1240BH24R0008 - Project Drawings.pdf
PDF 2 MB Posted
- Attached to
- Whiskey Creek Bridge Rehabilitation
- Solicitation number
- 1240BH24R0008
About this file
This set of project drawings and related federal contract opportunity posting are for the Whiskey Creek Bridge Rehabilitation project. The project drawings provide construction details for rehabilitating an existing timber bridge located on the Rogue River-Siskiyou National Forest. The drawings show plans, elevations, sections, and details for replacing the bridge's decking and rail system with glued-laminated materials, as well as approach work. The related federal contract opportunity posting provides additional context, with a solicitation number of 1240BH24R0008, solicitation name of Whiskey Creek Bridge Rehabilitation, opportunity type of solicitation, and responsible agency as the Department of Agriculture Forest Service R6-Pacific Northwest Region. The posting date for solicitation documents is given as February 14, 2024.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BRIDGE SITE
SHEET of
United States Department of Agriculture Forest Service
WHISKEY CREEK BRIDGE REHABILITATION
RECOMMENDED BY:
APPROVED:
REHLM Staff Officer
Date
Date
Director of Engineering Date
Project Manager Date
RO Structural Engineer
OREGON
JOSEPHINE COUNTY
PACIFIC NORTHWEST REGION
ROGUE RIVER-SISKIYOU NATIONAL FOREST
WILD RIVERS RANGER DISTRICT
PROJECT SITE
DRAWING INDEX
TITLESHEET
TITLE SHEET
VICINITY MAP2
R34865 - 2 TYPICAL SECTIONS4
ROADWAY CROSS-SECTIONS
7 R34865 - 5 SUPERSTRUCTURE
R34865 - 3 PLAN & PROFILE
R34865 - 1 ESTIMATED QUANTITIES AND GENERAL NOTES
R34865 - 7 ABUTMENT DETAILS
R34865 - 4 GENERAL LAYOUT
TOTAL NUMBER OF SHEETS = 11
Lat. 42.0224, Long. -123.7741
PROJECT SITE
FSR 4402000 - MP 5.4
(STRUCTURE NO. 061104000001062)
R34865 - 6 SUPERSTRUCTURE DETAILS
ROADWAY CROSS-SECTIONS10
Lat. 42.0224, Long. -123.7741
District Ranger Date
RIV
ER
Cave
O
Holland
O'Brien
Waldo
Junction
DEL NORTE CO S
Takilma
E CO
Fort Briggs
Browntown
Bridgeview
JO
S
E P
H
IN
E C
O
C U
R R
Y C
O
BRIDGE SITE
LEGEND
FOREST COLLECTOR ROAD
COUNTY ROAD
WHISKEY CREEK BRIDGE REHABILITATION T.41S., R.09W., SECTION 9, WILLAMETTE MERIDIAN
U.S. HIGHWAY
STATE ROAD
DISTRICT
WILD
RIVERS
RANGER
DRAWN
DESIGNER
STAMPS, LOGOS, AND SEALS
PROJECT NAME
DRAWING TITLE
CHECKED
ARCHIVE NO.DATE
PROJECT NO.
DRAWING SHEET NO.
OFSHEET
United States Department of Agriculture Forest Service
9/6 /23
:0
0 D
AV
ID
SC
OV
EL
L C:
\U
SE
RS
\D
AV
ID
SC
OV
EL
L\
DO
CU
ME
NT
S\
BR
ID
GE
P
RO
JE
CT
S\ W
HI
SK
EY
C
RE
EK
\A
CA
D\ 2 -
V
IC
IN
IT
Y
MA
P.
DW
G;
R06
PACIFIC NORTHWEST REGION
WHISKEY CREEK
BRIDGE
REHABILITATION
ROGUE RIVER-SISKIYOU
NATIONAL FOREST
WILD RIVERS DISTRICT
VICINITY MAP
David Scovell
David Scovell
Kathy Van Hecke
VICINITY MAP
PAY ITEM DESCRIPTIONPAY ITEM NUMBER NOTESQUANTITY PAY UNIT
Member Commercial Grade
Member Combination Symbol
DRAWN
DESIGNER
STAMPS, LOGOS, AND SEALS
PROJECT NAME
DRAWING TITLE
CHECKED
ARCHIVE NO.DATE
PROJECT NO.
