9-SOW (section C).doc
DOC document 467 KB Posted
- Solicitation number
- 1240LQ27R0001
- Issued by
-
Department of Agriculture Forest Service
About this file
This is a Statement of Work (SOW) for Architect-Engineer (A-E) services under a federal contract with the U.S. Forest Service for Bridge & Structures, Dam Design, and Investigation Studies work in Region 9 (Eastern Region), covering 14 states: Minnesota, Wisconsin, Michigan, Illinois, Indiana, Missouri, Ohio, West Virginia, Pennsylvania, New York, New Hampshire, Maine, Massachusetts, and Vermont.
The A-E shall provide comprehensive professional engineering services including investigation, design, maintenance, repair, alteration, reconstruction, and new construction for bridges, structures, and dams. Services encompass bridge design, inspection, plan review, and load rating; dam services including flood inundation studies, decommissioning design, rehabilitation design, and inspections; and ancillary standalone work such as topographic surveys, construction layout, hydrology and hydraulic modeling, and geotechnical investigations. Work is authorized through Task Orders, with the Government issuing requests for services specifying project scope, deliverables, cost limitations, and delivery schedules. The A-E must submit detailed proposals including project understanding, technical approach, total price, schedule, and personnel requirements. Proposals are subject to Government review, negotiations, and final approval before Task Order issuance. All design work must comply with AASHTO standards (LRFD Bridge Design Specifications, geometric design guidelines), Forest Service handbooks, and applicable federal agency guidance from USFS, USDI Bureau of Reclamation, U.S. Army Corps of Engineers, NRCS, FEMA, and FERC. Deliverables include preliminary (35%), advance final (95%), and final (100%) designs with AutoCAD Civil 3D drawings, specifications following CSI MasterFormat, design analysis, and construction cost estimates. Bridge inspection services must comply with National Bridge Inspection Standards and AASHTO's Manual for Bridge Evaluation, with load rating analysis using BRASS-Girder or TBAR software. The contract includes construction inspection services, design review, shop drawing review, and change order preparation. The A-E must maintain sufficient supervisory personnel, designate a Project Leader as single point of contact, obtain necessary permits and approvals, return Government-furnished materials within 14 days of work acceptance, and immediately report any critical bridge safety findings to the Contracting Officer's Representative.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| R9 AE Request and Quals and SF330s_PQH REV final.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Contract <insert contract number>
Eastern Region, R-9
Architectural / Engineering Services
SECTION C--DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK
FOR GENERAL ARCHITECT-ENGINEER A-E SERVICES
C.1 GENERAL
C.1.1 Purpose and Scope of Services
The Architect-Engineer (herein referred to as the A-E) shall furnish all services, materials, supplies, plant, labor, equipment, investigations, inspection, tests, studies, superintendence and travel as required in accordance with this Contract, the Task order, and the A-E's Technical/Price Proposal (hereafter referred to as the Proposal).
This contract will include Professional Engineering Services for the investigation, design, maintenance, repair, alteration, reconstruction, and new construction projects involving Bridges & Structures, Dams, and ancillary work related to these structures. Bridge & Structures services including bridge design, inspection, plan review, load rating, and related work. Dam services including flood inundation studies, decommissioning design, rehabilitation design, and inspections. Ancillary standalone work such as topographic survey, construction layout, hydrology and hydraulic modeling, and geotechnical investigation related to future bridge and dam work is also included in the scope.
The A-E shall furnish sufficient technical supervisory and administrative personnel at all times to insure prosecution of the work in accordance with the delivery schedule listed in each Task order.
C.1.2 Location of Projects
The work will be located throughout Southern Region, Region 9. The States having Forests are: Minnesota, Wisconsin, Michigan, Illinois, Indiana, Missouri, Ohio, West Virginia, Pennsylvania, New York, New Hampshire, Maine, Massachusetts, and Vermont.
C.1.3 Procedures for Requesting Services
C.1.3.1 Task orders: The Government will authorize services and products furnished under this contract by issuing a Task Order. Each Task Order will be placed in the following manner.
C.1.3.2 Request for A-E Services: The Government will submit request either in writing or orally for services to the A-E. The request will include the following information.
a. A unique identification number and name for the proposed Task order.
b. The date a Proposal is due the Government and where it is to be sent.
c. A description of the project including the objective for the requested services and any appropriate criterion that may apply such as cost or size limitations.
d. A description of the services and products needed (organized by the type of services). Services may include items not currently indicated elsewhere in the Contract.
e. Any additional specifications for the performance of services to include the content, quality and quantity of products.
g. A description of Government Furnished Services and/or Materials.
C.1.3.3 Scoping Meeting: A scoping meeting may be held prior to the date indicated for submission of a Proposal to clearly define the project in sufficient detail so that there is a mutual understanding between the Government and A-E as to the services to be provided. The A-E or The Government may request clarification by conference calls, meetings, or written correspondence. The Government will chair and designate the time and location for meetings. When the scope of a project is limited, easily definable, and an initial site visit is not required to understand the extent of the project, the Government may elect to hold the scoping meeting virtually.
C.1.3.4 Proposal: The A-E shall submit a detailed Proposal to the Government at the times and places specified in the Government's request. The Proposal shall be submitted by the close of business of the date specified.
