1240LU22B0001.pdf
PDF 582 KB Posted
- Attached to
- GAOA CUSTER GALLATIN NATIONAL FOREST - Main Fork Rock Creek Road #2421 Reconstruction Project
- Solicitation number
- 1240LU22B0001
About this file
This is a solicitation for a construction project to recondition and surface approximately 4.27 miles of the Main Fork Rock Creek Road #2421 in the Custer Gallatin National Forest. The project includes culvert removal and replacement, traffic control, and surface work on the road and trailheads. Boulder rock placement is also required at dispersed sites along the road's length. Additive items include further boulder placement and additional aggregate surfacing. The solicitation provides pricing tables, specifications for the road and culvert work, traffic control requirements, and performance periods. The contract will be a firm-fixed-price award made to the lowest priced responsive responsible offeror. The period of performance is 60 days with work to begin in June 2022.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Wage Determination.pdf | ||
| FSSS.docx | DOCX document | |
| Maps and Drawings.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOLICITATION, OFFER,
AND AWARD
2. TYPE OF SOLICITATION
6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.
PAGE OF PAGES
7. ISSUED BY CODE 8. ADDRESS OFFER TO
SOLICITATION
(Construction, Alteration, or Repair)
1. SOLICITATION NO. 3. DATE ISSUED
IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.
9.
INFORMATION
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."
CALL:
FOR
SEALED BID (IFB)
NEGOTIATED (RFP)
1051704
USDA FOREST SERVICE
3710 FALLON STREET STE C
BOZEMAN MT 59718
03H5
a. NAME
WES DUDLEY
b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
406-920-1530
GAOA
x
02/01/2022
1240LU22B0001
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)
MAIN FORK ROCK CREEK ROAD #2421 RECONSTRUCTION PROJECT, ALL SOLICITATION DOCUMENTS
AND ATTACHMENTS 2022.
11. The Contractor shall begin performance
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and is not required.is, b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
d. Offers providing less than
12b. CALENDAR DAYSYES NO
(If "YES", indicate within how many calendar days after award in Item 12b.)
10 60 calendar days and complete it within ________________ ________________ calendar days after receiving
SOLICITATION DOCUMENTS
03/15/2022
NSN 7540-01-155-3212
x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ _______ _____ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________
STANDARD FORM 1442 (Rev. 4-85)
Prescribed by GSA
FAR(48 CFR) 53.236-1(d)
1 11:00AM
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)
16. REMITTANCE ADDRESS (Include only if different than item 14.)
CODE FACILITY CODE
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGEMENT OF AMENDMENTS
OFFER (Must be fully completed by offeror)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this document and return (Contractor is not required to sign this document.)
Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award.
No further contractual document is necessary.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31a. NAME OF CONTRACTING OFFICER (Type or print)
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE
BY
2PAGE OF
28. NEGOTIATED AGREEMENT 29. AWARD
Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, copies to issuing office.)
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
STANDARD FORM 1442 (REV. 4-85) BACK
Continued...
ITEM NO.
(A)
SUPPLIES/SERVICES
(B)
QUANTITY
(C)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
NAME OF OFFEROR OR CONTRACTOR
3 42
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
1240LU22B0001
End of Period of Performance: 08/01/2022
GAOA Main Fork Rock Creek #2421, Trailhead & Campground 530 879 Road Construction
ELECTRONIC BIDS ARE ACCEPTED, SEND TO
wesley.dudley@usda.gov
HARD COPY PAPER BIDS ARE ALSO ACCEPTED, SEND
TO 3710 FALLON ST SUITE C BOZEMAN, MT 59718
ATTN: WES DUDLEY
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
SOLICITATION: 1240LU22B0001
USDA FOREST SERVICE
MAIN FORK ROCK CREEK ROAD #2421 RECONSTRUCTION PROJECT
PART I—THE SCHEDULE
SECTION B--SUPPLIES OR SERVICES AND PRICES/COSTS
B.1 SCHEDULE OF ITEMS
BASE ITEMS
Item Number Description Pay Unit
Estimated Quantity Unit Price Total
15101 Mobilization LS All XXXXX
30101 Aggregate Surfacing Course, Grading F, Compaction Method C Roadway
*CY 5,428
30102
Aggregate Surfacing Course, Grading F, Compaction Method C, Trailhead, Approaches and Turnouts
*CY 360
30103 Aggregate Surfacing Course, Grading F, Compaction Method C, M-K Trailhead
*CY 120
30307 Roadway Reconditioning, Roller Compaction *Mile 4.27
60201 18" Pipe Culvert, Type Metal, Compaction Method 6 LF 150
62201 Rental Equipment, Type Excavator HR 50
62202 Rental Equipment, Type Motor Grader HR 24
63501 Temporary Traffic Control LS All XXXXX
TOTAL
BASE ITEMS
(*) Denotes Contract Quantity Items
Additive Item 1
Item Number Description Pay Unit
Estimated Quantity Unit Price Total
25101 Boulder Placement Type Individual EA 150.0
Additive Item2
Item Number Description Pay Unit
Estimated Quantity Unit Price Total
30101 Aggregate Surfacing Course, Grading F, Compaction Method C Roadway
*CY 635
GRAND
TOTAL BASE
+ ADDITIVE 1
+ ADDITIVE 2
(*) Denotes Contract Quantity Items
B.2 SCHEDULE NOTES
a) Items labeled as additive are not required to be exercised by the government. If exercised, the contractor will be required to perform the optional work in accordance with the terms and conditions of this contract.
b) One award will be made from this solicitation, contractors must submit pricing for all items.
MAIN FORK ROCK CREEK ROAD #2421 RECONSTRUCTION PROJECT
SECTION C--DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK
C.1 PROJECT DESCRIPTION AND LOCATION
(a) Description of Work.
This project consists of reconditioning and surfacing approximately 4.27 miles of the Main Fork Rock Creek Road #2421 including the trailheads, turnouts, and road and camp approaches along the roadway starting at MP 4.36 to the terminus at Glacier Lake Trailhead. The work includes culvert removal and replacement, traffic control, and various other items related to the road work on the Main Fork Rock Creek Road #2421. Also includes boulder rock placement at staked locations along the entire length of the road as staked in the field. The trailhead and access at M- K Campground will also be reconditioned and surfaced under this project. A parking area and access will be constructed with time and equipment near the intersection of #2421 Main Fork Rock Creek and #2004 Hell Roaring Road. Boulders may be salvaged from theses locations.
Staking will be done by the Government. Stakes will only be provided at the Point of Beginning of the Project, End Point of the Project, culvert locations, and for boulder placement.
Remove and reset any signs that are in the construction zone or may be disturbed by construction activities.
The Contractor may construct a truck turn around between at the upper end of the road at an approved locations by the CO. Contractor must submit proposal for the turnaround.
Contractor shall place aggregate aprons at all road and camp sites.
All Culvert staking is the Contractor’s responsibility. All culverts shall be staked by the Contractor prior to ordering for exact length determination. The Government will stake the culvert stationing locations, and other required contract items.
Additive Item #1 will be for placing boulders to protect resources at many of the 127 dispersed sites located along the entire length of the #2421 Main Fork Rock Creek Road.
Additive Item #2 will be for aggregate surface course placed along the first mile of the #2421 Main Fork Rock Creek Road starting at the intersection with Road #2004.
Contractor shall include in the traffic control plan a black on orange Type III Hi-Vis temporary construction sign at start of the project. The sign shall have the wording “Main Fork Rock Creek Road #2421 Closed Monday – Friday 0800-1200 and 1300-1700 Date XX to Date XX” and shall comply with the latest version of the MUTCD. Only the last 4.27 miles where reconditioning will take place may be closed. This sign shall be in place minimum of 7 days prior to road closure. The contractor shall also include advanced notification of the road closure at the pavement/gravel transition.
MAIN FORK ROCK CREEK ROAD #2421 RECONSTRUCTION PROJECT
There will be a contractor working concurrently in the Greenough Campground site.
Contractors shall work together and schedule in a manner to reduce conflict.
(b) Project Location. Main Fork Rock Creek Road #2421 is located along the Beartooth Hwy 212 in the Beartooth Ranger District, Custer National Forest near Red Lodge, Montana.
The project recondition base bid begins at the staked location of the Main Fork Rock Creek Road #2421 and proceeds for approximately 4.27 miles to the end of the trailhead. Barrier rocks may be placed at staked locations along the entire length of the road.
(c) Magnitude of Constructions. Between $500,000 and $1,000,000.
(d) Pre-Bid Tour. There will be no prebid tour. Bidders are encouraged to visit the site.
Persons interested in viewing the project on their own may obtain directional information from the District Office in Red Lodge, MT, telephone (406) 446-2103.
(e) Start Work – It is estimated work will begin June 2022.
(f) Period of Performance – 60 calendar days.
(g) Safety Plan – Contractor shall provide adequate safety briefings and ensure safe practices are followed by all personnel involved in the project. Emergency contact numbers shall be readily available on site. A safety plan shall be submitted to the CO prior to starting work.
(h) Government Furnished Materials: Boulders may be collected along the road for placement. Boulders are not in a stockpile or in any readily available area.
(i) Submittals - The contractor shall submit Work Schedule, Traffic Control Plan, and Safety Plan to the CO one week prior to starting work. The Contractor shall regularly update the Work Schedule. Contractor shall not start work until Traffic Control Plan, Work Schedule, and Safety Plan have been approved in writing. Contractor shall submit all test results, testing samples, and other submittals for approval. Contractor shall submit aggregate testing results. Contractor shall submit sign drawings prior to ordering.
(j) Disturbances – The Contractor may work Monday through Friday excluding legal holidays. The week of July 4th is extremely busy in Red Lodge. Truck haul through town may be slow.
(k) Staging Area – Shall be approved by the CO.
(l) Electrical – There is no on-site electrical available.
(m) Security and Protection – Security is the Contractor’s responsibility. Limit access to the construction area to persons involved in the work. Provide secure storage for materials that are stored on site. Secure completed work as required to prevent loss.
MAIN FORK ROCK CREEK ROAD #2421 RECONSTRUCTION PROJECT
Barricades, warning signs, and lights shall comply with standards and code requirements for erection of structurally adequate barricades. All road warning signs, barricades, and traffic control devices shall conform to MUTCD. Where appropriate and needed, provide lighting, including flashing red or amber warning lights.