DRAWING SHEET NO.
OFSHEET
United States Department of Agriculture Forest Service
9/6 /23
:1
5 D
AV
ID
SC
OV
EL
L C:
\U
SE
RS
\D
AV
ID
SC
OV
EL
L\
DO
CU
ME
NT
S\
BR
ID
GE
P
RO
JE
CT
S\ W
HI
SK
EY
C
RE
EK
\A
CA
D\
ES
TI
MA
TE
D
QU
AN
TI
TI
ES
.D
W G;
R06
PACIFIC NORTHWEST REGION
WHISKEY CREEK
BRIDGE
REHABILITATION
ROGUE RIVER-SISKIYOU
NATIONAL FOREST
WILD RIVERS DISTRICT
ESTIMATED QUANTITIES
AND
GENERAL NOTES
David Scovell
David Scovell
Kathy Van Hecke
ROADWAY SECTION - Bridge to End of Project
DRAWN
DESIGNER
STAMPS, LOGOS, AND SEALS
PROJECT NAME
DRAWING TITLE
CHECKED
ARCHIVE NO.DATE
PROJECT NO.
DRAWING SHEET NO.
OFSHEET
United States Department of Agriculture Forest Service
R06
PACIFIC NORTHWEST REGION
WHISKEY CREEK
BRIDGE
REHABILITATION
ROGUE RIVER-SISKIYOU
NATIONAL FOREST
WILD RIVERS DISTRICT
TYPICAL SECTIONS
David Scovell
David Scovell
Kathy Van Hecke
ROADWAY SECTION - "L" Station 1+00 to "L" Station 2+00
OBJECT MARKER TYPE 3 INSTALLATION
ROADWAY SECTION - "L" Station 2+00 to Bridge
DESIGNER
STAMPS, LOGOS, AND SEALS
PROJECT NAME
DRAWING TITLE
CHECKED
ARCHIVE NO.DATE
PROJECT NO.
DRAWING SHEET NO.
OFSHEET
United States Department of Agriculture Forest Service
R06
PACIFIC NORTHWEST REGION
WHISKEY CREEK
BRIDGE
REHABILITATION
ROGUE RIVER-SISKIYOU
NATIONAL FOREST
WILD RIVERS DISTRICT
PLAN & PROFILE
David Scovell
David Scovell
Kathy Van Hecke
5PROFILE
PLAN
BE
G
IN
P
R O
JE
C
T
EN
D
P R
O
JE
C T
W hi sk ey
C re ek
CP2
CP1
EN
D
P R
O
JE
C T
BEGIN PROJECT
CONTROL POINT TABLE
Easting Northing Elevation Description
CP 1 10000.00 5000.00 500.0 5
8" Iron rod
CP 2 10061.424 4908.953 496.85 Metal spike
Point Number
Begin Project 10114.214 5060.026 497.4 - PI - Curve 1 10087.244 5050.512 - - PI - Curve 2 10003.114 5029.824 - -
End Project 10051.438 4882.347 498.0 - PI - Curve 3 10041.186 4901.927 - -
Alignment and grade, as shown on the plans, are subject to minor field adjustments
Construction slash shall be disposed of as specified by Item 20102. Slash disposal areas shall be as approved by the Contracting Officer (CO). Construction slash or residual slash shall not be buried within roadway embankments.
Clearing limits on all roads shall be a minimum of 6 feet from the finished subgrade shoulder or 12" beyond the top of cut, whichever is greater.
ROADWAY CONSTRUCTION NOTES
"V" DITCH SECTION
STAMPS, LOGOS, AND SEALS
PROJECT NAME
DRAWING TITLE
CHECKED
ARCHIVE NO.DATE
PROJECT NO.
DRAWING SHEET NO.
