Statement of Work.docx

DOCX document 2 MB Posted

Attached to
Right Fork Camp Area Vault Toilets
Solicitation number
1240LT24Q0062
Issued by

About this file

This document is a Statement of Work for a federal contract opportunity to install two single vault toilets at the Right Fork Trailhead. The work includes delivery and installation of the pre-cast concrete vault toilets, which shall be Gunnison style or an approved equal. The contract requires earthwork, solar fan kits, and specific color and accessory options for the toilets. The contractor must coordinate the installation timing with the manufacturer and complete the excavation, backfill, and site grading in accordance with the provided instructions. The solicitation number is 1240LT24Q0062 and the procuring agency is the Department of Agriculture Forest Service. The period of performance is 12 months from award, with all ground-disturbing work to be completed within 5 days of commencement.

View the file

Other files

File Type Posted
Maps.pdf PDF
1240LT24Q0062.pdf PDF
Schedule of Items.xlsx XLSX spreadsheet
Wage Determination Elko County Nevada.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

RIGHT FORK VAULT TOILETS

1.1 SCOPE OF CONTRACT

A. Description of work: To install two single vault toilets at Right Fork Trailhead. Toilets for Right Fork shall be single vault Gunnison style toilet or approved equal. Order includes delivery and installation per attached drawings and specifications.

B. Base Bid – 2 Gunnison Single Vault Toilets – 6’6” x 14’ 8”

Delivery and installation of two single vault toilets to Right Fork Trailhead. Toilets for Right Fork shall be single vault Gunnison style toilet or approved equal. Both vault toilet buildings shall include the following added cost open market options: Earthwork & solar fan kits. Colors shall be Natural Honey walls, Mocha Carmel roofs, with top sections Board and Batt. 3 roll stainless steel paper holders with privacy latch ADA handles shall be included, unisex signage with rear wall vent locations. Delivery shall include short truck and crane.

1.2 PROJECT LOCATION

A. Right Fork Trailhead and dispersed camping area are located off of Lamoille Canyon Road, near Spring Creek, NV 89815. From Spring Creek, travel east on NV SR 227E for approximately 5.5 miles. Turn right on forest Route 122 and continue south for approximately 5 miles until you reach the intersection with the dispersed camping area access. See map below for proposed vault toilet installation locations.

1.3 SITE INFORMATION AND LIMITATIONS

A. The following site conditions are considered incidental to the contract and the contractor will not be paid directly for any of the following items:

1. No work shall be performed prior to the contractor receiving a signed Notice to Proceed from the Contracting Officer.

2. Right Fork Trail will remain open with hikers present during construction

3. Right Fork Trail is accessed on a narrow dirt road with sharp corners. A short truck will be needed for this delivery.

4. Contractor will provide all materials and labor necessary to protect streams, wet or dry, during construction activities. The Contractor will be required to submit a stream protection plan and receive approval from the COR, in writing, prior to the beginning of construction.

5. All construction equipment shall be pressure washed before entering National Forest System lands. The removal of mud and debris from treads, tracks and undercarriage, with emphasis on axles, frame, cross-members, motor mounts, and underneath steps, running boards, and front bumper/brushguard assemblies will be required. The purpose is to reduce or eliminate the transportation of noxious weeds, which is required by Federal and State regulations.

6. Permits required by County, State, or Federal laws or regulations shall be obtained by the Contractor

7. Contractor shall provide adequate signing and barricades and take necessary safety measures to protect the public during all construction operations. Contractor shall minimize disturbance of all undisturbed areas.

8. No water, electricity, or other utilities will be available to the contractor.

1.4 TRAFFIC CONTROL AND CONSTRUCTION SIGNING

A. No work that endangers, interferes, or conflicts with traffic or access to work sites shall be performed until a plan for satisfactory warning and handling of traffic has been submitted by the contractor and approved by the COR. Construction signing for traffic control shall conform to the Manual of Uniform Traffic Control Devices (MUTCD). Contractor shall not be paid directly for this item, rather it will be considered incidental to other items of work listed in the Schedule of Items

1.5 WORK CAMPS, STAGING AND STORAGE AREAS

A. Areas for staging operations and storage of materials shall be approved by the COR. The Contractor must request in writing for approval from the COR to stage trailers on site.

B. Limited campsites can be made available for contractor, as approved by the Contracting Officer.

1.6 INSPECTION OF WORKSITE

A. The contractor acknowledges they have taken the necessary steps to ascertain the nature and location of work and have investigated and satisfied themselves as to the general and local conditions that can affect the work or its cost. Any failure of the contractor to take the actions described and acknowledged in this paragraph will not relieve the Contractor from the responsibility of estimating properly the difficulty and cost of successfully performing the work, or for proceeding to successfully perform the work without additional expenses to the government.

1.7 START DATE

A. August 1, 2024

1.8 CONTRACT TIME

A. 12 months from award. However, all ground disturbing work must be completed within 5 days of commencement.

1.9 SPECIFICATIONS

A. The following specifications are attached. Some sections in the schedule of items refer to other sections not listed and are subsidiary to, or are included in payment for other pay items in this contract. These items are considered incidental and no additional compensation will be made.

SECTION 011250 - MEASUREMENT AND PAYMENT

SECTION 013300 - SUBMITTAL PROCEDURES

SECTION 024100 - WASTE MATERIAL DISPOSAL

SECTION 133402 - PRECAST CONCRETE VAULT RESTROOM BUILDING

SECTION 133450 - PRECAST VAULT TOILET INSTALLATION

SECTION 312000 - EARTHWORK

SECTION 321204 - CRUSHED AGGREGATE BASE OR SURFACE COURSE

USDA FOREST SERVICE, R4

RIGHT FORK VAULT TOILETS

SECTION 011250 - MEASUREMENT AND PAYMENT

GENERAL

SUMMARY

Measurement and payment for contract work will be made only for and under those pay items included in the Schedule of Items. All other work, labor, materials, equipment, and incidentals necessary to successfully complete the project will be considered as included in the payment for items shown. This section defines the method of measurements and basis of payment for work items listed in the Schedule of Items.