The A-E's Proposal shall include:
a. The name and phone number of the A-E's Project Leader for the proposed Task order.
b. A description of the A-E's understanding of the scope of the project including any assumptions made in order to establish the price of the Proposal.
c. A description of the technical approach or methodology for performing the work.
d. The total price or fee for performing the work.
e. The schedule for accomplishment of services and delivery of products.
(Items f.-i. are only required if requested by the government)
f. A list of the tasks required to perform the work.
g. An itemized list of the personnel needed for each task with an estimate of the time (including travel time) required to perform the task.
h. An itemized list of the priced equipment, materials and supplies needed for each task including copies over and above the normal requirements.
i. A summary of the costs by tasks, products, and type of services.
Additional services and subcontractors: When subcontractor services are required the A-E shall include the following information in the Proposal upon request of the government.
a. The name and address of the source and/or subcontractor.
b. Information as to price, how it was obtained (cost elements) and profit.
c. A description of the work to be performed by the subcontractor.
d. A description of the subcontractor's qualifications to perform the work.
e. Quality control/quality assurance measures that will be employed to ensure compliance with the Task order.
A-E's Fees: The A-E's fee shall include the cost for all labor, engineering, special studies, consultant services, equipment, materials, supplies, travel, subcontractor services, and laboratory work required to accomplish the work for a Task order. The fee shall be based on the, Schedule of Items, and other supporting documents. Profit shall be included in the prices shown in the Schedule of Items and corresponding documents.
No payment shall be made for the lost time for breakdown, or for causes due to fault, negligence, or for the convenience of the A-E.
C.1.3.5 Government Review of Proposal: The Government will review the A-E's Proposal for compliance with the Government's Request for Services. The proposed fee will also be reviewed and compared to the Government's cost estimate other supporting documents and limitations for reimbursement of other direct costs.
C.1.3.6 Negotiations: Upon completion of the review, the Government will schedule a time and location for negotiations with the A-E. Negotiations can be held virtually, or by a meeting between the parties. Negotiations will be chaired by the Government. The purpose of the negotiations will be to reach a fair and reasonable price to perform the work; as well as, to reach agreement as to the services, products to be provided, delivery schedule, and concurrence with technical approach.
C.1.3.7 Final Proposal: Upon the determination of the Government that negotiations are complete, the A-E will be requested to submit a Final Proposal incorporating any changes agreed to during the negotiations. The Final Proposal shall represent the A-E's best and final offer (B&FO) for performing the work required by the proposed Task order. The Final Proposal shall be submitted to the Government at the time and place specified by the Government.
C.1.3.8 Government Review of Final Proposal: The Government will review the Contractor's Final Proposal for compliance with the terms agreed to during negotiations. If there is agreement, the Government will issue a Task order which will form a part of this contract. The Task order will incorporate the Final Proposal.
C.1.3.9 Termination of Negotiations: If the Government disagrees with certain aspects of the Final Proposal, the Government may reopen negotiations by requesting another Final Proposal addressing those aspects with which the Government disagrees. If agreement cannot be reached on a proposed Task Order, negotiations may be terminated by the Government and services procured by other means.
C.1.4 Performance of Services
C.1.4.1 Confirmation Notices: The A-E may be required, if required in the Task order, to provide a record of all conferences, meetings, discussions, verbal directions, telephone conversations, etc., (confirmation notices) participated in by the A-E on matters relative to the contract.
C.1.4.2 Meetings and Conferences: Periodic meetings shall be held whenever requested by the Government or the A-E for discussion of questions and problems relating to the work required under each Task order. The A-E and subcontractors shall attend and participate in all design conferences, including site/criteria, pre-design, and/or other conferences pertinent to the work, at the A-E Office, Government Office, virtually, or other location as directed by the Government. Generally formal meetings and conferences related to performance of the work will be identified and scoped out in the individual task orders. Meetings and conferences related to general contract administration or to address contract performance issues are not covered by this paragraph and are not reimbursable.
C.1.4.3 Brief Phone discussions: Either party may request a brief phone discussion for the purpose of technical discussions, clarification of task order requirements, project administration or discussing other related issues. Brief phone discussions normally do not exceed 1 hour in length and are not scoped or reimbursed, they are considered incidental to the work. The party requesting the call is responsible for setting it up, scheduling, and coordination.
C.1.4.4 Additional Subcontractors: When an unanticipated need for services arises that can not be provided by the A-E, the A-E shall obtain such services competitively as required to complete the work. Prior to hiring a subcontractor, the A-E shall submit the following information to the Government.
a. GSA Standard Form (SF) 1413 - Statement and Acknowledgement for Subcontractors.
b. Information as to price, how it was obtained, cost elements and profit.
c. A description of the work to be performed by the subcontractor.
d. A description of the subcontractor's qualifications.
e. Quality control/quality assurance measures that will be employed to ensure compliance with the Task order.
Under no circumstances shall the A-E hire a subcontractor without receiving written approval from the Government. The Government will make payment after completion of the subcontractor's services and receipt of an invoice from the A-E. Examples of specialized services include, soil boring/logs, surveying, and specialized geological/geotechnical services.
C.1.4.5 Coordination and Prosecution of the Work:
Supervisory Control: The A-E shall furnish sufficient technical supervisory and administrative personnel at all times to ensure prosecution of the work in accordance with the delivery schedule listed in each Task order.
Liaison: During the prosecution of the work under each Task order, the A-E shall keep in close liaison with the designated Contracting Officer’s Representative, who will coordinate the work. Requests made by other Government officials shall be referred to the Contracting Officer.
