This document is the Statement of Work (SOW) for the 2024 Forest Wide Tree Cooler Repair and Renovation project. The project consists of replacing six existing refrigeration system units across the Boise National Forest. The work includes removing and disposing of the existing refrigeration units, installing new Climate Control refrigeration systems with electric defrost, refrigerant controls, electronic thermostats, and associated piping and electrical work. The project locations are spread across multiple ranger districts in the Boise National Forest in Idaho. The work is to be completed in April 2024 within a 90-calendar day period. No separate measurement or payment is specified for the work, and payment is to be included in the contract unit prices.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
GENERAL SPECIFICATIONS 1
Section C - Description/Specifications/Statement of Work
GENERAL SPECIFICATIONS
2024 FOREST WIDE TREE COOLER REPAIR AND RENOVATION
11.7.2023
1.1 SCOPE OF CONTRACT
A. This project consists of a replacement of six existing refrigeration system units across the
Boise National Forest.
1. Work includes the following:
a. Remove and dispose of the existing refrigeration units in the facility, unless otherwise specified.
b. Demo existing refrigeration units and any associated appurtenances being replaced, as required.
c. Ensure functionality of control wiring of system. Replace control wiring if needed.
d. Provide and install a Climate Control refrigeration system, with electric defrost, required refrigerant controls, electronic thermostat, new refrigerant line set, mounting pad for condensing unit, condenser, controller, and evaporator, as required for each refrigeration system.
1) The units shall each use R-448A refrigerant.
2) Provide start-up and owner training, copies of any operational and maintenance plans for each site, and warranty information.
e. Provide and install an interior connection for the electrical to the existing circuitry serving the refrigeration unit. Rework existing connections as needed.
f. Other work as shown in the drawings.
1.2 PROJECT LOCATION
A. The project is located at multiple sites across the Boise National Forest.
1. Cascade (North) Tree Cooler, Cascade Compound on the Cascade Ranger District in the Boise National Forest, Valley County, Idaho, in section 36, T 14 N, R 3 E. It is located approximately 80 miles north of Boise Idaho. The project may be accessed from state highway 55 over paved roads.
2. Cascade (South) Tree Cooler, same site as Cascade (North) Tree Cooler detailed above.
3. High Valley Tree Cooler, High Valley Compound on the Emmette Ranger District in the Boise National Forest, Valley County, Idaho, in Section 07, T 10 N, R 3 E.
GENERAL SPECIFICATIONS 2
It is located approximately 60 miles north of Boise Idaho. The project may be accessed from Forest Road 618 to Forest Road 766 (High Valley Road).
4. Garden Valley Tree Cooler, Garden Valley Compound on the Emmette Ranger
District in the Boise National Forest, Boise County, Idaho, in Section 01, T 8 N, R
4 E. It is located approximately 2 miles East of the town of Garden Valley Idaho.
The Project may be accessed from state highway 17 over paved roads.
5. Idaho City Tree Cooler, Idaho City Compound on the Idaho City Ranger District in the Boise National Forest, Boise County, Idaho, Section 26, T 6 N, R 5 E. It is located approximately 40 miles north of Boise Idaho. The project may be accessed approximately ½ mile from state highway 21 over paved roads.
6. Lester Creek Tree Cooler, Lester Creek Compound on the Mountain Home Ranger
District in the Boise National Forest, Elmore County, Idaho, in Section 22, T 1 N, R 9 E. It is approximately 6 miles southwest of Pine Idaho. The project may be accessed from Forest Road 128.
1.3 REFERENCE SPECIFICATIONS
A. The publications listed below for a part of this specification to the extent referenced. The publications are referred to in the text by the basic designation only.
2021 International Existing Building Code
2021 International Plumbing Code
2020 National Electrical Code
2010 Americans with Disabilities Act/Architectural Barriers Act Guidelines
(ADA/ABAG) (http://www.access-board.gov/adaag/html/adaag.htm)
1.4 PROJECT TIMELINE AND OPERATIONS
A. This project will be completed while the office is occupied by the user and work shall be coordinated with the COR to minimize the interference to operations.
1.5 SITE INFORMATION AND LIMITATIONS
A. The following site conditions are considered incidental to the contract and the contractor will not be paid directly for any of the following items:
1. Construction sites will be open to Forest Service employees during construction.
The Contractor will be responsible for signing and limiting access where necessary.
Contractor will be responsible to work with COR on schedule.
2. Water may be available at all sites for construction purposes. Access will be coordinated with COR.
3. Utilities may be available at all sites for construction purposes.
4. Bathroom facilities will not be available at all sites.
1.6 WASTE MANAGEMENT AND DISPOSAL
A. Waste Management Plan: Submit a copy of plan within 14 days of date established for the Notice to Proceed.
B. Processing waste material for salvage and recycling is encouraged.
http://www.access-board.gov/adaag/html/adaag.htm
GENERAL SPECIFICATIONS 3
C. The contractor shall provide and maintain appropriate waste disposal containers or bins at the project site for the duration of the project construction. Verify with Contracting
Office for placement of disposal containers and bins on the project site.
D. Waste material and debris shall be picked up and deposited in the waste disposal bins on a daily basis. Containers must be emptied on a weekly basis unless more frequent emptying is needed.
E. Burning/burying of construction waste material on the site will not be permitted. Material shall be disposed of in accordance with the Waste Material Disposal specification.
