1240BH21Q0076_Wyeth Boat Launch__.pdf

PDF 6 MB Posted

Attached to
DESCHUTES NF - WYETH BOAT LAUNCH REPLACEMENT Federal contract opportunity
Solicitation number
1240BH21Q0076
Issued by
Department of Agriculture Forest Service

View the file

Other files for this federal contract opportunity

Other files attached to DESCHUTES NF - WYETH BOAT LAUNCH REPLACEMENT, newest first.
File Type Posted
SF25A-16d.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOLICITATION, OFFER,

AND AWARD

2. TYPE OF SOLICITATION

6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.

PAGE OF PAGES

7. ISSUED BY CODE 8. ADDRESS OFFER TO

SOLICITATION

(Construction, Alteration, or Repair)

1. SOLICITATION NO. 3. DATE ISSUED

IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.

9.

INFORMATION

a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."

CALL:

FOR

SEALED BID (IFB)

NEGOTIATED (RFP)

1045332

USDA-FS CSA NORTHWEST 6

1220 SW 3RD AVE

STE 310

PORTLAND OR 97204-2829

40BH

ATTN: STEVONNE FULLER

CSA #6

501 E. 5TH STREET

VANCOUVER, WA 98661

STEVONNE FULLER 360-891-5085

109/09/2021

1240BH21Q0076

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)

WYETH BOAT LAUNCH - DESCHUTES NATIONAL FOREST

SEE ATTACHED FOR DETAILS

The Government Estimate is: between $25,000 and $100,000

Offers are due no later than September 23, 2021 at 1700 PT. E-mail offers to Stevonne.fuller@usda.gov.

Note: It is the responsibility of the offeror to ensure the offer has been received.

All Offeror’s are urged and expected to inspect the site where the work will be performed. A scheduled Site Visit may be arranged during normal duty hours by contacting:

Jerold Wesley 63095 Deschutes Market Rd.

Bend, OR. 97701 Ph: 541-419-1988

11. The Contractor shall begin performance

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)

13. ADDITIONAL SOLICITATION REQUIREMENTS:

a. Sealed offers in original and is not required.is, b. An offer guarantee

c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

d. Offers providing less than

12b. CALENDAR DAYSYES NO

(If "YES", indicate within how many calendar days after award in Item 12b.)

10 60 calendar days and complete it within ________________ ________________ calendar days after receiving

09/23/2021

NSN 7540-01-155-3212

x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________

STANDARD FORM 1442 (Rev. 4-85)

Prescribed by GSA

FAR(48 CFR) 53.236-1(d)

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)

16. REMITTANCE ADDRESS (Include only if different than item 14.)

CODE FACILITY CODE

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGEMENT OF AMENDMENTS

OFFER (Must be fully completed by offeror)

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this document and return (Contractor is not required to sign this document.)

Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award.

No further contractual document is necessary.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31a. NAME OF CONTRACTING OFFICER (Type or print)

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE

BY

2PAGE OF

USDA-FS CSA NORTHWEST 6

1220 SW 3RD AVE

STE 310

PORTLAND OR 97204-2829

40BH

STEVONNE FULLER

28. NEGOTIATED AGREEMENT 29. AWARD

Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, copies to issuing office.)

10 U.S.C. 2304(c) 41 U.S.C. 253(c)

STANDARD FORM 1442 (REV. 4-85) BACK

Continued...

PART I—THE SCHEDULE

SECTION B--SUPPLIES OR SERVICES AND PRICES/COSTS

SCHEDULE OF ITEMS

ITEM NO. DESCRIPTION METHOD OF

MEASUREMENT UNIT ESTIMATED

QUANTITY UNIT PRICE TOTAL

WYETH BOAT LAUNCH REPLACEMENT

15101 Mobilization 1 LS $ $

15702 Silt Fence 300 LF $ $

20301 Removal of Concrete Boat Ramp, disposal method (a) 1 LS $ $

20401 Roadway Excavation, Compaction Method B, Tolerance B

CQ 27 CY $ $

20429 Waste CQ 81 CY $ $

20701 Earthwork geosynthetics, type Separation CQ 325 SY $ $

25104A Keyed Rip Rap, ODOT Class

700 CQ 61 CY $ $

25104B Keyed Rip Rap, ODOT Class

100 CQ 6 CY $ $

30103 Aggregate Base, Gradation D, Compaction Method D CQ 23 CY $ $

30109 Subbase, Gradation A, Compaction Method D CQ 25 CY $ $

30112

Aggregate surface coarse, grading 3/4 inch minus pit run aggregate, Compaction Method B

CQ 159 SY $ $

55501 Structural Steel Railing, Furnish, Fabricated & Erected 1 LS $ $

01545 Survey Layout & Control 1 LS $ $

02100 Silt Curtain 150 LF $ $

02200 Earthwork CQ 68 CY $ $

03360 Cast-in-Place Concrete Ramp CQ 450 SF $ $

03412

Precast Concrete Planks, Deliver & Install ((8) Government Furnished Planks)

480 SF $ $

TOTAL OF ALL ITEMS $

Note: This solicitation is subject to availability of funds. The Government reserves the right to order any partial quantities in accordance with funds available at the time of award.