(n) Maintenance of Traffic – The Contractor shall have all temporary construction signs and traffic control measures in place prior to beginning work. Contractor shall have an approved Traffic Control Plan in place prior to beginning work.
The Contractor is authorized to use roads under the jurisdiction of the Forest Service for all activities necessary to complete this contract, subject to limitations and authorizations designated in Road Order(s), as Shown On The Drawings, or specified under this contract, when such use will not damage the roads or National Forest resources and when traffic can be accommodated safely.
Before shutting down operations, take all necessary precautions to prevent damage to the project, such as temporary detours, approaches, crossings, or intersections; and provide for normal drainage and minimization of erosion.
The Contractor shall follow proper food storage restrictions available at the Beartooth District Office.
Any emergency vehicles shall be allowed immediate passage.
The Contractor will be allowed to close the road to public traffic from 0800-1200 and 1300- 1700. Monday through Friday. Longer periods will only be around at the Contractors written request and only for specific culvert installations. Maximum closure time will be 10 hours. The contractor shall keep the road open to passenger vehicles during holidays and weekends and between regular work periods. Information must be detailed in how the closures will be accomplished in the traffic control plan.
(o) Protection of Improvements – The Contractor shall complete sequences of construction activity in order to prevent damage to equipment, material, and articles incorporated into the work covered by this contract.
(p) Water – There is no potable water available on this job. Water for earthwork, surfacing, and incidental construction may be pumped from the Main Fork Rock Creek with prior approval.
(q) Toilet Facilities – The Contractor shall supply portable toilets to the project site.
(r) Underground Utilities – The Contractor shall call Montana One Call Prior to digging.
SECTION D--PACKAGING AND MARKING
D-1 PACKING AND MARKING
All shipments of materials, equipment and/or supplies shall be addressed to the Contractor and not to the Government.
D-2 PROJECT LABELING FOR OFFICIAL CORRESPONDENCE
The Government singularly identifies each project with a contract number at time of award. The contract number is a unique identifier to purposely and permanently represent an awarded project. The Government issued contract number is to be referenced on all official communication starting upon notice of award.
SECTION E--INSPECTION AND ACCEPTANCE
E.1 CLAUSES
52.246-12 Inspection of Construction (AUG 1996)
SECTION F--DELIVERIES OR PERFORMANCE
F.1 CLAUSES
52.211-13 Time Extensions (SEP 2000) 52.211-18 Variation in Estimated Quantity (APR 1984) 52.242-14 Suspension of Work (APR 1984)
52.211-10 Commencement, Prosecution, and Completion of Work (APR 1984)
The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 60 days after receipt of notice to proceed. The time stated for completion shall include final cleanup of the premises.
SECTION G--CONTRACT ADMINISTRATION DATA
OTHER REQUIREMENTS
Post Award Conference (NOV 1996)
A post award conference with the successful offeror is required. It will be scheduled and held within 30 days after the date of contract award. The conference will be held over the phone or online.
MAIN FORK ROCK CREEK ROAD #2421 RECONSTRUCTION PROJECT
SECTION H--SPECIAL CONTRACT REQUIREMENTS
OTHER REQUIREMENTS
USE OF PREMISES
(a) Before any camp, quarry, borrow pit, storage, detour, or bypass site, other than shown on the drawings, is opened or operated on USDA land or lands administered by the USDA, the Contractor shall obtain written permission from the Contracting Officer. A camp is interpreted to include a campsite or trailer parking area of any employee working on the project for the Contractor.
(b) Unless excepted elsewhere in the contract, the Contractor shall (i) provide and maintain sanitation facilities for the work force at the site and (ii) dispose of solid waste in accordance with applicable Federal, State and local regulations.
ARCHAEOLOGICAL OR HISTORIC SITES
If a previously unidentified archaeological or historic site(s) is encountered, the Contractor shall discontinue work in the general area of the site(s) and notify the Contracting Officer immediately.
CONTROL OF EROSION, SEDIMENTATION, AND POLLUTION
(a) Operations shall be scheduled and conducted to minimize erosion of soils and to prevent silting and muddying of streams, rivers, irrigation systems, and impoundments (lakes, reservoirs, etc.).
(b) Pollutants such as fuels, lubricants, bitumens, raw sewage, and other harmful materials shall not be discharged on the ground; into or nearby rivers, streams, or impoundments; or into natural or man-made channels. Wash water or waste from concrete or aggregate operations shall not be allowed to enter live streams prior to treatment by filtration, settling, or other means sufficient to reduce the sediment content to not more than that of the stream into which it is discharged.
(c) Mechanized equipment shall not be operated in flowing streams without written approval by the Contracting Officer.
MAIN FORK ROCK CREEK ROAD #2421 RECONSTRUCTION PROJECT
INSURANCE COVERAGE
Pursuant to FAR clause 52.228-5, Insurance-Work on a Government Installation, the Contractor will be required to present evidence to show, as a minimum, the amounts of insurance coverage indicated below:
(a) Workers Compensation and Employer's Liability. The Contractor is required to comply with applicable Federal and State workers' compensation and occupational disease statutes. If occupational diseases are not compensable under those statutes, they shall be covered under the employer's liability section of the insurance policy, except when contract operations are so commingled with a Contractor's commercial operations that it would not be practical to require this coverage. Employer's liability coverage of at least $100,000 shall be required, except in States with exclusive or monopolistic funds that do not permit worker's compensation to be written by private carriers.
(b) General Liability. (1) The Contractor shall have bodily injury liability coverage written on a comprehensive form of policy of at least $500,000 per occurrence. (2) The Contractor shall have property damage liability insurance shall be required in the amount of ____*___ per occurrence.
(c) Automobile Liability. The Contractor shall have automobile liability insurance written on a comprehensive form of policy. The policy shall provide for bodily injury and property damage liability covering the operation of all automobiles used in connection with performing the contract. Policies covering automobiles operated in the United States shall provide coverage of at least $200,000 per person and $500,000 per occurrence for bodily injury and $20,000 per occurrence for property damage or loss.
(d) Aircraft Public and Passenger Liability. When aircraft are used in connection with performing the contract, the Contractor shall have aircraft public and passenger liability insurance. Coverage shall be at least $200,000 per person and $500,000 per occurrence for bodily injury, other than passenger injury. Coverage for passenger injury shall be at least $200,000 multiplied by the number of seats or passengers, whichever is greater.
PART II--CONTRACT CLAUSES
SECTION I--CONTRACT CLAUSES
I.1 CLAUSES
52.252-2 Clauses Incorporated by Reference (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):
Federal Acquisition Regulation (FAR) Clauses:
https://www.acquisition.gov/browse/index/far (FAR clauses begin with 52) Department of Agriculture Acquisition Regulation (AGAR) Clauses:
https://www.acquisition.gov/agar (AGAR clauses begin with 452) Deviations to clauses may be viewed at:
https://www.dm.usda.gov/procurement/policy/FARClassDeviations.htm
52.202-1 Definitions (JUN 2020) 52.203-3 Gratuities (APR 1984) 52.203-5 Covenant against Contingent Fees (MAY 2014) 52.203-6 Restrictions on Subcontractor Sales to the Government (JUN 2020) 52.203-7 Anti-Kickback Procedures (JUN 2020) 52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity
(MAY 2014)
52.203-10 Price or Fee Adjustment for Illegal or Improper Activity (MAY 2014) 52.203-12 Limitation on Payments to Influence Certain Federal Transactions (JUN 2020) 52.203-17 Contractor Employee Whistleblower Rights & Requirements to Inform
Employees of Whistleblower Rights (JUN 2020) 52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or
Statements (JAN 2017) 52.204-2 Security Requirements (MAR 2021) Alternate II (APR 1984) 52.204-4 Printed or Copied Double-Sided on Postconsumer Fiber Content Paper (MAY
2011) 52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards (JUN
2020) 52.204-13 System for Award Management Maintenance (OCT 2018) 52.204-14 Service Contract Reporting Requirements (OCT 2016) 52.204-15 Service Contract Reporting Requirements for Indefinite Delivery Contracts (OCT
2016) 52.204-18 Commercial and Government Entity Code Maintenance (AUG 2020) 52.204-19 Incorporation by Reference of Representations and Certifications (DEC 2014) 52.204-23 Prohibition on Contracting for Hardware, Software, and Services Developed or
Provided by Kaspersky Lab and Other Covered Entities (NOV 2021) https://www.acquisition.gov/browse/index/far https://www.acquisition.gov/agar
MAIN FORK ROCK CREEK ROAD #2421 RECONSTRUCTION PROJECT
52.204-25 Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment (NOV 2021)
52.209-6 Protecting the Government's Interest when Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment (JUN 2020)
52.209-9 Updates of Publicly Available Information Regarding Responsibility Matters
(OCT 2018)
52.209-10 Prohibition on Contracting with Inverted Domestic Corporations (NOV 2015) 52.214-29 Order of Precedence – Sealed Bidding (JAN 1986) 52.219-6 Notice of Total Small Business Set-Aside (NOV 2020) 52.219-8 Utilization of Small Business Concerns (OCT 2018) 52.219-14 Limitations on Subcontracting (SEP 2021)
[Contracting Officer check as appropriate.] ☐ By the end of the base term of the contract and then by the end of each subsequent option period; or ☐ By the end of the performance period for each order issued under the contract.
