This is a Question and Answer document from January 29, 2025, addressing equipment usage for fence line work under Solicitation 1240LT25B0003 (South Schells Fence Restoration project).
The document clarifies that while the Statement of Work initially prohibited heavy equipment for fence line clearing, the Contracting Officer has modified this requirement. Due to existing two-track paths along fence lines and limited archaeological sites in the project area, contractors are now permitted to use heavy equipment along fence lines for installation and material transportation. However, contractors are specifically prohibited from using equipment blades to clear new paths.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 1240LT25B0003.pdf | ||
| South Schells SOW.docx | DOCX document | |
| SSchellsRestorationSIGNED.pdf | ||
| White Pine County Nevada Wage Determination.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Agriculture
United States Department of
Forest Service
Business Operations Procurement and Property Services
CSA #8
Caring for the Land and Serving People Printed on Recycled Paper
File Code: 6320 Date: 01/29/25
Subject: Question and answer concerning the use of heavy equipment Solicitaiton 1240LT25B0003
To: Contract File
Question: In the statement of work it states, “Vegetation clearing in the Project Area may be done using chainsaws or handsaws. Heavy Equipment May Not be used to clear the fence lines.”
Answer: On the South Schells project many of the fences have 2 tracks and/or paths along the fence where permitees have used equipment to maintain the fences over the years. There are limited archeological sites in the entire project area. Because of that we will allow the use of equipment along the fence line for the installation of the fence and transportation of materials. Contractors are not allowed to drop a blade on the ground to clear paths.
1/29/2025
X Derrick A Dodson
Signed by: Department of Agriculture
Derrick Dodson Contracting Officer cc: