SPECIFICATIONS_U.C. Pump Replacement.pdf
PDF 2 MB Posted
- Attached to
- Union Creek Well Pump Replacement Federal contract opportunity
- Solicitation number
- 1240BK22Q0060
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 2022_05_04_SF-30 _Amendment No. 1 _1240BK22Q0060_Water Well Report.pdf | ||
| 2022_05_02_DOL Wage Determination_No 2015-5571(Rev 16) 3_15_22.pdf | ||
| SITE MAP_U.C. Pump Replacement.pdf | ||
| RFQ_1240BK22Q0060_Union Creek Pump Replacement.doc | DOC document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
USDA FOREST SERVICE PROJECT SPECIFICATIONS
Rev. Date 02/2022 Union Creek Well Pump Replacement 1/1 Specification List
SPECIFICATION LIST
Union Creek Well Pump Replacement High Cascades Ranger District
Rogue River – Siskiyou National Forest Jackson County, Oregon
CONSTRUCTION SPECIFICATION INSTITUTE (CSI) SPECIFICATIONS
SECTION TITLE
DIVISION 01 – GENERAL REQUIREMENTS
01020 Intent of Contract 01025 Measurement and Payment 01200 Mobilization
DIVISION 11 – EQUIPMENT
11214 Submersible Water Well Pump with Motor
Rev. Date 02/2022 Union Creek Well Pump Replacement 01020 - 1/1 Intent of Contract
SECTION 01020
INTENT OF CONTRACT
1. PART 1 - GENERAL
1.01 SUMMARY
A. The intent of the contract is to provide for the complete construction of a fully functional project as described in the contract documents and Drawings. Unless otherwise provided, the Contractor shall furnish all labor, materials, equipment, tools, transportation, and supplies, and shall perform all work required to complete the project within reasonably close conformity to the Drawings and Specifications, and in accordance with provisions of the contract.
2. PART 2 – PRODUCTS (NOT USED)
3. PART 3 – EXECUTION (NOT USED)
4. PART 4 - MEASUREMENT AND PAYMENT (NOT USED)
END OF SECTION
Rev. Date 2/2022 Union Creek Well Pump Replacement 01025 - 1/3 Measurement and Payment
SECTION 01025
MEASUREMENT AND PAYMENT
1. PART 1 - GENERAL
1.01 SUMMARY
A. Measurement and payment for contract work will be made only for and under those pay items included in the Schedule of Items. All other work, labor, materials, equipment, and incidentals necessary to successfully complete the project will be considered as included in the payment for items shown. This section defines the method of measurements and basis of payment for work items listed in the Schedule of Items.
B. Not all units and measurement methods may be used under this Contract.
1.02 DETERMINATION OF QUANTITIES
A. The following measurements and calculations shall be used to determine contract quantities for payment.
1. For individual construction items, longitudinal and lateral measurements for area computation shall be made horizontally or corrected to horizontal measurement unless otherwise specified. Measurements for geotextiles, netting, and erosion control blankets shall be along slope lines.
2. For items that are measured by the linear foot, such as pipe culverts, fencing, guardrail, piping, utilities, and underdrains, measurement shall be made parallel to the base of foundation upon which the structures are placed.
3. For standard manufactured items (such as fence, wire, plates, rolled shapes, pipe conduits) identified by gauge, weight, section dimensions, and so forth, such identifications shall be considered the nominal weights or dimensions.
Unless controlled by tolerances in cited specifications, manufacturer's tolerances shall be accepted.
1.03 UNITS OF MEASUREMENT
A. Payment shall be by units defined and determined according to U.S. Standard measure and by the following:
1. Each (EA): One complete unit, which may consist of one or more parts.
2. Linear Foot (LF): Measurement of work along its length from point-to-point;
parallel to the base or foundation. Do not measure overlaps.
3. Lump Sum (LS): One complete unit, not directly measured. The bid amount is complete payment for all work described in the contract and necessary to complete the work for that item.