SECTION C--DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK

C.1 SCOPE OF CONTRACT

This work consists of the construction of a Boat Launch at the Wyeth Campground Boating Site. Project work shall include: demolition and removal of the existing concrete Wyeth Boat Launch and construction of a new boat ramp in the same footprint of the boat ramp to be demolished and removed.

The project will require earthwork excavation to occur within the waters of the Deschutes River. The project will also require construction of a cast-in-place “V-Groove” finish concrete boat launch, as well as, placement of government supplied precast concrete plank panels below the ordinary high water mark of the River. Contractor shall provide all necessary traffic control to complete the work.

Contractor shall furnish all necessary personnel, labor, materials, equipment, services, facilities, transportation, and incidentals to perform the Scope of Contract and Specifications provided in regards to this project.

The Contractor shall utilize products and materials that promote energy conservation, pollution prevention, waste reduction, use of recovered materials, that are environmentally preferable, with recycled content and that are recyclable, are made from biobased materials, and are energy efficient (Energy Star-qualified) to the maximum extent possible without jeopardizing the intended end use or detracting from the overall quality delivered.

C.2 PROJECT LOCATION

The project is located on the Deschutes National Forest. From the Deschutes National Forest Administration Headquarters, 63095 Deschutes Market Rd, Bend, OR 97701, head north on Deschutes Market Rd for 0.2 miles. Turn left onto Yeoman Rd travel for 0.7 miles. Turn left onto NE Purcell Blvd and travel for 0.3 miles. Turn right onto Empire Blvd and travel for 0.4 miles. At the traffic circle, take the 2nd exit and stay on Empire Blvd and travel for 1.1 miles. Turn left to merge onto US-97 S/Bend Pkwy and travel for 0.3 miles. Merge onto US-97 S/Bend Pkwy and continue to follow US-97 S for 30 min (28.9 miles). Turn right onto Burgess Rd and travel for 7.3 miles. Continue onto Pringle Falls Loop/County Road 43 and travel for 0.6 miles. Turn left onto F.S. Road 4370 and travel for 0.3 miles.

The destination, Wyeth Campground, Cascade Locks, OR 97045 will be on the left. Latitude and Longitude: 43.737742, -121.616220.

C.3 AGAR 452.211-72 STATEMENT OF WORK/SPECIFICATIONS (FEB 1988)

The Contractor shall furnish the necessary personnel, material, equipment, services and facilities (except as otherwise specified), to perform the Statement of Work/Specifications referenced in Section J.

C.4 AGAR 452.211-73 ATTACHMENTS TO STATEMENT OF WORK/SPECIFICATIONS

(FEB 1988)

The attachments to the Statement of Work/Specifications listed in Section J are hereby made part of this solicitation and any resultant contract.

C.5 APPLICABLE SPECIFICATIONS

Standard and Supplemental Specifications for FP-14 shown in the specifications listing contained in the attachments are applicable to this contract. All Specifications not included in the specification listing but referenced by listed Specifications, are applicable. The Supplemental Specifications shown on the specification list are physically attached.

C.6 BIOBASED PRODUCTS

The Contractor must comply with Section 9002 of the Farm Security and Rural Investment Act of 2002 (FSRIA), Executive Order (EO) 13423, “Strengthening Federal Environmental, Energy, and Transportation Management,” and the Federal Acquisition Regulation to provide biobased products.

The Contractor shall utilize products and material made from biobased materials (e.g. insulating foam, composite panels, and concrete and asphalt release fluids) to the maximum extent possible without jeopardizing the intended end use or detracting from the overall quality delivered to the end user. All supplies and materials shall be of a type and quality that conform to applicable Federal specifications and standards. All supplies and materials to be used in the performance of work described herein are subject to the approval of the Contracting Officer Representative (COR).

The following is an example list of products that may be used in this contract for minor construction for which biobased products are available. The list is not all inclusive. It is desirable that vendors be able to supply the greatest number of biobased products listed meeting the health and environmental specifications.

Graffiti and grease removers Insulation foam Concrete and asphalt release fluids Fluid-filled transformers Wood and concrete sealers Composite panels Adhesive and mastic removers Carpets Roof coating Hydraulic fluid Diesel fuel additives Greases

Dust suppressant 2-cycle engine oil Absorbents

Biobased products that are designated for preferred procurement under USDA’s BioPreferred program must meet the required minimum biobased content as stated in the

USDA Final Rule available at www.biopreferred.gov. The Contractor should provide data for their biobased products such as biobased content and source of biobased material.

In addition to the biobased products designated by the U.S. Department of Agriculture in the BioPreferred Program, the Contractor is encouraged to use other commercially available biobased products.

The awarded Contractor on each anniversary date of the contract shall compile a complete list of biobased products, including the information above, purchased to carry out the contract requirements. The Contractor shall list volume to be used and total cost for each individual product. This information will be used for reporting purposes.

