This is a Performance Work Statement (PWS) for road surface maintenance services issued by the US Department of Agriculture for the Wallowa-Whitman National Forest. The contractor shall provide road surface maintenance (pay item 811) for Passenger Car Roads and High Clearance Roads on specified single-lane segments throughout the La Grande, Whitman, and Wallowa Mountains Office Ranger Districts in Oregon. The estimated scope includes 252.2 miles in the La Grande District, 169.6 miles in the Whitman District, and 178.15 miles in the Wallowa Mountains Office, totaling approximately 599.95 miles. The base performance period runs from 15 April 2027 to 1 July 2028, with an option period from 2 July 2028 to 1 July 2029.

The contractor must furnish all labor, supervision, equipment, transportation (except government-furnished items), and incidentals for road maintenance. Required tasks include smoothing and shaping native or aggregate surfaced roads including traveled ways, shoulders, turnouts, and intersections to eliminate ruts, rills, and potholes; recovering and incorporating suitable materials; removing unsuitable materials and vegetation; and applying surface compaction using Compaction Method B (7-9 metric ton roller covering full width twice) on specified roads. Work must maintain proper road crown (3% slope), achieve suitable moisture content for compaction, keep road segments under 1 mile in length, remove berms daily, and achieve an Acceptable Quality Level of 95%. Key personnel include designated Contract Managers from each district: Jeffrey Fowlds (La Grande), Danny Story (Whitman), and Brandon Barnett (Wallowa Mountains Office). The contractor must submit equipment storage plans and contract manager information within 14 calendar days of award. Government-furnished materials include suitable stone, gravel, sand, and merchantable timber (minimum 16 feet length, 7 inches diameter at small end).

View the file

Other files

File Type Posted
ANNEX B Whitman.pdx.pdf PDF
ANNEX C Wallowa Mountains.pdf PDF
ANNEX A La Grande.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

US Department of Agriculture (USDA)

Performance Work Statement FY27/28 Road Surface Maintenance

Contents Project General Information

1.0 Scope of Work

2.0 Background

Contractor Requirements

3.0 Performance Tasks

4.0 Property

5.0 Travel (N/A)

6.0 Contractors Key Personnel

7.0 Security Requirements (N/A)

8.0 Data Rights (N/A)

9.0 Section 508 - Electronic and Information Technology Standards (N/A) Enclosures:

Project Road Surface Maintenance Service for the Wallowa-Whitman National Forest

General Information

1.0 Scope of Work

The Wallowa-Whitman National Forest requires surface maintenance service on Forest Service roads. The Contractor shall Provide Road Surface Maintenance for Passenger Car Roads and High Clearance Roads (811) on specified single-lane segments located throughout the district. Specific performance tasks are listed in paragraph 3

2.0 Background

2.1 Project Location:

The project is throughout the Wallowa-Whitman National Forest on the La Grande, Whitman and Wallow Mountains Office (WMO) Ranger Districts.

PWS Paragraph 3.5 La Grande Ranger District.

3502 Highway 30 La Grande, OR 97850-5268 541-962-8500 Attn: Jeff Fowlds, P: 541-962-8510, C: 541-975-0969. Jeffrey.fowlds@usda.gov

PWS Paragraph 3.6 Whitman Ranger District 1550 Dewey Ave Suite A Baker City, OR 97814 541-523-6391 Attn: Dan Story, P: 541-523-1367, C: 541-519-8384. Danny.story@usda.gov

PWS Paragraph 3.7 Wallowa Mountains Office (WMO) 201 East Second St.

Joseph, OR 97846-1251 541-426-5546 Attn: Brandon Barnett, P: 541-426-5668, C: 541-398-8186. brandon.barnett@usda.gov

2.2 ESTIMATED Period of Performance:

Base Period: 15 April 2027 to 1 July 2028 Option Period: 2 July 2028 to 1 July 2029

Contractor Requirements

3.0 Performance Tasks

3.1 General:

3.1.a This is a non-Personnel Services Contract. The Contractor shall furnish all labor, supervision, equipment, transportation, (except those designated as Government-furnished), and incidentals for road maintenance activities within the Wallowa-Whitman National Forest within the scope of this contract.

3.2 Specific Tasks: The contractor shall provide road surface maintenance on the Wallowa-Whitman NF Road system.

Services shall include Surface Maintenance. The following establishes the required tasks (pay items) and the minimum acceptable levels of service.

Existing conditions on the Wallowa-Whitman National Forest: Unpaved roads have historically been maintained approximately every 1-3 years. Ground moisture is variable and dependent on season, snowmelt rates, elevation and aspect. Some roads in this contract range enough in aspect and elevation that part or all of the roads may require watering mailto:Jeffrey.fowlds@usda.gov mailto:Danny.story@usda.gov mailto:brandon.barnett@usda.gov to reach suitable moisture levels while other parts of the road have adequate natural moisture.

3.3 Road Surface Maintenance (811): Smooth and shape native or aggregate surfaced roads including traveled way, shoulders, turnouts, and intersections. A road surface is maintained to standard when the surface, including turnouts, is shaped (crowned or sloped to drain) depending on road geometry without segregation of the surfacing materials. The road surface has no ruts, rills or potholes, suitable materials have been recovered and incorporated. Unsuitable materials, including vegetation and debris have been removed from road surface and disposed of outside of roadway. Fine material deposited along the road edges from previous traffic will be incorporated into the road surface. Road blading will require scarification and processing of existing roadway materials to recover aggregate from shoulders and ditch lines.