1.7 TRAFFIC CONTROL AND CONSTRUCTION SIGNING
A. No work that endangers, interferes, or conflicts with traffic or access to work sites shall be performed until a plan for satisfactory warning and handling of traffic has been submitted by the contractor and approved by the CO. Construction signing for traffic control shall conform to the Manual of Uniform Traffic Control Devices (MUTCD). All traffic control signs will be placed in areas adequate for a truck pulling a fifth wheel trailer to be turned around. Contractor shall not be paid directly for this item, rather it will be considered incidental to other items of work listed in the Schedule of Items.
B. Signing and barricades shall be adequate to protect Forest Service employees and the public.
1.8 WORK CAMPS, STAGING AND STORAGE AREAS
A. Areas for staging operations and storage of materials shall be approved by the CO.
B. Confine storage of materials and equipment as approved by the Contracting Officer.
C. Contractor shall maintain access to the facilities for Forest Service personnel.
1.9 INSPECTION OF WORKSITE
A. The contractor acknowledges they have taken the necessary steps to ascertain the nature and location of work and have investigated and satisfied themselves as to the general and local conditions that can affect the work or its cost. Any failure of the contractor to take the actions described and acknowledged in this paragraph will not relieve the Contractor from the responsibility of estimating properly the difficulty and cost of successfully performing the work, or for proceeding to successfully perform the work without additional expenses to the government.
1.10 START DATE
A. April 2024
1.11 CONTRACT TIME
A. 90 Calendar Days
END OF SECTION C
GENERAL SPECIFICATIONS 4
November 2023
SECTION 011250 - MEASUREMENT AND PAYMENT
SECTION 011400 - WORK RESTRICTIONS
SECTION 011700 - ACCIDENT PREVENTION
SECTION 011900 - MOBILIZATION
SECTION 013300 - SUBMITTAL PROCEDURES
SECTION 014100 - QUALITY CONTROL
SECTION 017320 - SELECTIVE DEMOLITION
SECTION 024102 - REMOVAL AND DISPOSAL OF STRUCTURES AND
OBSTRUCTIONS
SECTION 150500 - BASIC MECHANICAL MATERIALS AND METHODS
SECTION 156710 - CONDENSING UNITS
SECTION 232300 - REFRIGERANT PIPING
SECTION 236313 - AIR-COOLED REFRIGERANT CONDENSERS
SECTION 238216.13 - REFRIGERANT AIR COILS
SECTION 260000 - COMMON WORK RESULTS FOR ELECTRICAL
MEASUREMENT AND PAYMENT 011250-1
PART 3 -
USDA FOREST SERVICE, R4
Forest Wide Tree Cooler Renovation
SECTION 011250 - MEASUREMENT AND PAYMENT
PART 4 - GENERAL
4.1 SUMMARY
A. Measurement and payment for contract work will be made only for and under those pay items included in the Schedule of Items. All other work, labor, materials, equipment, and incidentals necessary to successfully complete the project will be considered as included in the payment for items shown. This section defines the method of measurements and basis of payment for work items listed in the Schedule of Items.
B. When more than one class, size, type, thickness, etc. is specified in the Schedule of Items for any pay item, suffixes will be added to the item number to differentiate between the pay items.
4.2 DETERMINATION OF QUANTITIES
A. The following measurements and calculations shall be used to determine contract quantities for payment.
1. For individual construction items, longitudinal and lateral measurements for area computations shall be made horizontally or corrected to horizontal measurement unless otherwise specified. Measurements for geotextiles, netting and erosion control blankets shall be along slope lines.
2. For excavation or embankment volumes, the average end area method shall be used to compute volumes. However, if in the judgment of the Contracting Officer (CO), the average end area method is impractical, measurement shall be made by volume in hauling vehicles or by other three-dimensional methods.
3. For Structures, they shall be measured according to neat lines shown on the drawings or as altered by the CO, in writing, to fit field conditions.
4. For items that are measured by the linear foot, such as pipe culverts, fencing, guardrail, piping, utilities, and underdrains, measurements shall be made parallel to the base or foundation upon which the structures are placed.
5. For aggregates weighed for payment, the tonnage shall not be adjusted for moisture content, unless otherwise provided for.
6. For standard manufactured items (such as fence, wire, plates, rolled shapes, pipe conduits) identified by gauge, weight, section dimensions, and so forth, such identifications shall be considered the nominal weights or dimensions. Unless controlled by tolerances in cited specifications, manufacturer's tolerances shall be accepted.
MEASUREMENT AND PAYMENT 011250-2
B. Earthwork Tolerances - Adjustments of horizontal or vertical alignment, within the tolerances specified in this contract, or shifts of balance points up to 100 feet shall be made by the contractor as necessary to produce the designed sections and to balance earthwork. Such adjustments shall not be considered as "Changes."
4.3 UNITS OF MEASUREMENT
A. Payment shall be by units defined and determined according to U.S. Standard measure and by the following:
1. Acre: Make longitudinal and transverse measurements for area computations horizontally.
2. 50lb Bag: Measurement will be for the actual number of 50lb bags of standard bentonite grout.
3. 94lb Bag: Measurement will be for the actual number of 94lb bags of standard cement or grout.
4. Cubic Yard (CY): A measurement computed by one of the following methods:
Excavation, Embankment, or Borrow. The measurement computed by the average end area method from measurements made longitudinally along a centerline or reference line.
Material in Place or Stockpile. The measurement computed using the dimensions of the in-place material.
Material in the Delivery Vehicle. The measurement computed using measurements of material in the hauling vehicles at the point of delivery. Vehicles shall be loaded to at least their water level capacity. Leveling of the loads may be required when vehicles arrive at the delivery point.
