1240LT22P0044 - Bessey Nursery Garage Door Replacement.pdf

PDF 504 KB Posted

Attached to
Bessey Nursery Garage Door Replacement
Solicitation number
1240LT22P0044
Issued by

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ORDER FOR SUPPLIES OR SERVICES

3. ORDER NO. 4. REQUISITION/REFERENCE NO.

PAGE OF PAGES

5. ISSUING OFFICE (Address correspondence to) b. STREET ADDRESS

IMPORTANT: Mark all packages and papers with contract and/or order numbers. 1

1. DATE OF ORDER 2. CONTRACT NO. (If any) 6. SHIP TO:

a. NAME OF CONSIGNEE

c. CITY d. STATE e. ZIP CODE

7. TO:

a. NAME OF CONTRACTOR

f. SHIP VIA

8. TYPE OF ORDER

b. COMPANY NAME

c. STREET ADDRESS

d. CITY e. STATE f. ZIP CODE

9. ACCOUNTING AND APPROPRIATION DATA

a. PURCHASE b. DELIVERY

REFERENCE YOUR:

Please furnish the following on the terms and conditions specified on both sides of this order and on the attached sheet, if any, including delivery as indicated.

Except for billing instructions on the reverse, this delivery order is subject to instructions contained on this side only of this form and is issued subject to the terms and conditions of the above-numbered contract.

10. REQUISITIONING OFFICE

11. BUSINESS CLASSIFICATION (Check appropriate box(es))

a. SMALL b. OTHER THAN SMALL c. DISADVANTAGED d. WOMEN-OWNED

13. PLACE OF

a. INSPECTION b. ACCEPTANCE

14. GOVERNMENT B/L NO. 15. DELIVER TO F.O.B. POINT

ON OR BEFORE (Date)

16. DISCOUNT TERMS

17. SCHEDULE (See reverse for Rejections)

09/29/2022

1240LT22P0044 1065604

USDA-FS CSA INTERMOUNTAIN 8

324 25TH ST

OGDEN UT 84401-2310

MAGGIE HENNEK

WEATHERCRAFT CO OF NORTH PLATTE

PO BOX 1949

NORTH PLATTE NE 69103-1949

12. F.O.B. POINT

60 Days After Notice to

Proceed

DEPT OF AGRICULTURE FOREST SERVICE

BESSEY NURSERY

40637 RIVER LOOP

HALSEY NE 69142

Solicitation 1240LT22Q0153

Quote dated 09/16/2022

NEBRASKA NATIONAL FOREST

ITEM NO.

(a)

SUPPLIES OR SERVICES

(b)

QUANTITY

ORDERED

(c)

UNIT

(d)

UNIT

PRICE

(e)

AMOUNT

(f)

QUANTITY

ACCEPTED

(g)

X

X

Destination Destination

f. SERVICE-DISABLED

VETERAN-OWNED

e. HUBZone

g. WOMEN-OWNED SMALL BUSINESS (WOSB)

ELIGIBLE UNDER THE WOSB PROGRAM

h. EDWOSB

PROJECT NAME: Bessey Nursery Garage Door Replacement

DESCRIPTION OF WORK: Work for this project consists of, but is not limited to, removal of the existing wooden one-piece overhead Continued ...

19. GROSS SHIPPING WEIGHT18. SHIPPING POINT 20. INVOICE NO.

21. MAIL INVOICE TO:

a. NAME

b. STREET ADDRESS

(or P.O. Box)

c. CITY d. STATE e. ZIP CODE

SEE BILLING

INSTRUCTIONS

ON REVERSE

17(h)

TOTAL

(Cont.

pages)

17(i)

GRAND

TOTAL

$65,405.00

22. UNITED STATES OF

AMERICA BY (Signature)

23. NAME (Typed)

TITLE: CONTRACTING/ORDERING OFFICER

LONNIE D. ROOT

$65,405.00

OPTIONAL FORM 347 (Rev. 2/2012)

Prescribed by GSA/FAR 48 CFR 53.213(f)

AUTHORIZED FOR LOCAL REPRODUCTION

PREVIOUS EDITION NOT USABLE

INVOICE PROCESSING PLATFORM IPP

ALL INVOICES MUST BE SUBMITTED

ELECTRONICALLY THROUGH THE

INVOICE PROCESSING PLATFORM IPP

VIA WWW IPP GOV

DATE OF ORDER

ORDER FOR SUPPLIES OR SERVICES

SCHEDULE - CONTINUATION

CONTRACT NO.

AMOUNTUNIT

PRICE

UNITQUANTITY

ORDERED

SUPPLIES/SERVICESITEM NO.

IMPORTANT: Mark all packages and papers with contract and/or order numbers.

ORDER NO.

QUANTITY

ACCEPTED

09/29/2022 1240LT22P0044

PAGE NO

(a) (b) (c) (d) (e) (f) (g) garage doors and furnishing labor and materials to install specified overhead sectional garage doors and accessories for the Nursery Shop and Nursery Implement

Storage.

PROJECT LOCATION: Bessey Nursery Complex on the Nebraska National Forests and

Grasslands located two (2) miles west of

Halsey, Nebraska. (Thomas County)

CONTRACTOR ACCEPTANCE

1) Work shall be completed in accordance with the attached Statement of Work and all terms and conditions identified herein.