The Contractor shall comply with the provision at FAR 52.223-1, Biobased Product Certification.

The Contractor shall comply with the clause at FAR 52.223-2, Affirmative Procurement of Biobased Products Under Service and Construction Contracts.

SECTION D--PACKAGING AND MARKING

{For this Solicitation, there are NO clauses in this Section}

SECTION E--INSPECTION AND ACCEPTANCE

E.1 FAR 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):

https://www.acquisition.gov/?q=browsefar

FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES

52.246-12 Inspection of Construction (AUG 1996)

E.2 AGAR 452.246-70 INSPECTION AND ACCEPTANCE (FEB 1988)

(a) The Contracting Officer or the Contracting Officer's duly authorized representative will inspect and accept the supplies and/or services to be provided under this contract.

(b) Inspection and acceptance will be performed at: the project site. Inspection procedures and requirements are included in FP-14 Standard Specifications for Construction of Roads & Bridges on Federal Highway Projects and FP-14 FS Supplemental Specifications (National) & CSI Specifications.

E.3 INSPECTION AND TESTING PERFORMED BY GOVERNMENT

The Government will perform sampling, testing and inspection of work in progress where these responsibilities are not expressly assigned to the Contractor by the Forest Service specifications or by the Special Project Specifications.

E.4 CONFORMITY WITH DRAWINGS AND SPECIFICATIONS

Unless working tolerances are specified, all work performed and materials furnished shall be in reasonably close conformity with lines, grades, cross sections, dimensions, and material requirements shown on the Drawings, indicated in the specifications, or designated on the ground. "Reasonably close conformity" is in compliance with reasonable and customary manufacturing and construction tolerances.

E.5 NOXIOUS WEED CONTROL

(a) In order to prevent the potential spread of noxious weeds onto National Forest lands, the Contractor shall be required to furnish the Forest Service with proof of weed-free equipment.

(b) Noxious weeds are defined as any exotic plant species established or that may be introduced in the State, which may render the land unfit for agriculture, forestry, livestock, wildlife, or other beneficial uses and which is designated by the Oregon Department of Agriculture or the Deschutes, Crook, Wheeler, or Grant County Weed Board or by other appropriate agencies having jurisdiction.

(c) All equipment and vehicles to be used at the job site shall be cleaned and certified free of noxious weeds and their seeds prior to entrance onto the National Forest (please see attached Equipment Cleaning Inspection/Verification Form). The restriction shall include equipment and https://www.acquisition.gov/?q=browsefar vehicles intended for off-road use, as well as on road use, whether they are owned, leased, or borrowed by the Contractor or subcontractor.

(d) Cleaning shall consist of the removal of all dirt, grease, debris, and materials that may harbor noxious weeds and their seeds. This may require the use of a pressure hose. Cleaning shall occur off Federal lands.

(e) Equipment, materials and vehicles shall be visually inspected by a designated Forest Service

Officer, and certified in writing to be reasonably clean and weed free. Inspections will take place at a location off Forest lands designated by the Forest Service in advance of equipment arrival. Equipment and vehicles are expected to proceed directly to the job site following the inspection.

SECTION F--DELIVERIES OR PERFORMANCE

F.1 FAR 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):

FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES

52.242-14 Suspension of Work (APR 1984)

F.2 FAR 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK

ALTERNATE I (APR. 1984)

The Contractor shall be required to:

(a) Commence work under this contract within _10__ calendar days after the date the Contractor receives the notice to proceed,

(b) Prosecute the work diligently, and

(c) Complete the entire work ready for use not later than November 30, 2021 and shall be completed within 60 calendar days after issuance of Notice to Proceed. The time stated for completion shall include final cleanup of the premises.

The completion date is based on the assumption that successful offeror will receive the Notice to Proceed by, October 1, 2021. The completion date will be extended by the number of calendar days after the above date that the Contractor receives the Notice To Proceed, except to the extent that the delay in issuance of the Notice To Proceed results from failure of the Contractor to execute the contract and give the required performance and payment bonds within the time specified in the offer.

F.3 MAXIMUM WORKWEEK—CONSTRUCTION SCHEDULE (NOV 1996)

Within __5__ calendar days after receipt of a written request from the Contracting Officer, the Contractor must submit the following in writing for approval:

(a) A schedule as required by FAR clause 52.236-15, Schedules for Construction Contracts, and

(b) The hours (including the daily starting and stopping times) and days of the week the Contractor proposes to carry out the work.

The maximum workweek that will be approved is ____TBD____.

SECTION G--CONTRACT ADMINISTRATION DATA

G.1 GOVERNMENT-FURNISHED PROPERTY

The Government will provide the following item(s) of Government property to the Contractor for use in the performance of this contract. This property shall be used and maintained by the Contractor in accordance with the provisions of the "Government Property" FAR clause contained elsewhere in the contract.