5. Each (EA): One complete unit, which may consist of one or more parts.
6. Gallons (GAL): The quantity shall be measured by any of the following methods:
Measured volume in container.
Metered volume by approved metering system.
Commercially package volume.
7. Hour (HR): Measurement will be for the actual number of hours (or fraction thereof) ordered by the Contracting Officer and performed by the contractor.
8. Linear Foot (LF): Measurement of work along its length from point-to-point;
parallel to the base or foundation. Do not measure overlaps.
9. Lump Sum (LS): One complete unit.
10. Mile: Measured horizontally along the centerline of each roadway, approach, or ramp.
11. Pound (LB): For sacked or packaged material, measurement will be the net weight as packed by the manufacturer.
12. Square Foot (SF): Measured on a plane parallel to the surface being measured.
13. Square Yard (SY): Measured on a plane parallel to the surface being measured.
14. Ton: Measured as a short ton consisting of 2,000 pounds.
4.4 METHOD OF MEASUREMENT
MEASUREMENT AND PAYMENT 011250-3
A. One of the following methods of measurement for determining final payment is designated on the Schedule of Items for each pay item:
1. ACTUAL QUANTITIES (AQ) - These quantities are determined from actual measurements of completed work.
2. DESIGNED QUANTITIES (DQ) - These quantities denote the final number or units to be paid for under the terms of the contract. They are based upon the original design data available prior to advertising the project. Original design data include the preliminary survey information, design assumptions, calculations, drawings, and the presentation in the contract. Changes in the number of units shown in the
Schedule of Items may be authorized under any of the following conditions:
As a result of changes in the work authorized by the CO.
As a result of the CO determining that errors exist in the original design that cause a pay item quantity to change by 15 percent or more.
As a result of the Contractor submitting to the CO a written request showing evidence of errors in the original design that cause a pay item quantity to change by 15 percent or more. The evidence must be verifiable and consist of calculations, drawings, or other data that show how the designed quantity is believed to be in error.
3. LUMP SUM QUANTITIES (LSQ) - These quantities denote one complete unit of work as required by or described in the contract, including necessary materials, equipment, and labor to complete the job. They shall not be measured.
4. STAKED QUANTITIES (SQ) - These quantities are determined from staked measurements prior to construction.
5. VEHICLE QUANTITIES (VQ) - These quantities are measured or weighed in hauling vehicles.
PART 5 - PRODUCTS (NOT APPLICABLE)
PART 6 - EXECUTION (NOT APPLICABLE)
END OF SECTION 011250
June 2024
WORK RESTRICTIONS 011400-1
USDA FOREST SERVICE, R4
Forest Wide Tree Cooler Renovation
SECTION 011400 - WORK RESTRICTIONS
PART 1 - GENERAL
1.1 USE OF PREMISES
A. Use of Site: Limit use of premises to work in areas indicated. Do not disturb portions of site beyond areas in which the Work is indicated.
1. Limits: NA
2. Government Occupancy: Allow for Government occupancy of site and use by the public.
3. Driveways and Entrances: Keep driveways and entrances serving premises clear and available to Occupants, Government employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials.
Schedule deliveries to minimize use of driveways and entrances.
Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.
B. Use of Existing Building: Maintain existing building in a weathertight condition throughout construction period. Repair damage caused by construction operations.
Protect building and its occupants during construction period.
1.2 OCCUPANCY REQUIREMENTS
A. Full Government Occupancy: Government will occupy site and existing building during entire construction period. Cooperate with Government during construction operations to minimize conflicts and facilitate Government usage. Perform the Work so as not to interfere with Government operations.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 011400
ACCIDENT PREVENTION 011700-1
Forest Wide Tree Cooler Renovation
SECTION 011700 - ACCIDENT PREVENTION
PART 1 - GENERAL
1.1 DESCRIPTION
A. The work of this section consists of establishing an effective accident prevention program and providing a safe environment for all personnel and visitors.
1.2 SUBMITTALS
A. Accident Prevention Program: Before on-site work begins, submit for approval an accident prevention program. The Contracting Officer (CO) will review the proposed program for compliance with OSHA and project requirements. If the program requires any revisions or corrections, the Contractor shall resubmit the program within 10 days.
No progress payments will be processed until the program is approved. The program shall include:
1. Name of responsible supervisor to carry out the program.
2. Weekly and monthly safety meetings.
3. First aid procedures.
4. Outline of each phase of the work, the hazards associated with each major phase, and the methods proposed to ensure property protection and safety of the public, government personnel, and the Contractor's employees. Identify the work included under each phase by reference to specification section or division numbers.
5. Training, both initial and continuing.
6. Planning for possible emergency situations, such as floods, fires, cave-ins, slides, explosions, power outages, and wind storms. Such planning shall take into consideration the nature of construction, site conditions, and degree of exposure of persons and property.
B. Certificates: Provide certificates from a mechanic that all mechanical equipment has been inspected and meets OSHA requirements.
C. Submit a copy of test reports, as required by OSHA, for personnel working with hazardous materials.
D. Submit a brief report of safety meetings and of inspections.
E. Upon request, submit proof of employees' qualifications to perform assigned duties in a safe manner.
1.3 QUALITY ASSURANCE
A. Clauses entitled "Accident Prevention" and "Permits and Responsibilities" of the General
Provisions. In case of conflicts between Federal, state, and local safety and health requirements, the most stringent shall apply. Equipment or tools not meeting OSHA
ACCIDENT PREVENTION 011700-2
requirements will not be allowed on the project sites. Failure to comply with the requirements of this section and related sections may result in suspension of work.