1.04 METHOD OF MEASUREMENT
A. One of the following methods of measurement for determining final payment is designated on the Schedule of Items for each pay item:
Rev. Date 2/2022 Union Creek Well Pump Replacement 01025 - 2/3 Measurement and Payment
1. ACTUAL QUANTITIES (AQ) - These quantities are determined from actual measurements of completed work.
2. DESIGNED QUANTITIES (DQ) - These quantities denote the final number or units to be paid for under the terms of the contract. They are based upon the original design data available prior to advertising the project. Original design data include the preliminary survey information, design assumptions, calculations, drawings, and the presentation in the contract. Changes in the number of units shown in the Schedule of Items may be authorized under any of the following conditions:
a. As a result of changes in the work authorized by the CO.
b. As a result of the CO determining that errors exist in the original design that causes a pay item quantity to change by 15 percent or more.
c. As a result of the Contractor submitting to the CO a written request showing evidence of errors in the original design that cause a pay item quantity to change by 15 percent or more. The evidence must be verifiable and consist of calculations, drawings, or other data that show how the designed quantity is believed to be in error.
3. LUMP SUM QUANTITIES (LSQ) - These quantities denote one complete unit of work as required by or described in the contract, including necessary materials, equipment, and labor to complete the job. They shall not be measured.
1.05 DEFINITION OF PAY ITEMS
A. 1200-1 Mobilization
1. See Specification 01200.
B. 11214-1 Submersible Pump Replacement (15 HP)
1. Item includes all work necessary for disassembly of existing equipment at well, removal of well seal, removal of downpipe, conductors, airline, and existing submersible pump. Installation of new pump, restraints, conductors (salvage and reuse existing unless item 11214-3 is awarded), drop pipe (salvage and reuse existing unless item 11214-4 is awarded), airline, conduit and all other existing equipment as needed. Disposal of equipment. All other materials, labor, and equipment as needed to complete the installation of a new submersible pump fully functional.
2. Payment will be made at the lump sum price stated in the Schedule of Items.
C. 11214-2 System Start Up and Water Testing
1. Incudes all other materials, labor, and incidentals for the system start up and functional verification. Also includes bacteriological water sampling, laboratory analysis, and reporting.
2. Payment will be made at the lump sum price stated in the Schedule of Items.
D. 11214-3 Down Well Conductors (3 - #4 plus 1 - #8 ground)
1. Option Item, only complete if ordered in writing by the Contracting Officer.
2. Includes all required electrical conductors, connectors, attachments, conduit, other requirements, and the disposal of the old conductors.
Rev. Date 2/2022 Union Creek Well Pump Replacement 01025 - 3/3 Measurement and Payment
3. Payment will be made at the unit price stated in the Schedule of Items.
Measurement will be made per linear foot from the wall mounted junction box to the submersible pump. Only one measurement will be made and not duplicated for individual conductors.
E. 11214-4 Down Well Pipe (2 ½” Schedule 40 Galvanized Steel)
1. Option Item, only complete if ordered in writing by the Contracting Officer.
2. Includes all materials, labor, and equipment as needed to complete the installation of new pipe and disposal of old pipe.
3. Payment will be made at the unit price stated in the Schedule of Items.
Measurement will be made per linear foot from the well head to the submersible pump.
2. PART 2 – PRODUCTS (NOT USED)
3. PART 3 – EXECUTION (NOT USED)
4. PART 4 - MEASUREMENT AND PAYMENT (NOT USED)
Rev. Date 02/2022 Union Creek Well Pump Replacement 01200 - 1/1 Mobilization
SECTION 01200
MOBILIZATION
1. PART 1 - GENERAL
1.01 SUMMARY
A. This work shall consist of preparatory work and operations necessary for the movement of personnel, equipment, supplies, and incidentals to the project site, and for all other work and operations that must be performed or that cause costs to be incurred prior to beginning work on the various items on the project site.