Description Qty. Location Date Available

Precast Concrete Planks 8

Storage Yard is located at the junction of: US-20 @ Powell Butte Road, Bend, OR

97701

At Notice to Proceed

G.2 AGAR 452.215-73 POST AWARD CONFERENCE (NOV 1996)

A post award conference with the successful offeror is required. It will be scheduled and held within 10 days after the date of contract award. The conference will be held at:

Deschutes National Forest Service 63095 Deschutes Market Rd.

Bend, OR. 97701

G.3 DESIGNATION OF CONTRACTING OFFICER’S REPRESENTATIVE

The Contracting Officer will designate a Contracting Officer's Representative (COR) at the time of contract award.

The COR is responsible for administering the performance of work under this contract. In no event, however, will any understanding, agreement, modification, change order, or other matter deviating from the terms of this contract be effective or binding upon the Government unless formalized by proper contractual documents executed by the Contracting Officer prior to completion of the contract.

The Contracting Officer should be informed as soon as possible of any actions or inactions by the Contractor or the Government which will change the required delivery or completion times stated in the contract, and the contract will be modified accordingly. (This does not apply to individual task assignments which were issued by the COR provided they do not affect the delivery schedule or performance period stated in the contract).

On all matters that pertain to the contract terms the Contractor must communicate with the Contracting Officer. Whenever, in the opinion of the Contractor, the COR requests effort outside the scope of the contract, the Contractor should so advise the COR. If the COR persists and there still exists a disagreement as to proper contractual coverage, the Contracting Officer should be notified immediately, preferably in writing if time permits. Proceeding with work without proper contractual coverage could result in nonpayment or necessitate submittal of a contract claim.

G.4 CONTRACTING OFFICER’S REPRESENTATIVE

Jerold Wesley Deschutes National Forest 63095 Deschutes Market Rd.

Bend, OR. 97701 Ph: 541-383-5626

G.5 CONTRACT RELEASE

When submitting final payment, Contractor shall provide a signed and dated contract release that includes the following information: "In consideration of receipt of final payment in the amount of $__________ Contractor hereby releases the United States of America from any and all obligations arising under this contract and any modifications thereof except as reserved herein. Reservations: ______________"

SECTION H--SPECIAL CONTRACT REQUIREMENTS

H.1 FAR 52.236-9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT,

UTILITIES, AND IMPROVEMENTS (APR 1984)

(a) The Contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs, and grass) on or adjacent to the work sites, which are not to be removed and which do not unreasonably interfere with the work required under this contract. The Contractor shall only remove trees when specifically authorized to do so, and shall avoid damaging vegetation that will remain in place. If any limbs or branches of trees are broken during contract performance, or by the careless operation of equipment, or by workman, the Contractor shall trim those limbs or branches with a clean cut and paint the cut with a tree-pruning compound as directed by Contracting Officer.

(b) The Contractor shall protect from damage all existing improvements and utilities (1) at or near the work site and (2) on adjacent property of a third party, the location of which are made know to or should be known by the Contractor. The Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the Contractor fails or refuses to repair the damage promptly, the Contracting Officer may have the necessary work performed and charge the cost to the Contractor.

H.2 PRODUCT SUBSTITUTION

Any modification of other items, designs, supplies, materials, products or equipment (including Government-furnished property), made necessary because of a substitution, will be the responsibility of the Contractor without adjustment in contract price or time. The Contracting Officer's approval of any substitute will not affect the Contractor's responsibility for such modification. Any and all substitutions will be requested by the Contractor after award of the contract has been made. No approvals will be made prior to award.

H.3 PRODUCT SUBSTITUTION REQUEST

A. When submitted within 30 days after contract award, the Contracting Officer will consider formal requests for substitution of products, equipment and methods, in place of those specified. Requests submitted after 30 days will be considered only in case of product unavailability or other conditions beyond the control of Contractor. Requests shall provide the information and be in the format as specified in paragraph B below.

B. Submit separate request for each substitution. Support each request with:

1. Complete data substantiating compliance of proposed substitution with requirements stated in contract documents:

a. Product identification, including manufacturer's name and address.

b. Manufacturer's literature; identify:

1) Product description

2) Reference standards

3) Performance and test data

c. Samples, as applicable

d. Name and address of similar projects on which product has been used, and date of each installation.

e. Comparative data of item to be deleted by proposed substitution. Include drawings to same (or larger) scale as pertinent portion of contract documents and marked to show how differences will be accommodated.

f. Show complete system/assembly as revised to accommodate proposed alternate for difference in performance, size, configuration, connections, service, accessibility, or any other significant characteristics.

g. Show complete layout of system except that which is identical to contract documents unless unchanged portion must be shown to indicate clearances, etc.

h. Include complete detail drawings of supports for all substitute equipment and complete load calculations for adequacy of support prepared and signed by a registered structural engineer.

1. Itemized comparison of the proposed substitution with product specified; list significant variations.

2. Data relating to changes in construction schedule.

3. Any effect of substitution on separate contracts.

4. List of changes required in other work or products.

5. Accurate cost data comparing proposed substitution with product specified.

6. Proposed amount of change to the contract.

7. Designation of required license fees or royalties.

8. Designation of availability of maintenance services, sources of replacement materials.

C. Substitutions will NOT be considered for acceptance when:

1. They are merely indicated or implied on shop drawings or product data submittals without a formal request from Contractor.

