This solicitation is for a construction project to prepare a recreation vehicle site at the Sand Lake Recreation Area on the Siuslaw National Forest in Oregon. The scope of work includes extending existing water, septic, and electrical utilities, along with minor site work. Contractors will trench and excavate the site, install plumbing components including a water line and outdoor faucet, extend electrical service and install a meter base and power pedestal, and perform finish grading. Submittals are due by August 18, 2023 and the estimated start date is September 11, 2023, with all work to be completed within 30 days of notice to proceed. The contractor will be responsible for obtaining permits and coordinating inspections. Payment will be made as lump sums for trenching, utilities work with the local utility district, electrical installation, and plumbing work.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment1.pdf | ||
| Solicitation.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1240BH23Q0054
1. REQUEST NO.
5a. ISSUED BY
NAME
a. NAME
c. STREET ADDRESS
d. CITY
10. PLEASE FURNISH QUOTATIONS TO
THE ISSUING OFFICE IN BLOCK 5a ON
OR BEFORE CLOSE OF BUSINESS (Date)
2. DATE ISSUED 3. REQUISITION/PURCHASE REQUEST NO. 4. CERT. FOR NAT. DEF.
UNDER BDSA REG. 2
AND/OR DMS REG.1
RATING
6. DELIVERY BY (Date)
7. DELIVERY
9. DESTINATION
a. NAME OF CONSIGNEE
b. STREET ADDRESS
PAGE OF PAGES
5b. FOR INFORMATION CALL: (No collect calls)
TELEPHONE NUMBER
AREA CODE NUMBER
8. TO:
b. COMPANY
e. STATE f. ZIP CODE
c. CITY
d. STATE e. ZIP CODE
IMPORTANT: This is a request for information, and quotations furnished are not offers. If you are unable to quote, please so indicate on this form and return it to the address in Block 5a. This request does not commit the Government to pay any costs incurred in the preparation of the submission of this quotation or to contract for supplies or services. Supplies are of domestic origin unless otherwise indicated by quoter. Any representations and/or certifications attached to this Request for Quotations must be completed by the quoter.
11. SCHEDULE (Include applicable Federal, State and local taxes)
THIS RFQ
REQUEST FOR QUOTATION
(THIS IS NOT AN ORDER)
IS IS NOT A SMALL BUSINESS SET ASIDEX
07/25/2023 1098597
1 68
3200 SW JEFFERSON WAY
CORVALLIS OR 97331
USDA-FS CSA NORTHWEST 6
30 Days After Notice to Proceed
USDA FOREST SERVICE
SIUSLAW NATIONAL FOREST
3200 SW JEFFERSON WAY
CORVALLIS
OR 97331
541 750-7116DARCY RAPOZA
08/18/2023 1600 PT
FOB DESTINATION
OTHER
(See Schedule)X
ITEM NO.
(a)
SUPPLIES/SERVICES
(b)
QUANTITY
(c)
UNIT
(d)
UNIT PRICE
(e)
AMOUNT
(f)
Hebo Sand Lake RV Site Preparation Siuslaw National Forest Hebo Ranger District Tillamook County, OR
0001 Provide and install site improvements to prepare the site for connecting a recreation vehicle (RV) or other small structure on wheels. Work involves plumbing, septic, and electrical utilities, along with other minor site work.
Delivery: 30 Days After Notice to Proceed
12. DISCOUNT FOR PROMPT PAYMENT
a. 10 CALENDAR DAYS (%) b. 20 CALENDAR DAYS (%) c. 30 CALENDAR DAYS (%) d. CALENDAR DAYS
NUMBER PERCENTAGE
NOTE: Additional provisions and representations
13. NAME AND ADDRESS OF QUOTER
b. STREET ADDRESS
c. COUNTY
d. CITY e. STATE f. ZIP CODE
14. SIGNATURE OF PERSON AUTHORIZED TO
SIGN QUOTATION
16. SIGNER
a. NAME (Type or print)
c. TITLE (Type or print)
a. NAME OF QUOTER
AREA CODE
NUMBER
15. DATE OF QUOTATION
b. TELEPHONE are are not attached
AUTHORIZED FOR LOCAL REPRODUCTION
Previous edition not usable
STANDARD FORM 18 (REV. 6-95)
Prescribed by GSA - FAR (48 CFR) 53.215-1(a)
PART I—THE SCHEDULE
SECTION B--SUPPLIES OR SERVICES AND PRICES/COSTS
Hebo Sand Lake RV Site Preparation
Siuslaw National Forest Hebo Ranger District
Tillamook County, OR
B-1 SCHEDULE OF ITEMS
Item No. Description MOM
Pay Unit
Est Qty Unit Price Total Price
SOW-1 Trenching / Earthwork LSQ LS ALL n/a $ SOW-2 TPUD Services LSQ LS ALL n/a $ SOW-3 Electrical LSQ LS ALL n/a $ SOW-4 Plumbing LSQ LS ALL n/a $
GRAND TOTAL $
Note:
Payment for bond premiums in accordance with Clause 52.232-5, Payments under Fixed-Price Construction contracts, shall not be in addition to the contract price. (bonding only applies to contracts over $35,000)
For technical questions contact Craig Evans at (541) 750-7083 or craig.evans@usda.gov.
The estimated start work date is 11 September 2023. All work shall be completed within 30 calendar days of issuance of NTP.
UNIQUE ENTITY IDENTIFIER (UEI) from SAM.GOV ________________________
EMAIL ______________________________
NOTE: prospective awardee shall be registered and active in the System for Award Management (SAM) data base when submitting an offer, and shall continue to be registered until time of award, during performance, and through final payment of a contract resulting from this solicitation. Information on registration may be obtained via the internet at:
http://www.sam.gov. All contractors and vendors must complete the electronic version of the Representations and Certifications in the SAM system. If at the time of receipt of offers, an Offeror is not actively and successfully registered in the SAM database, the Offeror will not be considered for award.
mailto:craig.evans@usda.gov
SECTION C--DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK
C-1 SCOPE OF CONTRACT
The intent of this project is to provide and install site improvements to prepare the site for connecting a recreation vehicle (RV) or other small structure on wheels.
Contractors will be required to extend the existing water, septic, and electrical utilities, along with other minor site work. Work shall include all incidental equipment, materials, and labor to yield a complete installation that is ready to connect to an RV.
Coordinate work with Tillamook People’s Utility District (TPUD) to extend a new 200-amp service underground to the south side of the concrete RV pad. The cost of TPUD supplied equipment and labor shall be included in this Contract.
C-2 PROJECT LOCATION
The project site is located within the gated work center in the SLRA, just to the south of the West Winds parking lot. The physical address of the SLRA is 7000 Galloway Rd., Cloverdale, OR 97112. Refer to Attachment #1 – Vicinity Map for additional details.
C-3 MAGNITUDE OF CONSTRUCTION PROJECT
The Government’s estimate between $25,000 and $100,000.
C-4 TECHNICAL SPECIFICATIONS
452.211-72 Statement of Work/Specifications (FEB 1988) The Contractor shall furnish the necessary personnel, material, equipment, services and facilities (except as otherwise specified), to perform the Statement of Work/Specifications referenced in Section J.
452.211-73 Attachments to Statement of Work/Specifications (FEB 1988) The attachments to the Statement of Work/Specifications listed in Section J are hereby made part of this solicitation and any resultant contract.
C-5 PRODUCT SAMPLES AND/OR SUBMITTALS
The following product samples and/or submittals are required for this project:
Title Referenced by
Specification No Time of Government Approval After Submittal
Work Schedule Statement of Work 5 Business Days Concrete Statement of Work 5 Business Days Metal Fasteners and Hardware Statement of Work 5 Business Days Security Lighting and Accessories Statement of Work 5 Business Days RV Power Pedestal Statement of Work 5 Business Days Service Meter Base Statement of Work 5 Business Days Plumbing Pipe and Accessories Statement of Work 5 Business Days Outdoor Faucet and Accessories Statement of Work 5 Business Days Valve(s) and Valve Box(es) Statement of Work 5 Business Days Warning Tape for Buried Utilities Statement of Work 5 Business Days
(End of clause)
SECTION D--PACKAGING AND MARKING
For this section there are no clauses.
SECTION E--INSPECTION AND ACCEPTANCE
E-1 CLAUSES
52.246-12 Inspection of Construction (AUG 1996)
E-2 INSPECTION AND ACCEPTANCE (AGAR 452.246-70) (FEB 1988)
(a) The Contracting Officer or the Contracting Officer's duly authorized representative will inspect and accept the supplies and/or services to be provided under this contract.
(b) Inspection and acceptance will be performed at the project location.
E-3 INSPECTION AND TESTING PERFORMED BY GOVERNMENT
The Government will perform sampling, testing, and inspection of work in progress where these responsibilities are not expressly assigned to the Contractor by the Forest Service specifications or by the Special Project Specifications.
E-4 CONFORMITY WITH DRAWINGS AND SPECIFICATIONS
Unless working tolerances are specified, all work performed and materials furnished shall be in reasonably close conformity with lines, grades, cross-sections, dimensions, and material requirements shown on the drawings, indicated in the specifications, or designated on the ground. “Reasonably close conformity” is in compliance with reasonable and customary manufacturing and construction tolerances.
SECTION F--DELIVERIES OR PERFORMANCE
F-1 CLAUSES
52.242-14 Suspension of Work (APR 1984)
COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK
(FAR 52.211-10)(APR 1984)
The Contractor shall be required to (a) commence work under this contract within 7 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 30 calendar days after issuance of the Notice to Proceed. The time stated for completion shall include final cleanup of the premises.
F-2 OTHER REQUIREMENTS
SUSPENSION OF WORK FOR OTHER THAN GOVERNMENT'S CONVENIENCE
The Contracting Officer may issue orders to suspend the work wholly or in part for such period of time as deemed necessary because of: (1) weather or ground conditions when further prosecution of the work might cause environmental or resource damage to the project, access roads to the project, or adjacent property. Such action would include but not be limited to instances such as siltation of streams, damage to access roads, rutting of project roads which causes otherwise suitable soils to be muddy or unsuitable; or (2) failure of the Contractor to comply with specifications such as but not limited to placement of frozen material in fills, placing of asphalts at temperatures lower than those specified, performing work prior to prerequisite approvals, operating equipment not meeting fire requirements, or when conditions exist which do not meet safety requirements. Whether or not a suspend work notice is issued, the Contractor shall be responsible for correcting any damage caused by its operation, whether inside or outside project limits, at no cost to the Government. Such suspensions shall not be considered as suspensions for the Convenience of the Government under FAR 52.242-14, Suspension of Work, and shall not qualify for an equitable adjustment.