2) All Items are being Awarded.

The terms and conditions of this contract are hereby accepted.

Weathercraft Companies DATE

FMMI Account: FS00.0207FSLM0722 BOC: 2540

Period of Performance: 10/03/2022 to

12/05/2022

0001 Bessey Nursery Garage Door Replacement 65,405.00

Product/Service Code: Z2JZ

Product/Service Description: REPAIR

OR ALTERATION OF MISCELLANEOUS

BUILDINGS

The total amount of award: $65,405.00. The obligation for this award is shown in box

17(i).

Prescribed by GSA FAR (48 CFR) 53.213(f)

OPTIONAL FORM 348 (Rev. 4/2006)AUTHORIZED FOR LOCAL REPODUCTION

PREVIOUS EDITION NOT USABLE

TOTAL CARRIED FORWARD TO 1ST PAGE (ITEM 17(H)) $65,405.00

Award No: 1240LT22P0044 Project Name: Bessey Nursery Garage Door Replacement

Table of Contents

PART I—THE SCHEDULE

SECTION B--SUPPLIES OR SERVICES AND PRICES/COSTS

B.1 SCHEDULE OF ITEMS – Bessey Nursery Garage Door Replacement

B.2 SCHEDULE NOTES

SECTION C--DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK

C.1 SCOPE OF CONTRACT

C.2 PROJECT LOCATON

C.4 TECHNICAL SPECIFICATIONS

452.211-72 Statement of Work/Specifications (FEB 1988)

452.211-73 Attachments to Statements of Work/Specifications (FEB 1988)

SECTION D--PACKAGING AND MARKING

D-1 PACKING AND MARKING

D-2 PROJECT LABELING FOR OFFICIAL COORESPONDENCE

SECTION E--INSPECTION AND ACCEPTANCE

E.1 CLAUSES

SECTION F--DELIVERIES OR PERFORMANCE

F.1 CLAUSES

SECTION G--CONTRACT ADMINISTRATION DATA

G.1 CLAUSES

SECTION H--SPECIAL CONTRACT REQUIREMENTS

H.1 CLAUSES

PART II--CONTRACT CLAUSES

SECTION I--CONTRACT CLAUSES

I.1 CLAUSES

PART III--LIST OF DOCUMENTS, EXHIBITS, AND OTHER ATTACHMENTS

SECTION J--LIST OF ATTACHMENTS

javascript:__doPostBack('ctl00$ctl00$body$homebody$RecentDocuments$C$RecentDocumentsControl$RecentDocumentResults$ctl00$DocumentNumberLink','')

PART I—THE SCHEDULE

SECTION B--SUPPLIES OR SERVICES AND PRICES/COSTS

B.1 SCHEDULE OF ITEMS – Bessey Nursery Garage Door Replacement

Item Supplies/Services Method of Measure

Unit of Issue

Quantity Unit Price Total Price

0001 Mobilization LSQ Lump Sum

1 $4,135.00 $4,135.00

0002 Selective demolition of 5 overhead doors in the Nursery Shop

LSQ Lump Sum

1 $475.00 $475.00

0003 Installation of 5 selected overhead doors in the Nursery Shop

LSQ Lump Sum

1 $23,170.00 $23,170.00

0004 Selective demolition of 8 overhead doors in the Implement Storage building

LSQ Lump Sum

1 $670.00 $670.00

0005 Installation of 8 selected overhead doors in the Implement Storage building

LSQ Lump Sum

1 $36,955.00 $36,955.00

TOTAL ALL ITEMS: $65,405.00

B.2 SCHEDULE NOTES

a) One award will be made from this solicitation, offeror must submit pricing for all items.

b) Payment for bond premiums in accordance with Clause 52.232-5, Payments under Fixed-Price Construction Contracts, shall not be in addition to the contract price. Include bond payments under “Mobilization”.

javascript:__doPostBack('ctl00$ctl00$body$homebody$RecentDocuments$C$RecentDocumentsControl$RecentDocumentResults$ctl00$DocumentNumberLink','')

SECTION C--DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK

C.1 SCOPE OF CONTRACT

Work for this project consists of, but is not limited to, removal of the existing wooden one-piece overhead garage doors and furnishing labor and materials to install specified overhead sectional garage doors and accessories for the following Bessey Nursery buildings:

1. Nursery Shop (03-06)

2. Nursery Implement Storage (03-07)

C.2 PROJECT LOCATON

This project is located on the Bessey Nursery Complex on the Nebraska National Forests and Grasslands located two (2) miles west of Halsey, Nebraska. Thomas County.

C.3 MAGNITUDE OF CONSTRUCTION PROJECT

Between $25,000 and $100,000

C.4 TECHNICAL SPECIFICATIONS

452.211-72 Statement of Work/Specifications (FEB 1988)

The Contractor shall furnish the necessary personnel, material, equipment, services and facilities (except as otherwise specified), to perform the Statement of Work/Specifications referenced in Section J.

(End of Clause)

452.211-73 Attachments to Statements of Work/Specifications (FEB 1988)

The attachments to the Statement of Work/Specifications listed in Section J are hereby made part of this solicitation and any resultant contract.

(End of Clause) javascript:__doPostBack('ctl00$ctl00$body$homebody$RecentDocuments$C$RecentDocumentsControl$RecentDocumentResults$ctl00$DocumentNumberLink','')

SECTION D--PACKAGING AND MARKING

D-1 PACKING AND MARKING

All shipments of materials, equipment and/or supplies shall be addressed to the Contractor and not to the Government.

D-2 PROJECT LABELING FOR OFFICIAL COORESPONDENCE

The Government singularly identifies each project with a contract number at time of award. The contract number is a unique identifier to purposely and permanently represent an awarded project. The Government issued contract number is to be referenced on all official communication starting upon notice of award.

javascript:__doPostBack('ctl00$ctl00$body$homebody$RecentDocuments$C$RecentDocumentsControl$RecentDocumentResults$ctl00$DocumentNumberLink','')

SECTION E--INSPECTION AND ACCEPTANCE

E.1 CLAUSES

52.246-12 Inspection of Construction (AUG 1996) 52.246-13 Inspection-Dismantling, Demolition, or Removal of Improvements (AUG 1996) javascript:__doPostBack('ctl00$ctl00$body$homebody$RecentDocuments$C$RecentDocumentsControl$RecentDocumentResults$ctl00$DocumentNumberLink','')

SECTION F--DELIVERIES OR PERFORMANCE

F.1 CLAUSES

52.211-13 Time Extensions (SEP 2000) 52.211-18 Variation in Estimated Quantity (APR 1984) 52.242-14 Suspension of Work (APR 1984)

52.211-10 Commencement, Prosecution, and Completion of Work (APR 1984)

The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 60 calendar days.

javascript:__doPostBack('ctl00$ctl00$body$homebody$RecentDocuments$C$RecentDocumentsControl$RecentDocumentResults$ctl00$DocumentNumberLink','')

SECTION G--CONTRACT ADMINISTRATION DATA

G.1 CLAUSES

G.2 OTHER REQUIREMENTS

452.215-73 Post Award Conference (NOV 1996)

A post award conference with the successful offeror is required. It will be scheduled and held within 10 days after the date of contract award. The conference will be held at a location to be determined.

G.3 INVOICES & PAYMENTS

All invoices are to be submitted via the electronic Invoice Processing Platform (IPP) System:

The "Submit Invoice-to" address for USDA orders is the Department of Treasury's Invoice processing Platform (IPP). The contractor must follow the instructions on how to register and submit invoices via IPP as prescribed in previous communications from USDA and Treasury.

This is a mandatory requirement initiated by the U.S. Department of Treasury and you can find more information at this website https://www.ipp.gov/index.htm Ensure your company has registered at https://www.ipp.gov/vendors/enrollment-vendors.htm to establish your account.

Offeror must have an established account prior to commencement of work.

Invoice Processing Platform (IPP) does not allow for the contractor to change the description of the line items being invoiced against and therefore an itemized invoice must be uploaded as an attachment(s).

Itemized invoice shall include at a minimum:

Contractor Name and Address Contract, Task Order or Purchase Order numbers Invoice Number Description of Services or work completed.

Date of services or completion.

javascript:__doPostBack('ctl00$ctl00$body$homebody$RecentDocuments$C$RecentDocumentsControl$RecentDocumentResults$ctl00$DocumentNumberLink','')

SECTION H--SPECIAL CONTRACT REQUIREMENTS

H.1 CLAUSES

452.237-74 Key Personnel (FEB 1988)

(a) The Contractor shall assign to this contract the following key personnel: Project Manager

(b) During the first ninety (90) days of performance, the Contractor shall make no substitutions of key personnel unless the substitution is necessitated by illness, death, or termination of employment. The Contractor shall notify the Contracting Officer within 15 calendar days after the occurrence of any of these events and provide the information required by paragraph (c) below. After the initial 90-day period, the Contractor shall submit the information required by paragraph (c) to the Contracting Officer at least 15 days prior to making any permanent substitutions.

(c) The Contractor shall provide a detailed explanation of the circumstances necessitating the proposed substitutions, complete resumes for the proposed substitutes, and any additional information requested by the Contracting Officer. Proposed substitutes should have comparable qualifications to those of the persons being replaced. The Contracting Officer will notify the Contractor within 15 calendar days after receipt of all required information of the decision on substitutions. The contract will be modified to reflect any approved changes of key personnel.

javascript:__doPostBack('ctl00$ctl00$body$homebody$RecentDocuments$C$RecentDocumentsControl$RecentDocumentResults$ctl00$DocumentNumberLink','')

PART II--CONTRACT CLAUSES

SECTION I--CONTRACT CLAUSES

I.1 CLAUSES

52.252-2 Clauses Incorporated by Reference (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):

Federal Acquisition Regulation (FAR) Clauses:

https://www.acquisition.gov/browse/index/far (FAR clauses begin with 52) Department of Agriculture Acquisition Regulation (AGAR) Clauses:

https://www.acquisition.gov/agar (AGAR clauses begin with 452) Deviations to clauses may be viewed at:

https://www.dm.usda.gov/procurement/policy/FARClassDeviations.htm

52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or

Statements (JAN 2017) 52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards (JUN

