This document is a set of technical specifications for a federal contract opportunity related to the West Boulder Cabin Foundation Repair project. The key details are:
The project involves replacing the foundation of the West Boulder Cabin and repairing the associated stonework. The work must be performed by an installer with a minimum of 5 years' experience in evaluating, installing, and repointing historic masonry, with specific knowledge of working with Natural Hydraulic Lime (NHL) mortar. The installer must demonstrate precision and accuracy to maintain the authenticity and integrity of the historic masonry and foundation. The required products include natural building stone, NHL 3.5 and NHL 5 mortar, and natural sand. The document provides detailed requirements for stone removal, replacement, and repair procedures. General specifications cover site cleanliness, disposal, utility coordination, and fire control measures. Payment will be based on the contract unit prices listed, with no separate measurement or payment for the work in this section.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 1240LU24Q0040 RFQ GAOA 1BF West Boulder Cabin Foundation Repair.pdf | ||
| 1240LUQ0040 Attachment A - Statement of Work (SOW) 1BF West Bouldner Cabin Foundation Repair.pdf | ||
| 1240LU24Q0040 Attachment D - Davis-Bacon Act WD MT2024007.pdf | ||
| 1240LU24Q0040 Attachment C - Maps Plans.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION 01000
MOBILIZATION
PART I: GENERAL
1.1 SUMMARY
A. Section Includes: Preparatory work and operations, including those necessary to the movement of personnel, equipment, supplies and incidentals to the project site;
and for other work and operations which must be performed or costs incurred prior to beginning work on the various items on the project site. This specification does not include moves between project sites.
PART II: PRODUCTS
(There are no applicable requirements.)
PART III: EXECUTION
(There are no applicable requirements.)
PART IV: MEASUREMENT AND PAYMENT
4.1 METHOD OF MEASUREMENT:
A. Units: Progress payments will be made as follows:
1. When 5% of the original Contract amount is earned from other bid items, 50% of the amount bid for mobilization or 5% of the original Contract amount, whichever is lesser, will be paid.
2. When 10% of the original Contract amount is earned from other bid items, 100% of the amount bid for mobilization or 10% of the original Contract amount, whichever is lesser, will be paid.
3. Upon completion of work for the project, payment of the amount bid for mobilization in excess of 10% of the original Contract amount will be paid.
4. The total sum of all payments shall not exceed the original Contract amount bid for mobilization, regardless of the fact that the Contractor may have shut down the work on the project or moved equipment away from the project and then back again.
SPECIFICATIONS
4.2 BASIS OF PAYMENT:
Payment: No direct payment for moves between project sites will be made. The Contractor shall include consideration for moves between project sites in the bid price for other items of the Contract. Prices and payment will be full compensation for the work described in this section. Payment will be made under:
Pay Item Pay Unit
(01000) Mobilization. . . . . . . . . . . . . . . . . Lump Sum
END OF SECTION
SECTION 01025
MEASUREMENT AND PAYMENT
PART I - GENERAL
1.1 Measurement and Payment - Measurement and payment for contract work will be made only for and under those pay items included in the SCHEDULE OF ITEMS. All other work and materials will be considered as included in the payment for items shown.
When more than one class, size, or thickness is specified in the SCHEDULE OF ITEMS for any pay item, suffixes will be added to the item number to differentiate between items to be bid.
1.2 Determination of Quantities - The following methods of measurement are used to determine contract quantities for payment.
For individual construction items, longitudinal and lateral measurements for area computations will be made horizontally or corrected to horizontal measurement unless otherwise specified. Measurements for seeding, mulching, geotextiles, netting, erosion control blankets, and sodding will be along slope lines.
Structures will be measured according to neat lines SHOWN ON THE DRAWINGS or as altered by the COR in writing to fit field conditions.
For standard manufactured items, such as fence, wire, plates, rolled shapes, pipe conduits, etc., identified by gauge, weight, section dimensions, etc., such identification shall be considered the nominal weights or dimensions. Unless controlled by tolerances in cited specifications, manufacturer's tolerances will be accepted.
1.3 Units of Measurement - Payment will be by units defined and determined according to U.S. Standard measure as follows:
A. Acre – Make longitudinal and transverse measurements for area computations horizontally.
B. Cubic Yard - A measurement computed by one of the following methods:
1. Excavation, Embankment, or Borrow - The measurement computed by the average end area method from measurements made longitudinally along a centerline or reference line.