SECTION G--CONTRACT ADMINISTRATION DATA
G-1 CLAUSES
POST AWARD CONFERENCE (AGAR 452.215-73)(NOV 1996)
A post award conference with the successful offeror is required. It will be scheduled and held within TBD days after the date of contract award. The conference will be held via Microsoft TEAMS.
G-2 OTHER REQUIREMENTS
DESIGNATION OF CONTRACTING OFFICER'S REPRESENTATIVE
The COR is responsible for administering the performance of work under this contract. In no event, however, will any understanding, agreement, modification, change order, or other matter deviating from the terms of this contract be effective or binding upon the Government unless formalized by proper contractual documents executed by the Contracting Officer prior to completion of the contract.
The Contracting Officer should be informed as soon as possible or any actions or inactions by the Contractor or the Government which will change the required delivery or completion times stated in the contract, and the contract will be modified accordingly. (This does not apply to individual task assignments which were issued by the COR provided they do not affect the delivery schedule or performance period stated in the contract.)
On all matters that pertain to the contract terms the Contractor must communicate with the Contracting Officer. Whenever, in the opinion of the Contractor, the COR requests effort outside the scope of the contract, the Contractor should so advise the COR. If the COR persists and there still exists a disagreement as to proper contractual coverage, the Contracting Officer should be notified immediately, preferably in writing if time permits. Proceeding with work without proper contractual coverage could result in nonpayment or necessitate submittal of a contract claim.
SECTION H--SPECIAL CONTRACT REQUIREMENTS
H-1 CLAUSES
452.228-71 Insurance Coverage (NOV 1996) Pursuant to FAR clause 52.228-5, Insurance-Work on a Government Installation, the Contractor will be required to present evidence to show, as a minimum, the amounts of insurance coverage indicated below:
(a) Workers Compensation and Employer's Liability. The Contractor is required to comply with applicable Federal and State workers' compensation and occupational disease statutes. If occupational diseases are not compensable under those statutes, they shall be covered under the employer's liability section of the insurance policy, except when contract operations are so commingled with a Contractor's commercial operations that it would not be practical to require this coverage. Employer's liability coverage of at least $100,000 shall be required, except in States with exclusive or monopolistic funds that do not permit worker's compensation to be written by private carriers.
(b) General Liability. (1) The Contractor shall have bodily injury liability coverage written on a comprehensive form of policy of at least $500,000 per occurrence.
(c) Automobile Liability. The Contractor shall have automobile liability insurance written on a comprehensive form of policy. The policy shall provide for bodily injury and property damage liability covering the operation of all automobiles used in connection with performing the contract. Policies covering automobiles operated in the United States shall provide coverage of at least $200,000 per person and $500,000 per occurrence for bodily injury and $20,000 per occurrence for property damage or loss.
(d) Aircraft Public and Passenger Liability. When aircraft are used in connection with performing the contract, the Contractor shall have aircraft public and passenger liability insurance. Coverage shall be at least $200,000 per person and $500,000 per occurrence for bodily injury, other than passenger injury. Coverage for passenger injury shall be at least $200,000 multiplied by the number of seats or passengers, whichever is greater.
H-2 OTHER REQUIREMENTS
POTENTIAL SAFETY HAZARDS
(a) Data and information furnished or referred to below is for the Contractor's information. The
Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor. This list shall not be deemed to be all-inclusive. The Contractor shall bear the sole responsibility for taking all appropriate actions necessary to prevent accidents and injuries to individuals at the worksite.
(b) The following checked activities have been identified by the Government as potential safety hazards.
[ ] Confined space entry.
[x ] Temporary excavation/deep trenching/slope stability.
[ ] Tree falling.
[ ] Fall hazard from work heights exceeding six feet.
[ ] Blasting.
[ ] Traffic control on high-volume and/or high-speed and/or limited visibility roads.
[x ] Heavy equipment operation.
[ ] Tree climbing and/or tower climbing.
[ ] Fire hazards.
[ ] Hazardous materials handling.
[x ] Electrical hazard.
[x ] Hydraulic and/or pneumatic and/or other high pressure hazards.
[x ] Mechanical hazards such as pulleys, springs, etc.
[ ] Other __________________________________
INDUSTRIAL CAMPS
Forest Service regulations for Use of Campgrounds prohibit occupancy of developed recreation sites for other than primarily recreation purposes. No industrial camping will be authorized at these sites.
A special use permit is required on National Forest land for industrial camps. These permits are to be obtained by the Contractor through the Contracting Officer. Such permission, if granted, will be without charge to the Contractor but may include use restrictions.
One self-contained camp unit will be allowed at each staging area and equipment or supply dump for use by a watchman.
SALVAGE RIGHTS
No Contractor salvage rights exist under the contract unless specifically provided elsewhere herein.
SPECIAL EQUIPMENT CLEANING REQUIREMENTS
All earth moving equipment (loaders, excavators, dump trucks, etc.) moved to the job site shall be cleaned of weeds and their seeds prior to each entrance onto the National Forest lands.
Cleaning shall consist of the removal of all dirt, grease, debris, and materials that may harbor noxious weeds and their seeds. This may require the use of a pressure hose.
Equipment shall be made available for visual inspection by the Forest Service prior to entering Forest Service lands. The Contractor shall advise of a proposed date for mobilization.
Inspections will take place at mutually agreeable en-route locations in advance of entry onto National Forest lands.
