1240LT25P0005 - South Fork Emergency Furnace Replacement (17 Pages).pdf

PDF 351 KB Posted

Attached to
SOUTH FORK EMERGENCY FURNACE REPLACEMENT
Solicitation number
1240LT25P0005
Issued by

About this file

This is a 17-page contract award document (1240LT25P0005) for an emergency furnace replacement project at the South Fork Guard Station in Provo, Utah. The contract was awarded to C C Mechanical Inc. of Lindon, UT for $8,152.00 under unusual and compelling urgency provisions.

The scope of work includes removing and disposing of an existing 20-year-old Carrier Weathermaker 9200 downflow gas furnace located in the attic of the Guard Station and replacing it with a new 40,000 BTU propane gas furnace with 90% or greater thermal efficiency. The work breakdown includes: furnace replacement and installation ($6,802), lifting equipment to/from attic through south window ($900), and adding 2 tees, 4 rodent screens and cleaning exhaust/intake PVC lines ($450). The period of performance is 30 calendar days from January 13, 2025 to February 14, 2025, with work required to begin within 10 days of notice to proceed. The project location is approximately 4.7 miles past the American Fork fee booth on the south side of the Alpine Loop Scenic Byway.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOLICITATION, OFFER,

AND AWARD

2. TYPE OF SOLICITATION

6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.

PAGE OF PAGES

7. ISSUED BY CODE 8. ADDRESS OFFER TO

SOLICITATION

(Construction, Alteration, or Repair)

1. SOLICITATION NO. 3. DATE ISSUED

IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.

9.

INFORMATION

a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."

CALL:

FOR

SEALED BID (IFB)

NEGOTIATED (RFP)

1144094

USDA-FS CSA INTERMOUNTAIN 8

324 25TH ST

OGDEN UT 84401-2310

40LT

WESTLEY BISSON

WESTLEY.BISSON@USDA.GOV

GREG WARBURTON

GREG.WARBURTON@USDA.GOV

WESTLEY BISSON 605-431-0135

1240LT25Q0011

1240LT25P0005

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)

All documents contained herein to include Wage Determinations, Statement of Work and

Specifications.

11. The Contractor shall begin performance within

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)

13. ADDITIONAL SOLICITATION REQUIREMENTS:

a. Sealed offers in original and is not required.is, b. An offer guarantee

c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

d. Offers providing less than

12b. CALENDAR DAYSYES NO

(If "YES", indicate within how many calendar days after award in Item 12b.)

10 30 calendar days and complete it within ________________ ________________ calendar days after receiving

FAR 52.211-10

NSN 7540-01-155-3212

x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________

STANDARD FORM 1442 (Rev. 8/2014)

Prescribed by GSA

FAR(48 CFR) 53.236-1(d)

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)

16. REMITTANCE ADDRESS (Include only if different than item 14.)

CODE FACILITY CODE

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGEMENT OF AMENDMENTS

OFFER (Must be fully completed by offeror)

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this document and return (Contractor is not required to sign this document.)

Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award.

No further contractual document is necessary.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31a. NAME OF CONTRACTING OFFICER (Type or print)

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE

BY

C C MECHANICAL INC

1396 W 200 S

STE 1A

LINDON UT 84042

1104880887#

2PAGE OF

USDA-FS CSA INTERMOUNTAIN 8

324 25TH ST

OGDEN UT 84401-2310

40LT

INVOICE PROCESSING PLATFORM IPP

ALL INVOICES MUST BE SUBMITTED

ELECTRONICALLY THROUGH THE

INVOICE PROCESSING PLATFORM IPP

VIA WWW IPP GOV

WESTLEY M. BISSON

28. NEGOTIATED AGREEMENT 29. AWARD

Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

copies to issuing office.)

10 U.S.C. 2304(c) 41 U.S.C. 3304(a)x x

STANDARD FORM 1442 (REV. 8/2014) BACK

$8,152.00

Continued...