OFSHEET
United States Department of Agriculture Forest Service
R06
PACIFIC NORTHWEST REGION
WHISKEY CREEK
BRIDGE
REHABILITATION
ROGUE RIVER-SISKIYOU
NATIONAL FOREST
WILD RIVERS DISTRICT
GENERAL LAYOUT
David Scovell
David Scovell
Kathy Van Hecke
W hi sk ey
C re ek
CP1
CP2
PLAN
Scale: 3 8" = 1'-0"
℄ Structure ("L" Line)
6" screws, typ
Stagger running planks as shown (repeat pattern)
W hiskeyC reek
RUNNING PLANK NOTES
RP1
RP4
RP2
Existing abutment
Existing abutment
Remove & replace existing nail-laminated deck, see SUPERSTRUCTURE DETAILS sheet
Timber Running Plank Schedule: (See PLAN) (7)-RP1 - 3x12 x 15'-2" (21)-RP2 - 3x12 x 16'-0" (7)-RP3 - 3x12 x 15'-0 12" (7)-RP4 - 3x12 x 7'-2" (7)-RP5 - 3x12 x 7'-0 12" (2)-RP6 - 3x12 x 13'-6" (verify)
Contractor to field verify dimensions.
Fasten running planks to glued-laminated timber deck with two rows of 516"Ø x 6" GRK RSS structural screws (or approved equal) per plank @ 24"± centers.Alternate centers with two screws at each end of plank.
Existing timber girders to remain, inspect per Note 1 on this sheet
New 3x6 x 17'-0" backing plank
DRAWN
DESIGNER
STAMPS, LOGOS, AND SEALS
PROJECT NAME
DRAWING TITLE
CHECKED
ARCHIVE NO.DATE
PROJECT NO.
DRAWING SHEET NO.
OFSHEET
United States Department of Agriculture Forest Service
9/6 /23
:2
6 D
AV
ID
SC
OV
EL
L C:
\U
SE
RS
\D
AV
ID
SC
OV
EL
L\
DO
CU
ME
NT
S\
BR
ID
GE
P
RO
JE
CT
S\ W
HI
SK
EY
C
RE
EK
\A
CA
D\
SU
PE
RS
TR
UC
TU
RE
D
ET
AI
LS
.D W
G;
R06
PACIFIC NORTHWEST REGION
WHISKEY CREEK
BRIDGE
REHABILITATION
ROGUE RIVER-SISKIYOU
NATIONAL FOREST
WILD RIVERS DISTRICT
SUPERSTRUCTURE
David Scovell
David Scovell
Kathy Van Hecke
6 3 4" x 40 12" x 17'-0" glued-laminated deck panel
15 - 6 3 4" x 33" x 17'-0" glued-laminated deck panels
6 3 4" x 42" x 17'-0" glued-laminated deck panel
48'-1 12" out-to-out glued-laminated deck panels and curbs
℄ curb block ℄ curb block
RP3
RP2 RP2 RP5
RP1 RP2 RP3
RP4 RP2 RP2 RP5
9 curb blocks spaced @ 5'-6" = 44'-0"2'-0" 2 '- 1 12"
New glued-laminated bridge curb, see SUPERSTRUCTURE DETAILS sheet
SCOPE OF WORK
1. Remove existing nail-laminated timber deck, and curb system. Coordinate inspection of tops of existing girders with contracting officer. Remove and replace decayed or damaged laminations as directed by the CO. Apply preservative field treatment full length of girders (see General Notes),
2. Remove miscellaneous timbers attached to girders and supporting underside of deck near beginning of bridge as directed by Contracting Officer (CO).
3. Clean bearing areas of soil and other debris, clean bearing assemblies, remove rust as directed,
4. Pressure wash existing concrete abutments and wingwalls, remove loose concrete and patch repair concrete as shown on ABUTMENT DETAILS sheet,
5. Install new glued-laminated deck panels and curb system, see SUPERSTRUCTURE DETAILS sheet,
6. Install new timber running planks on new deck,
7. Install timber backing planks at ends of new deck,
8. Install gabions at abutments as shown on ABUTMENT DETAILS sheet,
9. Modify bridge approaches as shown on PLAN & PROFILE sheet, '-0
" o ut
-to -o ut n ew g lu ed
-la m in at ed d ec k
'-2
1 2" c le ar w id th (f ac e-to -fa ce o f c ur bs
4" cu rb
4" cu rb
N ew x6 x
7' -0 ba ck in g pl an k
NOTE:
THESE PLANS ILLUSTRATE THE GOVERNMENTS BEST ESTIMATE
OF THE SITE CONDITIONS BASED ON THE ORIGINAL DRAWINGS
AND FIELD MEASUREMENTS.