When more than one class, size, type, thickness, etc. is specified in the Schedule of Items for any pay item, suffixes will be added to the item number to differentiate between the pay items.

DETERMINATION OF QUANTITIES

The following measurements and calculations shall be used to determine contract quantities for payment.

For individual construction items, longitudinal and lateral measurements for area computations shall be made horizontally or corrected to horizontal measurement unless otherwise specified. Measurements for geotextiles, netting and erosion control blankets shall be along slope lines.

For excavation or embankment volumes, the average end area method shall be used to compute volumes. However, if in the judgment of the Contracting Officer (CO), the average end area method is impractical, measurement shall be made by volume in hauling vehicles or by other three-dimensional methods.

For Structures, they shall be measured according to neat lines shown on the drawings or as altered by the CO, in writing, to fit field conditions.

For items that are measured by the linear foot, such as pipe culverts, fencing, guardrail, piping, utilities, and underdrains, measurements shall be made parallel to the base or foundation upon which the structures are placed.

For aggregates weighed for payment, the tonnage shall not be adjusted for moisture content, unless otherwise provided for.

For standard manufactured items (such as fence, wire, plates, rolled shapes, pipe conduits) identified by gauge, weight, section dimensions, and so forth, such identifications shall be considered the nominal weights or dimensions. Unless controlled by tolerances in cited specifications, manufacturer's tolerances shall be accepted.

Earthwork Tolerances - Adjustments of horizontal or vertical alignment, within the tolerances specified in this contract, or shifts of balance points up to 100 feet shall be made by the contractor as necessary to produce the designed sections and to balance earthwork. Such adjustments shall not be considered as "Changes."

UNITS OF MEASUREMENT

Payment shall be by units defined and determined according to U.S. Standard measure and by the following:

Acre: Make longitudinal and transverse measurements for area computations horizontally.

50lb Bag: Measurement will be for the actual number of 50lb bags of standard bentonite grout.

94lb Bag: Measurement will be for the actual number of 94lb bags of standard cement or grout.

Cubic Yard (CY): A measurement computed by one of the following methods:

Excavation, Embankment, or Borrow. The measurement computed by the average end area method from measurements made longitudinally along a centerline or reference line.

Material in Place or Stockpile. The measurement computed using the dimensions of the in-place material.

Material in the Delivery Vehicle. The measurement computed using measurements of material in the hauling vehicles at the point of delivery. Vehicles shall be loaded to at least their water level capacity. Leveling of the loads may be required when vehicles arrive at the delivery point.

Each (EA): One complete unit, which may consist of one or more parts.

Gallons (GAL): The quantity shall be measured by any of the following methods:

Measured volume in container.

Metered volume by approved metering system.

Commercially package volume.

Hour (HR): Measurement will be for the actual number of hours (or fraction thereof) ordered by the Contracting Officer and performed by the contractor.

Linear Foot (LF): Measurement of work along its length from point-to-point; parallel to the base or foundation. Do not measure overlaps.

Lump Sum (LS): One complete unit.

Mile: Measured horizontally along the centerline of each roadway, approach, or ramp.

Pound (LB): For sacked or packaged material, measurement will be the net weight as packed by the manufacturer.

Square Foot (SF): Measured on a plane parallel to the surface being measured.

Square Yard (SY): Measured on a plane parallel to the surface being measured.

Ton: Measured as a short ton consisting of 2,000 pounds.

METHOD OF MEASUREMENT

One of the following methods of measurement for determining final payment is designated on the Schedule of Items for each pay item:

LUMP SUM QUANTITIES (LSQ) - These quantities denote one complete unit of work as required by or described in the contract, including necessary materials, equipment, and labor to complete the job. They shall not be measured.

END OF SECTION 011250

April 2024

MEASUREMENT AND PAYMENT 011250-3

RIGHT FORK VAULT TOILETS

SECTION 013300 - SUBMITTAL PROCEDURES

1. GENERAL

0.1 SUMMARY

A. This Section includes administrative and procedural requirements for submitting Shop Drawings, Product Data, Samples, and other miscellaneous submittals. See Table 013300-1 for a summary of required submittals.

B. See other specification section within this package for additional requirements on submittal.

0.2 SUBMITTAL PROCEDURES

A. Coordination: Coordinate preparation and processing of submittals with performance of construction activities.

1. Coordinate transmittal of different types of submittals for related parts of the Work so processing will not be delayed because of need to review submittals concurrently for coordination.

a. The Contracting Officer (CO) reserves the right to withhold action on a submittal requiring coordination with other submittals until related submittals are received.

B. Processing Time: Allow enough time for submittal review, including time for re-submittals, as follows. Time for review shall commence on CO's receipt of submittal.

1. Initial Review: Allow 14 days for initial review of each submittal. Allow additional time if processing must be delayed to permit coordination with subsequent submittals. CO will advise Contractor when a submittal being processed must be delayed for coordination.

2. If intermediate submittal is necessary, process it in same manner as initial submittal.

3. Allow 14 days for processing each re-submittal.

4. No extension of the Contract Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing.

C. Identification: Place a permanent label or title block on each submittal for identification.

1. Indicate name of firm or entity that prepared each submittal on label or title block.

2. Provide a space on label or beside title block to record Contractor's review and approval markings and action taken by CO.

3. Include the following information on label for processing and recording action taken:

a. Project name.

b. Date.

c. Name and address of Contractor.

d. Name of manufacturer.

e. Unique identifier, including revision number.

f. Number and title of appropriate Specification Section.

g. Drawing number and detail references, as appropriate.

h. If more than one item is shown on submittal sheet, identify item.

D. Deviations: Highlight, encircle, or otherwise identify deviations from the Contract Documents on submittals.

E. Additional Copies: Unless additional copies are required for final submittal, and unless CO observes noncompliance with provisions of the Contract Documents, initial submittal may serve as final submittal.

F. Use for Construction: Use only final submittals with mark indicating action taken by CO in connection with construction.

PART 1 - PRODUCTS

1.1 ACTION SUBMITTALS – (Submittals requiring CO approval)

A. General: Prepare and submit Action Submittals required by individual Specification Sections.

1. Number of Copies: Submit one digital copy of each submittal by email to the contracting officer and the contracting officer’s technical representative, unless otherwise indicated. CO will return two copies. Mark up and retain one returned copy as a Project Record Document.

B. Product Data: Collect information into a single submittal for each element of construction and type of product or equipment.

1. If information must be specially prepared for submittal because standard printed data are not suitable for use, submit as Shop Drawings, not as Product Data.

2. Mark each copy of each submittal to show which products and options are applicable.

3. Include the following information, as applicable:

a. Name and contact information of manufacturer.

b. Manufacturer's written recommendations.

c. Manufacturer's product specifications.

d. Manufacturer's installation instructions.

e. Manufacturer's catalog cuts.

f. Compliance with recognized trade association standards.

g. Compliance with recognized testing agency standards.

C. Shop Drawings: Prepare Project-specific information, drawn accurately to scale. Do not base Shop Drawings on reproductions of the Contract Documents or standard printed data.

1. Preparation: Include the following information, as applicable:

a. Dimensions.

b. Identification of products.

c. Fabrication and installation drawings.

d. Roughing-in and setting diagrams.

e. Notation of dimensions established by field measurement.

2. Wiring Diagrams: Differentiate between manufacturer-installed and field-installed wiring.

D. Contractor's Construction Schedule: The contractor shall submit a Construction Schedule, for approval by CO, in accordance with the contract provisions within 5 day of commencement of work.

E. Samples: Prepare physical units of materials or products, including the following:

1. Samples for Initial Selection: Submit manufacturer's color charts consisting of units or sections of units showing the full range of colors, textures, and patterns available.

1.2 INFORMATIONAL SUBMITTALS – (Submittals NOT requiring CO approval) A. General: Prepare and submit Informational Submittals required by other Specification Sections.

1. Number of Copies: Submit a digital copy of each submittal by email to the contracting officer and the contracting officer’s technical representative of each submittal, unless otherwise indicated. CO will not return copies.

2. Certificates and Certifications: Certificates and certifications shall be signed by an officer or other individual authorized to sign documents on behalf of that entity.

3. Test and Inspection Reports: Comply with requirements in Section 014100 "Quality Control."

B. Material Test Reports: Prepare reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting test results of material for compliance with requirements.

C. Field Test Reports: Prepare reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting results of field tests performed either during installation of product or after product is installed in its final location, for compliance with requirements.

D. Maintenance Data: Prepare written and graphic instructions and procedures for operation and normal maintenance of products and equipment.

E. Manufacturer's Instructions: Prepare written or published information that documents manufacturer's recommendations, guidelines, and procedures for installing or operating a product or equipment. Include name of product and name, address, and telephone number of manufacturer.

PART 2 - EXECUTION

2.1 GENERAL

A. Review each submittal and check for compliance with the Contract Documents. Note corrections and field dimensions. Mark with approval stamp before submitting to CO.

B. Approval Stamp: Stamp each submittal with a uniform, approval stamp. Include Project name and location, submittal number, Specification Section title and number, name of reviewer, date of Contractor's approval, and statement certifying that submittal has been reviewed, checked, and approved for compliance with the Contract Documents.

C. CO will not review submittals that do not bear Contractor's approval stamp and will return them without action.

D. Submittals not required by the Contract Documents will not be reviewed and may be discarded.

E. Substitutions – Whenever materials, products, and equipment are listed by name or brand in the specifications and/or on the drawings, it is used as a measure of quality, utility, or standard. If the Contractor prefers to use any other brand or manufacturer of same quality, appearance and utility to that specified, he shall request substitution as provided below, not less than 30 days before the planned installation of the item. The Contracting Officer will approve or disapprove the request for substitution.

F. Requests for substitutions will only be considered if contractor submits the following:

1. Complete technical data including drawings, complete performance specifications, test data, samples and performance tests of the article proposed for substitution. Submit additional information if required by Contracting Officer. All items in the above information shall be circled, tagged, or marked in some way to indicate all deviations or differences which the proposed item differs from the originally specified item.

2. Similar data as above for item originally specified. All items shall be marked to identify where/how the proposed substitution will differ.

3. A statement by the Contractor that the proposed substitution is in full compliance with the contract documents, applicable codes, and laws.

4. The Contractor shall be responsible for any effect upon related work in the project for any substitution and shall pay any additional costs generated by any substitutions.

2.2 SUBMITTAL SCHEDULE – Submittals shall be made as required by and called for in the drawings and specifications. The following table is a summary of the required submittals for the project - the table is to assist the Contractor and may not be all inclusive – additional submittals may be required by specific specifications:

TABLE 013000-1

Spec. Section
Section Title
Subsection
Required Submittal
SOW
Stream Protection Plan and Simple Traffic Control Plan

Prior to mobilization

013300
Submittal Procedures
2.1D
Construction Schedule
133401
Precast Concrete Vault Restroom Building
1.2A
Manufacturer’s Literature
133401
Precast Concrete Vault Restroom Building
1.2B
Shop Drawings
133401
Precast Concrete Vault Restroom Building
1.2C
Design Calculations
133401
Precast Concrete Vault Restroom Building
1.2D
Concrete Delivery Certificates

MEASUREMENT AND PAYMENT

This work shall be considered incidental to Precast Vault Restroom Installation. No separate payment shall be made.

END OF SECTION 013300

SUBMITTAL PROCEDURES 013300-5

RIGHT FORK VAULT TOILETS

SECTION 024100 - WASTE MATERIAL DISPOSAL

1. GENERAL

SUMMARY

This Section includes the loading, handling, hauling, and placing of excess excavation material, unsuitable excavation material, clearing and grubbing debris, and construction and demolition debris.

EXECUTION

3.1 WASTE MATERIAL TO BE HAULED TO A LANDFILL

All demolition materials, garbage, and other refuse generated shall be removed from the project site and legally disposed of off Government property in an approved landfill.

The contractor is responsible for all costs and permits associated with landfill disposal.

The Government is not responsible for waste material upon its departure from the project site.

MEASUREMENT AND PAYMENT

This work shall be considered incidental to Precast Vault Restroom Installation. No separate payment shall be made.

END OF SECTION 024100

WASTE MATERIAL DISPOSAL 024100-1

RIGHT FORK VAULT TOILETS

SECTION 133402 - PRECAST CONCRETE VAULT RESTROOM BUILDING

1. GENERAL

SUMMARY

This section applies to the fabrication and installation of a precast concrete Vault Restroom building, including shipment to site, all work necessary to completely fabricate, and installation of other manufactured accessories needed or specified in this section for a complete Vault Restroom.

Related sections include the following:

Section 024100 “Waste Material Disposal.”

Section 311000 “Clearing and Grubbing.”

Section 312000 “Earthwork.”

Section 321204 “Crushed Aggregate Base or Surface Course.”

SUBMITTALS

Manufacturer’s Literature: Submit literature for the following items to the Contracting Officer (CO) for approval within 10 day after award of contract. Drawings and literature must be marked to show the exact model, size, and color proposed.

Door, louvered vents, and door hardware.

Paint, interior and exterior.

Caulk, ground and adhesive.

Concrete color additive, stains, concrete curing compound and concrete sealer.

Shop Drawings: Submit four sets of shop drawings of the Vault Restroom stamped by a Professional Engineer.

Design Calculations: Submit two sets of design calculations showing that the building is designed for the structural loads required, fabrication and transportation loads, and crack prevention and control.

Concrete Delivery Certificates: Supplier shall furnish a certificate with each truckload of concrete delivered showing the items in the following list. Submit these certificates to the CO upon delivery of the Vault Restroom.

Weight of cement in each load.

Weight of fine aggregate in each load.

Weight of coarse aggregate in each load.

Weight of water in each load.

Time of day cement was added to the aggregate and water.

PRODUCTS

PRECAST VAULT RESTROOM

Design criteria Snow Load: 350 lbs/ft2 Wind Load: 90 mph, exposure C from 2012 International Building Code Seismic Load: Category E from 2012 International Building Code Designed to meet the requirements of the Americans with Disabilities Act Requirements and Uniform Federal Accessibility Standard including as of the date of these specifications.

Design incorporates all design aspects of Sweet Smelling Technology as outlined by Brian Cook for the U.S. Forest Service. ("In Depth Design and Maintenance Manual for Vault Toilets" - July 1991 - Publication No. 9123 1601) Quality: Manufactured in a Precast Concrete Institute (PCI) Certified Plant for the type of product provided.

Manufacturers of precast concrete Vault Restrooms include, but are not limited to, the following:

CXT Incorporated- Building Division, Spokane, WA, (509) 921-8766, www.cxtinc.com Missoula Concrete Construction, Missoula, MT, (406) 549-9682, www.missoulaconcrete.com

BUILDING WALLS AND SLAB

Floor Slab: 5-inch minimum thickness.

Walls: 4-inch average thickness, 3-inch minimum wall thickness at the top of the walls.

Roof: 4 ¼ inch minimum concrete thickness

OPTIONAL POST TENSIONING

The contractor may elect to circumferentially post tension reinforcing steel for the floor and roof slabs to protect against leaking and cracking. Should the Contractor elect to post tension reinforcement steel in the roof slab, fluid applied elastomeric roofing may be deleted.

WALL VENTS

Wall vents: Airolite No. 609B, size shown on the drawings, The Airolite Co., Marietta, OH, www.airolite.com; or HEAVY DUTY KICK PROOF VENT by Romtec, Roseburg, OR.; or an approved equal. Only one vent per toilet room should be installed – the contracting officer will specify the location of the vent (to be in a wall or the door – the side of the building with the prevailing wind)

ROOF

Sloped slab shed type or gabled type with a turned down edge to prevent water from migrating down the bottom edge of the roof panel and back into the building.

Minimum 6:12 pitch desired

VENT STACK

Vent Stack: shall be a minimum 12 inch diameter HDPE (with a DR of 32.5) and extend from the vault to a minimum of 3 feet higher than the roof peak. Vent Stack shall be black.

BIRD SCREEN:

Provide steel bird screen, secured with stainless steel screws for all stacks to prevent birds from entering the vault.

PRECAST CONCRETE FORM WORK

Construct forms of plywood, lumber, or steel sheets or plates free of defects. Forms must be removable without injuring the concrete and must be constructed to maintain tolerances between mating surfaces of building components.

Form liners Walls: Wood-textured appearance, Symons Corporation’s “Random Barnwood,” or an approved equal.

Roof: Wood shake appearance Form coating: Non-staining type that will not leave residual matter on concrete surface or adversely affect proper bonding of subsequent coatings, caulking, grout or adhesive applied to concrete surfaces.

Form release agent or coating: As recommended by form liner manufacturer.

Coating containing mineral oils or other nondrying ingredients will not be permitted.

Vault:

Provide one concrete vault area per toilet riser.

Each concrete vault shall hold a minimum of 1,000 gallons of waste.

Concrete vault floor shall be sloped a minimum of 1 inch per foot towards the vault cleanout.

Vault Liner: Vault shall include a one-piece molded polyethylene (LDPE) liner with a minimum thickness of 0.10 inch and lip over top of vault. Liner shall be secured to sides of vault interior so that there are no voids between liner and sides of vault.

CONCRETE REINFORCEMENT

Reinforcing steel: ASTM A615, Grade 60.

Pre-stress strand (if used): ASTM A416, Grade 270.

All reinforcement shall be new, free from dirt, oil, paint, grease, loose mill scale, and loose or thick rust when placed.

CONCRETE MIX

Concrete supplier: Ready-mix or another approved precast concrete product firm.

Proportion cement, aggregate, and water to obtain concrete with good workability.

Concrete design Aggregate: Coarse No. 67 (Table 2, ASTM C33) Minimum cement content: 6.5 sacks per yd3 Cement type: ASTM C150 Type II, IIA, or III for building Maximum water-cement ratio: 0.45 Slump: 3 to 5 inches by ASTM C143 Air content: 4-7% by ASTM C231 Minimum strength concrete: 4,500 psi at 28 days Water: Potable Admixtures:

Air-entraining agent: ASTM C260 Water reducing agent: ASTM C494, Type A Use of other admixtures is subject to approval by the Contracting Officer

COLORED CONCRETE

Color additives: ASTM C979. Provide a 12”x 12”x 1” color sample to the Contracting Officer for approval. The following components shall contain colored concrete:

Building roof panels Building wall panels

CONCRETE CURING COMPOUND AND ROOFING

Curing compound: Colorless, ASTM C309, Type 1 or 1-D.

Fluid Applied Elastomeric Roofing: Acrylic latex resin-base elastomeric roofing material applied in fluid form suitable for use over concrete roof slabs. If manufacturer elects to post-tension roof panel, the roofing material may be deleted.

Color: Brown.

Material: “Rapid Roof” as manufactured by the Conclin Company or an approved equal.

CAULKING, GROUT, ADHESIVE, AND MORTAR

Caulking shall remain flexible and non-sag at temperatures from -50° to 140° Fahrenheit.

Exterior, roof peak joint: 100% silicone caulk, clear; GE Silicone II or an approved equal.

Exterior joints (including roof/wall and wall panel joints): Tripolymer sealant caulk which compliments exterior color and has a minimum 5 year guarantee.

Interior joints: Paintable silicone based caulking with a minimum 5 year guarantee.

Grout: Non-shrink type matching color of surrounding concrete as closely as possible.

Epoxy concrete adhesive: Two component, rigid, non-sag gel adhesive for bonding to dry or damp surfaces, moisture insensitive. Color to match surrounding concrete as closely as possible.

Portland cement mortar: One part Portland cement, three parts sand, and enough water to make a workable mixture.

FINISHES AND PAINTS

Paint and accessory materials: Similar to the “top-of-the-line” products of the manufacturer’s listed below.

Benjamin-Moore and Company, www.benjaminmoore.com Columbia Paint Company, www.columbiapaint.com Maximum lead content: 0.06 % by weight of lead.

Type of Paint Metal, interior and exterior Waterborne acrylic bonding primer, Columbia 04-022, or an approved equal.

Alkyd-oil Based Enamel, semi-gloss, Columbia 03-241, or an approved equal.

Exterior Concrete Stain- pure acrylic water repellent penetrating stain Sealer- clear acrylic anti-graffiti sealer Interior Concrete Floors- 1 part water based epoxy with a silica sand suspension to provide a uniform texture.

Interior walls and ceiling- modified acrylic, penetrating pigment followed by a clear acrylic anti-graffiti sealer.

Paint colors Metal window and door frames, louvered vents, and doors (interior and exterior): Java Brown Exterior concrete walls and floor: Sand Beige Exterior concrete roof: Java Brown Interior concrete walls: White Interior concrete floor: Gray

STEEL DOORS

Doors: Flush panel type, 1 ¾ inch thick, minimum gauge zinc-coated steel panels, with minimum 18 gauge internal bracing channels, equal to Steelcraft L-16 of size shown on the drawings.

Door frames shall be knockdown or welded type, single rabbet, minimum 16 gauge zinc-coated steel, width to suit wall thickness, equal to Steelcraft.

Three (3) rubber door silencers shall be provided on latch side of frame Door frame anchors Provide three (3) anchors per jamb located approximately at the same level as hinge locations.

Use anchor type suitable for fastening to precast concrete and designed for future removal of frame.

Anchors may be omitted if frame is cast in panel.

Door hinges One (1) pair shall be 4 ½ inch spring hinges One-half (½) pair shall be standard butt hinge Top and bottom hinge shall have an adjustable tension spring and be adjusted to a 5 lb. maximum pull.

