use cutting methods least likely to damage construction to remain or adjoining construction. |
| F. Remove demolition waste materials from Project site and legally dispose of them in an EPA-approved landfill or take them to a recycling facility. Do not burn demolished materials. |
| G. Clean adjacent structures and improvements of dust, dirt, and debris caused by selective demolition operations. Return adjacent areas to condition existing before selective demolition operations began. |
| PART 5 - GENERAL |
| 5.1 SECTION REQUIREMENTS |
| A. Submittals: None |
| B. If any of the existing roof sheathing has water damage it will need to be replaced with full (4’x8’) sheets of OSB that matches the existing sheathing. The contractor must notify the CO 48 hours prior to exposing the roof deck so the Forest Service... |
| PART 6 - PRODUCTS |
| 6.1 WOOD PRODUCTS, GENERAL |
| A. Use No. 1/Select Structural Douglas Fir / Larch boards. |
| 6.2 ROOF SHEATHING |
| A. 5/8” OSB, Exposure 1 sheathing. |
| 6.3 MISCELLANEOUS PRODUCTS |
| A. Fasteners: Size and type indicated. |
| 1. For roof sheathing, provide fasteners with hot-dip zinc coating complying with ASTM A 153/A 153M. |
| 2. Power-Driven Fasteners: CABO NER-272. |
| PART 7 - EXECUTION |
| 7.1 INSTALLATION |
| A. Securely attach to substrates, complying with the following: |
| 1. CABO NER-272 for power-driven fasteners. |
| B. Fastening Methods: |
| 1. Wall and Roof Sheathing: |
| a. Nail to wood framing members (trusses and rafters). |
| PART 1 - GENERAL |
| 1.1 SECTION REQUIREMENTS |
| A. Submittals: Manufacturers Product Data and Installation Instructions. |
| B. Identify each bundle of shingles with appropriate markings of UL or another testing and inspecting agency acceptable to authorities having jurisdiction. |
| 1. Exterior Fire-Test Exposure: ASTM E 108 or UL 790, Class A. |
| 2. Wind-Resistance-Test Characteristics: ASTM D 3161 or UL 997, passed. |
C. Warranties: Provide standard manufacturer's written warranty, signed by manufacturer agreeing to promptly repair or replace asphalt shingles that fail in materials or workmanship within 30 years from date of Substantial Completion, prorated, with ...
| PART 2 - PRODUCTS |
| 2.1 ASPHALT SHINGLES |
| A. Fiberglass Shingles: ASTM D 3462 and as follows: |
| 1. Laminated-Strip Asphalt Shingles: Laminated, multi-ply overlay construction, mineral-granule surfaced, and self-sealing. Straight cut butt edge. |
| B. Available Products: |
| 1. Owens Corning Corp; Duration Shingles |
| 2. CertainTeed; Landmark TL |
| 3. GAF; Timberline |
| 4. IKO; Cambridge |
| 5. TAMKO; Heritage |
C. Color: Dark Green or Gray selected by the Contracting Officer from the manufacturers standard color options for the line of shingles provided by the contractor.
| 2.2 ACCESSORIES |
| A. Synthetic Roofing Underlayment, mechanically attached, coated woven synthetic roofing underlayment. Apply according to manufactures written instructions. |
| 1. Products: Subject to compliance with requirements, provide the following or submit a comparable product for approval as outlines in Section 16000. |
| a. Interwrap - UDL30 |
| B. Self-Adhering Sheet Underlayment, High Temperature: Butyl or SBS-modified asphalt; slip-resisting-polyethylene surfaced; with release-paper backing; cold applied. |
| 1. Products: Subject to compliance with requirements, provide one of the following or submit a comparable product for approval as outlines in Section 16000. |
| a. Carlisle Coatings & Waterproofing Inc. - WIP 100 |
| b. Interwrap - PSU30 |
| C. Ridge Vent: Rigid UV-stabilized plastic ridge vent for use under ridge shingles. |
| D. Asphalt Roofing Cement: ASTM D 4586, Type II, asbestos free. |
| E. Roofing Nails: Aluminum, stainless-steel, or hot-dip galvanized steel shingle nails, minimum 0.120-inch-diameter, of sufficient length to penetrate 3/4 inch into solid wood decking. |
| F. Sheet Metal Flashing and Trim: Comply with requirements in Division 7 Section "Sheet Metal Flashing and Trim." |
| 1. Fabricate sheet metal flashing and trim to comply with recommendations in SMACNA's "Architectural Sheet Metal Manual." |
| 2. Drip Edge: Brake-formed sheet metal with at least a 2-inch (50-mm) roof deck flange and a 1-1/2-inch fascia flange with a 3/8-inch drip at lower edge. |
| 3. Open-Valley Flashing: Fabricate with 1-inch-high inverted-V profile at center of valley and equal flange widths required to meet the overlap noted in the drawings. |
| PART 3 - EXECUTION |
| 3.1 INSTALLATION |