52.219-28 Post Award Small Business Program Rerepresentation (SEP 2021) 52.222-3 Convict Labor (JUN 2003) 52.222-4 Contract Work Hours and Safety Standards -- Overtime Compensation (MAY
2018) 52.222-6 Construction Wage Rate Requirement (AUG 2018) 52.222-7 Withholding of Funds (MAY 2014) 52.222-8 Payrolls and Basic Records (JUL 2021) 52.222-9 Apprentices and Trainees (JUL 2005) 52.222-10 Compliance with Copeland Act Requirements (FEB 1988) 52.222-11 Subcontracts (Labor Standards) (MAY 2014) 52.222-12 Contract Termination - Debarment (MAY 2014) 52.222-13 Compliance with Construction Wage Rate Requirements and Related Regulations
(MAY 2014)
52.222-14 Disputes Concerning Labor Standards (FEB 1988) 52.222-15 Certification of Eligibility (MAY 2014) 52.222-21 Prohibition of Segregated Facilities (APR 2015) 52.222-26 Equal Opportunity (APR 2016) 52.222-27 Affirmative Action Compliance Requirements for Construction (APR 2015) 52.222-30 Construction Wage Rate Requirements-Price Adjustment (None or Separately
Specified Pricing Method) (AUG 2018) 52.222-35 Equal Opportunity for Veterans (JUN 2020) 52.222-36 Equal Opportunity for Workers with Disabilities (JUN 2020) 52.222-37 Employment Reports on Veterans (JUN 2020) 52.222-40 Notification of Employee Rights Under National Labor Relations Act (DEC
2010) 52.222-50 Combating Trafficking in Persons (NOV 2021) 52.222-54 Employment Eligibility Verification (NOV 2021) 52.222-55 Minimum Wages under Executive Order 13658 (JAN 2022) 52.222-62 Paid Sick Leave under Executive Order 13706 (JAN 2017) 52.223-2 Affirmative Procurement of Biobased Products under Service and Construction
MAIN FORK ROCK CREEK ROAD #2421 RECONSTRUCTION PROJECT
Contracts (SEP 2013) 52.223-3 Hazardous Material Identification and Material Safety Data Alt 1 (FEB 2021) 52.223-5 Pollution Prevention and Right-to-Know Information (MAY 2011) 52.223-6 Drug-Free Workplace (MAY 2001) 52.223-11 Ozone-Depleting Substances and High Global Warming Potential
Hydrofluorocarbons (JUN 2016) 52.223-12 Maintenance, Service, Repair, or Disposal of Refrigeration Equipment and Air
Conditioners (JUN 2016) 52.223-15 Energy Efficiency in Energy Consuming Products (MAY 2020) 52.223-17 Affirmative Procurement of EPA-designated Items in Service and Construction
Contracts (AUG 2018) 52.223-18 Encouraging Contractor Policies to Ban Text Messaging While Driving (JUN
2020) 52.223-20 Aerosols (JUN 2016) 52.223-21 Foams. (JUN 2016) 52.225-13 Restrictions on Certain Foreign Purchases (FEB 2021) 52.226-1 Utilization of Indian Organizations and Indian-Owned Economic Enterprises
(JUN 2000)
52.227-1 Authorization and Consent (JUN 2020) 52.227-2 Notice and Assistance Regarding Patent and Copyright Infringement (JUN 2020) 52.227-4 Patent Indemnity -- Construction Contracts (DEC 2007) 52.228-2 Additional Bond Security (OCT 1997) 52.228-5 Insurance – Work on a Government Installation (JAN 1997) 52.228-12 Prospective Subcontractor Requests for Bonds (MAY 2014) 52.228-14 Irrevocable Letter of Credit (NOV 2014) 52.229-3 Federal, State, and Local Taxes (FEB 2013) 52.232-5 Payments under Fixed-Price Construction Contracts (MAY 2014) 52.232-17 Interest (MAY 2014) 52.232-23 Assignment of Claims (MAY 2014) 52.232-27 Prompt Payment for Construction Contracts (JAN 2017) 52.232-33 Payment by Electronic Funds Transfer – System for Award Management (OCT
2018) 52.232-39 Unenforceability of Unauthorized Obligations (JUN 2013) 52.233-1 Disputes (MAY 2014) Alt 1 (DEC 1991) 52.233-3 Protest after Award (AUG 1996) 52.233-4 Applicable Law for Breach of Contract Claim (OCT 2004) 52.236-2 Differing Site Conditions (APR 1984) 52.236-3 Site Investigation and Conditions Affecting the Work (APR 1984) 52.236-5 Material and Workmanship (APR 1984) 52.236-6 Superintendence by the Contractor (APR 1984) 52.236-7 Permits and Responsibilities (NOV 1991) 52.236-8 Other Contracts (APR 1984) 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and
Improvements (APR 1984) 52.236-10 Operations and Storage Areas (APR 1984)
MAIN FORK ROCK CREEK ROAD #2421 RECONSTRUCTION PROJECT
52.236-11 Use and Possession Prior to Completion (APR 1984) 52.236-12 Cleaning Up (APR 1984) 52.236-13 Accident Prevention (NOV 1991) 52.236-14 Availability and Use of Utility Services (APR 1984) 52.236-15 Schedules for Construction Contracts (APR 1984) 52.236-16 Quantity Surveys (APR 1984) 52.236-17 Layout of Work (APR 1984) 52.236-21 Specifications and Drawings for Construction (FEB 1997) 52.242-5 Payments to Small Business Subcontractors (JAN 2017) 52.242-13 Bankruptcy (JUL 1995) 52.243-4 Changes (JUN 2007) 52.244-2 Subcontracts (JUN 2020) 52.244-6 Subcontracts for Commercial Products and Commercial Services (JAN 2022)
(DEVIATION APR 2020)
52.245-1 Government Property (SEP 2021) - Alt 1 (APR 2012) 52.245-9 Use and Charges (APR 2012) 52.246-21 Warranty of Construction (MAR 1994)
Alternate I (MAR 1994) 52.248-3 Value Engineering – Construction (OCT 2020) 52.249-2 Termination for Convenience of the Government (Fixed-Price) (APR 2012)--
Alternate I (SEP 1996) 52.249-10 Default (Fixed-Price Construction) (APR 1984) 52.253-1 Computer Generated Forms (JAN 1991)
52.217-7 Option for Increased quantity – Separately Priced Line Item (MAR 1989)
The Government may require the delivery of the numbered line item, identified in the Schedule as an option item, in the quantity and at the price stated in the Schedule. The Contracting Officer may exercise the option by written notice to the Contractor within 30 days.