2. PART 2 - PRODUCTS (NOT USED)
3. PART 3 - EXECUTION (NOT USED)
4. PART 4 - MEASUREMENT AND PAYMENT
4.01 PROGRESS PAYMENTS WILL BE MADE AS FOLLOWS:
A. When 5 percent or more of the original contract amount is earned from other pay items, 50 percent of the amount for mobilization, or 5 percent of the original contract amount, whichever is less, will be paid.
B. When 10 percent or more of the original contract amount is earned from other pay items, 100 percent of the amount for mobilization, or 10 percent of the original contract amount, whichever is less, will be paid.
C. Upon completion of all work on the project, any unpaid amount for mobilization will be paid.
D. The total of all payments shall not exceed the original contract amount for this item.
4.02 BASIS OF PAYMENT
A. Payment will be made under:
PAY ITEM DESCRIPTION PAY UNIT
01200-1 Mobilization Lump Sum
Date February 2022 Union Creek Well 11214 - 1/8 Pump Replacement
SECTION 11214
SUBMERSIBLE WATER WELL PUMP WITH MOTOR
1. PART 1 - GENERAL
1.01 SUMMARY
A. This section specifies the replacement of a submersible water well pump and related accessories at the Union Creek Well.
1.02 SUBMITTALS
A. Submit the following for review and approval by the CO:
1. Product data, performance curve, horsepower, and operation and maintenance manual for submersible pump and motor.
2. Motor nameplate data and wiring diagram for motor starting capacitor and relay. Provide make and model number of starting capacitor and relay unit.
3. Down well conductor product data.
4. Down well pipe product data.
B. In addition, provide the following:
1. Written record (sticker or other) to be placed in pumphouse describing pump, motor, rating, depth of installation, and date.
2. Bacteriological water test results.
1.03 LOCATION
A. The Union Creek site is located on the Rogue River-Siskiyou National Forest approximately 12 miles north of Prospect, Oregon along State Highway 62.
Approximately 1/4 mile south of Union Creek, turn right on Forest Road 6230, proceed approximately 1/2 mile with the well house on the right after crossing cattleguard. See attached site map for well location.
1.04 SITE BACKGROUND
A. The Union Creek water system serves the Union Creek resort, Beckie’s Café, Cabins, the Union Creek Campground, the Union Creek Wayside, and the Farewell Bend Campground.
B. The existing ground water well was constructed in 1997 and provides potable water to the facilities identified above. The Oregon Health Authority has regulatory oversight, viewing the system as a Public Water System with further classification as a Transient Non-Community Water System (OHA ID #4192683).
1.05 EXISTING CONFIGURATION
A. The well pumps potable water to a 30,000-gallon, above ground tank approximately 1 mile east of the well. The tank serves to provide storage and system pressure.
B. Well casing: 8” diameter (to depth of 138’) C. Total well depth: 625’ D. Well liner: 6” diameter, perforated from depth of 420’ to 440’
Date February 2022 Union Creek Well 11214 - 2/8 Pump Replacement
E. Pump: 15 horsepower, 6-inch Jucuzzi SandHandler Model 15S675-15, 15 stage, single phase (230v), 3450 RPM with Franklin motor. Installed August of 1998. See Figure-1 below for manufacturer’s published performance information.
F. Pump set at a depth of 483’
Figure-1 Existing Equipment Performance
Date February 2022 Union Creek Well 11214 - 3/8 Pump Replacement
G. Drop pipe: 2 ½” galvanized steel H. Airline to depth of 481’ I. Conductors: 3 - #4 plus 1 - #8 ground in 1 ¼” flexible conduit from wall mounted junction box to well head, see Figure-2 below (pump conductors enter topside of box).
J. Operable roof hatch (30”x36”) is present and aligned over well.
K. Well head equipment: Sanitary seal, tee, level gauge, sample tee, air release, valve, see
Figure-3 below.