Finish shall be US26D (dull chrome) Deadbolt shall be Mortised type, operated by key from outside only, which will receive the Forest Service cylinder; similar and equal to Yale 1152. Finish shall be US26D (dull chrome).

Door Louver shall be fixed, inverted split Y, non-vision, 18 gauge galvanized steel with factory prime coat, equal to FDLS series by Anemostat Door Products, www.anemostatwest.com. There shall be no insect screen between louvers.

Door sweep shall be an adjustable brush type placed at bottom of door.

Door stop shall be a cast metal base, US26D (dull chrome) finish with gray rubber 2 3/8 inch diameter bumper with a 1 inch projection Threshold shall be extruded aluminum with neoprene seal, Pemco #170, or an approved equal.

INTERIOR HARDWARE

Grab Bars: Grab bars shall be 18-guage type 304 stainless steel, 1 ½ inch diameter with 1 ½ inch clearance; minimum of length required for accessibility standards. Able to withstand 300-pound top load.

Toilet Paper Dispenser: Constructed of ¼” thick, type 304 stainless steel. Holds three (3) standard rolls of toilet paper. Fastening system able to withstand 300-pound top loading.

Double Coat Hook: Formed construction, type 304 stainless steel (Satin Finish), 16-guage minimum.

Toilet riser: Toilet riser shall be molded, smooth one-piece constructed of HDPE polyethylene, cross linked polyethylene, or stainless steel. With heavy duty seat and lid (Color: White); Meeting ADA standards. Apply Butyl rubber adhesive sealant to the top surface of the concrete vault before placing the structure on the vault.

SIGNS

Signs: Signs to have raised pictograms, letters, and braille to meet ADA. Signs shall designate standard unisex symbol for each single. All signs to be securely anchored into concrete with tamper resistant anchors.

WINDOWS

Window frames shall be constructed from steel tubing and fasten water-tight to building with vandal resistant fasteners.

Window glazing shall be translucent pebble finished mar-resistant Lexan polycarbonate. Minimum thickness of ¼ inch.

VAULT CLEANOUT

Frame: shall be constructed from steel frame poured integral with the concrete slab.

Cover/Lid: shall be constructed of minimum ¼ inch steel. Shall be hinged to the steel frame. Configured with a locking mechanism that will receive a government furnished padlock.

Gasket: Cover/Lid shall be gasketed around the entire perimeter of the lid to provide an airtight seal.

CRUSHED AGGREGATE LEVELING COARSE

According to Section 3212004 “Crushed Aggregate Base or Surface Course” Grading E.

EXECUTION

BUILDING CONSTRUCTION

Concrete Support and brace forms sufficiently to prevent distortion of forms due to pressure of the concrete during vibrating of concrete and the curing period.

Vertical grooves in the form liner pattern shall be continuous except for openings for doors.

Horizontal butt joints between liner panels will not be allowed.

Vertical butt joints between form liner panels shall be made at vertical groove in liner pattern except at outside corners.

Vertical grooves in form liner pattern shall be arranged so that there is equal space between vertical doorframe edges and the adjacent vertical grooves at each opening.

Form ties will not be allowed.

Thoroughly clean forms and form liners before each use.

Apply form coating and form release agent on all forms and form liners in accordance with the manufacturer’s recommendations The Contractor shall assume all responsibility for determining when to remove the concrete components from the forms without causing structural damage to the components. Vault Restrooms constructed with damaged components will be rejected.

Concrete Reinforcement Details of reinforcement: ACI 318.

Center steel reinforcement in the cross-sectional area of the walls. Provide at least 1 inch of concrete cover on the under surface of roof and floor. Provide diagonal reinforcement at openings.

Accurately place and adequately support reinforcing steel or strand in final position prior to starting placement of concrete. The maximum allowable variation for center-to-center spacing of reinforcing steel is ½ inch.

Use full length reinforcing steel whenever possible and keep the number of splices to a minimum. When splices are necessary on long runs, alter splices from opposite sides of the component for adjacent steel bars.

No. 4 or smaller shall be lapped a minimum of 12 inches;

Larger than No. 4 shall be lapped a minimum of 24 bar diameters.

Bend bars cold. Do not bend bars partially embedded in concrete Cold Weather Concrete Cold weather concrete: ACI 306 and as follows:

Do not place concrete if ambient temperature is expected to be below 35°F during the curing period unless heating equipment is readily available to maintain temperature of at least 45°F.

Use no materials containing frost or lumps of frozen.

Hot Weather Concrete The temperature of the concrete shall not exceed 80°F at the time of placement, and when the ambient temperature reaches 90°F, the concrete shall be protected with moist covering or other methods approved by the Contracting Officer.

Mixing And Delivery Of Ready Mix Concrete: ASTM C94, Section 11.5 through 11.9.

Placing And Consolidating Concrete Notify the Contracting Officer at least 24 hours before any concrete placement to permit inspection Place layers not more than 24 inches deep. Do not move concrete with vibrators or tampers Consolidate the concrete with suitable mechanical vibrators operating within the concrete or attached steel forms. Vibrate at any point sufficiently to accomplish compaction, but do not prolong to a point where segregation occurs.

Finishing Concrete Interior Floor and Exterior Slab Strike flush to within 1/8-inch variation in 6 feet.

Float and trowel slabs smooth until no marks remain.

Apply final light broom finish to exterior slabs only.

Interior Wall Surfaces and Ceiling Finish shall be that provided by smooth steel form or smooth trowel finish with no trowel marks.

Exterior Wall Surfaces: Barnwood texture provided by approved form liner.

Exterior Roof Surface: Shake texture provided by approved form liner.