52.223-9 Estimate of Percentage of Recovered Material Content for EPA-Designated Items
(May 2008)
(a) Definitions. As used in this clause— “Postconsumer material” means a material or finished product that has served its intended use and has been discarded for disposal or recovery, having completed its life as a consumer item.
Postconsumer material is a part of the broader category of “recovered material.”
“Recovered material” means waste materials and by-products recovered or diverted from solid waste, but the term does not include those materials and by-products generated from, and commonly reused within, an original manufacturing process.
(b) The Contractor, on completion of this contract, shall—
(1) Estimate the percentage of the total recovered material content for EPA-designated item(s) delivered and/or used in contract performance, including, if applicable, the percentage of post-consumer material content; and
(2) Submit this estimate to address on page 1.
MAIN FORK ROCK CREEK ROAD #2421 RECONSTRUCTION PROJECT
52.225-9 Buy American Act-Construction Materials (NOV 2021)
(a) Definitions. As used in this clause-
Commercially available off-the-shelf (COTS) item-
(1) Means any item of supply (including construction material) that is-
(i) A commercial product (as defined in paragraph (1) of the definition of “commercial product” at Federal Acquisition Regulation (FAR) 2.101);
(ii) Sold in substantial quantities in the commercial marketplace; and
(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace;
and
(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products.
"Construction material" means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work.
The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.
Cost of components means-
(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or
(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.
Domestic construction material means-
(1) For construction material that does not consist wholly or predominantly of iron or steel or a combination of both-
(i) An unmanufactured construction material mined or produced in the United States;
or
(ii) A construction material manufactured in the United States, if-
(A) The cost of its components mined, produced, or manufactured in the United
States exceeds 55 percent of the cost of all its components. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic. Components of unknown origin are treated as foreign; or
(B) The construction material is a COTS item; or
(2) For construction material that consists wholly or predominantly of iron or steel or a combination of both, a construction material manufactured in the United States if the cost of foreign iron and steel constitutes less than 5 percent of the cost of all components used in such construction material. The cost of foreign iron and steel includes but is not limited to the cost of foreign iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the construction material and a good faith estimate of the cost of all foreign iron or steel components excluding COTS fasteners. Iron or steel components of unknown origin are treated as foreign. If the construction material contains multiple components, the cost of all the materials used in such construction material is calculated in accordance with the definition of "cost of components".
Fastener means a hardware device that mechanically joins or affixes two or more objects together. Examples of fasteners are nuts, bolts, pins, rivets, nails, clips, and screws.
Foreign construction material means a construction material other than a domestic construction material.
Foreign iron and steel means iron or steel products not produced in the United States.
Produced in the United States means that all manufacturing processes of the iron or steel must take place in the United States, from the initial melting stage through the application of coatings, except metallurgical processes involving refinement of steel additives. The origin of the elements of the iron or steel is not relevant to the determination of whether it is domestic or foreign.
MAIN FORK ROCK CREEK ROAD #2421 RECONSTRUCTION PROJECT
Predominantly of iron or steel or a combination of both means that the cost of the iron and steel content exceeds 50 percent of the total cost of all its components. The cost of iron and steel is the cost of the iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the product and a good faith estimate of the cost of iron or steel components excluding COTS fasteners.
Steel means an alloy that includes at least 50 percent iron, between 0.02 and 2 percent carbon, and may include other elements.
"United States" means the 50 States, the District of Columbia, and outlying areas.
(b) Domestic preference. (1) This clause implements 41 U.S.C.chapter 83, Buy American, by providing a preference for domestic construction material. In accordance with 41 U.S.C. 1907, the domestic content test of the Buy American statute is waived for construction material that is a COTS item, except that for construction material that consists wholly or predominantly of iron or steel or a combination of both, the domestic content test is applied only to the iron and steel content of the construction materials, excluding COTS fasteners. (See FAR 12.505(a)(2)). The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.
(2) This requirement does not apply to information technology that is a commercial product or to the construction materials or components listed by the Government as follows:
NONE
(3) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(2) of this clause if the Government determines that-
(i) The cost of domestic construction material would be unreasonable. The cost of a particular domestic construction material subject to the requirements of the Buy American statute is unreasonable when the cost of such material exceeds the cost of foreign material by more than 20 percent;
(ii) The application of the restriction of the Buy American statute to a particular construction material would be impracticable or inconsistent with the public interest; or
(iii) The construction material is not mined, produced, or manufactured in the United
States in sufficient and reasonably available commercial quantities of a satisfactory quality.