Project Leader & Quality Control: The A-E shall appoint a Project Leader to serve as a single point of contact and liaison between the A-E and the Government for all work required under each Task order. Upon award of the contract, the A-E shall immediately advise the Government, in writing, of the name of the individual so designated. The A-E Project Leader will be responsible for the complete coordination of all work developed under each Task order. All work will be accomplished with adequate internal controls and review procedures to eliminate conflicts, errors, and omissions, and to ensure the technical accuracy of all design information. The A-E Project Leader shall review all submittals prior to delivery for contract compliance and shall certify in writing that the submittal has been reviewed and is in compliance with the contract. Project submittal received without certification may be rejected.
Site Visits, Inspections, and Investigations: The A-E shall notify the Government of all visits and inspect/investigate the site of each identified project as necessary and required during the preparation and accomplishment of the work. All data developed under the Task order shall be related to current site conditions and to other proposed work within the specific project area. It is realistic to expect that occasionally adjacent work to engineering services could be required to support the principal purpose of investigational studies for required Forest Service bridge, dam, etc. structures.
C.2 SERVICES REQUIRED
C.2.1
INVESTIGATION AND STUDIES
C.2.1.1 The A-E shall perform the required services in accordance with the requirements stated herein and as stated in the Task order. The work under this section may include general site reconnaissance, bridge, dam, or other related structure safety or condition inspections, field explorations, sampling, surveys, and geophysical investigations. Investigative work may also include engineering studies with development of alternatives, cost estimates, and recommendations. Work may include feasibility investigation, site assessments and investigations, foundation investigation, dam operation and maintenance plans, dam screening level risk assessment, dam breach analysis and downstream hazard assessments, dam hazard classification analysis and determination, geologic and soil mapping, soil sampling, evaluation, and typing, boring and core sampling with associated logging, and slope stability analysis.
C.2.1.2 All investigations or studies shall be summarized in a report or included in a design analysis when applicable.
C.2.1.3 Reports shall present the following:
a. Discussions of the study and investigation.
b. Description of all plans and schemes considered for obtaining the desired end result of the study.
c. All drawings and sketches required to present and illustrate the details and results of the study.
d. Required estimates of construction costs, including comparative costs for indicated alternate plans and schemes.
e. Results, conclusions and recommendations.
f. Copies of the Task order and Confirmation Notices.
C.2.2
DESIGN SERVICES
C.2.2.1 General:
C.2.2.1.1 The A-E shall perform the required services in accordance with the requirements stated herein and as stated in the Task order. Design services may include designs for Bridges & Structures, Dam rehabilitation, reconstruction, maintenance and repair, decommissioning, and ancillary work. Ancillary standalone work such as topographic survey, bathymetry, construction layout, hydrology and hydraulic modeling, and geotechnical investigation related to future bridge and dam design is also included in the scope.
C.2.2.1.2 The A-E shall obtain necessary permits, licenses and approvals from all local, State and Federal authorities necessary for the performance of the A-E's services. Should it become necessary in the performance of the work and services for the A-E to secure the right of ingress and egress to perform any of the work on properties not owned or controlled by the Government, the A-E shall secure the consent of the owner prior to effecting entry on such property. In the event the owner requires the payment of any fee for a license to enter upon and/or use such property, the fee is considered incidental to the task unless otherwise specified in the Schedule of Items.
C.2.2.1.3 The A-E may utilize Government designs, drawings, specifications and standards to meet the requirements of the proposed project where appropriate.
C.2.2.1.4 Preliminary Sketches: Prepare, subject to the approval of the Government, preliminary studies, sketches, and layout plans and reports including estimates of cost of the proposed project and of all structures, utilities, and appurtenances thereto. If more than three resubmissions of such studies, sketches, plans, or reports are required because of changes initiated by the Government, an adjustment in the contract price will be made as provided in the "Change" clause of this contract.
C.2.2.1.5 Design Standards: All work shall be designed in accordance with industry accepted engineering/architectural standards and additional standards or instructions provided by the Government.
· Roads and Road Bridges –
· AASHTO’s LRFD Bridge Design Specifications
· AASHTO’s A Policy on Geometric Design of Highways and Streets
· AASHTO’s Guidelines for Geometric Design of Very Low-Volume Local Roads.
· AASHTO’s Roadside Design Guide
· Specific requirements identified in Forest Service Handbook (FSH) 7709.56b, Chapter 70.
· Trail Bridges-
· FSH 7709.56b, Chapter 80, Trail Bridge Design
· AASHTO’s LRFD Bridge Design Specifications
· AASHTO’s LRFD Guide Specifications for the Design of Pedestrian Bridges
· Dams and related Structures – Design will be performed in accordance with generally accepted methods as detailed in guidelines provided by:
· USFS FSH 7509.11
· USFS FSM 7500
· USDOI Bureau of Reclamation (BOR)
· U.S. Army Corps of Engineers (USACE)
· USDA Natural Resources Conservation Service (NRCS)
· FEMA
· USDOE Federal Energy Regulatory Commission (FERC)
· Other federal agencies as approved by the CO.
· Hydrology and Hydraulic Modeling-
· Hydrology follows guidance in FSH 7709.56, chapter 50 Hydrology and Geomorphology or as specified in the individual Task Order.