2. They are requested directly by a subcontractor or supplier.

3. Acceptance will require substantial revision of contract documents.

4. Substitution has not been requested in accordance with this and related clauses.

D. Substitute products shall not be ordered or installed without written acceptance of the Contracting Officer.

E. Contracting Officer will determine acceptability of proposed substitutions.

F. Number of Substitution Submittals: Only one proposed alternative will be considered for each item.

Provide specified item if substitution proposal is rejected.

H.4 CONTRACTOR’S REPRESENTATION & RESPONSIBILITY

A. In making formal request for substitution the Contractor represents he/she:

1. Have investigated proposed product and determined that it is equal to or superior in all respects to that originally specified.

2. Will provide same warranties and bond for substitute as for originally specified product.

3. Will coordinate installation of accepted substitution into the work, and will make such changes as may be required for the work to be complete in all respects.

4. Will waive claims for additional costs caused by substitution, which may subsequently become apparent.

5. Cost data is complete and includes related costs under the contract, but not:

a. Costs under separate contracts.

b. Contracting Officer costs for redesign or revision of contract documents.

B. The Contractor assumes full responsibility that the substitution and/or alternate items or procedures proposed will meet the job requirements.

C. The Contractor is solely responsible for the cost of redesign and modifications to this and other parts of the work caused by the substitutions or alternates furnished.

H.5 SUBMITTALS, SHOP DRAWINGS, MATERIAL CERTIFICATIONS, AND TEST

REPORTING

The following shall be submitted on this project:

Title Referenced by Specification No.

Time of Government Approval After Submittal

Project Schedule FAR 52.236-15 5 days

Health and Safety Plan (Accident Prevention) FP-14 Spec. 107.08 5 days

Hazardous Spill Plan FP-14 Spec. 107.10 5 days AWS in Standard Qualification License for Welder CSI Spec. 05170 5 days Traffic Control Plan FP-14 156, FP-14 635

& MUTCD Part 6 14 days

Designation of Representative R6-FS-6300-6 Superintendence By The Contractor [FAR 52.222-8]

N/A

Material Certifications and Testing Reports The following material certifications and/or testing reports shall be submitted on this project:

Title Referenced by Specification No.

Crushed Aggregate Base Gradation FP-14 301, FP-14 FS Supplemental Specifications (National), Section 703.05, Table 703-3, CSI Specification 02200 Earthwork

Riprap Gradation CSI Specification 02102 Bank Stabilization

Concrete Mix Design , Including Admixtures CSI Specification 03360 Concrete Form Work

Structural Steel Railing Shop Drawings & Certified Test Results

CSI Specification 05170 Metal Framing For Plank Support System

V-Groove Finish Tool CSI Specification 03360 V-Grooved Cast-In-Place Concrete Ramp, Drawing Sheet # 10, V-Groove Detail.

H.6 LANDSCAPE PRESERVATION

The Contractor shall give attention to the effect of contract operation upon the landscape, shall take care to maintain natural surroundings undamaged, and shall conduct the work at all times in compliance with the following requirements.

a. Prevention of the Landscape Defacement. The Contractor shall not remove, deface, injure, or destroy trees, shrubs, lawns, or other natural features or any other improvements in the work area unless specifically authorized by the Contracting Officer. Unless otherwise provided herein, the Contractor shall confine contract operations to within the areas designated in contract documents.

b. Protection of Streams, Lakes, and Reservoirs. The Contractor shall take sufficient precautions to prevent pollution of streams, lakes, small ponds, and reservoirs with fuels, oils, bitumen’s, calcium chloride, silt, or other harmful materials. Mechanical equipment shall not be operated in live streams without written approval of the Contracting Officer.

H.7 LANDSCAPE and RESOURCE PRESERVATION

All site work shall be in compliance with 52.236-9, 52.237-2, & AGAR 452.236.71, ~73, ~74 and the following project specific requirements:

Wash water or waste from concrete or aggregate operations shall not be allowed to enter live streams prior to treatment by filtration, settling, or other means sufficient to reduce the sediment content to nor more than that of the stream into which it is discharged.

Wash water or waste from concrete or aggregate operations shall be contained, removed from the site, and disposed of off government land.

Mechanized equipment shall not be operated in live streams without written approval by the Contracting Officer.

All petroleum products or other hazardous substances (as defined in 29 CFR 1910.120) shall not be released on or into land, rivers, streams, and impoundments, or into natural or manmade channels leading thereto. Servicing of all equipment shall be done only in the areas approved by the Contracting Officer or their designated representative. The Contractor shall dispose of waste oil, vehicle oil filters (drained of free-flowing oil), and oily rags in accordance with applicable State and Federal regulations and such material shall be transported off government property in accordance with State and Federal regulations.