THE CONTRACTOR SHALL VERIFY ACTUAL CONDITIONS,
- BOTH NEW AND EXISTING - PRIOR TO ORDERING MATERIALS
Fasten deck panels to each girder with min. of 3 - 12" ring shank nails equally spaced and offset as shown
4"
4"
3 per panel @ 33" panels
4 per panel @ end panels
℄ Girder
℄ Girder
℄ Girder
R P6
R P6 ro w s of x1 ru nn in g pl an ks
Remove existing timber framing at underside of deck per Note 2
Bridge curb system, see details this sheet
Existing treated timber girders (to remain)
14 rows~3x12 rough sawn timber running planks
17'-0" out-to-out glued-laminated deck panels
15'-2 12" clear width
5'-6" 5'-6"
6 3 4" glued-laminated deck panels See GENERAL LAYOUT Sheet
10 3 4" 10 3 4"
TIMBER CURB CONNECTION DETAILS
Scale: 1" = 1'-0"
ELEVATION - CURB BLOCK ELEVATION - CURB RAIL SPLICE
PLAN - ANCHOR PLATEPLAN - CURB BLOCK
2'-4"
4"
5" 10" 5"
4"
4"
4"
5" 10" 5"
4"
4"
7"
2'-0"
2"2"
Fabricate From 3 8" Plate
4"Ø bolt & nut
2'-4"
Deck panels
Curb block
9" 1'
-0
10 3 4"
1' -9
2'-4" Curb rail
Curb block
1 2"
Traffic face
Curb rail
Deck panels
Half-lap splice
BRIDGE CURB DETAILS
Scale: 1 12" = 1'-0"
TYPICAL DECK SECTION
Scale: 12" = 1'-0"
1'
9"
1' -0
9"
10 3 4"
ELEVATION SECTION
℄ Curb Block
℄ Ext'g Structure ("L" Line)
See GIRDER REPAIR DETAILS, this sheet
GIRDER REPAIR DETAILS
Scale: 1 12" = 1'-0"
11"
Existing timber girder
Remove & replace top lamination where decayed or damaged (verify) ve rif y
ELEVATION SECTION
Tight fit, typ
Glue and nail new lamination
3" Space nails sets @ 12"±
2-40d ring shank nails
3"
10 3 4" x 9" glued-laminated curb rail
6 3 4" glulam deck panels
Anchor plate, see detail this sheet
Anchor plate, see detail this sheet
Fabricate blocks from 103 4"x 12" glued-laminated material
℄ rail & block ℄ rail, block & ⅊
℄ Block
℄ 13 16"Ø holes for 3 4"Ø bolts
Anchor plate, see detail this sheet
4"Ø x 2'-7" bolt
3 5 8"
3 12"
Malleable iron washers typical against wood curbcurb
Plane rough sawn or surfaced 2x12 material to produce required finished dimension
[Pay Item 55702]
DRAWN
DESIGNER
STAMPS, LOGOS, AND SEALS
PROJECT NAME
DRAWING TITLE
CHECKED
ARCHIVE NO.DATE
PROJECT NO.
DRAWING SHEET NO.
OFSHEET
United States Department of Agriculture Forest Service
9/6 /23
:2
6 D
AV
ID
SC
OV
EL
L C:
\U
SE
RS
\D
AV
ID
SC
OV
EL
L\
DO
CU
ME
NT
S\
BR
ID
GE
P
RO
JE
CT
S\ W
HI
SK
EY
C
RE
EK
\A
CA
D\
SU
PE
RS
TR
UC
TU
RE
D
ET
AI
LS
.D W
G;
R06
PACIFIC NORTHWEST REGION
WHISKEY CREEK
BRIDGE
REHABILITATION
ROGUE RIVER-SISKIYOU
NATIONAL FOREST
WILD RIVERS DISTRICT
SUPERSTRUCTURE
DETAILS
David Scovell
David Scovell
Kathy Van Hecke
1 3 4"
1 3 4"
12" ring shank nails (typical)
Fabricate curb rails from 103 4"x 9" glued-laminated material
10 3 4"x 12" x 2'-4" glued-laminated curb block
Contractor to coordinate inspection of girders after removal of deck. Removal and replacement of decayed laminations to be performed where ordered by the contracting officer (CO).