· Hydraulic Modeling will general be done in accordance with the latest version of HEC-RAS following the procedures in the User manual and Technical Reference guides.
C.2.2.1.6 As-built Verification: The A-E shall make on-site investigations, as necessary, to verify existing site conditions, including Government Furnished "As Built" drawings, and correct or supplement data as necessary to reflect existing conditions. The initial on-site investigation to verify available and/or develop "as-built" drawings, shall be described and documented with photographs. Design data utilized herein shall reflect the current existing condition.
C.2.2.1.7 People With Disabilities: Structures shall be designed to facilitate access by people with disabilities in accordance with the provisions of the American with Disabilities Act and Architectural Barriers Act Accessibility Guideline, latest edition, and other guidance provided by the Government.
C.2.2.1.8 Photographs: The A-E shall arrange for photographs of the site and/or structures in connection with the project as necessary to portray the initial conditions affecting the design. One copy of all photos taken shall be furnished the Government as directed by the Task order.
C.2.2.1.9 Discrepancies: The A-E shall advise the Government of any discrepancies, ambiguities and lack of clarity noted in Government Furnished drawings and specifications.
C.2.2.1.10 Initiation of Work: The A-E shall not proceed or initiate any successor design level of work prior to receipt of approval of the preceding design level.
C.2.2.1.11 Construction Time and Phasing: The A-E shall provide an estimate of the construction time in calendar days to complete the project when requested by the government. The estimate will be based upon a standard 40-hour week utilizing normal size crews of workers. The evaluation of construction time will consider restrictions such as working hours, security, access, noise level, joint occupancy requirements, etc.
C.2.2.1.12 Return of Government Items: All Government Furnished materials shall be returned to the Government within 14 calendar days after the date of acceptance of the work to be accomplished under the applicable Task order.
C.2.2.1.13 Omissions & Errors: After submission of the Drawings, Specifications, and cost estimate, the A-E shall make any corrections thereto as may be necessary because of errors or omissions, including the preparation of addenda during the offer period that may be required as a result of such deficiencies.
C.2.2.2 Cost Estimates:
C.2.2.2.1 Construction Costs: Cost estimates shall be accurate and realistic, reflecting current prices for work and materials, and taking into account probable labor shortages that may occur because of other known proposed projects in the area. The estimates shall be broken down into major items of construction, as approved by the Government. Each major item shall be further broken down into component units of labor and materials with the quantity and cost of each unit shown. Lump sum amounts for major items, which cannot be readily analyzed, will not be accepted. Cost estimates shall present separate costs for each line item, broken down into costs for individual buildings, facilities and components thereof, as directed by the Government. All estimates of construction cost submitted under each Task Order shall reflect the current unit and lump sum prices at the time of submittal. An estimate is required for:
a. Preliminary Design: A preliminary-type estimate is required if this 35% stage of design submittal is required.
b. Advance Final Design.
c. Final Design: This estimate shall be revised to reflect final design review comments and shall be submitted with the final design and related data.
The A-E shall maintain the confidential nature of all cost estimates prepared under each Task order.
C.2.2.3 Specifications:
C.2.2.3.1 General: The A-E shall subscribe to a nationally recognized specification service with a comprehensive set of guide specifications which follows the Construction Specifications Institute’s MasterFormat if required by the project. The A-E shall also have a copy of the latest Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects for transportation projects. The specifications shall be updated on a regular basis. The Government may furnish at any time the A-E a portion or all of the specifications required for a project. The A-E shall be responsible for incorporating and editing any Government furnished specifications into the A-E's specification package.
C.2.2.3.2 Outline Specifications: Prepare outline specifications covering all contemplated construction materials and equipment to be incorporated in the project as the result of original designs by the A-E. The outline should list the divisions used and the guide specifications required under each CSI or FHWA division. Outline specifications shall be provided with the preliminary submittal.
C.2.2.3.3 Advanced Final (95%) Specifications: A complete set of typed specifications and other sections developed for the project, including Schedule of Items with appropriate quantities, and an index of the Technical Sections (includes Division I) of the specifications will be submitted with the Advance Final Data. Final project specifications will be corrected for review comments; original specifications will be submitted with the Final Data. The following information is to be furnished with the preliminary data:
a. Phasing (order of work) requirements
b. A list of any Government Furnished Materials to be used by the Contractor. The list must include complete descriptions and quantities of each item and place where materials are or will be available to the Contractor.
c. Materials to be removed and reused: Indicate whether any material removed is to remain the property of the Government, and if so, a list or a statement that the items are listed on the Drawings.
C.2.2.3.4 Specifications: Prepare Specifications in a single volume covering all items of work. They shall include the Statement of Work, Special Conditions and Technical Provisions and a list of Items and Quantities. The intent is to prepare complete Specifications so that the project construction may be readily advertised for offers and contracted for as a whole or in parts. Items shall be developed so that total construction costs of line items may be determined.
C.2.2.3.5 Contractor's Approval and Test Schedule: A schedule of the Contractor's approvals and testing shall be prepared listing all shop drawings, samples, tests, certificates of compliance, and color schedules to be submitted in accordance with the Specifications. Each item listed shall be referenced to the paragraph in the specifications, which required the Contractor's action thereon.