The Contractor shall notify the Contracting Officer, or designated representative, of any hazardous materials (as defined in 29 CFR 1910.120) to be used on the job and shall have Material Safety Data Sheets (MSDS) for those materials available on the job. All such materials shall be labeled in accordance with federal and state regulations.

H.8 CONFORMITY WITH DRAWINGS AND SPECIFICATIONS

Unless working tolerances are specified, all work performed and materials furnished shall be in reasonably close conformity with lines, grades, cross sections, dimensions, and material requirements shown on the drawings, indicated in the specifications, or designated on the ground. "Reasonably close conformity" is in compliance with reasonable and customary manufacturing and construction tolerances.

A. Definition. "Work" includes, but is not limited to, materials, workmanship, and manufacture and fabrication of components.

B. The Contractor shall maintain an adequate inspection system and perform such inspections as will ensure that the work performed under the contract conforms to contract requirements.

The Contractor shall maintain complete inspection records and make them available to the Government. All work shall be conducted under the general direction of the Contracting Officer and is subject to Government inspection and test at all places and at all reasonable times before acceptance to ensure strict compliance with the terms of the contract.

B. Government inspections and tests are for the sole benefit of the Government and do not—

1. Relieve the Contractor of responsibility for providing adequate quality control measures;

2. Relieve the Contractor of responsibility for damage to or loss of the material before acceptance;

3. Constitute or imply acceptance; or

a. Affect the continuing rights of the Government after acceptance of the completed work under paragraph (I) below.

C. The presence or absence of a Government inspector does not relieve the Contractor from any contract requirement, nor is the inspector authorized to change any term or condition of the specification without the Contracting Officer's written authorization.

D. The Contractor shall promptly furnish, without additional charge, all facilities, labor, and material reasonably needed for performing such safe and convenient inspections and tests as may be required by the Contracting Officer. The Government may charge to the Contractor any additional cost of inspection or test when work is not ready at the time specified by the Contractor for inspection or test, or when prior rejection makes re-inspection or retest necessary. The Government shall perform all inspections and tests in a manner that will not unnecessarily delay the work. Special, full size, and performance tests shall be performed as described in the contract.

E. The Contractor shall, without charge, replace or correct work found by the Government not to conform to contract requirements, unless in the public interest the Government consents to accept the work with an appropriate adjustment in contract price. The Contractor shall promptly segregate and remove rejected material from the premises.

F. If the Contractor does not promptly replace or correct rejected work, the Government may (1) by contract or otherwise, replace or correct the work and charge the cost to the Contractor or (2) terminate for default the Contractor's right to proceed.

G. If, before acceptance of the entire work, the Government decides to examine already completed work by removing it or tearing it out, the Contractor, on request, shall promptly furnish all necessary facilities, labor, and material. If the work is found to be defective or nonconforming in any material respect due to the fault of the Contractor or its subcontractors, the Contractor shall defray the expenses of the examination and of satisfactory reconstruction. However, if the work is found to meet contract requirements, the Contracting Officer shall make an equitable adjustment for the additional services involved in the examination and reconstruction, including, if completion of the work was thereby delayed, an extension of time.

H. Unless otherwise specified in the contract, the Government shall accept, as promptly as practicable after completion and inspection, all work required by the contract or that portion of the work the Contracting Officer determines can be accepted separately. Acceptance shall be final and conclusive except for latent defects, fraud, gross mistakes amounting to fraud, or the Government's rights under any warranty or guarantee.

H.9 CONSTRUCTION STAKES, LINES, AND GRADES

(a) Unless a Pay Item for Construction Staking is included in the Schedule of Items, the Government will set initial construction stakes establishing lines, slopes, and continuous control points, reference lines, and bench marks for other structures and improvements and will furnish the Contractor with all necessary information relating to lines, slopes, and grades.

(b) These stakes and control points shall constitute the field control from which the Contractor shall establish other necessary controls and execute the work. The Contractor shall furnish, without additional compensation, all additional stakes, all templates, batter boards, and other materials and supplies necessary for marking and maintaining points and lines established. If any construction control points have been destroyed or displaced or are erroneous, the Contractor shall promptly notify the Contracting Officer.

(c) The Contractor is responsible for the preservation of all stakes and control points. The cost of replacing them will be charged to the Contractor when destroyed due to Contractor's negligence or operation.

(d) In the case of alterations which involve any changes in construction staking, the Contractor shall cooperate with the Contracting Officer and facilitate the prompt re-establishment of the field control for the altered or adjusted work.

H.10 CONTRACTOR’S USE OF EXISTING ROADS

The Contractor is authorized to use roads in the immediate construction project area for performance of work under this contract. The authorization is limited to roads necessary for direct access between the construction area and storage sites, disposal areas, and other work areas designated in the contract.

The roads authorized for use will be subject to the following general conditions:

(1) State laws governing traffic rules and equipment requirements on State and County Highways.

(2) Federal Regulations contained in 36 CFR 261.12. These regulations prohibit use in excess of State Codes for weight and size, damaging a road while using it, and blocking a road open to use by others.

The Contractor shall be responsible for and perform road maintenance commensurate with his use of Forest Service roads in the construction area.