Special care shall be taken to assure removal of the following noxious weeds and their seeds:
spotted knapweed (Centaurea maculosa) diffuse knapweed (C. diffusa) yellow starthistle (C. solstitialis) gorse (Ulex europaeus) rush skeletonweed (Chondrilla juncea) tansy ragwort (Senecio jecobaea) purple loosestrife (Lythrum salicaria) distaff thistle (Carthamus lanatus) scotch broom (Cytisus scoparius)
The Contractor shall take special care under this contract to prevent contamination of water at the work sites with any petroleum residues from mechanical equipment operations. This shall include daily inspection and cleaning as appropriate.
AVAILABILITY AND USE OF UTILITY SERVICES (FAR 52.236-14) (APR 1984)
(a) The Government shall make all reasonably required amounts of utilities available to the Contractor from existing outlets and supplies in the immediate vicinity of the work. The Contractor shall carefully conserve any utilities furnished without charge.
LANDSCAPE PRESERVATION
(a) Prevention of Oil Spills. If the Contractor maintains storage facilities for oil or oil products on site, appropriate preventive measures shall be taken to insure that any spill of such oil or oil products does not enter any stream or other waters of the United States or any of the individual states. If a spill of petroleum product should occur in water, the Contractor shall take immediate action to clean up or contain the spill, then immediately notify the Engineer and the Oregon
Emergency Response System (OERS), telephone 1-800-452-0311 or 1-503-378-4124, and then immediately notify the Contracting Officer.
Contractor shall have a SPILL RESPONSE KIT on the project whenever equipment is operating.
The spill kit shall be sufficient to absorb 34 gallons of oil, designed to float on the surface, while absorbing oil and repelling water. The KIT shall meet or exceed the physical properties of “New Pig Products Spill Kit #408”.
Oil absorbing mats are required under all stationary equipment, or equipment being serviced within the Forest Boundary to prevent leaking or spilled petroleum base products from contaminating soil and water resources. Such material will be furnished by Contactor and approved by Contracting Officer.
Servicing of all equipment shall be done only in the areas approved by the Contracting Officer.
If the total oil or oil products storage exceeds 1320 gallons or if any single container exceeds a capacity of 660 gallons, the Contractor shall prepare a Spill Prevention Control and Countermeasures (SPCC) Plan. Such plan shall meet applicable EPA requirements (40 CFR
112) including certification by a registered professional engineer.
Equipment shall be furnished on a fully operational basis, of modern design and in good operating condition with no fuel or oil leaks. Repairs and move-in/move-out are the Contractor’s responsibility. All equipment shall be power washed and shall be clean prior to entering Forest Service Land.
(b) No objectionable material shall be allowed to enter any stream, river, lake, or other body of water. Material which falls in these areas shall be retrieved and disposed of, or incorporated in the work as directed by the Contracting Officer, and damage to vegetation or structures outside the project limits shall be repaired as directed by the Contracting Officer.
(c) The Contractor shall not operate equipment or otherwise disturb the natural vegetation and soil beyond the areas flagged on the ground or beyond two feet from edge of walkways, top of cuts, or toe of fills.
(d) The Contractor will make every reasonable attempt to preserve the scenic and natural environment along this construction project.
PROSECUTION OF WORK
(a) Construction activity shall be limited to the hours between 8:00 a.m. and 6:00 p.m., Monday through Friday, excluding Federal holidays, unless other hours are approved in writing by the Contracting Officer. The Contractor shall conduct activities so that interference with the public shall be kept at a minimum. The project site shall be open to public access and free of hazards on weekends. Any activities requiring closure to the public and / or Forest Service personnel shall be scheduled with the COR at least 7 days in advance.
(b) The Contractor shall use measures and precautions necessary to warn and protect the public and Government personnel during work at the project site. Such actions include, but are not limited to, furnishing and maintaining barricades and signs around the work site and roping off the area.
PRODUCT SUBSTITUTION
Any modification of items, designs, materials, products or equipment (including Government- Furnished property), made necessary because of a substitution, will be the responsibility of the Contractor without adjustment in contract price or time. The Contracting Officer's approval of any substitute will not affect the Contractor's responsibility for such modification. Any and all substitutions will be requested by the Contractor after award of the contract has been made.
No approvals will be made prior to award.
FINAL CLEANUP
Contractor shall remove and dispose all of its own trash and refuse from the contract area.
Material to be removed includes, but is not limited to camp refuse such as tin cans, aluminum foil, glass, paper, garbage, used engine oil, oil filters, oil cans, grease cartridges, etc. This Cleanup is a subsidiary item for which no special payment will be made. All debris shall be disposed off National Forest Land and in accordance with State and Local disposal requirements.
METHODS OF MEASUREMENT
The following method of measurement for determining final payment is DESIGNATED on the SCHEDULE OF ITEMS for each pay item:
(a) Designed Quantities (DQ). These quantities denote the final number or units to be paid for under the terms of the contract. They are based upon the original design data available prior to advertising the project. Original design data include the preliminary survey information, design assumptions, calculations, drawings, and the presentation in the contract. Changes in the number of units SHOWN in the SCHEDULE OF ITEMS may be authorized under any of the following conditions:
(1) As a result of changes in the work authorized by the Contracting Officer.
(2) As a result of the Contracting Officer determining that errors exist in the original design that cause a pay item quantity to change by 15 percent or more.