C.2.2.4 Design Analysis: The design analysis submitted for review shall include all information, narrative descriptions, catalog cuts, product information, project scope, confirmation notices, computations and all previously made review comments with the A-E's annotations as necessary to support and describe the design developed. They shall be in such detail as to permit complete understanding of the project design. When brand names or equal are used to specify a product the design analysis shall contain catalog cuts and other information in sufficient detail to clearly identify the product and its saline characteristics. When products are specified by standards and not by name, the design analysis shall identify at least two sources of products meeting the listed standards. The design analysis shall be prepared to present the data in an organized manner for:
a. Review, approval, and record purposes,
b. Use in adapting designs to other sites,
c. Future reevaluation and modification of construction.
d. Review and acceptance of contractor submittal.
C.2.2.4.1 Preparation
a. Size and Layout. The design analysis shall be legible and clearly expressed.
b. Organization. The design analysis for projects with more than one building or facility will be organized into volumes for each major facility with a title page and complete table of contents for each volume. Each volume shall include the name of the facility, the name of the project if different, the project number, fiscal year, date of publication, and the drawing and specification numbers assigned to the facility.
c. Design Calculations. Calculations shall be computed and checked by separate individuals. The names or initials of these individuals will be indicated on the page or insert carrying the calculations. Presentation will be clear and legible with a tabulation showing all design loads and conditions. The source of loading conditions, formulas, and references will be identified. Assumptions and conclusions will be explained and cross-referencing will be clear.
d. Use of Computer Programs. When computer programs are used, the design analysis should include a complete listing of the input and output data, spreadsheet formulas, and calculations necessary for preparation of the input data. Input should be annotated to facilitate a reviewer's verification of data. Computer output should be in a format that identifies results by proper column headings and line identification keyed to a sketch of the structure if necessary. Voluminous output data may be included in a separate volume or, output presentation may be limited to key sections or to typical results when output is repetitive. Results should be verified by a "ball park" hand analysis. The required level of verification is dependent on such factors as complexity of analysis, importance of results and level of confidence in the program. Software used for design shall be pre-approved by the government. Alternate software may be submitted to the government for review and approval.
e. Other Data. Codes, manuals, special investigations and reports are to be considered and used as applicable.
f. Submission. Except when specifically exempted, the design analysis will accompany all drawings submitted for review, approval, information, or record.
C.2.2.4.2 Format and Content. The basic format for the Concept, Early Preliminary, Advanced Final, and Corrected Final Design analysis is essentially the same, adjusted for the particular level of design and the type of facility.
C.2.2.5 Drawings:
C.2.2.5.1 General: All drawings shall be prepared in AutoCAD Civil 3D release 2020 version or newer in a 11” x 17” or 22” x 34” format. Drawing format and style shall be fully compatible with the Forest Service CAD Standards, and AE shall use the coversheet and title block examples provided. The DWT for the templates and CTB files are provided. Font size and line weights shall provide adequate clarity if produced at size 22”x34” and then reduced and reproduced in half sizes format (11” x 17”). Generally, font size less than 1/16” will not be accepted without prior approval. A graphical scale bar shall be provided for each view or drawing as needed so that if paper copies are reduced or enlarged the scale is still accurate. Text based scales such as 1”=10’ with no scale bar accompanying it are not allowed.
Plans shall indicate design standards or limitations stated by the Design Engineer, such as but not limited to, roadway criteria, structural criteria, timber grades, treatment and use category, steel grades, concrete strength, etc.
At each of the intermediate submission stages, the drawings shall be provided in electronic format as required in the Submittal/Delivery Schedule. If the contractor is required to maintain a FTP site then copies of all documents shall be posted in PDF format. When requested, drawings shall be made available in AutoCAD, DWG format.
The electronic copies shall be provided in both PDF and DWG formats. The PDF formatted drawings shall bear the name and electronic signature of the sheet’s designer, along with their PE stamp. The AE shall provide locations for Forest Service electronic signatures. The PDF drawings shall be provided in a method agreed to by the COR. The cloud-based secure file storage site provided by the Forest Service is the preferred method, though portable drives may be acceptable in some circumstances.
C.2.2.5.2 Preliminary (35%), advance final (95%), and final (100%) drawings shall be submitted in accordance with the delivery schedule established in each Task order. Multiple sheet drawings shall be labeled in the lower right hand corner as either "preliminary", "advance", or "final."
C.2.2.6 Design Phases.
C.2.2.6.1 Concept-level Design The intent of this phase is for the Government and the AE to preliminarily agree to a type, size, and location of the structure. The AE is expected to compile all survey, H&H, geotech, constructability, and current construction market information into a recommendation for the most cost effective (or multiple options, if warranted) structure to be constructed at the site. Any other pertinent information regarding the quality, speed of construction, constructability, complexity, or anticipated challenges shall be provided. Finally, a preliminary cost estimate shall be provided.
C.2.2.6.2 Preliminary Designs: General.
a. Prepare preliminary designs based upon the project criteria and instructions. Preliminary designs are required for all features of the project, including the siting of facilities.
b. The preliminary design (35% complete) data shall consist of
-Preliminary Drawings
-Table of Contents of the Specifications
-List of Guide Specifications to be utilized
-Design Analysis
-Preliminary Estimate of Construction Cost
-Construction Phasing Data
C.2.2.6.3 Advance Final Design (95%):
a. General: The advanced final design shall represent a product which is nearly completed with only the omission of a few minor details/items. All previous review comments shall have been incorporated into the design.
b. The advance final design shall consist of 95% drawings, specifications with table of contents, design analysis, construction schedule and phasing data, construction cost estimate and schedule of items, and a list of all submittals (include in design analysis).