B. Qualifications of Employees
1. Ensure that employees are physically qualified to perform their assigned duties in a safe manner.
2. To as great an extent as possible, do not allow employees to work whose ability or alertness is impaired because of drugs, fatigue, illness, intoxication, or other conditions that may expose themselves or others to injury.
3. Operators of vehicles, mobile equipment, hoisting equipment, and hazardous plant equipment shall be able to understand signs, signals, and operating instructions, and be capable of operating such equipment. Provide operating instructions for all equipment. Newly hired operators shall be individually tested by an experienced operator or supervisor to determine if they are capable of safely operating equipment.
1.4 ACCIDENT REPORTING
A. Reportable Accidents: A reportable accident is defined as death, occupational disease, traumatic injury to employees or the public, property damage by accident in excess of
$100, and fires. Within 7 days of a reportable accident, fill out and forward to the CO a
DI-134 form, which may be obtained from CO.
B. All Other Accidents: The Contractor shall report all other accidents to the CO as soon as possible and assist the CO and other officials as required in the investigation of the accident.
PART 2 - PRODUCTS
2.1 FIRST AID FACILITIES: provide adequate facilities for the number of employees and the type of construction at the site.
2.2 PERSONNEL PROTECTIVE EQUIPMENT: meet requirements of NIOSH and MSHA, where applicable, as well as ANSI.
2.3 BARRIERS: see division 1 section “Temporary Facilities and Controls” for barriers.
PART 3 - EXECUTION
3.1 EMERGENCY INSTRUCTIONS: post telephone numbers and reporting instructions for ambulance, physician, hospital, fire department, and police in conspicuous locations at the work site.
3.2 ESCAPE ROUTES: provide and maintain adequate escape routes at all times in accordance with the Life Safety Code (NFPA 101-91). No corridor, aisle, stairway, door, or exit shall be obstructed or used in a manner that interferes with escape routes.
ACCIDENT PREVENTION 011700-3
3.3 PROTECTIVE EQUIPMENT
A. Inspect personal protective equipment daily and maintain in a serviceable condition.
Clean, sanitize, and repair, as appropriate, personal items before issuing them to another individual.
B. Inspect and maintain other protective equipment and devices before use and on a periodic basis to ensure safe operation.
3.4 SAFETY MEETINGS
A. As a minimum, conduct weekly 15-minute "toolbox" safety meetings. These meetings shall be conducted by a foreman and attended by all construction personnel at the worksite.
B. Conduct monthly safety meetings for all levels of supervision. Notify the CO so that he may attend. These meetings shall be used to review the effectiveness of the Contractor's safety effort, to resolve current health and safety problems, to provide a forum for planning safe construction activities, and for updating the accident prevention program.
The CO will enter the results of the meetings into his daily log.
3.5 HARD HATS AND PROTECTIVE EQUIPMENT AREAS
A. A hard hat area will be designated by the CO. The hard hat area shall be posted by the
Contractor in a manner satisfactory to the CO.
B. It is the Contractor's responsibility to require all those working on or visiting the site to wear hard hats and other necessary protective equipment at all times. As a minimum, provide six hard hats for use by visitors. Change liners before reissuing hats.
3.6 TRAINING
A. First Aid: Provide adequate training to ensure prompt and efficient first aid.
B. Hazardous Material: Train and instruct each employee exposed to hazardous material in safe and approved methods of handling and storage. Hazardous materials are defined as explosive, flammable, poisonous, corrosive, oxidizing, irritating, or otherwise harmful substances that could cause death or injury.
END OF SECTION 011700
MOBILIZATION 011900-1
Forest Wide Tree Cooler Renovation
SECTION 011900 - MOBILIZATION
PART 1 - GENERAL
1.1 SUMMARY
A. This item is intended to compensate the Contractor for operations including, but not limited to, those necessary for the movement of personnel, equipment, supplies, and incidentals to the project site; for payment of premiums for bonds and insurance for the project; and for any other work and operations which must be performed or costs that must be incurred incident to the initiation of meaningful work at the site and for which payment is not otherwise provided for under the contract.
1.2 MEASUREMENT AND PAYMENT
A. The measurement shall be lump sum for mobilization. Payment shall be as follows:
1. Bond premiums will be reimbursed after receipt of the evidence of payment.
2. 50% of the lump sum, not to exceed 5% of the original contract amount, will be paid following completion of 5% of the original contract amount not including mobilization and bond premiums.
3. Payment of the remaining portion of the lump sum, up to 10% of the original contract amount, will be paid following completion of 10% of the original contract amount not including mobilization and bond premiums.
4. Any portion of the lump sum in excess of 10% of the original contract amount will be paid after final acceptance.
5. Progress payments for mobilization and preparatory work shall be subject to retainage.
PART 2 - PRODUCTS (NOT USED)
PART 3 - EXECUTION (NOT USED)
END OF SECTION 011900
SUBMITTAL PROCEDURES 013300-1
Forest Wide Tree Cooler Renovation
SECTION 013300 - SUBMITTAL PROCEDURES
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes administrative and procedural requirements for submitting Shop
Drawings, Product Data, Samples, and other miscellaneous submittals. See Table
013300-1 for a summary of required submittals.
B. See other specification section within this package for additional requirements on submittal.
1.2 SUBMITTAL PROCEDURES
A. Coordination: Coordinate preparation and processing of submittals with performance of construction activities.
1. Coordinate transmittal of different types of submittals for related parts of the Work so processing will not be delayed because of need to review submittals concurrently for coordination.