2. Material in Place or Stockpile - The measurement computed with dimensions of the in-place material.
3. Material in the Delivery Vehicle - The measurement computed using measurements of material in the hauling vehicles at the point of delivery.
Vehicles shall be loaded to at least their water level capacity. Leveling of the loads may be required when vehicles arrive at the delivery point.
C. Cubic Yard Mile - A combination of linear and volumetric measurement meaning the movement of a cubic yard of material 1 mile.
D. Each - One complete unit, which may consist of one or more parts.
E. Gallon – The quantity may be measured by any of the following methods:
1. Measured volume container.
2. Metered volume. Use an approved metering system
3. Commercially packaged volumes.
F. Hour – Measurement will be for the actual number of hours ordered and performed by the Contractor.
G. Linear Foot – Measure from end to end, parallel to the base or foundation being measured, or horizontal.
H. MFBM - One thousand board feet measure based on nominal widths, thickness, and extreme usable length of each piece of lumber or timber actually incorporated in the job.
I. Mile – Measure horizontal along the centerline of each roadway, approach road, or ramp.
J. Pound – If sacked or packaged material is furnished, the net weight as packed by the manufacturer may be used.
K. Square Foot - Measure on a plane parallel to the surface being measured or horizontal.
L. Square Yard – Measure on a plane parallel to the surface being measured or horizontal.
M. Station - One hundred linear feet measured horizontally.
N. Station Yard - A combination of linear and volumetric measurement meaning the movement of a cubic yard of material one station.
O. Thousand Gallons Mile - A combination of linear and volumetric measurement meaning the movement of 1,000 gallons of material 1 mile.
P. Ton - Short ton consisting of 2,000 pounds.
Q. Ton Mile - A combination of linear and weight measurement meaning the movement of 1 ton of material 1 mile.
1.4 Methods of Measurement - One of the following methods of measurement for determining final payment is DESIGNATED on the SCHEDULE OF ITEMS for each pay item:
A. Contract Quantities (CQ) AND Design Quantities (DQ) - These quantities denote the final number of units to be paid for under the terms of the contract. They are based upon the original design data available prior to advertising the project.
Original design data include the preliminary survey information, design assumptions, calculations, drawings, and the presentation in the contract. Changes in the number of units SHOWN in the SCHEDULE OF ITEMS may be authorized under any of the following conditions:
1. As a result of changes in the work authorized by the Contracting Officer.
2. As a result of the Contracting Officer determining that errors exist in the original design data used to determine designed quantities that cause a pay item to change by more than 15 percent.
3. As a result of the Contractor submitting to the Contracting Officer a written request showing evidence of errors in the original design data used to determine design quantities that cause a pay item total to change by more than 15%. The evidence must be verifiable and consist of calculations, drawings, or other data that show how the designed quantity is believed to be in error.
B. Staked Quantities (SQ) - These quantities are determined from staked measurements prior to construction.
C. Actual Quantities (AQ) - These quantities are determined from measurements of completed work.
D. Vehicle Quantities (VQ) - These quantities are measured or weighed in hauling vehicles.
E. Lump Sum Quantities (LSQ) - These quantities denote one complete unit of work as required by or described in the contract, including necessary materials, equipment, and labor to complete the job. They will not be measured.
PART II - PRODUCTS (Not Applicable)
PART III - EXECUTION (Not Applicable)
SECTION 01400
QUALITY CONTROL AND QUANTITY MEASUREMENT
PART I - GENERAL
1.1 Scope - This work shall consist of providing quality control in conformance with the
Inspection of Construction provisions of this contract to ensure compliance with the drawings, specifications, and provisions of the contract, and measuring the quantities of completed work in conformance with the provisions of the applicable specifications. The Contractor shall provide all personnel, equipment, tests, and reports necessary to meet the requirements of this specification.
1.2 Measurement and Payment - No separate payment will be made for the work included under this section. Payment for this work is considered incidental to other items of work.
PART II - PRODUCTS (Not Applicable)
PART III – EXECUTION (Not Applicable)
SECTION 01 33 00
SUBMITTAL PROCEDURES
PART 1 – GENERAL
1.01 PROCEDURES FOR SUBMITTALS
A. Reviewing, Certifying, Approving Authority: Contractor shall be responsible for reviewing and certifying that submittals are in compliance with contract requirements.