C.2.2.6.4 Final Design (100%)
a. General: Accomplish the final detail design of the project complete with all component parts and appurtenances. The final designs shall be based upon the project criteria and where furnished or required, upon approved preliminary and advance final designs.
b. For structures involving site adaptation of plans, the final design shall be for all modifications, additions and appurtenances required to adapt the design of structures as shown on the plans to local site conditions.
c. The Final Design shall consist of complete drawings (all previous review comments incorporated, complete specifications, complete design analysis, final cost estimate, and any other documents required for the advanced final review which were revised. The government reserves the right to review and return for correction Final Design drawings that have not had all previous comments satisfactorily addressed.
C.3 PROJECT IMPLEMENTATION SERVICES
C.3.1 The A-E may be tasked to perform the following inspection services and as identified in the Task orders:
C.3.2 Design Review. The A-E may be tasked to provide technical, contractibility and operability reviews on proposed construction projects as directed by the Government. The review will cover such items as adequacy of design, detail, and omissions and inconsistencies between Drawings and Specifications., vague or ambiguous notes and references and lack of coordination between the civil, structural, architectural, electrical and mechanical Drawings.
C.3.3 Construction Inspection Services. The A-E may be tasked to perform all services, as directed in the Task order for surveillance inspection during the progress of construction up to and including the completion and final acceptance of the project in accordance with the requirements. These services will be required on an as needed basis for all work under the construction contract. One-day notice should be adequate to execute this portion of the contract.
C.3.3.1 General. The A-E shall report to and assist the Contracting Officers Representative (COR). The Contracting Officer shall maintain construction administration responsibility for the contract during the construction of the project.
C.3.3.2 A-E Full Time Project Representative. The A-E shall designate and assign a project representative (subject to approval of the Government) who will serve as the point of contact during the on-site observation and inspection of the construction work in progress and to ascertain that the work is executed in conformance with the Drawings and Specifications. Additionally, the A-E shall perform the following services:
a. Evaluate suggestions or recommendations submitted by the contractor and make recommendations.
b. Monitor the construction schedule, identify conditions which may delay construction completion and make recommendations concerning contract time extensions.
c. Interpret and clarify the intent of the drawings and specifications as directed by the Government.
d. Attend conferences held at the project site.
e. Observe tests at the project site, required by contract documents as actually conducted, and maintain record and report on such test procedures.
f. Maintain records and files of correspondence, site conference reports, shop drawings, addenda, change orders, and supplementary drawings issued subsequent to award of contract.
g. Inspect all phases of construction for compliance with plans and specifications. Maintain a diary utilizing Government approved forms. Each day's entry shall be signed by the A-E project representative and submitted to the Contracting Officer's Representative daily.
h. Maintain progress charts and submit monthly progress charts to the Government.
i. Develop a construction deficiency list for, and participate in, all inspections. Make recommendations concerning final acceptance.
C.3.3.3 Limitation of Authority. The A-E shall not authorize deviations from the contract documents, enter into the area of responsibility of the construction contractor's superintendent, advise or issue directions to any aspects of construction means, methods, techniques, sequences or procedures for safety precautions and programs in connection with the work, or issue a certificate of payment during the construction work without authorization from the Government.
C.3.4 Review of Shop Drawings, Materials, Fixtures and Equipment. The A-E may be tasked to review shop drawings and material submittal and make recommendations for approval or disapproval within seven days of receipt of.
C.3.5 Change Orders. The A-E may be tasked to prepare a change order when the construction contract requires modification due to differing site conditions, design deficiency or other reasons directed by the Government.
a. The A-E shall prepare detailed working drawings as required to depict the change. Drawings shall meet the basic requirements of Section C.2.2.E for drawings.
b. The A-E shall prepare detail specifications in accordance with the requirements of Section C.2.2.C.4.
c. Cost Estimate. The A-E shall prepare a cost estimate in accordance with Section C.2.2.B.1-2. The A-E shall protect the confidentiality of the cost estimate.
d. The A-E shall fill out Government furnished Standard Form (SF-30) Modification of Contact along with supplemental forms, and submit these forms along with the drawings, specifications, and cost estimate to the Government.
C.4 BRIDGE INSPECTIONS
The A-E shall provide all equipment, supplies, personnel, supervision, materials, quality control, and incidentals for the complete site investigation, condition assessment, and related analysis in accordance with National Bridge Inspection Standards (NBIS), and ASHTO’s Manual for Bridge Evaluation.
Safety. The Contractor shall use any traffic regulatory signs necessary to ensure safety of the inspection teams during the field inspections. If closure of any bridge to traffic is required, the engineer shall coordinate through the COR.