Figure-2 Wall Mounted Junction Box
Conductors from well
Conductors from starter panel
Date February 2022 Union Creek Well 11214 - 4/8 Pump Replacement
Figure-3 Existing Well
2. PART 2 – PRODUCTS
2.01 GENERAL
A. The full extent of materials required to implement this work may not be quantified herein. The intent of this project is to provide all necessary equipment and appurtenances for a complete and functional system.
Valve-A Through Wall Discharge
Valve-B
Sample Tap
Date February 2022 Union Creek Well 11214 - 5/8 Pump Replacement
B. Provide robust, quality products and materials meeting applicable codes and standards with an expected minimum service life.
C. Unless otherwise noted, furnish all new material and equipment; the standard design and product of manufacturers regularly engaged in the production of such equipment.
D. All materials in contact with potable water shall comply with applicable National Sanitation Foundation (NSF) Standards. Provide products clearly marked with NSF certification or furnish documentation demonstrating NSF compliance.
E. Plumbing, fittings, and other appurtenances shall be compatible with equipment installed and existing plumbing connected to and suitable for intended use.
2.02 SUBMERSIBLE PUMP AND MOTOR
A. Performance:
1. 15 horsepower motor rating, 75 gallons per minute minimum at a total dynamic head of 575’. New pump and motor shall closely equal performance of existing equipment identified in section 1.05-E.
B. Pump:
1. Case.
a. Stainless Steel.
2. Bowls, Impellers, Guide Vanes, Screen.
a. Stainless steel, bronze or mineral and algae-resisting plastic.
3. Check Valve.
a. Stainless steel or bronze poppet-type, 125 psi rated.
4. Shaft.
a. Stainless Steel.
5. Wear Rings.
a. Stainless steel for plastic impellers.
C. Pump Motor:
1. Motor shall be specifically designed, mechanically and electrically, for submerged service. Provide hermetically sealed, water lubricated motor with stainless steel outer shell and stainless-steel bolts. Furnish motor with a field replaceable plug-in power lead connector, stainless steel output shaft, bronze bearings, bottom thrust bearing, and pressure equalizing diaphragm. Motor to have external running and starting capacitors and relay. Motor to be Franklin or approved equal.
2. Provide motor nameplate for power supply voltage as follows:
a. Single phase, 230 volts
2.03 DOWN WELL CONDUCTORS
A. 3 - #4 AWG stranded copper conductors plus ground conductor, type RW neoprene jacket, UL approved, color coded and designed specifically for submersible pump installations.
B. Splice kit
1. Resin insulation in poured kits, 1 kit per conductor.
Date February 2022 Union Creek Well 11214 - 6/8 Pump Replacement
C. Cable tie
1. One piece nylon, locking non-releasable type, 3/16 inch wide, 50 pounds minimum loop tensile strength. Panduit Pan-ty PLT3S or approved equal.
2.04 DOWN WELL PIPE
A. 2 ½” diameter Galvanized steel pipe, ASTM A53/A Schedule 40.
B. Fittings: ANSI B16.3 galvanized.
C. Joints: Threaded and coupled.
D. Bleeder Valve: ¾” diameter, brass or bronze body.
3. PART 3- EXECUTION
3.01 WORK PERIOD
A. Due to increased levels of water use during the recreation season, onsite work shall only be performed during the period of October 1, 2022, through November 15, 2022. This period may be extended beyond November 15th with CO approval as weather and snow permits.
B. Provide onsite work schedule detailing dates and times for well shut down. Shut down of well shall be limited to not more than 72 hours total time (3 days) with 14 days advance notice. Shut down shall not occur on Saturday or Sunday. Shut down time includes process for completing bacteriological water testing described in section 3.08.
3.02 WORK RESTRICTIONS
A. Contractor will have use of the immediate site around installation areas. Contractor’s use of premises will not block the use of premises by the Government nor users of the recreation site. Work will take place Monday through Friday, 8:00 am – 4:30 pm.