ITEM NO.

(A)

SUPPLIES/SERVICES

(B)

QUANTITY

(C)

UNIT

(D)

UNIT PRICE

(E)

AMOUNT

(F)

NAME OF OFFEROR OR CONTRACTOR

3 17

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

C C MECHANICAL INC

1240LT25P0005

UEI: XTVCWP9V76W8

PROJECT NAME: SOUTH FORK EMERGENCY FURNACE

REPLACEMENT

PROJECT DESCRIPTION: Work includes, but is not limited to, replacing one furnace in the attic of the South Fork Guard Station. The current furnace is a 20 year old Carrier Weathermaker 9200 downflow gas furnace.

PROJECT LOCATION: Address: S. Fork Ranger Station

Rd., Provo Utah 84604

The south Fork Ranger station is located approximately 4.7 miles past the American Fork fee booth. The Guard Station is located on the south side of the Alpine Loop Scenic Byway just past the turnoff for Tibble Fork Reservoir. See the next page for a map.

CO: WESTLEY BISSON (Westley.Bisson@usda.gov)

COR: GREG WARBURTON (Greg.Warburton@usda.gov)

GTM: SAMTA BRAHMBHATT (Samta.Brahmbhatt@usda.gov)

Delivery: 30 Days After Notice to Proceed

Delivery Location Code: 8455

USDA FOREST SERVICE

WASATCH-CACHE NF

1729 W 5TH SOUTH AUTO WORK CENTER

SALT LAKE CITY UT 84104 US

FMMI Account: FS00.0419QMQM0122 BOC: 2540

Period of Performance: 01/13/2025 to 02/14/2025

0001 SOUTH FORK EMERGENCY FURNACE REPLACEMENT - 40,000 8,152.00

BTU GAS FURNACE, Removal and disposal of existing

Carrier Weathermaker 9200 furnace and all other work in accordance with Statement of Work and

Specifications.

Contract Type: firm-fixed-price

Product/Service Code: J045

Product/Service Description: MAINT/REPAIR/REBUILD

OF EQUIPMENT- PLUMBING, HEATING, AND WASTE

DISPOSAL EQUIPMENT

The total amount of award: $8,152.00. The obligation for this award is

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

Sponsored by GSA

FAR (48 CFR) 53.110

Award No: 1240LT25P0005 South Fork Emergency Furnace Replacement

FAC 2024-05 May 22, 2024

Table of Contents

PART I—THE SCHEDULE

SECTION B--SUPPLIES OR SERVICES AND PRICES/COSTS

B.1 SCHEDULE OF ITEMS

B.2 SCHEDULE NOTES

SECTION C--DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK

C.1 SCOPE OF CONTRACT

C.2 PROJECT LOCATION

C.3 MAGNITUDE OF CONSTRUCTION PROJECT

C.4 TECHNICAL SPECIFICATIONS

SECTION D--PACKAGING AND MARKING

D.1 PACKING AND MARKING

D.2 PROJECT LABELING FOR OFFICIAL CORRESPONDENCE

SECTION E--INSPECTION AND ACCEPTANCE

E.1 CLAUSES

SECTION F--DELIVERIES OR PERFORMANCE

F.1 CLAUSES

G.1 CLAUSES

SECTION H--SPECIAL CONTRACT REQUIREMENTS

H.1 CLAUSES

PART II--CONTRACT CLAUSES

SECTION I--CONTRACT CLAUSES

I.1 CLAUSES

PART III--LIST OF DOCUMENTS, EXHIBITS, AND OTHER ATTACHMENTS

SECTION J--LIST OF ATTACHMENTS

J.1 ATTACHMENTS

FAC 2024-05 May 22, 2024

PART I—THE SCHEDULE

SECTION B--SUPPLIES OR SERVICES AND PRICES/COSTS

B.1 SCHEDULE OF ITEMS

SOUTH FORK EMERGENCY FURNACE REPLACEMENT

Item Supplies/Services Qty Unit of

Issue Unit Price Total Price

0001 Replacement of unit heater including installation of new unit, and removal and disposal of old unit. Unit heater must be Propane gas powered, have thermal efficiency of 90% or greater, and have a heating capacity equivalent to 40,000 BTUH.