H.11 ROAD USE AND MAINTENANCE REQUIREMENTS

Use of Roads

(a) The Contractor is authorized to use roads that are a part of the construction project and those Forest Service roads designated below for performance of work under this contract.

Road No.

Termini

Authorizations, Restrictions & Requirements

Maintenance Required

(Yes or No) 4370 Wyeth Boat Ramp Area to Wyeth Campground None No

(b) If the Contractor requests use of a National Forest road or segment not designated for his use, the Forest Service may authorize such use if not in conflict with the current Road Rules document. Authorization to use such additional roads may include maintenance requirements and use limitations.

(c) The roads authorized for use will be subject to the following provisions.

1. The Road Rules in the current Region 6 Road Rules Document are applicable to all commercial road users. This document is available for inspection at the office of the Forest Supervisor and shall be applicable except when modified by provisions of the contract.

2. State laws governing traffic rules and equipment requirements on State and County highways.

3. Federal regulations contained in 36 CFR 261.12. These regulations prohibit use of vehicles or equipment in excess of State legal highway loads or posted limits without valid State and Forest Service overload permits, damaging a road while using it, and blocking a road open to use by others, except as may be otherwise provided in the contract.

Load Limits - No vehicles or equipment shall exceed Forest Service highway, road, or bridge loads and widths or posted limits without valid Forest Service overload, over width permits. Forest Service overload permits for this project may be obtained from the Forest Engineer.

4. Federal Regulations contained in 36 CFR 261.54 as applied to the area by an order issued under 36 CFR

261.50. These regulations authorized the Forest Service, as a sovereign act, to issue additional restrictions and closures any time conditions warrant. Such closures will be in addition to those shown in the current Road Rules Document and will be posted on the road.

H.12 TRAFFIC CONTROL

The Contractor shall provide, erect and maintain all necessary barricades, suitable and sufficient lights, danger signals, signs, and other traffic control devices, and shall take all necessary precautions for the protection of the work and safety of the public. Roads closed to traffic shall be protected by effective barricades, and obstructions shall be illuminated during the hours of darkness. Suitable warning signs shall be provided to properly control and direct traffic.

The Contractor shall erect warning signs in advance to any place on the project where operations may interfere with the use of the road or trail by traffic and at all intermediate points where the new work crosses or coincides with an existing road or trail. All road barricades, warning signs, lights, temporary signals, flagman and pilot car operators and equipment, and other protective devices, except for special devices, shall conform to Part VI of the Manual on Uniform Traffic Control Devices for Streets and Highways, published by the Federal Highway Administration and applicable safety codes.

The Contractor shall furnish, erect, maintain, and remove when notified any project identification signs shown on the drawings

Necessary warning signs and guards shall be posted during blasting operations to safeguard the public.

H.13 CONTROL OF MATERIALS

Rights In and Use of Materials

(a) The Contractor, with the written approval of the Contracting Officer, may use on the project suitable stone, gravel, and sand, or other material found in the excavation. Payment will be made both for the excavation of such materials at the corresponding contract unit price and for the pay items for which the excavated material is used. The Contractor shall replace without additional compensation sufficient suitable materials to complete the portion of the work which was originally contemplated to be constructed with such material.

(b) Materials produced or processed from Government lands in excess of the quantities required for performance of this contract are the property of the Government. The Government is not obligated to reimburse the Contractor for the cost of their production.

Material Sources

(a) Designated Sources - Sources of local materials are designated on the drawings. The Government assumes responsibility for the quality and quantity of material in the source. The Contractor shall determine the equipment and work required to produce the specified product.

The Contractor shall utilize all suitable material in the source. The designation of source will include the rights of the Contractor to use certain area(s) for plant site, stockpiles, and haul roads.

When materials are subject to weight measurement, the weight/volume relationship used for determination of designed quantities will be shown on the Drawings.

Should the designated source, due to causes beyond the control of the Contractor, contain insufficient suitable material, the Government will provide another source with an equitable adjustment in accordance with Clauses 52.243-5, Changes and Changed Conditions or Clause 52.236-2, Differing Site Conditions.

(b) Contractor Furnished Sources - When the material sources are not designated as provided above or the Contractor elects not to use designated sources, the Contractor shall be responsible for providing the specified product with no adjustment in contract price, unless weight/volume relationship differences between designated source material and Contractor furnished source material result in financial disadvantage to the Government. Quality Testing shall be the responsibility of the Contractor.

Test results shall be furnished to the Contracting Officer. Storage Stockpiling of Materials:

Materials shall be stored to assure the preservation of quality and fitness for the work. Stored materials shall be located to facilitate their prompt inspection. Sites on Forest Service administered land, approved by the Forest Service, may be used for storage purposes and for the placing of Contractor's plant equipment. All storage sites provided by the Forest Service shall be restored at Contractor's expense. Contractor shall be responsible for making arrangements for storage on other than Forest Service administered lands.