2020) 52.204-13 System for Award Management Maintenance (OCT 2018) 52.204-18 Commercial and Government Entity Code Maintenance (AUG 2020) 52.204-19 Incorporation by Reference of Representations and Certifications (DEC 2014) 52.204-23 Prohibition on Contracting for Hardware, Software, and Services Developed or

Provided by Kaspersky Lab and Other Covered Entities (JUL 2018) 52.204-25 Prohibition on Contracting for Certain Telecommunications and Video

Surveillance Services or Equipment (AUG 2020) 52.209-6 Protecting the Government's Interest when Subcontracting with Contractors

Debarred, Suspended, or Proposed for Debarment (JUN 2020) 52.209-10 Prohibition on Contracting with Inverted Domestic Corporations (NOV 2015) 52.215-8 Order of Precedence—Uniform Contract Format (OCT 1997) 52.219-6 Notice of Total Small Business Set-Aside (NOV 2020) 52.219-28 Post Award Small Business Program Representation (SEP 2021) 52.222-3 Convict Labor (JUN 2003) 52.222-6 Construction Wage Rate Requirement (AUG 2018) 52.222-7 Withholding of Funds (MAY 2014) 52.222-8 Payrolls and Basic Records (JUL 2021) 52.222-9 Apprentices and Trainees (JUL 2005) 52.222-10 Compliance with Copeland Act Requirements (FEB 1988) 52.222-11 Subcontracts (Labor Standards) (MAY 2014) 52.222-12 Contract Termination - Debarment (MAY 2014) javascript:__doPostBack('ctl00$ctl00$body$homebody$RecentDocuments$C$RecentDocumentsControl$RecentDocumentResults$ctl00$DocumentNumberLink','') https://www.acquisition.gov/browse/index/far https://www.acquisition.gov/agar https://www.dm.usda.gov/procurement/policy/FARClassDeviations.htm

52.222-13 Compliance with Construction Wage Rate Requirements and Related Regulations

(MAY 2014)

52.222-14 Disputes Concerning Labor Standards (FEB 1988) 52.222-15 Certification of Eligibility (MAY 2014) 52.222-21 Prohibition of Segregated Facilities (APR 2015) 52.222-26 Equal Opportunity (APR 2016) 52.222-27 Affirmative Action Compliance Requirements for Construction (APR 2015) 52.222-30 Construction Wage Rate Requirements-Price Adjustment (None or Separately

Specified Pricing Method) (AUG 2018) 52.222-36 Equal Opportunity for Workers with Disabilities (JUN 2020) 52.222-37 Employment Reports on Veterans (JUN 2020) 52.222-50 Combating Trafficking in Persons (OCT 2020) 52.222-55 Minimum Wages under Executive Order 13658 (NOV 2020) 52.222-62 Paid Sick Leave under Executive Order 13706 (Jan 2017) 52.223-2 Affirmative Procurement of Biobased Products under Service and Construction

Contracts (SEP 2013) 52.223-5 Pollution Prevention and Right-to-Know Information (MAY 2011) 52.223-11 Ozone-Depleting Substances and High Global Warming Potential

Hydrofluorocarbons (Jun 2016) 52.223-17 Affirmative Procurement of EPA-designated Items in Service and Construction

Contracts (AUG 2018) 52.223-18 Encouraging Contractor Policies to Ban Text Messaging While Driving (JUN

2020) 52.223-20 Aerosols (Jun 2016) 52.223-21 Foams. (Jun 2016) 52.225-13 Restrictions on Certain Foreign Purchases (FEB 2021) 52.227-1 Authorization and Consent (JUN 2020) 52.227-2 Notice and Assistance Regarding Patent and Copyright Infringement (JUN 2020) 52.227-4 Patent Indemnity -- Construction Contracts (DEC 2007) 52.228-2 Additional Bond Security (OCT 1997) 52.228-5 Insurance – Work on a Government Installation (JAN 1997) 52.228-12 Prospective Subcontractor Requests for Bonds (MAY 2014) 52.228-14 Irrevocable Letter of Credit (NOV 2014) 52.232-5 Payments under Fixed-Price Construction Contracts (MAY 2014) 52.232-17 Interest (MAY 2014) 52.232-23 Assignment of Claims (MAY 2014) 52.232-27 Prompt Payment for Construction Contracts (JAN 2017) 52.232-33 Payment by Electronic Funds Transfer – System for Award Management (OCT

2018) 52.232-39 Unenforceability of Unauthorized Obligations (JUN 2013) 52.233-1 Disputes (MAY 2014) Alt 1 (DEC 1991) 52.233-3 Protest after Award (AUG 1996) 52.233-4 Applicable Law for Breach of Contract Claim (OCT 2004) 52.236-2 Differing Site Conditions (APR 1984) 52.236-3 Site Investigation and Conditions Affecting the Work (APR 1984) javascript:__doPostBack('ctl00$ctl00$body$homebody$RecentDocuments$C$RecentDocumentsControl$RecentDocumentResults$ctl00$DocumentNumberLink','')