| A. Comply with recommendations in ARMA's "Residential Asphalt Roofing Manual" and asphalt shingle recommendations in NRCA's "The NRCA Roofing and Waterproofing Manual." |
| B. Apply self-adhering sheet underlayment at eaves and rakes from edges of roof to at least 36 inches inside exterior wall line. |
| C. Apply self-adhering sheet underlayment at valleys extending 18 inches on each side. |
| D. Install valleys complying with ARMA and NRCA instructions. Construct sheet metal open valleys. |
| E. Install metal flashings and other sheet metal to comply with recommendations in ARMA's "Residential Asphalt Roofing Manual," and asphalt shingle recommendations in NRCA's "The NRCA Roofing and Waterproofing Manual." |
| F. Install first and remaining courses of asphalt shingles stair-stepping diagonally across roof deck with manufacturer's recommended offset pattern at succeeding courses, maintaining uniform exposure. |
| PART 1 - GENERAL |
| 1.1 SUMMARY |
| A. This Section includes the following: |
| 1. Fascia. |
| 2. Soffit. |
| 3. Seamless Gutters and downspouts. |
| 4. Permanently mounted fall protection anchors. |
| 1.2 SUBMITTALS |
| A. Product Data: For each product indicated. |
| B. Shop Drawings or Manufacture’s Product Brochures: Include plans, elevations, sections, details, and attachments to other Work. |
| PART 2 - PRODUCTS |
| 2.1 FASCIA |
| A. General: Of metal and in shapes and sizes required to fully cover and protect sub-fascia. Use compatible attachment devices, sealants, and touch up paint. |
| B. Color: Dark Green - or other standard color from supplier’s color selection. |
| C. Formed-Aluminum Fascia: Minimum 0.032 inch thick, unless otherwise indicated. |
| 2.2 SOFFIT |
| A. General: Provide both vented and non-vented interlocking aluminum soffit panels. |
| B. Color: White - or other standard color from supplier’s color selection. |
| C. Provide all necessary support channels and accessories to install a complete soffit system. |
| D. Follow the soffit manufacturer’s instructions for installation. |
| 2.3 GUTTERS AND DOWNSPOUTS |
| A. General: Of metal and in shapes and sizes required to adequately drain water from the areas of the roof served by each section of gutter. Include hangers or other attachment devices; end plates; and trim and other accessories indicated or require... |
| B. Color: Dark Green - or other color from supplier’s standard color selection. |
| C. Formed-Aluminum Seamless Gutters and Downspouts: Minimum 0.032 inch thick, unless otherwise indicated. |
| D. Secure gutters and downspouts to fascia in a manner typical of a commercial installation. The climate in this area leads to heavy snow and ice accumulations which will cause additional stress to the gutter mounting system. |
| 2.4 PERMANENTLY INSTALLED FALL PROTECTION ANCHORS |
| A. Provide OSHA approved anchor devices designed for permanent installation under the ridge cap of an asphalt shingled roof. Install at locations identified on the drawings. |
| 2.5 ACCESSORIES |
| A. Exposed Fasteners: Stainless steel, nonmagnetic, of manufacturer's standard type and size for product and application indicated. Match finish of exposed heads with material being fastened. |
| B. Concealed Fasteners: Same metal as item fastened or other noncorrosive metal as recommended by manufacturer. |
| C. Asphalt Mastic: SSPC-Paint 12, solvent-type asphalt mastic, nominally free of sulfur and containing no asbestos fibers, compounded for 15-mil (0.4-mm) dry film thickness per coat. |
| D. Mastic Sealant: Polyisobutylene; nonhardening, nonskinning, nondrying, nonmigrating sealant. |
| E. Foam-Rubber Seal: Manufacturer's standard foam. |
| PART 3 - EXECUTION |
| 3.1 INSTALLATION |
| A. Coordinate installation of products with installation of roof deck and other substrates, vapor retarders, roofing insulation, roofing membrane, flashing, and wall construction, as required to ensure that combined elements are waterproof and weather... |
| B. Isolation: Where metal surfaces of units contact dissimilar metal or corrosive substrates, including wood, apply bituminous coating on concealed metal surfaces or provide other permanent separation as recommended in writing by manufacturer. |
| C. Expansion Provisions: Install running lengths to allow controlled expansion for movement of metal components in relation not only to one another but also to adjoining dissimilar materials, including flashing and roofing membrane materials, in a ma... |
| D. Immediately after installation, clean exposed metal surfaces according to manufacturer's written instructions. Touch up damaged metal coatings. |