The Contracting Officer (CO) reserves the right to withhold action on a submittal requiring coordination with other submittals until related submittals are received.
B. Processing Time: Allow enough time for submittal review, including time for re-submittals, as follows. Time for review shall commence on CO's receipt of submittal.
1. Initial Review: Allow 14 days for initial review of each submittal. Allow additional time if processing must be delayed to permit coordination with subsequent submittals. CO will advise Contractor when a submittal being processed must be delayed for coordination.
2. If intermediate submittal is necessary, process it in same manner as initial submittal.
3. Allow 14 days for processing each re-submittal.
4. No extension of the Contract Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing.
C. Identification: Place a permanent label or title block on each submittal for identification.
1. Indicate name of firm or entity that prepared each submittal on label or title block.
2. Provide a space on label or beside title block to record Contractor's review and approval markings and action taken by CO.
3. Include the following information on label for processing and recording action taken:
Project name.
Date.
SUBMITTAL PROCEDURES 013300-2
Name and address of Contractor.
Name of manufacturer.
Unique identifier, including revision number.
Number and title of appropriate Specification Section.
Drawing number and detail references, as appropriate.
If more than one item is shown on submittal sheet, identify item.
D. Deviations: Highlight, encircle, or otherwise identify deviations from the Contract
Documents on submittals.
E. Additional Copies: Unless additional copies are required for final submittal, and unless
CO observes noncompliance with provisions of the Contract Documents, initial submittal may serve as final submittal.
F. Use for Construction: Use only final submittals with mark indicating action taken by CO in connection with construction.
1.3 MEASUREMENT AND PAYMENT
A. No separate measurement and/or payment will be made for this section. Payment shall be included with work shown in the schedule of items.
PART 2 - PRODUCTS
2.1 ACTION SUBMITTALS – (Submittals requiring CO approval)
A. General: Prepare and submit Action Submittals required by individual Specification
Sections.
1. Number of Copies: Submit three copies of each submittal, unless otherwise indicated. CO will return two copies. Mark up and retain one returned copy as a
Project Record Document.
B. Product Data: Collect information into a single submittal for each element of construction and type of product or equipment.
1. If information must be specially prepared for submittal because standard printed data are not suitable for use, submit as Shop Drawings, not as Product Data.
2. Mark each copy of each submittal to show which products and options are applicable.
3. Include the following information, as applicable:
Manufacturer's written recommendations.
Manufacturer's product specifications.
Manufacturer's installation instructions.
Manufacturer's catalog cuts.
Wiring diagrams showing factory-installed wiring.
Compliance with recognized trade association standards.
Compliance with recognized testing agency standards.
SUBMITTAL PROCEDURES 013300-3
C. Shop Drawings: Prepare Project-specific information, drawn accurately to scale. Do not base Shop Drawings on reproductions of the Contract Documents or standard printed data.
1. Preparation: Include the following information, as applicable:
Dimensions.
Identification of products.
Fabrication and installation drawings.
Roughing-in and setting diagrams.
Wiring diagrams showing field-installed wiring, including power, signal, and control wiring.
Notation of dimensions established by field measurement.
2. Wiring Diagrams: Differentiate between manufacturer-installed and field-installed wiring.
D. Contractor's Construction Schedule: The contractor shall submit a Construction
Schedule, for approval by CO, in accordance with the contract provisions within 5 day of commencement of work.
E. Samples: Prepare physical units of materials or products, including the following:
1. Samples for Initial Selection: Submit manufacturer's color charts consisting of units or sections of units showing the full range of colors, textures, and patterns available.
2.2 INFORMATIONAL SUBMITTALS – (Submittals NOT requiring CO approval)
A. General: Prepare and submit Informational Submittals required by other Specification
Sections.
1. Number of Copies: Submit three copies of each submittal, unless otherwise indicated. CO will not return copies.
2. Certificates and Certifications: Certificates and certifications shall be signed by an officer or other individual authorized to sign documents on behalf of that entity.
3. Test and Inspection Reports: Comply with requirements in Section 014100
"Quality Control."
B. Material Test Reports: Prepare reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting test results of material for compliance with requirements.
C. Field Test Reports: Prepare reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting results of field tests performed either during installation of product or after product is installed in its final location, for compliance with requirements.
D. Maintenance Data: Prepare written and graphic instructions and procedures for operation and normal maintenance of products and equipment.
SUBMITTAL PROCEDURES 013300-4
E. Manufacturer's Instructions: Prepare written or published information that documents manufacturer's recommendations, guidelines, and procedures for installing or operating a product or equipment. Include name of product and name, address, and telephone number of manufacturer.
PART 3 - EXECUTION
3.1 GENERAL
A. Review each submittal and check for compliance with the Contract Documents. Note corrections and field dimensions. Mark with approval stamp before submitting to CO.
B. Approval Stamp: Stamp each submittal with a uniform, approval stamp. Include Project name and location, submittal number, Specification Section title and number, name of reviewer, date of Contractor's approval, and statement certifying that submittal has been reviewed, checked, and approved for compliance with the Contract Documents.
C. CO will not review submittals that do not bear Contractor's approval stamp and will return them without action.
D. Submittals not required by the Contract Documents will not be reviewed and may be discarded.
E. Substitutions – Whenever materials, products, and equipment are listed by name or brand in the specifications and/or on the drawings, it is used as a measure of quality, utility, or standard. If the Contractor prefers to use any other brand or manufacturer of same quality, appearance and utility to that specified, he shall request substitution as provided below, not less than 30 days before the planned installation of the item. The Contracting Officer will approve or disapprove the request for substitution.