1 EA $6,802.00 $6,802.00

0002 Lifting of new & old heater to/from attic through south window

1 LS $900.00 $900.00

0003 Add 2 Tees, 4 Rodent screens & clean Exhaust & Intake PVC Lines

1 LS $450.00 $450.00

TOTAL: $8,152.00

EA = EACH

B.2 SCHEDULE NOTES

A) One award will be made from this solicitation, contractors must submit pricing for all items.

FAC 2024-05 May 22, 2024

SECTION C--DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK

C.1 SCOPE OF CONTRACT

Work includes, but is not limited to, replacing one furnace in the attic of the South Fork Guard Station. The current furnace is a 20 year old Carrier Weathermaker 9200 downflow gas furnace.

C.2 PROJECT LOCATION

Address: S. Fork Ranger Station Rd., Provo Utah 84604

The south Fork Ranger station is located approximately 4.7 miles past the American Fork fee booth. The Guard Station is located on the south side of the Alpine Loop Scenic Byway just past the turnoff for Tibble Fork Reservoir. See the next page for a map.

C.3 MAGNITUDE OF CONSTRUCTION PROJECT

Below $25,000.00

C.4 TECHNICAL SPECIFICATIONS

AGAR 452.211-72 Statement of Work/Specifications (FEB 1988) The Contractor shall furnish the necessary personnel, material, equipment, services and facilities (except as otherwise specified), to perform the Statement of Work/Specifications referenced in Section J.

AGAR 452.211-73 Attachments to Statement of Work/Specifications (FEB 1988) The attachments to the Statement of Work/Specifications listed in Section J are hereby made part of this solicitation and any resultant contract.

SECTION D--PACKAGING AND MARKING

D.1 PACKING AND MARKING

All shipments of materials, equipment and/or supplies shall be addressed to the Contractor and not to the Government.

D.2 PROJECT LABELING FOR OFFICIAL CORRESPONDENCE

The Government singularly identifies each project with a contract number at time of award. The contract number is a unique identifier to purposely and permanently represent an awarded project. The Government issued contract number is to be referenced on all official communication starting upon notice of award.

SECTION E--INSPECTION AND ACCEPTANCE

E.1 CLAUSES

FAR 52.246-12 Inspection of Construction (AUG 1996) FAR 52.246-13 Inspection-Dismantling, Demolition, or Removal of Improvements (AUG

1996)

SECTION F--DELIVERIES OR PERFORMANCE

F.1 CLAUSES

FAR 52.242-14 Suspension of Work (APR 1984)

FAR 52.211.10 Commencement, Prosecution, and Completion of Work (APR 1984)

The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 30 calendar days. The time stated for completion shall include final cleanup of the premises.

SECTION G--CONTRACT ADMINISTRATION DATA

G.1 CLAUSES

AGAR 452.204-70 Modification for Contract Closeout (DEVIATION JUN 2024)

AGAR 452.215-73 Post Award Conference (NOV 1996)

A post award conference with the successful offeror is required. It will be scheduled and held within 10 days after the date of contract award. The conference will be held at project site or via Microsoft Teams.

https://www.usda.gov/sites/default/files/documents/agar-class-deviation-contract-closeout-clause.pdf

FAC 2024-05 May 22, 2024

SECTION H--SPECIAL CONTRACT REQUIREMENTS

H.1 CLAUSES

AGAR 452.237-74 Key Personnel (FEB 1988)

(a) The Contractor shall assign to this contract the following key personnel:

_____________PERSONNEL REQUIRED FOR PROJECT COMPLETION__________.

(b) During the first ninety (90) days of performance, the Contractor shall make no substitutions of key personnel unless the substitution is necessitated by illness, death, or termination of employment. The Contractor shall notify the Contracting Officer within 15 calendar days after the occurrence of any of these events and provide the information required by paragraph (c) below. After the initial 90-day period, the Contractor shall submit the information required by paragraph (c) to the Contracting Officer at least 15 days prior to making any permanent substitutions.