Measurement for blading will be linear mile measured along the centerline of the roadway. Measurement will be measured to the nearest one-tenth (0.1) mile.

3.4 Surface Compaction: Aggregate surface traveled ways requiring compaction shall be compacted using Compaction Method B (7-9 metric ton pneumatic, steel, or equivalent vibratory roller, operated to cover the full width two times). For aggregate surface roads, adjust moisture content to a level suitable for compaction. Operate roller compaction equipment over the full width of the traveled way until there is no visible evidence of further consolidation. All Measurement for compaction will be linear mile measured along the centerline of the roadway. Measurement will be measured to the nearest one-tenth (0.1) mile. Road Listing tables in section 3.5 will specify which roads shall receive Compaction Method B.

Note: Roads should be worked with suitable moisture content for blading and compacting. If the contractor elects to do the work in naturally damper conditions, then the road will naturally have suitable moisture and not need additional watering. If the contractor does the work in dry conditions, then additional watering will be required. Moisture content is suitable when fine material (less than ¼” in size) from the top 4” of road surface can be rolled into a ball greater than 1” in diameter in the palm of your hand. Material that is too wet or too dry to form a ball is not suitable

3.5 LaGrande District Road Surface Maintenance (811) consists of an estimated 252.2 miles. These miles will be separated into Base and Option Items. See PWS ANNEX A, La Grande Road Surface Maintenance Road Listing and Maps for more information. The COR is Jeffrey Fowlds, jeffrey.fowlds@usda.gov.

3.6 Whitman District Road Surface Maintenance (811) consists of an estimated 169.6 miles. These miles will be separated into Base and Option Items. See PWS ANNEX B, Whitman Road Surface Maintenance Road Listing and Maps.

The COR is Danny Story, danny.story@usda.gov.

3.7 WMO Road Surface Maintenance (811) consists of an estimated 178.15 miles. These miles will be separated into Base and Option Items. See PWS ANNEX C, Wallowa Valley Road Surface Maintenance Road Listing and Maps. The COR is Brandon Barnett, brandon.barnett@usda.gov

Standard: The contractor shall ensure potholes and washboards are removed from road surface, crown, in-slope or out-slope is uniform (3% is typically acceptable); road surface material contains sufficient moisture (is not too wet or too dry to achieve compaction); bridge decks on permanent bridges are clean of rock and dirt generated from grading operations;

and road segments being graded are no longer than 1 mile in length. Berms created during grading operations are removed from the roadway prior to the end of each day’s work and not left in place overnight. Work shall comply with Acceptable Quality Levels 811, listed in the Quality Assurance Surveillance Program (QASP) at Attachment 2.

Acceptable Quality Level (AQL) 95%

4.0 Property

4.1 Government Furnished

4.1.a The Contractor, with the written approval of the Contracting Officer, may use suitable stone, gravel, and sand, or other material found in the excavation on the project. Payment will be made both for the excavation of such materials at the corresponding contract unit price and for the pay items for which the excavated material is used. The Contractor shall mailto:jeffrey.fowlds@usda.gov mailto:danny.story@usda.gov mailto:brandon.barnett@usda.gov replace without additional compensation sufficient suitable materials to complete the portion of the work which was originally contemplated to be constructed with such material.

4.1.b Materials produced or processed from Government lands more than the quantities required for performance of this contract are the property of the Government. The Government is not obligated to reimburse the Contractor for the cost of their production.

4.1.c Merchantable Timber: All merchantable timber is government property. The minimum utilization standards for merchantable timber are: Length = 16 Feet; Diameter (Inside Bark) at Small End = 7 Inches. If during the course of work merchantable timber impedes progress of services, fall and buck merchantable material into lengths not to exceed 40 feet.

4.2 Contractor Property

4.2.a The contractor may store equipment and materials within the Wallowa-Whitman National Forest as approved by the COR. The contractor shall submit an equipment and materials storage to the COR for approval within 14 calendar days of contract award. (Deliverable 3).

4.2.b The contractor stores equipment and material at its own risk and is responsible for the security of any contractor property stored on Government lands and facilities. The contractor holds the Government harmless for property security and damage.

5.0 Travel (N/A)

6.0 Contractors Key Personnel

The Contractor shall provide a Contract Manager and designated alternate, as applicable, who has full authority to act for the Contractor on all contract matters relating to this contract. The Contract Manager or alternate shall be available during the Government's regular working hours and shall be available on site within one hour after the Government's regular working hours. The Contractor shall submit the name and contact information of the contract manager in writing to the COR within 14 calendar days of award. (Deliverable 04).

7.0 Security Requirements (N/A)

8.0 Data Rights (N/A)

9.0 Section 508 - Electronic and Information Technology Standards (N/A)

Enclosures:

ANNEX A, La Grande Road Surface Maintenance Road Listing and Maps ANNEX B, Whitman Road Surface Maintenance Maps ANNEX C, WMO Road Surface Maintenance Maps

Project
General Information
1.0 Scope of Work
2.0 Background
Contractor Requirements
3.0 Performance Tasks
4.0 Property
5.0 Travel (N/A)
6.0 Contractors Key Personnel
7.0 Security Requirements (N/A)
8.0 Data Rights (N/A)
9.0 Section 508 - Electronic and Information Technology Standards (N/A)