52.236-5 Material and Workmanship (APR 1984) 52.236-6 Superintendence by the Contractor (APR 1984) 52.236-7 Permits and Responsibilities (NOV 1991) 52.236-8 Other Contracts (APR 1984) 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and

Improvements (APR 1984) 52.236-10 Operations and Storage Areas (APR 1984) 52.236-11 Use and Possession Prior to Completion (APR 1984) 52.236-12 Cleaning Up (APR 1984) 52.236-13 Accident Prevention (NOV 1991)

Alternate I (NOV 1991) 52.236-17 Layout of Work (APR 1984) 52.236-21 Specifications and Drawings for Construction (FEB 1997) 52.243-5 Changes and Changed Conditions (APR 1984) 52.244-6 Subcontracts for Commercial Items (Jul 2021) (DEVIATION APR 2020) 52.245-1 Government Property (SEP 2021) - Alt 1 (APR 2012) 52.245-9 Use and Charges (APR 2012) 52.246-21 Warranty of Construction (MAR 1994) 52.248-3 Value Engineering – Construction (OCT 2020) 52.249-1 Termination for Convenience of the Government (Fixed-Price) (Short Form)

(APR 1984)

Alternate I (SEP 1996)

52.249-10 Default (Fixed-Price Construction) (APR 1984) Alternate I (APR 1984)

52.253-1 Computer Generated Forms (JAN 1991) 452.232-70 Reimbursement for Bond Premiums – Fixed-Price Construction Contracts (NOV

1996) 452.236-72 Use of Premises (NOV 1996) 452.236-73 Archeological or Historic Sites (FEB 1988) 452.236-74 Control of Erosion, Sedimentation and Pollution (NOV 1996) 452.236-76 Samples and Certificates (FEB 1988) 452.236-77 Emergency Response (NOV 1996)

52.223-99 Ensuring Adequate COVID-19 Safety Protocols for Federal Contractors (OCT

2021) (DEVIATION)

(a) Definition. As used in this clause - United States or its outlying areas means—

(1) The fifty States;

(2) The District of Columbia;

(3) The commonwealths of Puerto Rico and the Northern Mariana Islands;

(4) The territories of American Samoa, Guam, and the United States Virgin Islands; and

(5) The minor outlying islands of Baker Island, Howland Island, Jarvis Island, Johnston Atoll, Kingman Reef, Midway Islands, Navassa Island, Palmyra Atoll, and Wake Atoll.

javascript:__doPostBack('ctl00$ctl00$body$homebody$RecentDocuments$C$RecentDocumentsControl$RecentDocumentResults$ctl00$DocumentNumberLink','')

(b) Authority. This clause implements Executive Order 14042, Ensuring Adequate COVID Safety Protocols for Federal Contractors, dated September 9, 2021 (published in the Federal Register on September 14, 2021, 86 FR 50985).

(c) Compliance. The Contractor shall comply with all guidance, including guidance conveyed through Frequently Asked Questions, as amended during the performance of this contract, for contractor or subcontractor workplace locations published by the Safer Federal Workforce Task Force (Task Force Guidance) at https:/www.saferfederalworkforce.gov/contractors/.

(d) Subcontracts. The Contractor shall include the substance of this clause, including this paragraph (d), in subcontracts at any tier that exceed the simplified acquisition threshold, as defined in Federal Acquisition Regulation 2.101 on the date of subcontract award, and are for services, including construction, performed in whole or in part within the United States or its outlying areas.

52.225-9 Buy American Act-Construction Materials (FEB 2021)

(a) Definitions. As used in this clause-

Commercially available off-the-shelf (COTS) item-

(1) Means any item of supply (including construction material) that is-

(i) A commercial item (as defined in paragraph (1) of the definition at Federal

Acquisition Regulation (FAR) 2.101);

(ii) Sold in substantial quantities in the commercial marketplace; and

(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace;

and

(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products.

"Construction material" means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work.

The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.

Cost of components means-javascript:__doPostBack('ctl00$ctl00$body$homebody$RecentDocuments$C$RecentDocumentsControl$RecentDocumentResults$ctl00$DocumentNumberLink','')

(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or

(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.

Domestic construction material means-

(1) For construction material that does not consist wholly or predominantly of iron or steel or a combination of both-

(i) An unmanufactured construction material mined or produced in the United States;

or

(ii) A construction material manufactured in the United States, if-

(A) The cost of its components mined, produced, or manufactured in the United

States exceeds 55 percent of the cost of all its components. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic. Components of unknown origin are treated as foreign; or

(B) The construction material is a COTS item; or

(2) For construction material that consists wholly or predominantly of iron or steel or a combination of both, a construction material manufactured in the United States if the cost of foreign iron and steel constitutes less than 5 percent of the cost of all components used in such construction material. The cost of foreign iron and steel includes but is not limited to the cost of foreign iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the construction material and a good faith estimate of the cost of all foreign iron or steel components excluding COTS fasteners. Iron or steel components of unknown origin are treated as foreign. If the construction material contains multiple components, the cost of all the materials used in such construction material is calculated in accordance with the definition of "cost of components".

javascript:__doPostBack('ctl00$ctl00$body$homebody$RecentDocuments$C$RecentDocumentsControl$RecentDocumentResults$ctl00$DocumentNumberLink','')

Fastener means a hardware device that mechanically joins or affixes two or more objects together. Examples of fasteners are nuts, bolts, pins, rivets, nails, clips, and screws.