(c) Request for determination of inapplicability of the Buy American statute. (1) (i) Any
Contractor request to use foreign construction material in accordance with
MAIN FORK ROCK CREEK ROAD #2421 RECONSTRUCTION PROJECT
paragraph (b)(3) of this clause shall include adequate information for Government evaluation of the request, including-
(A) A description of the foreign and domestic construction materials;
(B) Unit of measure;
(C) Quantity;
(D) Price;
(E) Time of delivery or availability;
(F) Location of the construction project;
(G) Name and address of the proposed supplier; and
(H) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(3) of this clause.
(ii) A request based on unreasonable cost shall include a reasonable survey of the market and a completed price comparison table in the format in paragraph (d) of this clause.
(iii) The price of construction material shall include all delivery costs to the construction site and any applicable duty (whether or not a duty-free certificate may be issued).
(iv) Any Contractor request for a determination submitted after contract award shall explain why the Contractor could not reasonably foresee the need for such determination and could not have requested the determination before contract award. If the Contractor does not submit a satisfactory explanation, the Contracting Officer need not make a determination.
(2) If the Government determines after contract award that an exception to the Buy
American statute applies and the Contracting Officer and the Contractor negotiate adequate consideration, the Contracting Officer will modify the contract to allow use of the foreign construction material. However, when the basis for the exception is the unreasonable price of a domestic construction material, adequate consideration is not less than the differential established in paragraph (b)(3)(i) of this clause.
(3) Unless the Government determines that an exception to the Buy American statute applies, use of foreign construction material is noncompliant with the Buy American statute.
MAIN FORK ROCK CREEK ROAD #2421 RECONSTRUCTION PROJECT
(d) Data. To permit evaluation of requests under paragraph (c) of this clause based on unreasonable cost, the Contractor shall include the following information and any applicable supporting data based on the survey of suppliers:
Foreign and Domestic Construction Materials Price Comparison
Construction Material Description Unit of Measure Quantity Price (dollars)* Item1:
Foreign construction material _______ _______ _______ Domestic construction material _______ _______ _______
Item2:
Foreign construction material _______ _______ _______ Domestic construction material _______ _______ _______
[* Include all delivery costs to the construction site and any applicable duty (whether or not a duty-free entry certificate is issued)].
[List name, address, telephone number, and contact for suppliers surveyed. Attach copy of response; if oral, attach summary.]
[Include other applicable supporting information.]
52.228-1 Bid Guarantee (SEP 1996)
(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.
(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States. The Contracting Officer will return bid guarantees, other than bid bonds –
(1) To unsuccessful bidders as soon as practicable after the opening of bids, and (2) To the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.
(c) The amount of the bid guarantee shall be 10 percent of the bid price or $25,000, whichever is less.
MAIN FORK ROCK CREEK ROAD #2421 RECONSTRUCTION PROJECT
(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.
(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.
52.228-11 Individual Surety - Pledge of Assets (FEB 2021) (DEVIATION APR 2020)
(a) The Contractor shall obtain from each person acting as an individual surety on a performance bond or a payment bond -
(1)A pledge of assets that meets the eligibility, valuation, and security requirements described in the Federal Acquisition Regulation (FAR) 28.203-1; and
(2) Standard Form 28, Affidavit of Individual Surety, [except that the words “being duly sworn, depose and say” on the Standard Form 28 are replaced with the word “affirm” and the Standard Form 28 is not required to be sworn and notarized in block 12].
(b)The Contracting Officer may release a portion of the security interest on the individual surety's assets based upon substantial performance of the Contractor's obligations under its performance bond. The security interest in support of a performance bond shall be maintained—
(1) Contracts for the construction, alteration, or repair of any public building or public work of the Federal Government exceeding $150,000 (40 U.S.C. 3131). Until completion of any warranty period, or for 1 year following final payment, whichever is later.
(2) Contracts subject to alternative payment protection (see FAR 28.102-1(b)(1)). For the full contract performance period plus 1 year.
(3) Other contracts not subject to the requirements of paragraph (b)(1) of this clause. Until completion of any warranty period, or for 90 days following final payment, whichever is later.
(c)A surety's assets pledged in support of a payment bond may be released to a subcontractor or supplier upon Government receipt of a Federal district court judgment, or a sworn statement by the subcontractor or supplier that the claim is correct along with a notarized authorization of the release by the surety stating that it approves of such release. The security interest on the individual surety's assets in support of a payment bond shall be maintained—
(1) Contracts for the construction, alteration, or repair of any public building or public work of the Federal Government exceeding $150,000 which require performance and payment bonds (40 U.S.C. 3131). For 1 year following final payment, or until resolution of https://www.acquisition.gov/far/part-28#FAR_28_203_1
MAIN FORK ROCK CREEK ROAD #2421 RECONSTRUCTION PROJECT
all pending claims filed against the payment bond during the 1-year period following final payment, whichever is later.
(2) Contracts subject to alternative payment protection (see FAR 28.102-1(b)(1)). For the full contract performance period plus 1 year.
(3) Other contracts not subject to the requirements of paragraph (c)(1) of this clause. For
90 days following final payment.