F. Requests for substitutions will only be considered if contractor submits the following:
1. Complete technical data including drawings, complete performance specifications, test data, samples and performance tests of the article proposed for substitution.
Submit additional information if required by Contracting Officer. All items in the above information shall be circled, tagged, or marked in some way to indicate all deviations or differences which the proposed item differs from the originally specified item.
2. Similar data as above for item originally specified. All items shall be marked to identify where/how the proposed substitution will differ.
3. A statement by the Contractor that the proposed substitution is in full compliance with the contract documents, applicable codes, and laws.
4. The Contractor shall be responsible for any effect upon related work in the project for any substitution and shall pay any additional costs generated by any substitutions.
3.2 SUBMITTAL SCHEDULE – Submittals shall be made as required by and called for in the drawings and specifications. The following table is a summary of the required
SUBMITTAL PROCEDURES 013300-5
submittals for the project - the table is to assist the Contractor and may not be all inclusive
– additional submittals may be required by specific specifications:
TABLE 013000-1
Spec.
Section Section Title
Subse ction Required Submittal
013300 Submittal Procedures 2.1D Construction Schedule
014100 Quality Control 1.3 A Contractor quality control plan
014100 Quality Control 1.3 B Permits, Licenses, and Certificates
014100 Quality Control 1.3 C Test and inspection reports
014100 Quality Control 1.3 D As-Built drawings
END OF SECTION 013300
QUALITY CONTROL 014100-1
Forest Wide Tree Cooler Renovation
SECTION 014100 - QUALITY CONTROL
PART 1 - GENERAL
1.1 This work shall consist of providing quality control in conformance with the inspection, testing, and product certification requirements of this contract to ensure compliance with the drawings and specifications. The Contractor shall provide all personnel, equipment, tests, and reports necessary to meet the requirements of the contract.
1.2 QUALITY CONTROL
A. The Contractor shall provide and maintain a quality control system that will ensure all services, supplies, and construction work required under this contract conforms to the contract requirements. The Contractor shall perform, or cause to be performed, the sampling, inspection, and testing required to substantiate that all services, supplies, and construction conform to the contract requirements.
B. Special Tests and Inspections: Contractor will engage a testing agency to conduct required special tests and inspections. The Contractor shall authorize the testing agency to perform the required testing and inspections on the work completed. The authority shall include:
1. Testing agency will interpret tests and inspections and state in each report whether tested and inspected work complies with or deviates from the Contract Documents.
2. Testing agency will re-test and re-inspect corrected work.
C. Retesting/Reinspecting: Contractor shall provide quality-control services for retesting and reinspection for replaced construction work or for work that failed to comply with the requirements under the contract.
1.3 SUBMITTALS
A. Contractor Quality Control Plan
B. Permits, Licenses, and Certificates
C. Test and Inspection Reports
D. As-Built Drawings
1.4 MEASUREMENT AND PAYMENT
A. No separate payment will be made for the work included under this section; rather payment shall be considered to be included in the items of work listed in the Schedule of
Items.
PART 2 - PRODUCTS (Not Applicable)
QUALITY CONTROL 014100-2
PART 3 - EXECUTION
3.1 QUALITY CONTROL SYSTEM
A. General: Perform required testing, inspections, sampling, and similar services per direction specified in the contract drawings and specifications and in accordance with established industry standards.
3.2 CONTRACTOR QUALITY CONTROL PLAN
A. At the time of the preconstruction conference, the Contractor shall submit for approval a written Contractor Quality Control Plan.
1. If the plan requires any revisions or corrections, the Contractor shall resubmit the plan within 10 days.
2. The Government reserves the right to require changes in the plan during the contract period as necessary.
3. No change in the approved plan may be made without written concurrence by the
Contracting Officer.
4. At a minimum, the plan shall include the following:
A list of personnel responsible for quality control and assigned duties. Include each person's qualifications.
A copy of a letter of direction to the Contractor's Quality Control Supervisor outlining assigned duties.
Names, qualifications, and descriptions of laboratories to perform sampling and testing, and samples of proposed report forms.
Methods of performing, documenting, and enforcing quality control of all work.
Methods of monitoring and controlling environmental pollution and contamination as required by all applicable regulations and laws.
3.3 TEST AND INSPECTION REPORTS
A. Submit three copies of complete test results no later than three calendar days after the test was performed.
B. Submit failing test results and proposed remedial actions within four hours of noted deficiency.
C. Testing and Inspection Reports shall include the following:
1. Date of issue.
2. Project title and number.
3. Name, address, and telephone number of testing agency.
4. Dates and locations of samples, tests, or inspections.
5. Names of individuals performing tests and inspections.
6. Reference Specification Section(s).
7. Complete test or inspection data.
8. Test and inspection results and an interpretation of test results.
QUALITY CONTROL 014100-3
9. Ambient conditions at time sample was taken, tested, or inspected.
10. Comments or professional opinion on whether tested or inspected work complies with the Contract Document requirements.
11. Name and signature of laboratory inspector.
12. Recommendations on retesting and reinspecting.
3.4 PERMITS, LICENSES, AND CERTIFICATES
A. For Contracting Officer’s records, submit copies of permits, licenses, certifications, inspection reports, releases, jurisdictional settlements, notices, receipts for fee payments, judgments, correspondence, records, and similar documents, established for compliance with standards and regulations relevant to the on performance of the work.