3'-0" 3'-0"
Malleable iron washer typical against wood
9" 1'
-0 "1'
-9
ELEVATION VIEW A-A
ABUTMENT PLAN
DRAWN
DESIGNER
STAMPS, LOGOS, AND SEALS
PROJECT NAME
DRAWING TITLE
CHECKED
ARCHIVE NO.DATE
PROJECT NO.
DRAWING SHEET NO.
OFSHEET
United States Department of Agriculture Forest Service
9/6 /23
:3
8 D
AV
ID
SC
OV
EL
L C:
\U
SE
RS
\D
AV
ID
SC
OV
EL
L\
DO
CU
ME
NT
S\
BR
ID
GE
P
RO
JE
CT
S\ W
HI
SK
EY
C
RE
EK
\A
CA
D\
AB
UT
ME
NT
D
ET
AI
LS
.D
W G;
R06
PACIFIC NORTHWEST REGION
WHISKEY CREEK
BRIDGE
REHABILITATION
ROGUE RIVER-SISKIYOU
NATIONAL FOREST
WILD RIVERS DISTRICT
ABUTMENT DETAILS
David Scovell
David Scovell
Kathy Van Hecke
ABUTMENT ELEVATION
CONCRETE REPAIR NOTES:
JOINT DETAIL
A
A
STAMPS, LOGOS, AND SEALS
PROJECT NAME
DRAWING TITLE
CHECKED
ARCHIVE NO.DATE
PROJECT NO.
DRAWING SHEET NO.
OFSHEET
United States Department of Agriculture Forest Service
9/6 /23
:5
4 D
AV
ID
SC
OV
EL
L C:
\U
SE
RS
\D
AV
ID
SC
OV
EL
L\
DO
CU
ME
NT
S\
BR
ID
GE
P
RO
JE
CT
S\ W
HI
SK
EY
C
RE
EK
\A
CA
D\
PL
AN
P
RO
FI
LE
2.D W
G;
R06
PACIFIC NORTHWEST REGION
WHISKEY CREEK
BRIDGE
REHABILITATION
ROGUE RIVER-SISKIYOU
NATIONAL FOREST
WILD RIVERS DISTRICT
ROADWAY
CROSS- SECTIONS
David Scovell
David Scovell
Kathy Van Hecke
ROADWAY CROSS-SECTIONS
"L" STATION 1+75
"L" STATION 1+50
"L" STATION 1+25
"L" STATION 1+00
"L" STATION 2+00
"L" STATION 2+25
STAMPS, LOGOS, AND SEALS
PROJECT NAME
DRAWING TITLE
CHECKED
ARCHIVE NO.DATE
PROJECT NO.
DRAWING SHEET NO.
OFSHEET
United States Department of Agriculture Forest Service
9/6 /23
:5
4 D
AV
ID
SC
OV
EL
L C:
\U
SE
RS
\D
AV
ID
SC
OV
EL
L\
DO
CU
ME
NT
S\
BR
ID
GE
P
RO
JE
CT
S\ W
HI
SK
EY
C
RE
EK
\A
CA
D\
PL
AN
P
RO
FI
LE
2.D W
G;
R06
PACIFIC NORTHWEST REGION
WHISKEY CREEK
BRIDGE
REHABILITATION
ROGUE RIVER-SISKIYOU
NATIONAL FOREST
WILD RIVERS DISTRICT
ROADWAY
CROSS- SECTIONS
David Scovell
David Scovell
Kathy Van Hecke
"L" STATION 3+50.44
ROADWAY CROSS-SECTIONS
"L" STATION 3+15
"L" STATION 3+00
"L" STATION 3+25
"L" STATION 3+40
| 2023-09-21T11:34:31-0700 | |
| BRIAN WHITE |
| 2023-09-22T12:52:21-0700 | |
| Kathryn L. Van Hecke, PE |
| 2023-09-13T14:59:36-0700 | |
| ERIC GRIM |
| 2023-10-11T12:36:35-0700 | |
| CHRISTY DARDEN |
| 2023-09-22T12:08:10-0700 | |
| SCOTT BLOWER |