B. Scheduling: Allow review period, beginning with receipt by approving authority that includes at least 10 working days for submittals for contracting officer approval. Period of review for submittals with contracting officer approval begins when Government receives submittal from contractor. Period of review for each resubmittal is the same as for initial submittal.
C. Variations: Variations from contract requirements require Government approval pursuant to contract Clause entitled “FAR 52.236-21, Specifications and Drawings for Construction” and will be considered where advantages to government.
D. Submittal Schedule:
SECTION DESCRIPTION SUBMITTED APPROVED
Section C Safety Plan
Excavation Plan
Foundation Installation Plan
Mortar & Mix Design
Work Schedule
END OF SECTION 01 33 00
SECTION 04902 – FOUNDATION REPLACEMENT
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes the following:
1. Replacing foundation.
2. Repairing stonework, including replacing damaged units.
1.2 SUBMITTALS
A. Product Data: For each type of product indicated. Include recommendations for application and use.
B. Samples: For each exposed material required for replacing or repairing existing materials.
C. Qualification Data: For restoration specialists.
1.3 QUALITY ASSURANCE
A. Installer Qualifications.
1. Installer shall have minimum 5 years’ experience of evaluating, installing, and repointing historic masonry, along with the knowledge, techniques, and methodology required to reproduce masonry foundations from the 1920s. This includes demonstrable knowledge of mixing and installing Natural Hydrated Lime mortar, stone wall building techniques, matching stone sources, experience sourcing, storing, mixing, applying NHL mortar types (3,5 and 5) and knowing when to use each.
2. Installer shall work with a high degree of precision and accuracy to maintain the authenticity and integrity of historic masonry, foundations, and structures.
3. Contractor shall have demonstrated expertise in performing masonry work meeting the Secretary of the Interior's Standards for Historic Preservation.
1.4 MEASUREMENT AND PAYMENT
A. There will be no separate measurement or payment for work in this section. Payment will be included at the contract unit price as shown on the Schedule of Items for the building.
PART 2 - PRODUCTS
2.1 MANUFACTURERS
A. In other Part 2 articles where titles below introduce lists, the following requirements apply for product selection:
1. Available Products: Subject to compliance with requirements, products that may be incorporated into the Work include, but are not limited to, the products specified.
2. Products: Subject to compliance with requirements, provide one of the products specified.
3. Available Manufacturers: Subject to compliance with requirements, manufacturers offering products that may be incorporated into the Work include, but are not limited to, the manufacturers specified.
4. Manufacturers: Subject to compliance with requirements, provide products by the manufacturers specified.
a. Saint-Astier®
b. Or approved equal
2.2 STONE MATERIALS
A. Stone: Provide natural building stone of variety, color, finish, size, and shape to match existing stone.
1. For existing stone that exhibits a range of colors, finishes, sizes, or shapes, provide stone that matches that range.
2.3 MORTAR MATERIALS
A. Hydrated Lime: Pure and Natural Hydraulic Lime, containing no additives. Conforms to European Norms (EN) 459.
1. NHL 3.5
2. NHL 5
B. Mortar Sand: ASTM C 144, unless otherwise indicated.
1. Color: Provide natural sand; of color necessary to produce required mortar color.
2. Match size, texture, and gradation of existing mortar sand as closely as possible.
Blend several sands, if necessary, to achieve suitable match.
C. Water: Potable. (Available on site.)
2.4 MIXES
A. Mortar Mixes: Measure cementitious materials and sand in a dry condition by volume or equivalent weight. Mix materials in a clean, mechanical batch mixer.
B. Do not use admixtures of any kind in mortar, unless otherwise indicated.
PART 3 - EXECUTION
3.1 PROTECTION
A. Protect persons, motor vehicles, surrounding surfaces of building being restored, building site, plants, and surrounding buildings from harm resulting from stone restoration work.
3.2 STONE REMOVAL, REPLACEMENT, AND REPAIR
A. Stone Removal: Carefully remove stone that has deteriorated, shifted, or is damaged beyond repair.
B. Support and protect remaining stonework that surrounds removal area. Maintain flashing, reinforcement, lintels, and adjoining construction in an undamaged condition.