3.5 AS-BUILT DRAWINGS
A. The Contractor shall maintain a set of the contract drawings depicting as-built conditions.
These drawings shall be maintained in a current condition and shall be available for review. All variations from the original contract drawings shall be indicated in red on the drawings. Upon completion of the contract work, as-built drawings shall be submitted to the Contracting Officer.
3.6 SAMPLING, TESTING, AND CERTIFICATION REQUIREMENTS
A. Sampling, testing, and Certification requirements and frequency for specific items shall be as specified in the drawings and specification. The following table is a summary of the required sampling, testing, and certification for the project - the table is to assist the
Contractor, but may not be all inclusive – additional submittals may be required by specific specification section:
B.
END OF SECTION 014100
SELECTIVE DEMOLITION 017320-1
Forest Wide Tree Cooler Renovation
SECTION 017320 - SELECTIVE DEMOLITION
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes demolition and removal of the following:
1. Selected portions of a building.
2. Repair procedures for selective demolition operations.
1.2 DEFINITIONS
A. Remove: Detach items from existing construction and legally dispose of them off-site, unless indicated to be removed and salvaged or removed and reinstalled.
B. Remove and Salvage: Detach items from existing construction and deliver them to
Government.
C. Remove and Reinstall: Detach items from existing construction, prepare them for reuse, and reinstall them where indicated.
D. Existing to Remain: Existing items of construction that are not to be removed and that are not otherwise indicated to be removed, removed and salvaged, or removed and reinstalled.
1.3 MATERIALS OWNERSHIP
A. Except for items or materials indicated to be reused, salvaged, reinstalled, or otherwise indicated to remain Government property, demolished materials shall become
Contractor's property and shall be removed from Project site.
1.4 SUBMITTALS
A. Schedule of Selective Demolition Activities: Indicate detailed sequence of selective demolition and removal work, with starting and ending dates for each activity, including interruption of utility services.
B. Waste Manifests for materials deemed hazardous by the State of Utah including refrigerant and fluorescent lights.
1.5 QUALITY ASSURANCE
A. Regulatory Requirements: Comply with governing EPA notification regulations before beginning selective demolition. Comply with hauling and disposal regulations of authorities having jurisdiction.
B. Standards: Comply with ANSI A10.6 and NFPA 241.
SELECTIVE DEMOLITION 017320-2
C. Pre-demolition Conference: Conduct conference at Project site with contractor, subcontractors and Contracting Officer’s Representative.
1.6 PROJECT CONDITIONS
A. Conduct selective demolition so Government operations will not be disrupted. Provide not less than 72 hours' notice to CO of activities that will affect Government operations.
B. Maintain access to existing building amenities, pathways, and other adjacent occupied or used facilities.
1. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from the COR.
C. Government assumes no responsibility for condition of areas to be selectively demolished.
1. Conditions existing at time of inspection for bidding purpose will be maintained by
Government as far as practical.
D. Hazardous Materials, Location to be disposed.
1. 4-foot fluorescent light tubes: Throughout building.
2. Various paint products listed in hazardous waste disposal specification.
E. Hazardous Materials: Additional Hazardous materials were not found to be present in building to be selectively demolished.
1. Do not disturb hazardous materials or items suspected of containing hazardous materials except under procedures specified elsewhere in the Contract Documents.
F. Storage or sale of removed items or materials on-site will not be permitted.
1.7 MEASUREMENT AND PAYMENT
A. There will be no separate measurement or payment for work in this section. Payment will be included at the contract unit price for items shown on the Schedule of Items.
PART 2 - PRODUCTS
2.1 REPAIR MATERIALS
A. Use repair materials identical to existing materials.
1. If identical materials are unavailable or cannot be used for exposed surfaces, use materials that visually match existing adjacent surfaces to the fullest extent possible.
2. Use materials whose installed performance equal or surpasses that of existing materials.
SELECTIVE DEMOLITION 017320-3
3.1 EXAMINATION
A. Verify that utilities have been disconnected and capped.
B. Survey existing conditions and correlate with requirements indicated to determine extent of selective demolition required.
C. When unanticipated mechanical, electrical, or structural elements that conflict with intended function or design are encountered, investigate and measure the nature and extent of conflict. Promptly submit a written report to CO.
3.2 PREPARATION
A. Site Access and Temporary Controls: Conduct selective demolition and debris-removal operations to ensure minimum interference with roads, streets, walks, walkways, and other adjacent occupied and used facilities.
1. Do not close or obstruct roads, without permission from CO. Provide alternate routes around closed or obstructed traffic ways if required by governing regulations.
2. Erect temporary protection, such as walks, fences, railings, canopies, and covered passageways, where required by authorities having jurisdiction.
3. Protect existing site improvements, appurtenances, and landscaping to remain.
B. Temporary Facilities: Provide temporary barricades and other protection required to prevent injury to people and damage to adjacent buildings and facilities to remain.
C. Temporary Enclosures: Provide temporary enclosures for protection of existing building and construction, in progress and completed, from exposure, foul weather, other construction operations, and similar activities. Provide temporary weathertight enclosure for building exterior.
3.3 POLLUTION CONTROLS
A. Dust Control: Use temporary enclosures, and other suitable methods to limit spread of dust and dirt. Comply with governing environmental-protection regulations.
B. Disposal: Remove and transport debris in a manner that will prevent spillage on adjacent surfaces and areas.
1. Remove debris from elevated portions of building by chute, hoist, or other device that will convey debris to grade level in a controlled descent.
C. Cleaning: Clean adjacent structures and improvements of dust, dirt, and debris caused by selective demolition operations. Return adjacent areas to condition existing before selective demolition operations began.
SELECTIVE DEMOLITION 017320-4
3.4 SELECTIVE DEMOLITION
A. General: Demolish and remove existing construction only to the extent required by new construction and as indicated. Use methods required to complete the Work within limitations of governing regulations.
1. Neatly cut openings and holes plumb, square, and true to dimensions required. Use cutting methods least likely to damage construction to remain or adjoining construction.
2. Cut or drill from the exposed or finished side into concealed surfaces to avoid marring existing finished surfaces.
3. Do not use cutting torches until work area is cleared of flammable materials. At concealed spaces, such as duct and pipe interiors, verify condition and contents of hidden space before starting flame-cutting operations. Maintain portable fire-suppression devices during flame-cutting operations.
4. Locate selective demolition equipment and remove debris and materials so as not to impose excessive loads on supporting walls, floors, or framing.
5. Use cardboard or a drum to store fluorescent lighting to prevent breakage. Label the container clearly as ““Universal Waste Mercury-Containing Lamp(s)”
6. Demo condensing units and drinking fountain in a manner that will not release refrigerant.
7. Dispose of universal hazardous waste as required by EPA and State laws. A disposal site is listed above.
B. Removed and Reinstalled Items:
1. Clean and repair items to functional condition adequate for intended reuse. Paint equipment to match new equipment.
2. Pack or crate items after cleaning and repairing. Identify contents of containers.
3. Protect items from damage during transport and storage.
4. Reinstall items in locations indicated. Comply with installation requirements for new materials and equipment. Provide connections, supports, and miscellaneous materials necessary to make item functional for use indicated.
C. Existing Items to Remain: Protect construction indicated to remain against damage and soiling during selective demolition. When permitted by CO, items may be removed to a suitable, protected storage location during selective demolition and cleaned and reinstalled in their original locations after selective demolition operations are complete.
3.5 PATCHING AND REPAIRS
A. General: Promptly repair damage to adjacent construction caused by selective demolition operations.
B. Repairs: Where repairs to existing surfaces are required, patch to produce surfaces suitable for new materials.
1. Completely fill holes and depressions in existing masonry walls that are to remain with an approved masonry patching material applied according to manufacturer's written recommendations.
SELECTIVE DEMOLITION 017320-5
C. Finishes: Restore exposed finishes of patched areas and extend restoration into adjoining construction in a manner that eliminates evidence of patching and refinishing.
D. Floors and Walls: Where walls or partitions that are demolished extend one finished area into another, patch and repair floor and wall surfaces in the new space. Provide an even surface of uniform finish color, texture, and appearance. Remove existing floor and wall coverings and replace with new materials, if necessary, to achieve uniform color and appearance.
E. Ceilings: Patch and repair existing ceilings as necessary to provide an even-plane surface of uniform appearance.
3.6 DISPOSAL OF DEMOLISHED MATERIALS
A. General: Promptly dispose of demolished materials. Do not allow demolished materials to accumulate on-site.
B. Dispose of universal hazardous waste as required above.
C. Burning: Do not burn demolished materials.
D. Disposal: Transport demolished materials off Government property and legally dispose of them.
END OF SECTION 017320
FEBRUARY 2022
REMOVAL AND DISPOSAL OF STRUCTURES AND OBSTRUCTIONS 024102-1
Forest Wide Tree Cooler Renovation
SECTION 024102 - REMOVAL AND DISPOSAL OF STRUCTURES AND OBSTRUCTIONS
PART 1 - GENERAL
1.1 SUMMARY
A. Includes removal disposal, and backfilling of existing septic tanks, water and sewer lines, valves, concrete pads and walkways, utilities and all other items to the extent shown on the Drawings. This item also includes scarifying and regrading the area around features and structures removed.
B. Related Sections Include the Following:
1. Section 024100 “Waste Material Disposal.”
2. Section 329206 “Seeding.”
1.2 MEASUREMENT AND PAYMENT
A. There will be no separate measurement or payment for this item.
PART 2 - PRODUCTS
2.1 SELECT BACKFILL
A. Select backfill shall be native or imported soil, sand, or granular soil free of stones larger than 6 inches in greatest dimension.
PART 3 - EXECUTION
3.1 GENERAL
A. Topsoil stripping and storage, if required, shall comply with the applicable specification.
B. The Contractor may use any means to remove the structures or items shown on the
Drawings to be removed, as long as the safety of the public is provided and the surrounding site and structures are preserved
C. All of a substructure shall be demolished to a depth of 1 foot below the present ground level. All wood, concrete, and metal materials to be removed shall be broken into sufficiently small pieces to enable handling and disposal. All other structures shall be backfilled and the surrounding ground restored to as near normal conditions as practicable in accordance with these specifications.
D. Backfill for removed items may be excess material from other excavation or borrow from an approved source.
1. Backfill shall be brought up in 12-inch compacted layers.
REMOVAL AND DISPOSAL OF STRUCTURES AND OBSTRUCTIONS 024102-2
2. Compaction shall be by mechanical tampers, with at least three passes over the entire surface.
3. Maximum size of rock in backfill shall be 8 inches.
4. Backfill shall be compacted and rounded 6 inches above the natural ground.
5. If the backfill is not in an existing roadway or parking area, and at least 20 feet away from any proposed structure, the backfill…