C.4.1 Routine Inspection
a. The A-E shall supply an inspection team with one qualified bridge inspector meeting the requirements of a Team Leader as outlined in the National Bridge Inspection Standards. The A-E shall complete the routine inspections and complete the Region 9 standard inspection forms or software in use by the Forest Service and sign as the Bridge Inspection Team Leader for each structure. The A-E shall be responsible for all pre-work, scheduling, tools and equipment.
b. Each bridge shall receive a thorough field inspection to determine its general condition. Specialized inspection methods such as underwater diving, electronic or specialized nondestructive inspection, Under Bridge Inspection Truck, etc., recommendations for such inspections shall be made.
c. Inspection shall be primarily visual, supplemented by basic inspection methods such as hammer soundings, coring of wood members, resistograph, chain dragging of concrete decks, etc.
d. If corings obtained, the location of corings of wood members shall be shown in sketches of the bridge inspection report or the coring log summary. A visual interpretation of any coring’s shall be part of the report. Enough corings shall be taken to determine the likelihood or extent of any deterioration. All core holes shall be plugged with treated hardwood dowels.
e. Channel and Waterways. The adequacy of a channel cross section will be a matter of judgment. A written description shall be made during field inspection to indicate waterway sufficiency. Subjective descriptors such as "evidence of water over structure," "debris on pier cap", or "adequate waterway evident" are acceptable. Channel cross-section measurements shall be taken from the top of the bridge at terrain break points and pier locations, and shall be taken in the same location as the previous inspection. Clearly indicate where the point of vertical measurement is taken, either top of rail, top of deck or top of curb.
f. Pile Bents. Inspection of pile bents will not require the passage of heavy loads. If a loaded vehicle passes during the interval a structure is being inspected, observations will be made and a note added to the inspection report to the effect that the structure was observed under passage of a (describe type of load).
g. If there is any damage to or deterioration of a bridge from the last inspection, recommendations shall be made as to whether a new load rating is necessary. Type III object markers should be on every bridge. Note on the inspection report all missing object markers, color and size of any object markers not meeting MUTCD, and the posted loading (if any) at each bridge site.
h. The A-E shall immediately report to the Contracting Officer's Representative any bridge or bridge site in such condition that vehicular use is not safe or which presents a major safety hazard of any form to the traveling public.
If preliminary inspection indicates potential Critical Finding(s), provide initial draft report, with C.F.-supplement, and notify the Gov’t Project Leaders within 24-hours.
In event of imminent danger, flag or barricade or leave parked truck to restrict public access to site, pending the notifications above and further actions.
Provide additional consultation and recommendation of potential remedies to Critical Findings, as needed, supporting the creation of Government’s Plan of Action.
i. The A-E shall identify work items with estimated quantities for each bridge. Inspector shall review the previous inspection report for consistency and note any major differences or findings.
j. The A-E shall take at least ten color photographs (digital) of each bridge:
Near approach, Far approach, Upstream from deck, Downstream from deck, Typical Deck, Typical superstructure, Near abutment, Far abutment, Upstream elevation, and Downstream elevation. Other photos showing any defects or other special features shall be included.
k. Access to bridge components shall be responsibility of the AE. Use of ladders, rope-access, or Under-Bridge-Inspection truck may be utilized as needed. AE is responsible for completing scheduling arrangements, closure coordination, and for following safety practices.
l. Bridge Scour: Each bridge shall be evaluated for scour per SNBI regulation. A-E shall inspect the all footings, piers, and pier foundations as applicable. This work might entail wading, shallow diving and probing.
m. Reporting: Report inspection findings using USFS bridge inspection software.
C.4.2 Underwater Inspection (when identified in the task order) A. The underwater bridge inspection shall be completed in conformance with AASHTO Manual for Bridge Evaluation and SNBI regulations. The underwater inspection shall be a Level I, Routine Inspection as defined in the current FHWA Underwater Inspection of Bridges, except as follows:
a. No Level II inspection is required. Contractor shall complete the Level I inspection and make recommendations for future Level II or Level III Inspections.
b. Level I inspection maybe visual by diving, use of Remote Operated Vehicles, advanced imaging technologies that will meet the intent of the underwater inspection.
c. No soundings of the channel are required. A visual inspection of the footing and surrounding ground line for scour maybe by diving, use of remote operated vehicles, or advanced imaging technologies that will meet the intent of the underwater inspection.
B. All diving operations associated with the inspection shall be conducted in compliance with OSHA 29 CFR 1910 Subpart T- Commercial Diving Operations (including OSHA Directive CPL 02-00-143), and Association of Diving Contractors International “CONSENSUS STANDARDS For Commercial Diving Operations”. Dive plans will need to be reviewed by the USFS Region 9 Dive Safety Officer prior to commencement of the dives.
C. A-E shall provide personnel that meet the requirements of Title 23, CFR 650, of the National Bridge Inspection Standards.
D. The dive inspection team shall submit a dive plan to the Contracting officer prior to work proceeding.
E. A report shall be prepared by the A-E which will include the following:
a. An evaluation of the overall condition of the underwater components including photographs, sketches, and diagrams used to substantiate the findings.
b. Recommendations for any short-term or long-term repairs or maintenance.
c. Conclusions as to the condition of the streambed in the immediate vicinity of the footings.
d. It shall be done of the Forest Service NBIS inspection template or software used by the Forest Service.
e. NBI condition ratings for substructure, channel condition, and channel protection, and scour condition.
C.4.3 Scour Appraisal and/or Scour Plan of Action (POA) {when identified in the task order} A. Perform the scour appraisal using the Forest Service-provided form. Identify the Scour Vulnerability code per SNBI regulation.
B. Forest Service will provide existing structure drawings with foundation types if available.
C. Report should evaluate existing scour countermeasures as well as recommend additional countermeasures as necessary.
D. Scour vulnerability codes of C or D will require a Scour POA. Notify the CO of bridges requiring a POA and if directed proceed with POA preparation as described below.