C. Remove in an undamaged condition as many whole stone units as possible.
1. Remove mortar, loose particles, and soil from stone by cleaning with hand chisels, brushes, and water.
2. Remove sealants by cutting close to stone with utility knife and cleaning with solvents.
D. Clean stone surrounding removal areas by removing mortar, dust, and loose particles.
E. Replace removed stone with other removed stone, where possible, or with new stone matching existing stone, including size. Butter vertical joints for full width before setting and set units in full bed of mortar, unless otherwise indicated.
1. Tool mortar joints to match joints of original existing stonework.
F. Cold-Water Soak: Apply cold water by prolonged spraying until surface encrustation has softened sufficiently to permit its removal by water wash.
1. Remove soil and softened surface encrustation from stone with cold water applied by low-pressure spray.
END OF SECTION 049020
SECTION 33 36 50
EXCAVATION
PART 1 – GENERAL
1.01SUMMARY
A. Work includes the excavation, backfill, and any site work required for foundation installation.
1.02SUBMITTALS
A. Submit type and size of equipment to be used for the excavation and backfill.
PART 2 – PRODUCTS
2.01EQUIPMENT
A. General: Contractor shall supply equipment required to excavate material under the cabin necessary for removal of old foundation and installation of new foundation. Equipment shall be capable of digging a 3-foot-deep hole around the cabin.
PART 3 – EXECUTION
A. General: Excavate hole to dimensions required to install new foundation.
B. Backfill: Backfill around foundation.
3.01INSTALLATION
A. Contractor is responsible for conducting a utility locate prior to excavation.
B. Backfill around new foundation as described in Part 3. Backfill to 6” below top of foundation, sloping material away from the foundation at 5% slope for 8’ away from the foundation.
END OF SECTION 33 36 50
C-3 GENERAL SPECIFICATIONS
a) Existing Facilities. In addition to the requirements of the Use of Premises Clause, AGAR 452.236-70, all existing facilities structures damaged by the Contractor shall be replaced or repaired by the Contractor at no additional cost to the Government. This includes any facilities inside or outside the project limits, including along any access routes.
Do not trim or damage vegetation except with specific Contracting Officers (CO) approval.
b) Pollution and Erosion Control. During all operations under this contract, the
Contractor shall exercise reasonable measures to prevent or minimize soil erosion and pollution of water and other resources. All refuse, including garbage, rubbish, and solid or liquid wastes, from the Contractor's operations, including camps, parking areas, and equipment maintenance areas shall be stored, collected, and disposed of in a sanitary and nuisance-free manner. Refuse shall be disposed of in State-approved landfills unless otherwise approved by the Contracting Officer (CO).
c) Coordination with District Operations. The work will take place in areas critical to daily ranger district operations. The Contractor shall maintain regular contact and coordination with the Contracting Officer / COR to assure that district operations are not hindered by the work.
d) Storage and Stockpiling. The Contractor shall confine storage of equipment, materials, and vehicles to within the limits delineated by the Contracting Officer. The Contractor shall be solely responsible for the loss of or damage to materials stored on Forest Service lands or elsewhere.
e) Coordination with Other Contractors. The Contractor shall maintain regular contact and coordination with all other contractors working on the district compounds to assure that the operations of other contractors are not hindered by the work.
f) Worksite Cleanliness and Final Cleanup. Maintain the project work areas in a clean and orderly condition throughout the progress of work under this contract. All refuse, including garbage, rubbish, and solid or liquid wastes from the Contractor's operations shall be stored and collected in a sanitary manner and disposed of off Government property in a legal manner. Maintain strict control of hazardous materials to prevent contamination of the site.
g) Equipment Specifications. Equipment and tools shall be in good mechanical and operating condition, fully capable of performing all phases of the specified work.
h) Weather Conditions. Work will be suspended if, in the opinion of the Contracting Officer, weather conditions preclude effective protection of resources, site rehabilitation, or otherwise impact project end results in a significant, negative manner.
i) Sanitary Facilities – Sanitary facilities are not available on site.
j) Notification. Contractor shall notify the C.O. at least two weeks prior to entering a work site.