(c) The Contractor shall provide a detailed explanation of the circumstances necessitating the proposed substitutions, complete resumes for the proposed substitutes, and any additional information requested by the Contracting Officer. Proposed substitutes should have comparable qualifications to those of the persons being replaced. The Contracting Officer will notify the Contractor within 15 calendar days after receipt of all required information of the decision on substitutions. The contract will be modified to reflect any approved changes of key personnel.

(End of clause)

PART II--CONTRACT CLAUSES

SECTION I--CONTRACT CLAUSES

I.1 CLAUSES

FAR 52.252-2 Clauses Incorporated by Reference (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):

Federal Acquisition Regulation (FAR): https://www.acquisition.gov/browse/index/far (Clauses are located at FAR part 52 and begin with 52)

Department of Agriculture Acquisition Regulation (AGAR):https://www.acquisition.gov/agar (Clauses are located at AGAR part 452 and begin with 452)

Deviations to clauses may be viewed at: Policies & Regulations | USDA

FAR 52.203-17 Contractor Employee Whistleblower Rights (NOV 2023) (Whistleblower

Guidance to contractor employees) FAR 52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or

Statements (JAN 2017) FAR 52.204-2 Security Requirements (MAR 2021) Alternate II (APR 1984) FAR 52.204-13 System for Award Management Maintenance (OCT 2018) FAR 52.204-18 Commercial and Government Entity Code Maintenance (AUG 2020) FAR 52.204-19 Incorporation by Reference of Representations and Certifications (DEC

2014) FAR 52.204-21 Basic Safeguarding of Covered Contractor Information Systems (NOV

2021) FAR 52.204-23 Prohibition on Contracting for Hardware, Software, and Services

Developed or Provided by Kaspersky Lab Covered Entities (DEC 2023) FAR 52.204-25 Prohibition on Contracting for Certain Telecommunications and Video

Surveillance Services or Equipment (NOV 2021) FAR 52.204-27 Prohibition on a ByteDance Covered Application (JUN 2023) FAR 52.204-30 Federal Acquisition Supply Chain Security Act Orders—Prohibition (Dec

2023) FAR 52.209-10 Prohibition on Contracting with Inverted Domestic Corporations (NOV

2015) FAR 52.215-8 Order of Precedence—Uniform Contract Format (OCT 1997) FAR 52.219-28 Post Award Small Business Program Rerepresentation (FEB 2024) FAR 52.222-3 Convict Labor (JUN 2003) FAR 52.222-6 Construction Wage Rate Requirement (AUG 2018) FAR 52.222-7 Withholding of Funds (MAY 2014) FAR 52.222-8 Payrolls and Basic Records (JUL 2021) https://www.acquisition.gov/browse/index/far https://www.acquisition.gov/far/part-52 https://www.acquisition.gov/agar https://www.acquisition.gov/agar/part-452-solicitation-provisions-and-contract-clauses https://www.usda.gov/da/ocp/ppd/policies-regulations https://view.officeapps.live.com/op/view.aspx?src=https%3A%2F%2Fcontent.govdelivery.com%2Fattachments%2FUSDAPSD%2F2023%2F04%2F04%2Ffile_attachments%2F2456937%2FWhistleblower%2520Guidance.docx&wdOrigin=BROWSELINK https://view.officeapps.live.com/op/view.aspx?src=https%3A%2F%2Fcontent.govdelivery.com%2Fattachments%2FUSDAPSD%2F2023%2F04%2F04%2Ffile_attachments%2F2456937%2FWhistleblower%2520Guidance.docx&wdOrigin=BROWSELINK