3.03 INSPECTION
A. Prior to commencement of work, perform a site inspection to review existing conditions and verify project requirements. Report to the Contracting Officer any concerns or factors that would affect completion of the work.
3.04 DELIVERY, STORAGE OF PRODUCTS
A. Deliver, store, and handle products using means and methods that will prevent damage, deterioration, and loss, including theft. Deliver products to project site in manufacturer’s original sealed container, complete with labels and instructions for handling, storing, protecting, and installing.
B. Inspect products on delivery to ensure compliance with Contract Documents and to ensure that products are undamaged and properly protected.
C. Store products that are subject to damage by the elements, under cover in a weathertight enclosure above ground.
3.05 DISINFECTION
A. Thoroughly disinfect all new and salvaged equipment and materials prior to placement in well by spraying or swabbing with a five percent hypochlorite solution.
Date February 2022 Union Creek Well 11214 - 7/8 Pump Replacement
3.06 INSTALLATION
A. Prior to system shut down, document configuration and installation of all existing piping and equipment affecting the work.
B. Shut down power supply to pump.
C. Close valve-A directly to the south of the well to isolate the well from the remainder of the system (see Figure-3).
D. Carefully disassemble existing well head and connecting piping as needed to allow removal of down pipe, conductors, airline, and pump. Salvage and protect all materials and equipment scheduled for reinstallation.
E. Install pump according to manufacturer's recommendations with intake at a depth of approximately 483’ (match existing).
F. Install downpipe (salvaged or new based on option item award), conductors (salvaged or new based on option item award), ties, torque arrestors, airline, and other related materials and equipment.
G. Reinstall well seal and all existing equipment to match existing configuration. Provide and install incidental fittings and appurtenances as needed.
3.07 EQUIPMENT SALVAGE
A. The existing submersible pump and motor shall be salvaged and remain the property of the Government. Place in the well house upon completion of the project. All other removed or excess material shall be removed from the site.
3.08 WELL FLUSHING AND BACTERIOLOGICAL WATER TESTING
A. Reference Figure-3 for existing valves and through wall discharge pipe.
B. Keep valve-A closed to prevent well water from leaving the pump house. Open valve-
B and flush well utilizing through wall discharge pipe. Provide temporary flexible hose and other methods to dissipate energy and direct water away from building. Flush thoroughly and test for the presence of residual disinfect, continue to flush until residual is no longer present.
C. After flushing is complete, take a water sample at the well sample tap. Perform laboratory analysis to determine the presence of Total Coliform and E. Coli. The Contractor shall mark all tests as “special” prior to delivery to the lab. Provide test results within 24 hours after flushing is completed.
D. If initial bacteriological test results are positive for either Total Coliform or E. Coli, shock the well and well head piping with a chlorine solution of 50 ppm, flush until disinfectant residual is no longer present and resample.
E. Once bacteriological test results are absent, open valve-A, close valve-B, and return the system to normal operation.
3.09 SYSTEM DEMONSTRATION
A. Upon substantial completion of work and absent bacteriological test results, coordinate with the CO a mutually agreed to time to demonstrate full operation.
Date February 2022 Union Creek Well 11214 - 8/8 Pump Replacement
4. PART 4 - MEASUREMENT AND PAYMENT
4.01 METHOD OF MEASUREMENT
A. Measurement will be made for all items shown below as described in Specification 01025.
4.02 BASIS OF PAYMENT
A. Payment will be made under (see schedule of items for base and option):
PAY ITEM DESCRIPTION PAY UNIT
11214-1 Submersible Pump Replacement (15 HP) LS 11214-2 System Start Up and Water Testing LS 11214-3 Down Well Conductors (3 - #4 plus 1 - #8) LF 11214-4 Down Well Pipe (2 ½” Schedule 40 Galvanized Steel) LF
File details come from the government source that posted it. Updated .