Foreign construction material means a construction material other than a domestic construction material.

Foreign iron and steel means iron or steel products not produced in the United States.

Produced in the United States means that all manufacturing processes of the iron or steel must take place in the United States, from the initial melting stage through the application of coatings, except metallurgical processes involving refinement of steel additives. The origin of the elements of the iron or steel is not relevant to the determination of whether it is domestic or foreign.

Predominantly of iron or steel or a combination of both means that the cost of the iron and steel content exceeds 50 percent of the total cost of all its components. The cost of iron and steel is the cost of the iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the product and a good faith estimate of the cost of iron or steel components excluding COTS fasteners.

Steel means an alloy that includes at least 50 percent iron, between 0.02 and 2 percent carbon, and may include other elements.

"United States" means the 50 States, the District of Columbia, and outlying areas.

(b) Domestic preference. (1) This clause implements 41 U.S.C.chapter 83, Buy American, by providing a preference for domestic construction material. In accordance with 41 U.S.C. 1907, the domestic content test of the Buy American statute is waived for construction material that is a COTS item, except that for construction material that consists wholly or predominantly of iron or steel or a combination of both, the domestic content test is applied only to the iron and steel content of the construction materials, excluding COTS fasteners. (See FAR 12.505(a)(2)). The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.

(2) This requirement does not apply to information technology that is a commercial item or to the construction materials or components listed by the Government as follows:

____________________NONE____________________________

(3) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(2) of this clause if the Government determines that-javascript:__doPostBack('ctl00$ctl00$body$homebody$RecentDocuments$C$RecentDocumentsControl$RecentDocumentResults$ctl00$DocumentNumberLink','')

(i) The cost of domestic construction material would be unreasonable. The cost of a particular domestic construction material subject to the requirements of the Buy American statute is unreasonable when the cost of such material exceeds the cost of foreign material by more than 20 percent;

(ii) The application of the restriction of the Buy American statute to a particular construction material would be impracticable or inconsistent with the public interest; or

(iii) The construction material is not mined, produced, or manufactured in the United

States in sufficient and reasonably available commercial quantities of a satisfactory quality.

(c) Request for determination of inapplicability of the Buy American statute. (1) (i) Any

Contractor request to use foreign construction material in accordance with paragraph (b)(3) of this clause shall include adequate information for Government evaluation of the request, including-

(A) A description of the foreign and domestic construction materials;

(B) Unit of measure;

(C) Quantity;

(D) Price;

(E) Time of delivery or availability;

(F) Location of the construction project;

(G) Name and address of the proposed supplier; and

(H) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(3) of this clause.

(ii) A request based on unreasonable cost shall include a reasonable survey of the market and a completed price comparison table in the format in paragraph (d) of this clause.

(iii) The price of construction material shall include all delivery costs to the construction site and any applicable duty (whether or not a duty-free certificate may be issued).

(iv) Any Contractor request for a determination submitted after contract award shall explain why the Contractor could not reasonably foresee the need for such determination and could not have requested the determination before contract javascript:__doPostBack('ctl00$ctl00$body$homebody$RecentDocuments$C$RecentDocumentsControl$RecentDocumentResults$ctl00$DocumentNumberLink','') award. If the Contractor does not submit a satisfactory explanation, the Contracting Officer need not make a determination.

(2) If the Government determines after contract award that an exception to the Buy

American statute applies and the Contracting Officer and the Contractor negotiate adequate consideration, the Contracting Officer will modify the contract to allow use of the foreign construction material. However, when the basis for the exception is the unreasonable price of a domestic construction material, adequate consideration is not less than the differential established in paragraph (b)(3)(i) of this clause.

(3) Unless the Government determines that an exception to the Buy American statute applies, use of foreign construction material is noncompliant with the Buy American statute.

(d) Data. To permit evaluation of requests under paragraph (c) of this clause based on unreasonable cost, the Contractor shall include the following information and any applicable supporting data based on the survey of suppliers:

Foreign and Domestic Construction Materials Price Comparison

Construction Material Description Unit of Measure Quantity Price (dollars)* Item1:

Foreign construction material _______ _______ _______ Domestic construction material _______ _______ _______

Item2:

Foreign construction material _______ _______ _______ Domestic construction material _______ _______ _______

[* Include all delivery costs to the construction site and any applicable duty (whether or not a duty-free entry certificate is issued)].

[List name, address, telephone number, and contact for suppliers surveyed. Attach copy of response; if oral, attach summary.]

[Include other applicable supporting information.]

52.228-11 Individual Surety - Pledge of Assets (FEB 2021) (DEVIATION APR 2020)

(a) The Contractor shall obtain from each person acting as an individual surety on a performance bond or a payment bond -javascript:__doPostBack('ctl00$ctl00$body$homebody$RecentDocuments$C$RecentDocumentsControl$RecentDocumentResults$ctl00$DocumentNumberLink','')

(1)A pledge of assets that meets the eligibility, valuation, and security requirements described in the Federal Acquisition Regulation (FAR) 28.203-1; and

(2) Standard Form 28, Affidavit of Individual Surety, [except that the words “being duly sworn, depose and say” on the Standard Form 28 are replaced with the word “affirm” and the Standard Form 28 is not required to be sworn and notarized in block 12].