FAC 2024-05 May 22, 2024

FAR 52.222-9 Apprentices and Trainees (JUL 2005) FAR 52.222-10 Compliance with Copeland Act Requirements (FEB 1988) FAR 52.222-11 Subcontracts (Labor Standards) (MAY 2014) FAR 52.222-12 Contract Termination - Debarment (MAY 2014) FAR 52.222-13 Compliance with Construction Wage Rate Requirements and Related

Regulations (MAY 2014) FAR 52.222-14 Disputes Concerning Labor Standards (FEB 1988) FAR 52.222-15 Certification of Eligibility (MAY 2014) FAR 52.222-21 Prohibition of Segregated Facilities (APR 2015) FAR 52.222-26 Equal Opportunity (APR 2016) FAR 52.222-27 Affirmative Action Compliance Requirements for Construction (APR

2015) FAR 52.222-30 Construction Wage Rate Requirements-Price Adjustment (None or

Separately Specified Pricing Method) (AUG 2018) FAR 52.222-36 Equal Opportunity for Workers with Disabilities (JUN 2020) FAR 52.222-50 Combating Trafficking in Persons (NOV 2021) FAR 52.222-55 Minimum Wages for Contractor Workers under Executive Order 14026

(JAN 2022)

FAR 52.222-62 Paid Sick Leave under Executive Order 13706 (JAN 2022) FAR 52.223-2 Reporting of Biobased Products Under Service and Construction Contracts

(MAY 2024)

FAR 52.223-3 Hazardous Material Identification and Material Safety Data (FEB 2021)-

Alternate l (JULY 1995) FAR 52.223-5 Pollution Prevention and Right-to-Know Information (MAY 2024) FAR 52.223-11 Ozone-Depleting Substances and High Global Warming Potential

Hydrofluorocarbons (MAY 2024) FAR 52.223-20 Aerosols (MAY 2024) FAR 52.223-21 Foams (MAY 2024) FAR 52.223-23 Sustainable Products & Services (MAY 2024) FAR 52.225-13 Restrictions on Certain Foreign Purchases (FEB 2021) FAR 52.226-8 Encouraging Contractor Policies to Ban Text Messaging While Driving

(MAY 2024)

FAR 52.227-4 Patent Indemnity -- Construction Contracts (DEC 2007) FAR 52.232-5 Payments under Fixed-Price Construction Contracts (MAY 2014) FAR 52.232-23 Assignment of Claims (MAY 2014) FAR 52.232-27 Prompt Payment for Construction Contracts (JAN 2017) FAR 52.232-33 Payment by Electronic Funds Transfer – System for Award Management

(OCT 2018)

FAR 52.232-39 Unenforceability of Unauthorized Obligations (JUN 2013) FAR 52.232-40 Providing Accelerated Payments to Small Business Subcontractors (MAR

2023) FAR 52.233-1 Disputes (MAY 2014) Alt 1 (DEC 1991) FAR 52.233-3 Protest after Award (AUG 1996) FAR 52.233-4 Applicable Law for Breach of Contract Claim (OCT 2004) FAR 52.236-2 Differing Site Conditions (APR 1984)

FAC 2024-05 May 22, 2024

FAR 52.236-3 Site Investigation and Conditions Affecting the Work (APR 1984) FAR 52.236-5 Material and Workmanship (APR 1984) FAR 52.236-6 Superintendence by the Contractor (APR 1984) FAR 52.236-7 Permits and Responsibilities (NOV 1991) FAR 52.236-8 Other Contracts (APR 1984) FAR 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and

Improvements (APR 1984) FAR 52.236-10 Operations and Storage Areas (APR 1984) FAR 52.236-11 Use and Possession Prior to Completion (APR 1984) FAR 52.236-12 Cleaning Up (APR 1984) FAR 52.236-13 Accident Prevention (NOV 1991) FAR 52.236-14 Availability and Use of Utility Services (APR 1984) FAR 52.236-21 Specifications and Drawings for Construction (FEB 1997) FAR 52.243-5 Changes and Changed Conditions (APR 1984) FAR 52.244-6 Subcontracts for Commercial Products and Commercial Services (FEB