(d)The Contracting Officer may allow the Contractor to substitute an individual surety, for a performance or payment bond, after contract award. The Contractor shall comply with the requirements of paragraph (a) of this clause within the timeframe established by the Contracting Officer.
52.228-15 Performance and Payment Bonds -- Construction (JUN 2020) (DEVIATION APR
2020)
(a)Definitions. As used in this clause -- “Original contract price” means the award price of the contract; or, for requirements contracts, the price payable for the estimated total quantity; or, for indefinite-quantity contracts, the price payable for the specified minimum quantity. Original contract price does not include the price of any options, except those options exercised at the time of contract award.
(b) Amount of required bonds. Unless the resulting contract price is valued at or below the threshold specified in Federal Acquisition Regulation 28.102-1(a) on the date of award of this contract, the successful offeror shall furnish performance and payment bonds to the Contracting Officer as follows:
(1) Performance Bonds (Standard Form 25, EXCEPT THAT A SEAL IS NOT REQUIRED). The penal amount of performance bonds at the time of contract award shall be 100 percent of the original contract price.
(2) Payment Bonds (Standard Form 25-A, EXCEPT THAT A SEAL IS NOT REQUIRED). The penal amount of payment bonds at the time of contract award shall be 100 percent of the original contract price.
(3) Additional bond protection.
(i) The Government may require additional performance and payment bond protection if the contract price is increased. The increase in protection generally will equal 100 percent of the increase in contract price.
(ii) The Government may secure the additional protection by directing the Contractor to increase the penal amount of the existing bond or to obtain an additional bond.
(c) Furnishing executed bonds. The Contractor shall furnish all executed bonds, including any necessary reinsurance agreements, to the Contracting Officer, within the time period specified in the Bid Guarantee provision of the solicitation, or otherwise specified by the Contracting Officer, but in any event, before starting work.
(d) Surety or other security for bonds. The bonds shall be in the form of firm commitment, supported by corporate sureties whose names appear on the list contained in Treasury https://www.acquisition.gov/far/part-28#FAR_28_102_1
MAIN FORK ROCK CREEK ROAD #2421 RECONSTRUCTION PROJECT
Department Circular 570, individual sureties, or by other acceptable security such as postal money order, certified check, cashier’s check, irrevocable letter of credit, or, in accordance with Treasury Department regulations, certain bonds or notes of the United States. Treasury Circular 570 is published in the Federal Register or may be obtained from the:
U.S. Department of Treasury Financial Management Service Surety Bond Branch 3700 East West Highway, Room 6F01 Hyattsville, MD 20782 Or via the internet at http://www.fms.treas.gov/c570/.
(e) Notice of subcontractor waiver of protection (40 U.S.C. 3133(c)). Any waiver of the right to sue on the payment bond is void unless it is in writing, signed by the person whose right is waived, and executed after such person has first furnished labor or material for use in the performance of the contract.
52.228-17 Individual Surety – Pledge of Assets (Bid Guarantee) (FEB 2021)
(a)Offerors shall obtain from each person acting as an individual surety on a bid guarantee—
(1) A pledge of assets that meets the eligibility, valuation, and security requirements described in the Federal Acquisition Regulation (FAR) 28.203-1; and
(2) Standard Form 28, Affidavit of Individual Surety.
(b)The Offeror shall include with its offer the information required at paragraph (a) of this provision within the timeframe specified in the provision at FAR 52.228-1, Bid Guarantee, or as otherwise established by the Contracting Officer.
(c)The Contracting Officer may release the security interest on the individual surety's assets in support of a bid guarantee based upon evidence that the offer supported by the individual surety will not result in contract award.
52.232-40 Providing Accelerated Payments to Small Business Subcontractors (NOV 2021)
(DEVIATION APR 2020)
(a)[(1) In accordance with 31 U.S.C. 3903 and 10 U.S.C. 2307, upon receipt of accelerated payments from the Government, the Contractor shall make accelerated payments to its small business subcontractors under this contract [in accordance with the accelerated payment date established], to the maximum extent practicable and prior to when such payment is otherwise required under the applicable contract or subcontract, [with a goal of 15 days] after receipt of a proper invoice and all other required documentation from the small business subcontractor [if a specific payment date is not established by contract.
(2) The Contractor agrees to make such payments to its small business subcontractors without any further consideration from or fees charged to the subcontractor].
http://www.fms.treas.gov/c570/ https://www.acquisition.gov/far/part-28#FAR_28_203_1 https://www.acquisition.gov/far/part-52#FAR_52_228_1
MAIN FORK ROCK CREEK ROAD #2421 RECONSTRUCTION PROJECT
(b) The acceleration of payments under this clause does not provide any new rights under the Prompt Payment Act.
(c) Include the substance of this clause, including this paragraph (c), in all subcontracts with small business concerns, including subcontracts with small business concerns for the acquisition of commercial products or commercial services.
52.252-6 Authorized Deviations in Clauses (NOV 2020)
(a) The use in this solicitation or contract of any Federal Acquisition Regulation (48 CFR Chapter 1) clause with an authorized deviation is indicated by the addition of “(DEVIATION)” after the date of the clause.
(b) The use in this solicitation or contract of any Agriculture Acquisition Regulation (48 CFR…