(b)The Contracting Officer may release a portion of the security interest on the individual surety's assets based upon substantial performance of the Contractor's obligations under its performance bond. The security interest in support of a performance bond shall be maintained—

(1) Contracts for the construction, alteration, or repair of any public building or public work of the Federal Government exceeding $150,000 (40 U.S.C. 3131). Until completion of any warranty period, or for 1 year following final payment, whichever is later.

(2) Contracts subject to alternative payment protection (see FAR 28.102-1(b)(1)). For the full contract performance period plus 1 year.

(3) Other contracts not subject to the requirements of paragraph (b)(1) of this clause. Until completion of any warranty period, or for 90 days following final payment, whichever is later.

(c)A surety's assets pledged in support of a payment bond may be released to a subcontractor or supplier upon Government receipt of a Federal district court judgment, or a sworn statement by the subcontractor or supplier that the claim is correct along with a notarized authorization of the release by the surety stating that it approves of such release. The security interest on the individual surety's assets in support of a payment bond shall be maintained—

(1) Contracts for the construction, alteration, or repair of any public building or public work of the Federal Government exceeding $150,000 which require performance and payment bonds (40 U.S.C. 3131). For 1 year following final payment, or until resolution of all pending claims filed against the payment bond during the 1-year period following final payment, whichever is later.

(2) Contracts subject to alternative payment protection (see FAR 28.102-1(b)(1)). For the full contract performance period plus 1 year.

(3) Other contracts not subject to the requirements of paragraph (c)(1) of this clause. For

90 days following final payment.

(d)The Contracting Officer may allow the Contractor to substitute an individual surety, for a performance or payment bond, after contract award. The Contractor shall comply with the requirements of paragraph (a) of this clause within the timeframe established by the Contracting Officer.

javascript:__doPostBack('ctl00$ctl00$body$homebody$RecentDocuments$C$RecentDocumentsControl$RecentDocumentResults$ctl00$DocumentNumberLink','') https://www.acquisition.gov/far/part-28#FAR_28_203_1

52.228-13 Alternative Payment Protections (JUL 2000) (For use when the estimated or actual value exceeds $35,000 but does not exceed $150,000)

(a) The Contractor shall submit one of the following payment protections:

Payment Bond Irrevocable Letter of Credit

(b) The amount of the payment protection shall be 100 percent of the contract price.

(c) The submission of the payment protection is required within __10__ days of contract award.

(d) The payment protection shall provide protection for the full contract performance period plus a one-year period.

(e) Except for escrow agreements and payment bonds, which provide their own protection procedures, the Contracting Officer is authorized to access funds under the payment protection when it has been alleged in writing by a supplier of labor or material that a nonpayment has occurred, and to withhold such funds pending resolution by administrative or judicial proceedings or mutual agreement of the parties.

(f) When a tripartite escrow agreement is used, the Contractor shall utilize only suppliers of labor and material that signed the escrow agreement.

52.232-40 Providing Accelerated Payments to Small Business Subcontractors (DEC 2013)

(DEVIATION APR 2020)

(a)[(1) In accordance with 31 U.S.C. 3903 and 10 U.S.C. 2307, upon receipt of accelerated payments from the Government, the Contractor shall make accelerated payments to its small business subcontractors under this contract [in accordance with the accelerated payment date established], to the maximum extent practicable and prior to when such payment is otherwise required under the applicable contract or subcontract, [with a goal of 15 days] after receipt of a proper invoice and all other required documentation from the small business subcontractor [if a specific payment date is not established by contract.

(2) The Contractor agrees to make such payments to its small business subcontractors without any further consideration from or fees charged to the subcontractor].

(b) The acceleration of payments under this clause does not provide any new rights under the Prompt Payment Act.

(c) Include the substance of this clause, including this paragraph (c), in all subcontracts with small business concerns, including subcontracts with small business concerns for the acquisition of commercial items.

javascript:__doPostBack('ctl00$ctl00$body$homebody$RecentDocuments$C$RecentDocumentsControl$RecentDocumentResults$ctl00$DocumentNumberLink','')

52.252-6 Authorized Deviations in Clauses (NOV 2020)

(a) The use in this solicitation or contract of any Federal Acquisition Regulation (48 CFR Chapter 1) clause with an authorized deviation is indicated by the addition of “(DEVIATION)” after the date of the clause.

(b) The use in this solicitation or contract of any Agriculture Acquisition Regulation (48 CFR __4___) clause with an authorized deviation is indicated by the addition of “(DEVIATION)” after the name of the regulation.