Cracks and Patching Cracks in concrete components caused by Contractor fabrication, shrinkage during curing, handling, shipping, and installation shall be cause for rejection if the Government determines that the crack will affect the serviceability or structural integrity of the component.

Fill small holes, depressions, and air or rock pockets in all surfaces with non-shrinking Portland cement based patching material while concrete is still green and within one day of form removal. Patch shall match the color, finish, and texture of surrounding surface.

Patching will not be allowed on any component with holes, chips, or exposed reinforcement totaling more than 18 in3 or with any defects more than 2 inches deep. Those components will be rejected and must be replaced at Contractor’s expense.

Curing And Hardening Concrete Keep all concrete surfaces moist for at least six days after being placed. Acceptable methods include ponding, wet burlap, curing paper, plastic sheets, and membrane curing compound. Other methods are subject to the approval of the Contracting Officer.

Membrane curing compounds will not be allowed where curing compound will interfere with penetration or adhesion of final finish Colored Concrete Use the same type and brand of cement, coloring agent, aggregates, and other additives throughout the building. Use ingredients from the same lot or manufacturing process. Use aggregates from only one source.

Use uniform batches of concrete to ensure consistency of the finished concrete color. Weigh all ingredients. Add color by weight as recommended by manufacturer of the concrete color. Uniformly disperse the color throughout each batch during the mixing operation.

Wash and thoroughly clean the mixer and transporting equipment before mixing colored concrete. Repeat each time a change is made to a different color.

Structural Joints Joining details other than those detailed below will not be allowed unless shown on shop drawings that are stamped by a Professional Engineer and approved by the Contracting Officer prior to manufacture of buildings.

Anchor weld plates into concrete panels and weld together with a continuous weld. Thoroughly clean welds prior to application of caulk or paint.

Join wall components together with two welded plate pairs at each joint.

Weld plate: 6 inches long; with one pair located in the top quarter and one pair in the bottom quarter of the seam.

Seal inside seams with paintable caulk.

Seal outside seams with caulk to match building color or clear.

Join walls and roof with weld plates, minimum 3” x 6”, at each building corner.

Where the Contracting Officer determines that the joint between walls and the roof is true enough to prevent point loadings on the walls, seal the joint between walls and roof gas-tight with paintable caulk.

Where the joint between the walls and roof is not true enough to prevent point loading, grout the joint with approved rigid non-shrinking grout that will distribute the weight of the roof evenly around the perimeter of the building walls.

Seal exterior seams with caulk that is clear or matches building color.

Join the floor slab and walls with a grout mixture on the interior and two weld plate pairs for each wall component, one near each end of each wall panel, or each corner on each side, whichever is greater.

Weld plate: 6 inches long Grout: Provide smooth cover between walls and floor Finishes And Paint Apply materials in accordance with manufacturer’s recommendations.

Examine surfaces to ensure all are properly prepared to receive finish.

Allow a minimum of 14 days curing time for concrete before paints are applied to concrete. Allow longer time when recommended by paint manufacturer.

If needed to ensure uniform application, prepare concrete surface for paint application by acid etching with 30% H=hydrochloric acid. Flush with water and allow to thoroughly dry.

Painting shall not be done under the following conditions:

Temperature is 50°F or below.

Surfaces are damp.

Dusty areas.

Schedule of Finishes Metalwork (steel doors, door vents and frames, and roof posts) One coat metal primer Two coats alkyd oil enamel in Java Brown Exterior surfaces of building walls and roof, unless concrete color manufacturer recommends a different procedure:

Two coats of stain Linseed oil (may be applied and allowed to cure for brown buildings) One coat of clear sealer Interior Concrete Surfaces Walls and ceiling of building: Two coats of pigment followed by one coat of clear sealer.

Interior floor: One coat of epoxy with a silica sand suspension.

Fluid Roofing Apply a minimum of two coats of elastomeric roofing on top of the roof slab.

Prepare concrete surface and apply and cure roofing in accordance with manufacturer’s recommended procedures.

Minimum coverage: 3 gallons per square (100 ft2) Apply joint tape to hairline cracks between applications of the two coats of elastomeric roofing.

This item may be deleted if there are no cracks.

Metal Doors And Frames Install steel doorframe in accordance with manufacturer’s recommendations.

Fit door accurately in frame Mount louvers on door with cadmium or zinc-plated corrosion resistant non-removable metal screws Install hardware in accordance with manufacturer’s instructions after finish painting is completed.

Install sweep on bottom of door and adjust so it contacts the threshold when door is closed.

CLEARING AND GRUBBING

Site clearing and grubbing shall be in accordance with Section 311000 “Clearing and Grubbing”.

EXCAVATION, BACKFILL, AND SITE GRADING

Excavation, backfill, and site grading shall be in accordance with Section 312000 “Earthwork” and Section 311204 “Crushed Aggregate Base or Surface Course”.

Coordination with the Building Manufacturer Contractor shall coordinate with the manufacturer of the precast concrete building to accommodate installation at the time of delivery.

The Contractor shall be responsible to obtain installation instructions from the manufacturer and perform the excavation, backfill, and site grading in accordance with those instructions.

The Contractor must have excavation complete prior to delivery of the precast concrete building and the building must be placed within 24 hours of the excavation being complete.

The excavation shall be over excavated two feet (horizontal measurement) on each side of the slab to allow for compaction and minor adjustments in orientation.

Stockpile excavated material away from the excavation to facilitate crane and delivery truck access. The crane and delivery truck typically need to be side-to-side during placement.

Compact the natural ground at the bottom of the vault excavation with a minimum of three passes with an approved whacker-type mechanical tamper.

The Contractor must be on site at the time of delivery to perform the backfill operation as soon as the precast concrete building is in place.