2024) FAR 52.246-21 Warranty of Construction (MAR 1994) Alternate I (MAR 1994) FAR 52.248-3 Value Engineering – Construction (OCT 2020) FAR 52.249-1 Termination for Convenience of the Government (Fixed-Price) (Short

Form) (APR 1984) Alternate I (SEP 1996) FAR 52.249-10 Default (Fixed-Price Construction) (APR 1984) FAR 52.253-1 Computer Generated Forms (JAN 1991) AGAR 452.236-71 Prohibition Against the Use of Lead-Based Paint (NOV 1996) AGAR 452.236-72 Use of Premises (NOV 1996) AGAR 452.236-73 Archaeological or Historic Sites (FEB 1988) AGAR 452.236-74 Control of Erosion, Sedimentation, and Pollution (NOV 1996) AGAR 452.236-76 Samples and Certificates (FEB 1988) AGAR 452.236-77 Emergency Response (NOV 1996)

FAR 52.225-9 Buy American Act-Construction Materials (OCT 2022)

(a) Definitions. As used in this clause—

Commercially available off-the-shelf (COTS) item—

(1) Means any item of supply (including construction material) that is–

(i) A commercial product (as defined in paragraph (1) of the definition of “commercial product” at Federal Acquisition Regulation (FAR) 2.101);

(ii) Sold in substantial quantities in the commercial marketplace; and

(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and https://www.acquisition.gov/far/part-2#FAR_2_101

FAC 2024-05 May 22, 2024

(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products.

"Construction material" means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies.

However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.

Cost of components means—

(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or

(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.

Critical component means a component that is mined, produced, or manufactured in the United States and deemed critical to the U.S. supply chain. The list of critical components is at FAR 25.105.

Critical item means a domestic construction material or domestic end product that is deemed critical to U.S. supply chain resiliency. The list of critical items is at FAR 25.105.

Domestic construction material means—

(1) For construction material that does not consist wholly or predominantly of iron or steel or a combination of both-

(i) An unmanufactured construction material mined or produced in the United States; or

(ii) A construction material manufactured in the United States, if–

(A) The cost of its components mined, produced, or manufactured in the United States exceeds 60 percent of the cost of all its components, except that the percentage will be 65 percent for items delivered in calendar years 2024 through 2028 and 75 percent for items delivered starting in calendar year 2029.

Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic. Components of unknown origin are treated as foreign; or https://www.acquisition.gov/far/part-25#FAR_25_105

FAC 2024-05 May 22, 2024

(B) The construction material is a COTS item; or

(2) For construction material that consists wholly or predominantly of iron or steel or a combination of both, a construction material manufactured in the United States if the cost of foreign iron and steel constitutes less than 5 percent of the cost of all component used in such construction material. The cost of foreign iron and steel includes but is not limited to the cost of foreign iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the construction material and a good faith estimate of the cost of all foreign iron or steel components excluding COTS fasteners.

Iron or steel components of unknown origin are treated as foreign. If the construction material contains multiple components, the cost of all the materials used in such construction material is calculated in accordance with the definition of "cost of components".

Fastener means a hardware device that mechanically joins or affixes two or more objects together. Examples of fasteners are nuts, bolts, pins, rivets, nails, clips, and screws.

Foreign construction material means a construction material other than a domestic construction material.

Foreign iron and steel means iron or steel products not produced in the United States.

Produced in the United States means that all manufacturing processes of the iron or steel must take place in the United States, from the initial melting stage through the application of coatings, except metallurgical processes involving refinement of steel additives. The origin of the elements of the iron or steel is not relevant to the determination of whether it is domestic or foreign.

Predominantly of iron or steel or a combination of both means that the cost of the iron and steel content exceeds 50 percent of the total cost of all its components. The cost of iron and steel is the cost of the iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the product and a good faith estimate of the cost of iron or steel components excluding COTS fasteners.

Steel means an alloy that includes at least 50 percent iron, between 0.02 and 2 percent carbon, and may include other elements.

"United States" means the 50 States, the District of Columbia, and outlying areas.

(b) Domestic preference.

(1) This clause implements 41 U.S.C. Chapter 83, Buy American, by providing a preference for domestic construction material. In accordance with 41 U.S.C. 1907, the domestic content test of the Buy American statute is waived for construction material that is a COTS item, except that for construction material that consists wholly or predominantly of iron or steel or a combination of both, the domestic content test is applied only to the iron and steel content of the construction materials, excluding COTS fasteners. (See FAR 12.505(a)(2)). The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.

http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 https://www.acquisition.gov/far/part-12#FAR_12_505 https://www.acquisition.gov/far/part-12#FAR_12_505

FAC 2024-05 May 22, 2024

(2) This requirement does not apply to information technology that is a commercial product or to the construction materials or components listed by the Government as follows:

NONE

(3) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(2) of this clause if the Government determines that-

(i) The cost of domestic construction material would be unreasonable.

(A) For domestic construction material that is not a critical item or does not contain critical components.

(1) The cost of a particular domestic construction material subject to the requirements of the Buy American statute is unreasonable when the cost of such material exceeds the cost of foreign material by more than 20 percent;

(2) For construction material that is not a COTS item and does not consist wholly or predominantly of iron or steel or a combination of both, if the cost of a particular domestic construction material is determined to be unreasonable or there is no domestic offer received, and the low offer is for foreign construction material that is manufactured in the United States and does not exceed 55 percent domestic content, the Contracting Officer will treat the lowest offer of foreign construction material that exceeds 55 percent domestic content as a domestic offer and determine whether the cost of that offer is unreasonable by applying the evaluation factor listed in paragraph (b)(3)(i)(A)(1) of this clause.

(3) The procedures in paragraph (b)(3)(i)(A)(2) of this clause will no longer apply as of January 1, 2030.

(B) For domestic construction material that is a critical item or contains critical components.

(1) The cost of a particular domestic construction material that is a critical item or contains critical components, subject to the requirements of the Buy American statute, is unreasonable when the cost of such material exceeds the cost of foreign material by more than 20 percent plus the additional preference factor identified for the critical item or construction material containing critical components listed at FAR 25.105.

(2) For construction material that does not consist wholly or predominantly of iron or steel or a combination of both, if the cost of a particular domestic construction material is determined to be unreasonable or there is no domestic offer received, and the low offer is for foreign construction material that does not exceed 55 percent domestic content, the Contracting Officer will treat the lowest foreign offer of construction material that is manufactured in the United States and exceeds 55 percent domestic content as a domestic offer, and

FAC 2024-05 May 22, 2024 determine whether the cost of that offer is unreasonable by applying the evaluation factor listed in paragraph (b)(3)(i)(B)(1) of this clause.

(3) The procedures in paragraph (b)(3)(i)(B)(2) of this clause will no longer apply as of January 1, 2030.

(ii) The application of the restriction of the Buy American statute to a particular construction material would be impracticable or inconsistent with the public interest; or

(iii) The construction material is not mined, produced, or manufactured in the United States in sufficient and reasonably available commercial quantities of a satisfactory quality.

(c) Request for determination of inapplicability of the Buy American statute.

(1) (i) Any Contractor request to use foreign construction material in accordance with paragraph (b)(3) of this clause shall include adequate information for Government evaluation of the request, including-

(A) A description of the foreign and domestic construction materials;

(B) Unit of measure;

(C) Quantity;

(D) Price;

(E) Time of delivery or availability;

(F) Location of the construction project;

(G) Name and address of the proposed supplier; and

(H) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(3) of this clause.