C-4 HAULING AND DISPOSAL OF MATERIALS
a) All loads shall be completely covered during hauling.
b) All materials removed from the site shall be disposed of in a legal manner off National
Forest System lands. All fees associated with material disposal shall be paid by the Contractor.
C-5 CLEANUP AND DISPOSAL
The Contractor shall at all times keep the area in an orderly condition. Upon completing the work, the Contractor shall remove from the site and premises any rubbish, tools, equipment, and materials that are not the property of the Forest Service. Upon completing the work, the Contractor shall leave the work areas in a clean, neat, and orderly condition satisfactory to the Contracting Officer.
C-6 EXISTING UTILITIES
The Contractor is responsible for location of all utilities prior to beginning work. Damaged utilities shall be repaired at the Contractor’s expense.
C-7 - FOOD AND GARBAGE STORAGE
All food, beverages, and scented or flavored toiletries must be stored unavailable to bears at night and when unattended during the day. Attractants include but are not limited to TRASH, canned food, pop, beer, garbage, grease, processed livestock or pet food, toothpaste, and chap stick. All attractants shall be hung at least 10-feet off the ground and 4-feet from any vertical support or stored inside a bear resistant container or vehicle. Cars, pick-up cabs, enclosed horse trailers, hard sided campers or camper shells are all considered bear resistant. Food should be stored out of sight in vehicles. Coolers, pop-up campers, backpacks, and tents are not considered bear resistant.
C-8 – FIRE CONTROL (FS.236.1)
(a) Contractor's Responsibility for Contractor-Caused Fires – The Contractor, whether or not directed by the Forest Service, shall immediately extinguish, without expense to the Government, all fires on or in the vicinity of the project which are caused by Contractor's employees, whether set directly or indirectly as a result of Contractor operations. The Contractor may be held liable for all damages and costs of additional labor, subsistence, equipment, supplies, and transportation resulting from fires set or caused by the Contractor's employees or resulting from contract operations.
(b) Other Fires – For the purpose of fighting forest fires on or in the vicinity of the project, which are not caused by the Contractor or his employees, the Contractor when requested by the Contracting Officer shall place his employees and equipment temporarily at the disposal of the Forest Service. Payment for such services will be made by the Government at not less than the current rate for fire-fighting services established by the Forest Service in the area concerned.
Any employees and equipment furnished will be relieved from fire fighting as soon as the Forest Service finds that it is practicable to employ other labor and equipment adequate for the protection of the area.
An equitable adjustment in contract time may be made for this period.
(c) Fire Plan – At all times during closed fire season period, as specified by State law, the
Contractor shall comply with each of the following provisions to the extent applicable to his operation under the contract.
1. Fire Tools – The Contractor will provide for each employee in the contract area at least one approved hand tool of a type appropriate in the contract area, such as shovel, pulaski, or ax. Tools required and furnished under (2) and (4) below, shall count toward fulfillment of the above requirement. Where additional tools, beyond those required under (2) and (4) below, are to be provided, the Contractor shall seal such tools in one or more boxes painted red and marked "Tools for Fire Only." All tools required herein shall be kept sharp and in good serviceable condition and maintained at locations to be designated by the Forest Service.
2. Fire Extinguishers and Tools on Mobile or Stationary Equipment – Each unit of powered equipment used in connection with this contract, including automobiles, trucks, tractors, etc., shall be equipped with serviceable tools and fire extinguishers as follows:
One - fire extinguisher, dry chemical type of not less than 2-1/2 pound capacity with 4 BC or higher rating.
One - shovel, round point #0 lady or equal.
One - ax, 2 pounds or over, 26-inch minimum length, or one pulaski.
One - water container (at least 1-gallon capacity), not required with stationary equipment.
3. Blasting – Fuse or prima cord shall not be used unless authorized in writing by the CO with special precautions stated.
4. Smoking – Smoking shall not be permitted within the contract area except on surfaced or dirt roads, at landings, within closed vehicles, in camps, or at other posted places, and shall never be allowed while working or traveling on foot.
5. Storage of Petroleum and Other Highly Flammable Products – Gasoline, oil, grease, or other highly flammable material will be stored either in a separate building used exclusively for such storage, or at a site where all combustible debris and vegetation is cleared away within a radius of 25 feet. Fire extinguishers and/or sand barrels may be required at such locations specified by the Forest Service when unusually hazardous conditions exist.