Bedding The Contractor shall place a leveling course prior to placement of the vault or building.

Compact leveling course with one pass of an approved mechanical tamper.

Grade leveling course so there will be no high spots in the middle.

Compact with a second pass of a tamper.

Slope the top of the bedding one percent from back to front of building.

Minimum compacted leveling course for building slab shall be 6 inches.

Backfill Backfill shall be permitted only after the work to be covered has been approved by the Contracting Officer.

Backfill shall be placed in 8" thick (loose measurement) lifts and compacted with three complete passes of an approved vibratory compactor.

Finish Grading All surfaces and slopes shall be shaped to blend with the original ground line, mounded over or smoothed off, and raked, and left in a uniform and neat condition. Stockpiled topsoil shall be smoothly distributed over disturbed areas and hand raked to blend with ground line. Final grade shall be flush with top of front slab to provide accessibility.

The surface of shall be graded and shaped as shown on the drawings. Surface drainage shall be diverted so that water will not enter into the area.

Cleanup After backfilling and grading has been completed, the disturbed area shall be finished to present as near a natural appearance as possible and cleaned up by removing all debris and materials not utilized.

Clean building walls, floors, and roof using soapy water.

Disposal All unsuitable excavated material, oversize boulders, stumps, small limbs, brush, sod and other construction refuse shall be disposed of off-site at a State-approved disposal site.

MEASUREMENT AND PAYMENT

Payment will be lump sum for each Pre-cast Concrete Vault Restroom installed including all work within 10 feet of the as shown on the drawings. Payment shall include all work associated with clearing, excavation, fill, aggregate, backfill and grading necessary to complete the item.

END OF SECTION 133401

April 2024

PRECAST CONCRETE VAULT RESTROOM BUILDING 133402-13

USDA FOREST SERVICE, R4

RIGHT FORK VAULT TOILETS

SECTION 133450 - PRECAST VAULT TOILET INSTALLATION

1. GENERAL

SCOPE

This item shall consist of excavating, backfilling, and site grading for precast concrete vault comfort stations. It is the responsibility of the Contractor to coordinate with the Government for on site delivery dates and times of Government furnished restrooms.

RELATED WORK

The work shall be in accordance with the following subsidiary specifications. The subsidiary specifications are referred to in the text by the Section designation only.

Section 311000Clearing and Grubbing (Recreation)
Section 024100Waste Material Disposal (Landfill)

PRODUCTS

CLASSIFICATION

Excavation will be unclassified as to materials and shall include all materials which are encountered in the required excavation.

BACKFILL AND EMBANKMENT MATERIAL

Backfill and embankment material shall be loam, sandy clay, sand, gravel, soft shale, or other suitable material free from brush, perishable material, dirt clods, rocks, or boulders larger than six inches in greatest dimension, or frozen material.

Backfill and embankment within six inches of concrete shall contain no rock larger than two inches and no rock two inches or larger shall lie closer than six inches to the ground surface.

Backfill and embankment material shall be excavated material whenever it meets specification requirements. Whenever excavated material contains less than 10 percent of oversized material, the Contractor will be required to remove boulders larger than 6" from the excavated material at no additional compensation and utilize it as backfill material. Whenever material meeting the specification requirements is not available from excavation, the Contractor will be required to import material from a designated or approved source.

SELECT BORROW

When excavated soil does not meet the requirements for backfill, and Contractor shall backfill with select borrow where directed.

WASHED GRAVEL LEVELING COURSE

Gravel shall comply with Section 321204, Crushed aggregate base or surface course, Grading “C”. Two inches of gravel shall be used as a leveling course beneath the concrete vault.

EXECUTION

3.1 STAKING BY THE GOVERNMENT

The Government will stake the building location and orientation. It shall be the responsibility of the contractor to establish the excavation depth and finish floor elevation per the drawings, ensuring finish floor elevation allows for out-sloping and drainage away from the structure.

CLEARING AND GRUBBING

Before starting any excavation, the Contractor shall have completed all necessary clearing and grubbing within the specified working limits, in accordance with Section 311000.

CONSERVING TOPSOIL

Topsoil shall be removed from the area to be excavated and from the area where excavated material will be piled prior to excavating. Topsoil shall be kept separate from excavated material. Topsoil will be reused on those areas from which it came after backfilling and embankment construction is complete.

SAFETY, SHORING, AND PROTECTION

The Contractor shall meet the prescribed safety rules and regulations. Walls of excavations 4' or more in depth shall be supported by bracing, shoring, or other methods, unless the walls are sloped to a safe angle from the bottom. If shored, the excavation shall be of proper width to accommodate shoring and bracing, as required, to keep walls from collapsing, and to allow for proper installation of the work. All existing improvements, either on public or private property, will be fully protected from damage. All supports shall be removed after construction is completed, and shall be withdrawn in a manner that will prevent the collapse of the sides of the excavation. All openings in the ground, caused by the removal of supports, shall be filled with suitable material properly compacted.

REMOVAL OF WATER

The Contractor shall provide and maintain, at all times during construction, ample means and devices with which to promptly remove and properly dispose of all water entering the excavations or other parts of the work without damage to adjacent property. All excavations shall be kept free from standing water. Any damage caused by water in the excavation shall be repaired by the Contractor at his expense.

EXCAVATION, BACKFILL, AND SITE GRADING

Coordination with the Manufacturer - The contractor will be required to coordinate with the manufacturer of the comfort stations to accommodate installation at the time of delivery. The Contractor will be responsible to obtain installation instructions from the manufacturer and perform the excavation, backfill, and site grading in accordance with those instructions.

This is the start of the file's text. The full file is on GovTribe.