E. Prepare a POA using the Forest Service-provided template for the bridges identified in the task order. The CO will provide information regarding tiered-level contact personnel.
F. Scour-Critical Existing Bridges. A plan of action should be developed for each existing bridge determined to be scour critical.
(1) The plan of action should include instructions regarding the type and frequency of inspections to be made at the bridge, particularly in regard to monitoring the performance and closing of the bridge, if necessary, during and after flood events. (See HEC 18, Chapter 7.)
(2) The plan of action should include a schedule for the timely design and construction of scour countermeasures determined to be needed for the protection of the bridge. (See HEC 18, Chapter 7.)
G. Generally, the POA should:
· Indicate a coordinated and global action plan, and response strategy;
· Define major events or a monitoring triggers; and
· Provide information for requesting technical assistance or conducting an in-depth foundation investigation.
C.4.4 Road Bridge Load Rating Bridge load ratings shall be completed in accordance with AASHTO Manual for Bridge Evaluation, 3rd Edition (MBE), Current Interims, using Load and Resistance Factor Rating methodology outlined in Chapter 6, Part A. The following outlines additional Load rating requirements.
Load Rating Criteria:
1. Load rating vehicles shall include:
a. Design Load: HL-93, HL-93 Michigan Modified (where applicable), and PHL-93 (where applicable). Inventory LF = 1.75 and Operating LF = 1.35
b. AASHTO Legal Loads – Type 3, 3-3, 3S2 and all SHVs. LF = 1.3
c. Notional Rating Load (NRL). LF = 1.3
d. State Routine or Annual Permit Loads. LF per Table 6A.4.5.4.2a-1, MBE.
e. Other State Legal Loads. LF per state DOT load rating guidelines.
2. Evaluate each bridge for all applicable limit states per MBE Table B6A-1. Provide results under Strength I & II and Service II as required by the MBE. If optional limit states such as Service III or Service I control the rating, contact the COR to determine which limit state shall control the rating results.
3. Condition Factor – per engineer’s judgment based on inspection reports.
4. For Shear in concrete bridges, referenced by MBE 6A.5.8, Use simplified analysis if bridge inspections show no signs of shear distress.
5. Do not allow plastic analysis of steel bridges.
6. Provide recommended posting requirements for bridge based on superstructure or deck in accordance with FHWA and State requirements. Include posting sign requirements as required by and enforced by the State.
Load Rating Program and Analysis:
1. All steel and concrete bridges: BRASS-Girder 9.0.2 or latest version (by Wyoming DOT).
2. All timber superstructures, slabs, and timber panel decks: TBAR version 2.4.2.1 or latest version (by USDA Forest Service)
3. Bridges with timber plank decks that control the TBAR rating shall have the deck re-analyzed with hand calculations (Mathcad acceptable). TBAR is overly conservative on some timber plank deck calculations.
4. Complex structures requiring refined methods such as finite element analysis will need to be identified as to the method of analysis used prior to work commencing. The reporting will be the same as outlined below.
Region 9 Bridge Load Rating Report Guidelines:
Provide a report following the guidelines below. The form shall be printed on 8 ½” x 11” paper, but can be portrait or landscape, and can be double sided. The individual reports shall contain, as a minimum, the following items:
1. Cover page
a. Date of Report
b. Structure Number (SN), Forest Road or Trail Number (FR / FT)-Milepost, Structure Name
c. Forest, District, County
d. Load Rating Engineer Stamp
2. Table of Contents
a. (Header/footer on all pages references bridge)
3. Summary Page
a. Signatures
i. Load Rating Engineer
ii. Checked by Engineer
iii. Regional Bridge Program Manager
b. Dates for each signature above
c. LRFR Table
i. Vehicles
ii. Rating Factor
iii. Safe Load Capacity (SLC)
iv. Safe Posting Load (SPL, if applicable)
v. Controlling member / stress / location
vi. Limit State
d. Recommended posting in accordance with state and USFS (if applicable)
4. Background
a. Plan information
i. Each component of bridge type, i.e., RC slab, rolled beam superstructure, concrete abutments, age, etc.
ii. Dimensions of components and members
iii. Bridge descriptions
b. Inspection information
i. Who, When, summary of component ratings including scour, areas of concern to account for in rating,
c. Rating methodology, limit states,
d. Assumptions
e. References
f. Exceptions and observations
g. Old LR information if available
5. Geometrics and Hand Calculations
a. Sketches outlining configurations
b. Clarifying loadings if required
i. Strip width
ii. Beam spacing relative to decking
iii. Etc.
c. Dead Loads
d. Material and component structural properties used (can be part of assumptions above)
6. Computer calculations including input data for each
a. Mathcad
b. Brass
c. TBar
d. CANDE
e. Visual Analysis
f. Etc.
7. Detailed Information
a. Plans, Sketches, Pictures, etc.
Findings: If a bridge needs to be posted or the posting has changed the AE needs to notify the COR via email within 1 working day. The COR will then determine the course of action.
C.4.5 Trail Bridge Load Rating Bridge load ratings shall be completed in accordance with AASHTO Manual for Bridge Evaluation, 3rd Edition (MBE), Current Interims, using Load and Resistance Factor Rating methodology outlined in Chapter 6, Part A. The following outlines additional Load rating requirements.
7. Load rating vehicles for each bridge will be…