6. Precautions for Stoves – Stovepipes on all temporary buildings, trailers, and tents using wood burning stoves, will be equipped with roof jacks and serviceable spark arresters of mesh with openings no larger than 5/8 inch.
All stovepipes, inside and out, will not be closer than 2 feet from any wood or other flammable material or 1 foot if the combustible material is protected by a metal or asbestos shield.
7. Welding – Welding or use of cutting torches will be permitted only in areas that have been cleared or are free of all material capable of carrying fire. Flammable debris and vegetation must be removed from within a minimum of 10 feet radius of all welding and cutting torch operations. A shovel and a 5-gallon standard backpack water container (filled), with hand pump attached, shall be immediately available for use in the event of a fire start.
8. Fire Plan – Prior to initiating work on the contract area, during the closed fire season period, a fire prevention and suppression plan will usually be prepared. The Contractor and the Forest Service will jointly prepare this plan. Such plan shall include a detailed list of men and equipment at the Contractor's disposal for implementing the plan. The fire plan shall also specify additional measures and/or special requirements, such as Hoot Owl restrictions, necessary during periods of critical fire weather conditions.
When Hoot Owl restrictions are invoked, the Forest Service may curtail or shut down all or portions of a Contractor's operations. The following requirements may be imposed:
a) All high fire risk operations could be terminated at 1300 local time.
b) All burning could be stopped, including debris burning fires.
c) Patrolman may be required for a period of 2 hours after high fire risk operations and 1 hour after end of work shift. The Contractor shall provide the patrolman unless the contract is for equipment rental, in which case the Government will provide the patrolman.
C-9 MEASUREMENT AND PAYMENT
The method of measurement will be as designated in the SCHEDULE OF ITEMS. The accepted quantity will be paid for at the contract unit price for the Pay Item shown in the SCHEDULE OF ITEMS. Payment will be for all labor, equipment, transportation, supervision, operating supplies, materials, and incidentals necessary to complete the work as specified.
| 1. Replacing foundation. |
| 2. Repairing stonework, including replacing damaged units. |
| 1. Installer shall have minimum 5 years’ experience of evaluating, installing, and repointing historic masonry, along with the knowledge, techniques, and methodology required to reproduce masonry foundations from the 1920s. This includes demonstrable ... |
| 2. Installer shall work with a high degree of precision and accuracy to maintain the authenticity and integrity of historic masonry, foundations, and structures. |
| 3. Contractor shall have demonstrated expertise in performing masonry work meeting the Secretary of the Interior's Standards for Historic Preservation. |
| 1. Available Products: Subject to compliance with requirements, products that may be incorporated into the Work include, but are not limited to, the products specified. |
| 2. Products: Subject to compliance with requirements, provide one of the products specified. |
| 3. Available Manufacturers: Subject to compliance with requirements, manufacturers offering products that may be incorporated into the Work include, but are not limited to, the manufacturers specified. |
| 4. Manufacturers: Subject to compliance with requirements, provide products by the manufacturers specified. |
| a. Saint-Astier® |
| b. Or approved equal |
| 1. For existing stone that exhibits a range of colors, finishes, sizes, or shapes, provide stone that matches that range. |
| 1. NHL 3.5 |
| 2. NHL 5 |
| 1. Color: Provide natural sand; of color necessary to produce required mortar color. |
| 2. Match size, texture, and gradation of existing mortar sand as closely as possible. Blend several sands, if necessary, to achieve suitable match. |
| 1. Remove mortar, loose particles, and soil from stone by cleaning with hand chisels, brushes, and water. |
| 2. Remove sealants by cutting close to stone with utility knife and cleaning with solvents. |
| 1. Tool mortar joints to match joints of original existing stonework. |
| 1. Remove soil and softened surface encrustation from stone with cold water applied by low-pressure spray. |
| C-4 HAULING AND DISPOSAL OF MATERIALS |
| C-5 CLEANUP AND DISPOSAL |
| The Contractor shall at all times keep the area in an orderly condition. Upon completing the work, the Contractor shall remove from the site and premises any rubbish, tools, equipment, and materials that are not the property of the Forest Service. Up... |
| C-6 EXISTING UTILITIES |
| C-8 – FIRE CONTROL (FS.236.1) |
C-9 MEASUREMENT AND PAYMENT