(3) As a result of the Contractor submitting to the Contracting Officer a written request showing evidence of errors in the original design that cause a pay item quantity to change by 15 percent or more. The evidence must be verifiable and consist of calculations, drawings, or other data that show how the designed quantity is believed to be in error.
(b) Staked Quantities (SQ). These quantities are determined from staked measurements prior to construction.
(c) Actual Quantities (AQ). These quantities are determined from measurement of completed work.
(d) Vehicle Quantities (VQ). These quantities are measured or weighed in hauling vehicles.
(e) Lump Sum Quantities (LSQ). These quantities denote one complete unit of work as required by or described in the contract including necessary materials, equipment, and labor to complete the job. They will not be measured.
STATE ELECTRICAL INSPECTION AND COUNTY BUILDING PERMITS
The Contractor shall arrange for and provide the State Electrical inspection. When requesting the inspection inform the Building Permit Department of the federal limitation described below.
The Contractor shall not obtain any building permits or inspections other than the State Electrical inspection.
Federal law [validated by the State Attorney General, Oregon Department of Justice] verify that the Federal Government and its Contractors may be exempted from State/Local Building Permits and Fees for projects located on Federal Installations [including all federal lands]. Contractor State Licenses will not be jeopardized by following this requirement to avoid the State/County permit system. This applies to the prime Contractor and all subcontractors.
PHYSICAL DATA (FAR 52.236-4) (APR 1984)
Data and information furnished or referred to below is for the Contractor's information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor.
(a) The indications of physical conditions in the Solicitation Package are the result of site investigations by visual inspection and measurements.
PART II--CONTRACT CLAUSES
SECTION I--CONTRACT CLAUSES
I.1 CLAUSES
52.252-2 Clauses Incorporated by Reference (FEB 1998) This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):
Federal Acquisition Regulation (FAR) Clauses:
https://www.acquisition.gov/browse/index/far (FAR clauses begin with 52) Department of Agriculture Acquisition Regulation (AGAR) Clauses:
https://www.acquisition.gov/agar (AGAR clauses begin with 452) FAR and AGAR Deviations to clauses may be viewed at: Policies & Regulations | USDA
52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements (JAN 2017)
52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards (JUN 2020) (applies over $30,000)
52.204-13 System for Award Management Maintenance (OCT 2018) 52.204-18 Commercial and Government Entity Code Maintenance (AUG 2020) 52.204-19 Incorporation by Reference of Representations and Certifications (DEC 2014) 52.204-23 Prohibition on Contracting for Hardware, Software, and Services Developed or
Provided by Kaspersky Lab and Other Covered Entities (NOV 2021) 52.204-25 Prohibition on Contracting for Certain Telecommunications and Video
Surveillance Services or Equipment (NOV 2021) 52.209-6 Protecting the Government's Interest when Subcontracting with Contractors
Debarred, Suspended, or Proposed for Debarment (NOV 2021) (applies over $35,000)
52.209-10 Prohibition on Contracting with Inverted Domestic Corporations (NOV 2015) 52.219-6 Notice of Total Small Business Set-Aside (NOV 2020) 52.219-28 Post Award Small Business Program Rerepresentation (MAR 2023) 52.222-3 Convict Labor (JUN 2003) 52.222-6 Construction Wage Rate Requirement (AUG 2018) 52.222-7 Withholding of Funds (MAY 2014) 52.222-8 Payrolls and Basic Records (JUL 2021) 52.222-9 Apprentices and Trainees (JUL 2005) 52.222-10 Compliance with Copeland Act Requirements (FEB 1988) 52.222-11 Subcontracts (Labor Standards) (MAY 2014) 52.222-12 Contract Termination - Debarment (MAY 2014) 52.222-13 Compliance with Construction Wage Rate Requirements and Related Regulations
(MAY 2014)
52.222-14 Disputes Concerning Labor Standards (FEB 1988) 52.222-15 Certification of Eligibility (MAY 2014)
1240BH23Q0054
https://www.acquisition.gov/browse/index/far https://www.acquisition.gov/agar https://www.usda.gov/da/ocp/ppd/policies-regulations
52.222-21 Prohibition of Segregated Facilities (APR 2015) 52.222-26 Equal Opportunity (APR 2016) 52.222-27 Affirmative Action Compliance Requirements for Construction (APR 2015) 52.222-36 Equal Opportunity for Workers with Disabilities (JUN 2020) 52.222-50 Combating Trafficking in Persons (NOV 2021) 52.222-55 Minimum Wages for Contractor Workers under Executive Order 14026 (JAN
2022) 52.222-62 Paid Sick Leave under Executive Order 13706 (JAN 2022) 52.223-2 Affirmative Procurement of Biobased Products under Service and Construction
Contracts (SEP 2013) 52.223-5 Pollution Prevention and Right-to-Know Information (MAY 2011) 52.223-18 Encouraging Contractor Policies to Ban Text Messaging While Driving (JUN
2020) 52.225-13 Restrictions on Certain Foreign Purchases (FEB 2021) 52.227-4 Patent Indemnity -- Construction Contracts (DEC 2007) 52.228-2 Additional Bond Security (OCT 1997) (applies over $35,000) 52.228-5 Insurance – Work on a Government Installation (JAN 1997) 52.228-12 Prospective Subcontractor Requests for Bonds (DEC 2022) (applies over
$35,000) 52.228-14 Irrevocable Letter of Credit (NOV 2014) (applies over $35,000) 52.232-5 Payments under Fixed-Price Construction Contracts (MAY 2014) 52.232-23 Assignment of Claims (MAY 2014) 52.232-27 Prompt Payment for Construction Contracts (JAN 2017) 52.232-33 Payment by Electronic Funds Transfer – System for Award Management (OCT