452.228-71 Insurance Coverage (NOV 1996) Alt 1 (NOV 1996)

Pursuant to FAR clause 52.228-5, Insurance-Work on a Government Installation, the Contractor will be required to present evidence to show, as a minimum, the amounts of insurance coverage indicated below:

(a) Workers Compensation and Employer's Liability. The Contractor is required to comply with applicable Federal and State workers' compensation and occupational disease statutes. If occupational diseases are not compensable under those statutes, they shall be covered under the employer's liability section of the insurance policy, except when contract operations are so commingled with a Contractor's commercial operations that it would not be practical to require this coverage. Employer's liability coverage of at least $100,000 shall be required, except in States with exclusive or monopolistic funds that do not permit worker's compensation to be written by private carriers.

(b) General Liability. The Contractor shall have bodily injury liability insurance coverage written on a comprehensive form of policy of at least $500,000 per occurrence.

(c) Automobile Liability. The Contractor shall have automobile liability insurance written on a comprehensive form of policy. The policy shall provide for bodily injury and property damage liability covering the operation of all automobiles used in connection with performing the contract. Policies covering automobiles operated in the United States shall provide coverage of at least $200,000 per person and $500,000 per occurrence for bodily injury and $20,000 per occurrence for property damage or loss.

(d) Aircraft Public and Passenger Liability. When aircraft are used in connection with performing the contract, the Contractor shall have aircraft public and passenger liability insurance. Coverage shall be at least $200,000 per person and $500,000 per occurrence for bodily injury, other than passenger injury. Coverage for passenger injury shall be at least $200,000 multiplied by the number of seats or passengers, whichever is greater.

javascript:__doPostBack('ctl00$ctl00$body$homebody$RecentDocuments$C$RecentDocumentsControl$RecentDocumentResults$ctl00$DocumentNumberLink','')

PART III--LIST OF DOCUMENTS, EXHIBITS, AND OTHER ATTACHMENTS

SECTION J--LIST OF ATTACHMENTS

J.1 Wage Determinations Thomas County (NE20220075) (09.02.2022) (6 Pages)

J.2 Statement of Work (17 Pages)

J.3 Drawing and Map (2 Pages) javascript:__doPostBack('ctl00$ctl00$body$homebody$RecentDocuments$C$RecentDocumentsControl$RecentDocumentResults$ctl00$DocumentNumberLink','')

1240LT22P0044 (2).pdf
1240LT22P0044 - Bessey Nursery Garage Door Replacement.pdf
PART I—THE SCHEDULE
SECTION B--SUPPLIES OR SERVICES AND PRICES/COSTS
B.1 SCHEDULE OF ITEMS – Bessey Nursery Garage Door Replacement
B.2 SCHEDULE NOTES
SECTION C--DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK
C.1 SCOPE OF CONTRACT
C.2 PROJECT LOCATON
C.4 TECHNICAL SPECIFICATIONS
452.211-72 Statement of Work/Specifications (FEB 1988)
452.211-73 Attachments to Statements of Work/Specifications (FEB 1988)
SECTION D--PACKAGING AND MARKING
D-1 PACKING AND MARKING
D-2 PROJECT LABELING FOR OFFICIAL COORESPONDENCE
SECTION E--INSPECTION AND ACCEPTANCE
E.1 CLAUSES
SECTION F--DELIVERIES OR PERFORMANCE
F.1 CLAUSES
SECTION G--CONTRACT ADMINISTRATION DATA
G.1 CLAUSES
SECTION H--SPECIAL CONTRACT REQUIREMENTS
H.1 CLAUSES
PART II--CONTRACT CLAUSES
SECTION I--CONTRACT CLAUSES
I.1 CLAUSES
52.223-21 Foams. (Jun 2016)
52.252-6 Authorized Deviations in Clauses (NOV 2020)
PART III--LIST OF DOCUMENTS, EXHIBITS, AND OTHER ATTACHMENTS
SECTION J--LIST OF ATTACHMENTS
ADPD980.tmp
PART I—THE SCHEDULE
SECTION B--SUPPLIES OR SERVICES AND PRICES/COSTS
B.1 SCHEDULE OF ITEMS – Bessey Nursery Garage Door Replacement
B.2 SCHEDULE NOTES
SECTION C--DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK
C.1 SCOPE OF CONTRACT
C.2 PROJECT LOCATON
C.4 TECHNICAL SPECIFICATIONS
452.211-72 Statement of Work/Specifications (FEB 1988)
452.211-73 Attachments to Statements of Work/Specifications (FEB 1988)
SECTION D--PACKAGING AND MARKING
D-1 PACKING AND MARKING
D-2 PROJECT LABELING FOR OFFICIAL COORESPONDENCE
SECTION E--INSPECTION AND ACCEPTANCE
E.1 CLAUSES
SECTION F--DELIVERIES OR PERFORMANCE
F.1 CLAUSES
SECTION G--CONTRACT ADMINISTRATION DATA
G.1 CLAUSES
SECTION H--SPECIAL CONTRACT REQUIREMENTS
H.1 CLAUSES
PART II--CONTRACT CLAUSES
SECTION I--CONTRACT CLAUSES
I.1 CLAUSES
52.223-21 Foams. (Jun 2016)
52.252-6 Authorized Deviations in Clauses (NOV 2020)
PART III--LIST OF DOCUMENTS, EXHIBITS, AND OTHER ATTACHMENTS
SECTION J--LIST OF ATTACHMENTS

File details come from the government source that posted it. Updated .