(ii) A request based on unreasonable cost shall include a reasonable survey of the market and a completed price comparison table in the format in paragraph (d) of this clause.

(iii) The price of construction material shall include all delivery costs to the construction site and any applicable duty (whether or not a duty-free certificate may be issued).

(iv) Any Contractor request for a determination submitted after contract award shall explain why the Contractor could not reasonably foresee the need for such determination and could not have requested the determination before contract award. If the Contractor does not submit a satisfactory explanation, the Contracting Officer need not make a determination.

(2) If the Government determines after contract award that an exception to the Buy American statute applies and the Contracting Officer and the Contractor negotiate adequate consideration, the Contracting Officer will modify the contract to allow use of the foreign

FAC 2024-05 May 22, 2024 construction material. However, when the basis for the exception is the unreasonable price of a domestic construction material, adequate consideration is not less than the differential established in paragraph (b)(3)(i) of this clause.

(3) Unless the Government determines that an exception to the Buy American statute applies, use of foreign construction material is noncompliant with the Buy American statute.

(d) Data. To permit evaluation of requests under paragraph (c) of this clause based on unreasonable cost, the Contractor shall include the following information and any applicable supporting data based on the survey of suppliers:

Foreign and Domestic Construction Materials Price Comparison Construction Material Description Unit of Measure Quantity Price (Dollars)* Item1

Foreign construction material _______ _______ _______ Domestic construction material _______ _______ _______ Item 2

Foreign construction material _______ _______ _______ Domestic construction material _______ _______ _______

[*Include all delivery costs to the construction site and any applicable duty (whether or not a duty-free entry certificate is issued)].

[List name, address, telephone number, and contact for suppliers surveyed. Attach copy of response; if oral, attach summary.] [Include other applicable supporting information.]

(End of clause)

FAR 52.252-6 Authorized Deviations in Clauses (NOV 2020)

(a) The use in this solicitation or contract of any Federal Acquisition Regulation (48 CFR Chapter 1) clause with an authorized deviation is indicated by the addition of “(DEVIATION)” after the date of the clause.

(b) The use in this solicitation or contract of any Agriculture Acquisition Regulation (48 CFR 4) clause with an authorized deviation is indicated by the addition of “(DEVIATION)” after the name of the regulation.

(End of clause)

PART III--LIST OF DOCUMENTS, EXHIBITS, AND OTHER ATTACHMENTS

SECTION J--LIST OF ATTACHMENTS

J.1 ATTACHMENTS

J.1 Wage Determinations (Building) (Utah County, Utah) (UT20240087) (09.27.2024) (7 Pages)

J.2 Statement of Work (6 Pages)

J.3 Specifications (85 Pages)

ADP718A.tmp
PART I—THE SCHEDULE
SECTION B--SUPPLIES OR SERVICES AND PRICES/COSTS
B.1 SCHEDULE OF ITEMS
B.2 SCHEDULE NOTES
SECTION C--DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK
C.1 SCOPE OF CONTRACT
C.2 PROJECT LOCATION
C.3 MAGNITUDE OF CONSTRUCTION PROJECT
C.4 TECHNICAL SPECIFICATIONS
SECTION D--PACKAGING AND MARKING
D.1 PACKING AND MARKING
D.2 PROJECT LABELING FOR OFFICIAL CORRESPONDENCE
SECTION E--INSPECTION AND ACCEPTANCE
E.1 CLAUSES
SECTION F--DELIVERIES OR PERFORMANCE
F.1 CLAUSES
G.1 CLAUSES
SECTION H--SPECIAL CONTRACT REQUIREMENTS
H.1 CLAUSES
PART II--CONTRACT CLAUSES
SECTION I--CONTRACT CLAUSES
I.1 CLAUSES
PART III--LIST OF DOCUMENTS, EXHIBITS, AND OTHER ATTACHMENTS
SECTION J--LIST OF ATTACHMENTS
J.1 ATTACHMENTS