2018) 52.232-39 Unenforceability of Unauthorized Obligations (JUN 2013) 52.232-40 Providing Accelerated Payments to Small Business Subcontractors (MAR 2023) 52.233-1 Disputes (MAY 2014) Alt 1 (DEC 1991) 52.233-3 Protest after Award (AUG 1996) 52.233-4 Applicable Law for Breach of Contract Claim (OCT 2004) 52.236-2 Differing Site Conditions (APR 1984) 52.236-3 Site Investigation and Conditions Affecting the Work (APR 1984) 52.236-5 Material and Workmanship (APR 1984) 52.236-6 Superintendence by the Contractor (APR 1984) 52.236-7 Permits and Responsibilities (NOV 1991) 52.236-8 Other Contracts (APR 1984) 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and
Improvements (APR 1984) 52.236-10 Operations and Storage Areas (APR 1984) 52.236-11 Use and Possession Prior to Completion (APR 1984) 52.236-12 Cleaning Up (APR 1984) 52.236-13 Accident Prevention (NOV 1991) 52.236-16 Quantity Surveys (APR 1984) 52.236-17 Layout of Work (APR 1984) 52.236-21 Specifications and Drawings for Construction (FEB 1997)
52.243-5 Changes and Changed Conditions (APR 1984) 52.244-6 Subcontracts for Commercial Products and Commercial Services (JUN 2023) 52.246-21 Warranty of Construction (MAR 1994) 52.249-1 Termination for Convenience of the Government (Fixed-Price) (Short Form)
(APR 1984)
52.249-10 Default (Fixed-Price Construction) (APR 1984) 52.253-1 Computer Generated Forms (JAN 1991) 452.232-70 Reimbursement for Bond Premiums – Fixed-Price Construction Contracts (NOV
1996) 452.236-71 Prohibition Against the Use of Lead-Based Paint (NOV 1996) 452.236-72 Use of Premises (NOV 1996) 452.236-73 Archaeological or Historic Sites (FEB 1988) 452.236-74 Control of Erosion, Sedimentation, and Pollution (NOV 1996) 452.236-76 Samples and Certificates (FEB 1988) 452.236-77 Emergency Response (NOV 1996)
52.204-27 Prohibition on a ByteDance Covered Application (JUN 2023)
(a) Definitions. As used in this clause— Covered application means the social networking service TikTok or any successor application or service developed or provided by ByteDance Limited or an entity owned by ByteDance Limited.
Information technology, as defined in 40 U.S.C. 11101(6)—
(1) Means any equipment or interconnected system or subsystem of equipment, used in the automatic acquisition, storage, analysis, evaluation, manipulation, management, movement, control, display, switching, interchange, transmission, or reception of data or information by the executive agency, if the equipment is used by the executive agency directly or is used by a contractor under a contract with the executive agency that requires the use—
(i) Of that equipment; or
(ii) Of that equipment to a significant extent in the performance of a service or the furnishing of a product;
(2) Includes computers, ancillary equipment (including imaging peripherals, input, output, and storage devices necessary for security and surveillance), peripheral equipment designed to be controlled by the central processing unit of a computer, software, firmware and similar procedures, services (including support services), and related resources; but
(3) Does not include any equipment acquired by a Federal contractor incidental to a Federal contract.
(b) Prohibition. Section 102 of Division R of the Consolidated Appropriations Act, 2023 (Pub. L.
117-328), the No TikTok on Government Devices Act, and its implementing guidance under
Office of Management and Budget (OMB) Memorandum M-23-13, dated February 27, 2023, “No TikTok on Government Devices” Implementation Guidance, collectively prohibit the presence or use of a covered application on executive agency information technology, including certain equipment used by Federal contractors. The Contractor is prohibited from having or using a covered application on any information technology owned or managed by the Government, or on any information technology used or provided by the Contractor under this contract, including equipment provided by the Contractor’s employees; however, this prohibition does not apply if the Contracting Officer provides written notification to the Contractor that an exception has been granted in accordance with OMB Memorandum M-23-13.
(c) Subcontracts. The Contractor shall insert the substance of this clause, including this paragraph (c), in all subcontracts, including subcontracts for the acquisition of commercial products or commercial services.
BUY AMERICAN ACT-CONSTRUCTION MATERIALS (FAR 52.225-9)(OCT 2022)
(a) Definitions. As used in this clause— Commercially available off-the-shelf (COTS) item—
(1) Means any item of supply (including construction material) that is–
(i) A commercial product (as defined in paragraph (1) of the definition of “commercial product” at Federal Acquisition Regulation (FAR) 2.101);
(ii) Sold in substantial quantities in the commercial marketplace; and
(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and
(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products.
"Construction material" means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.
Cost of components means—
(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or
(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, 1240BH23Q0054 https://www.acquisition.gov/far/part-2#FAR_2_101 plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.
Critical component means a component that is mined, produced, or manufactured in the United States and deemed critical to the U.S. supply chain. The list of critical components is at FAR 25.105.
Critical item means a domestic construction material or domestic end product that is deemed critical to U.S. supply chain resiliency. The list of critical items is at FAR 25.105.