Earthwork Tolerance:

Changes within specified tolerances (such as adjustment of horizontal or vertical alignment) shall be made as necessary to maintain earthwork quantities substantially as designed within balance points. Such adjustments shall not be considered as "Changes" under Clause 52.243-5.

H.14 SAFTEY

Contractor shall be aware of the public when moving equipment around the project since there will be pedestrian traffic around the construction site.

(a) Forest labor activities and chainsaw work is inherently dangerous. Hazards include, but are not limited to: chain saw injuries, long driving distances on low-grade forest roads, tripping hazards, hypothermia, fatigue, muscle strains, chemical burns, gasoline fire potential, dehydration, insect stings, overhead/falling debris, and lightning. Chainsaw hazards result from improper cutting techniques and fatigue, inattention to proper safety procedures and bar-tip location, improperly held/positioned chainsaw, poorly trained sawyers and lack of, or inadequate personal protective equipment.

(b) Driving along forest roads during early and late hours, before or after sunlight will subject drivers and riders to low light angles, dusty conditions, icy and/or muddy roads; as well as encounters with log hauling trucks, road machinery, hunters not watching the roadway, campers and other forest users that may not be intently aware of other motorists who are sharing the roadway.

(c) Other typical hazards include:

(1) Tripping hazards on forest vegetation and other debris including rocks and other hazards inclusive of slippery surfaces during periods of rain and snow.

(2) Hypothermia may occur at anytime regardless of the absence of extreme weather conditions.

(3) Fatigue may occur towards the end of the working day.

(4) Muscle strains may occur due to improper lifting, bending, twisting, or turning particularly when mounting and dismounting heavy equipment.

(5) Chemical burns may occur during the transfer of oil or gas, or by the unexpected discharge of chemical fire extinguishers.

(6) Gasoline fires may occur at anytime, but are most likely during refueling hot chainsaws, or during the transfer of petroleum products.

(7) Dehydration may occur during both warm and cool periods, and whenever employees are performing arduous tasks while neglecting to ingest adequate fluids that contain electrolytes.

(8) Insect stings or bites may occur at anytime while in the forest and may include ticks, bees, wasps, or other types of biting stinging insects.

(9) Overhead and/or falling debris may occur at anytime in the work area. It may include treetops breaking out during periods of windy conditions, snow stress, or because of decaying limbs/trunks. Also included are rolling rocks, logs, and other debris which might become dislodged on steep slopes.

(10) Lightning should be regarded as a serious threat whenever active cumulonimbus’s (thunderhead clouds) are forecast for the area, especially while working near or under tall trees.

NOTE: Contractor shall provide a job specific safety plan addressing the hazards identified above and other potential hazards known to the Contractor. The plan shall be presented at the Post-Award Conference for discussion.

H. 15 NOXIOUS WEED CONTROL

(a) In order to prevent the potential spread of noxious weeds onto the Deschutes National Forest, the Contractor shall be required to furnish the Forest Service with proof of weed-free equipment before entering the National Forest.

(b) Noxious weeds are defined as any exotic plant species established or that may be introduced in the State, which may render the land unfit for agriculture, forestry, livestock, wildlife, or other beneficial uses and which is designated by the Oregon Department of Agriculture or the Crook, Wheeler, Deschutes, or Grant County Weed Board or by other appropriate agencies having jurisdiction.

(c) All equipment and vehicles to be used at the job site shall be cleaned and certified free of noxious weeds and their seeds prior to entrance onto the National Forest. The restriction shall include equipment and vehicles intended for off-road use, as well as on road use, whether they are owned, leased, or borrowed by the Contractor or subcontractor.

(d) Cleaning shall consist of the removal of all dirt, grease, debris, and materials that may harbor noxious weeds and their seeds. This may require the use of a pressure hose. Cleaning shall occur off Federal lands.

(e) Equipment, materials and vehicles shall be visually inspected by a designated Forest Service Officer, and certified in writing to be reasonably clean and weed free. Inspections will take place at a location designated by the Forest Officer in advance of equipment and material arrival. Equipment and vehicles are expected to proceed directly to the job site following the inspection. Materials to be used on the project will be delivered to the job site following the inspection. Materials to be used on the project will be delivered to the project after inspection and approval.

(f) Certification shall remain valid for each identified piece of equipment or vehicle only for the duration of the specified project and only as long as the vehicle or equipment remains at the job site. Equipment and vehicles (excepting passenger vehicles - this includes pickups and vans) that leave the job site will need to be recertified as weed free before they are allowed to return to the job site or re-enter the National Forest.

H.16 ADDITIONAL REQUIREMENTS OR RESTRICTIONS

Indicate any other special conditions, site restrictions, or use limitations on this project including, but not limited to, the following:

• It’s the contractor’s responsibility for suppling Groove Tools needed to groove the Cast-In-Place concrete section of the boat ramp. Finish tools are no longer available for loan from the Oregon State Marine Board.

• Clean all heavy equipment prior to entering National Forest System Lands to prevent the spread of weeds (USDA FS 2005, R6 Standard #2).

• Use only weed free sources of gravel, fill and rock that is judged to be weed…