Domestic construction material means—
(1) For construction material that does not consist wholly or predominantly of iron or steel or a combination of both-
(i) An unmanufactured construction material mined or produced in the United States; or
(ii) A construction material manufactured in the United States, if–
(A)The cost of its components mined, produced, or manufactured in the United States exceeds 60 percent of the cost of all its components, except that the percentage will be 65 percent for items delivered in calendar years 2024 through 2028 and 75 percent for items delivered starting in calendar year 2029. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic. Components of unknown origin are treated as foreign; or
(B) The construction material is a COTS item; or
(2) For construction material that consists wholly or predominantly of iron or steel or a combination of both, a construction material manufactured in the United States if the cost of foreign iron and steel constitutes less than 5 percent of the cost of all component used in such construction material. The cost of foreign iron and steel includes but is not limited to the cost of foreign iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the construction material and a good faith estimate of the cost of all foreign iron or steel components excluding COTS fasteners. Iron or steel components of unknown origin are treated as foreign. If the construction material contains multiple components, the cost of all the materials used in such construction material is calculated in accordance with the definition of "cost of components".
Fastener means a hardware device that mechanically joins or affixes two or more objects together. Examples of fasteners are nuts, bolts, pins, rivets, nails, clips, and screws.
Foreign construction material means a construction material other than a domestic construction material.
Foreign iron and steel means iron or steel products not produced in the United States. Produced in the United States means that all manufacturing processes of the iron or steel must take place in the United States, from the initial melting stage through the application of coatings, except metallurgical processes involving refinement of steel additives. The origin of the elements of the iron or steel is not relevant to the determination of whether it is domestic or foreign.
Predominantly of iron or steel or a combination of both means that the cost of the iron and steel content exceeds 50 percent of the total cost of all its components. The cost of iron and steel is the cost of the iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the product and a good faith estimate of the cost of iron or steel components excluding COTS fasteners.
Steel means an alloy that includes at least 50 percent iron, between 0.02 and 2 percent carbon, and may include other elements.
1240BH23Q0054
https://www.acquisition.gov/far/part-25#FAR_25_105
"United States" means the 50 States, the District of Columbia, and outlying areas.
(b) Domestic preference.
(1) This clause implements 41 U.S.C.chapter 83, Buy American, by providing a preference for domestic construction material. In accordance with 41 U.S.C. 1907, the domestic content test of the Buy American statute is waived for construction material that is a COTS item, except that for construction material that consists wholly or predominantly of iron or steel or a combination of both, the domestic content test is applied only to the iron and steel content of the construction materials, excluding COTS fasteners. (See FAR 12.505(a)(2)). The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.
(2) This requirement does not apply to information technology that is a commercial product or to the construction materials or components listed by the Government as follows:
NONE
(3) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(2) of this clause if the Government determines that-
(i) The cost of domestic construction material would be unreasonable.
(A) For domestic construction material that is not a critical item or does not contain critical components.
(1) The cost of a particular domestic construction material subject to the requirements of the Buy American statute is unreasonable when the cost of such material exceeds the cost of foreign material by more than 20 percent;
(2) For construction material that is not a COTS item and does not consist wholly or predominantly of iron or steel or a combination of both, if the cost of a particular domestic construction material is determined to be unreasonable or there is no domestic offer received, and the low offer is for foreign construction material that is manufactured in the United States and does not exceed 55 percent domestic content, the Contracting Officer will treat the lowest offer of foreign construction material that exceeds 55 percent domestic content as a domestic offer and determine whether the cost of that offer is unreasonable by applying the evaluation factor listed in paragraph (b)(3)(i)(A)(1) of this clause.
(3) The procedures in paragraph (b)(3)(i)(A)(2) of this clause will no longer apply as of January 1, 2030.
(B) For domestic construction material that is a critical item or contains critical components.
(1) The cost of a particular domestic construction material that is a critical item or contains critical components, subject to the requirements of the Buy American statute, is unreasonable when the cost of such material exceeds the cost of foreign material by more than 20 percent plus the additional preference factor identified for the critical item or construction material containing critical components listed at FAR 25.105.
(2) For construction material that does not consist wholly or predominantly of iron or steel or a combination of both, if the cost of a particular domestic construction material is determined to be unreasonable or there is no domestic offer received, and the low offer is for foreign construction material that does not exceed 55
1240BH23Q0054
http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 https://www.acquisition.gov/far/part-12#FAR_12_505 percent domestic content, the Contracting Officer will treat the lowest foreign offer of construction material that is manufactured in the United States and exceeds 55 percent domestic content as a domestic offer, and determine whether the cost of that offer is unreasonable by applying the evaluation factor listed in paragraph (b)(3)(i)(B)(1) of this clause.
(3) The procedures in paragraph (b)(3)(i)(B)(2) of this clause will no longer apply as of January 1, 2030.
(ii) The application of the restriction of the Buy American statute to a particular construction material would be impracticable or inconsistent with the public interest; or
(iii) The construction material is not mined, produced, or manufactured in the United States in sufficient and reasonably available commercial quantities of a satisfactory quality.
(c) Request for determination of inapplicability of the Buy American statute.
(1) (i)Any Contractor request to use foreign construction material in accordance with paragraph (b)(3) of this clause shall include adequate information for Government evaluation of the request, including-
(A) A description of the foreign and domestic construction materials;
(B) Unit of measure;
(C) Quantity;
(D) Price;
(E) Time of delivery or availability;
(F) Location of the construction project;
(G) Name and address of the proposed supplier; and
(H) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(3) of this clause.
(ii) A request based on unreasonable cost shall include a reasonable survey of the market and a completed price comparison table in the format in paragraph (d) of this clause.
(iii) The price of construction material shall include all delivery costs to the construction site and any applicable duty (whether or not a duty-free certificate may be issued).
(iv) Any Contractor request for a determination submitted after contract award shall explain why the Contractor could not reasonably foresee the need for such determination and could not have requested the determination before contract award. If the Contractor does not submit a satisfactory explanation, the Contracting Officer need not make a determination.
(2) If the Government determines after contract award that an exception to the Buy American statute applies and the Contracting Officer and the Contractor negotiate adequate consideration, the Contracting Officer will modify the contract to allow use of the foreign construction material. However, when the basis for the exception is the unreasonable price of a domestic construction material, adequate consideration is not less than the differential established in paragraph (b)(3)(i) of this clause.
(3) Unless the Government determines that an exception to the Buy American statute applies, use of foreign construction material is noncompliant with the Buy American statute.
(d) Data. To permit evaluation of requests under paragraph (c) of this clause based on unreasonable cost, the Contractor shall include the following information and any applicable supporting data based on the survey of suppliers:
Foreign and Domestic Construction Materials Price Comparison
Construction Material Description Unit of Measure Quantity Price (Dollars)* Item1
Foreign construction material _______ _______ _______ Domestic construction material _______ _______ _______ Item 2
Foreign construction material _______ _______ _______ Domestic construction material _______ _______ _______
[*Include all delivery costs to the construction site and any applicable duty (whether or not a duty-free entry certificate is issued)].
[List name, address, telephone number, and contact for suppliers surveyed. Attach copy of response; if oral, attach summary.] [Include other applicable supporting information.]
INDIVIDUAL SURETY - PLEDGE OF ASSETS (FAR 52.228-11)(FEB 2021)
(DEVIATION MAY 2023)
(a) The Contractor shall obtain from each person acting as an individual surety on a performance bond or a payment bond -
(1)A pledge of assets that meets the eligibility, valuation, and security requirements described in the Federal Acquisition Regulation (FAR) 28.203-1; and
(2) Standard Form 28, Affidavit of Individual Surety, [except that the words “being duly sworn, depose and say” on the Standard Form 28 are replaced with the word “affirm” and the Standard Form 28 is not required to be sworn and notarized in block 12].
(b)The Contracting Officer may release a portion of the security interest on the individual surety's assets based upon substantial performance of the Contractor's obligations under its performance bond. The security interest in support of a performance bond shall be maintained—
(1) Contracts for the construction, alteration, or repair of any public building or public work of the Federal Government exceeding $150,000 (40 U.S.C. 3131). Until completion of any warranty period, or for 1 year following final payment, whichever is later.
(2) Contracts subject to alternative payment protection (see FAR 28.102-1(b)(1)). For the full contract performance period plus 1 year.
(3) Other contracts not subject to the requirements of paragraph (b)(1) of this clause. Until completion of any warranty period, or for 90 days following final payment, whichever is later.
(c) A surety's assets pledged in support of a payment bond may be released to a subcontractor or supplier upon Government receipt of a Federal district court judgment, or a sworn statement by the subcontractor or supplier that the claim is correct along with a notarized authorization of the release by the surety stating that it approves of such release. The security interest on the individual surety's assets in support of a payment bond shall be maintained—
(1) Contracts for the construction, alteration, or repair of any public building or public work of the Federal Government exceeding $150,000 which require performance and payment bonds (40 U.S.C. 3131). For 1 year following final payment, or until resolution of all pending
1240BH23Q0054
https://www.usda.gov/sites/default/files/documents/far-class-deviation-eliminate-hard-copy.pdf https://www.acquisition.gov/far/part-28#FAR_28_203_1 claims filed against the payment bond during the 1-year period following final payment, whichever is later.
(2) Contracts subject to alternative payment protection (see FAR 28.102-1(b)(1)). For the full contract performance period plus 1 year.
(3) Other contracts not subject to the requirements of paragraph (c)(1) of this clause. For 90 days following final payment.
(d)The Contracting Officer may allow the Contractor to substitute an individual surety, for a performance or payment bond, after contract award. The Contractor shall comply with the requirements of paragraph (a) of this clause within the timeframe established by the Contracting Officer.
ALTERNATIVE PAYMENT PROTECTIONS (FAR 52.228-13)(JUL 2000)
(a) The Contractor shall submit one of the following payment protections
Payment Bond Cashier’s Check
(b) The amount of the payment protection shall be 100 percent of the contract price.
(c) The submission of the payment protection is required within 10 days of contract award.
(d) The payment protection shall provide protection for the full contract performance period plus a one-year period.
(e) Except for escrow agreements and payment bonds, which provide their own protection procedures, the Contracting Officer is authorized to access funds under the payment protection when it has been alleged in writing by a supplier of labor or material that a nonpayment has occurred, and to withhold such funds pending resolution by administrative or judicial proceedings or mutual agreement of the parties.
(f) When a tripartite escrow agreement is used, the Contractor shall utilize only suppliers of labor and material that signed the escrow agreement.
PERFORMANCE AND PAYMENT BONDS -- CONSTRUCTION (FAR 52.228-15)(JUN
2020) (DEVIATION MAY 2023)