1240BE26Q0091 Attachment 3 Statement of Work.pdf
PDF 174 KB Posted
- Solicitation number
- 1240BE26Q0091
- Issued by
-
Department of Agriculture Forest Service
About this file
This is a Statement of Work (SOW) for HVAC repairs at the USFS Southern Research Station in Athens, Georgia. The contractor must replace/repair failed HVAC system components in the 27,934-square-foot North Building (constructed 1968), primarily actuators and fan motors on room fan coil units and air handling unit components. The work location is 320 East Green Street, Athens, GA 30602, and the building will remain occupied during execution. The government will furnish only 52 Honeywell Valve Actuators (Part Number X13611033010/U); the contractor must provide all other parts, tools, and materials.
Key contractual requirements include: contractor must begin work within 14 calendar days and complete it by March 19, 2027 (180 calendar days maximum); provide a Work Plan with project timeline; submit a Quality Control Plan demonstrating performance standards and quality monitoring procedures; maintain a superintendent on-site at all times; provide daily debris removal to an off-site commercial disposal location (no onsite dumpster available); and offer a minimum one-year warranty on all work performed (parts and labor). The contractor must comply with OSHA regulations, applicable building codes, and international mechanical codes. Travel costs and all associated expenses must be included in the fixed-price response. Access is limited to normal business hours (0730-1700 M-F, excluding Federal Holidays), with contractor personnel required to check in daily with the Government Technical Monitor for site access and coordination.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ATTACHMENT 3
STATEMENT OF WORK
Project: USFS, South Research Station, Athens North Building (NB) HVAC Repairs
General Information
1.0 Scope of Work
Replacement/Repair of failed HVAC system components in the North Building (NB) at the Southern Research Facility in Athens, GA.
Location: USFS, Southern Research Station, 320 East Green St, Athens, GA 30602
2.0 Background
The North Building (16-0001-ATH) is a 27,934 square-foot building, constructed in 1968. The building is a two-story concrete and brick structure. The building is primarily used as office space, with some supporting research laboratory and storage space. The building will be occupied during the execution of this work.
An inspection of the HVAC system identified multiple system components that require replacement. The majority of these components are actuators and fan motors on room fan coil units (FCU). The remaining items are issues related to air handling units (AHU) and components. Table 1 lists the failed components and their location in the building.
No potentially hazardous materials are expected to be encountered during the execution of work under this Scope of Work.
Contractor Requirements
3.0 Technical Requirements/Tasks
3.1 North Building HVAC System Component Replacement
Contractor Shall: Replace/repair all items listed in Table 1. Contractor shall ensure all items are installed and functioning per manufacturer specifications. Any unforeseen nonfunctioning parts or needed repairs discovered during the execution of this work shall be documented and conveyed to the government. The government may, at its discretion, determine if repairs are in scope and issue a modification for additional work, or forego the unforeseen work entirely.
3.2 Contractor’s Key Personnel: Contractor shall identify a person to be an on-site point of contact to represent contractor, coordinate daily contract services, and a contract for government and contractor personnel working onsite.
3.3 Contractor Work Plan
The Contractor shall provide a Work Plan containing a project timeline for various work elements from initial inspection, parts ordering, repair and maintenance, and final inspection.
3.4 Contractor Quality Control Plan, Contractor Inspection
The Contractor shall provide a Quality Control Plan (QCP) as part of their Technical Proposal. The Plan must demonstrate how the Contractor shall assure that quality of performance meets the objectives and requirements of the contract. The QCP shall specify:
- How quality will be monitored to ensure performance standards are met.
- How the work will be supervised.
- How results of the monitoring will result in quality performance.
- Identify the personnel responsible for performing quality control and contractor inspection prior project completion.
3.5 Clean Up/Disposal
Contractor shall provide daily removal of work-related debris and trash from the building to an off-site commercial disposal location. The Contractor is encouraged divert as much material as possible from disposal in a solid waste landfill by utilizing salvage businesses for the recyclable content generated from the work.
Note: An onsite dumpster is NOT available for use by the Contractor.
Contractor shall provide final cleaning to restore project area to original condition or better.
4.0 Government Furnished
Parts: The government shall provide only 52 Honeywell Valve Actuators, Part Number X13611033010/U
Parking and storage areas: Vicinity of the work area. Coordinate final locations with the Government Technical Monitor (who is also the site point of contact-SPOC).
5.0 Utilities:
120V power supply in the vicinity of the work area. Contractor shall provide any required extension cords.
Potable water supply in the vicinity of the work area. Contractor shall provide any required hoses.
Access to public restrooms.
6.0 Deliverables/Schedule
The Contractor shall begin performance within 14 calendar days and complete it within 180 calendar days after receiving authorization to begin work from the Contracting Officer.
Complete project no later than March 19, 2027
Warranty: Contractor shall provide a minimum of 1 year warranty on work performed (parts and labor).
7.0 Travel
Travel costs associated with the work shall be included in the overall fixed price provided in response to this
SOW.
8.0 Contractor’s Key Personnel
The contractor shall have a superintendent on site at all times while work is being performed. The Contractor’s employees performing services as described herein shall be controlled, directed, and supervised, at all times, by the Contractor. Contractor management will ensure that the employees properly comply with the performance work standards outlined in this Statement of Work. The work set forth may not be interpreted or implemented in any manner that results in the Contractor creating or modifying Federal Policy. The Government will control access to the facilities and will perform the inspection and acceptance of the completed work. The term Contractor as applied herein includes Subcontractors and Trades People.
9.0 Security Requirements
The Athens North Building is secured at all times. Access to the work site during normal business hours (0730- 1700 M-F, excluding Federal Holidays)
Contractor’s employees and subcontractors are required to check in with the GTM/site point of contact every day prior to beginning work. Daily, the GTM will identify requirements for sign in and provide access to locked work areas when needed.
9.0 Data Rights:
N/A
10.0 Section 508 – Electronic and Information Technology Standards:
N/A
11.0 Safety:
All work undertaken under this Statement of Work shall be performed in compliance with all applicable OSHA Regulations for protection of the workers and public.
13.0 Applicable Licenses, Codes, and References:
All work shall be in compliance with the following applicable codes, but not limited to:
• International Building Code
• International Existing Building Code
• International Mechanical Code
• International Plumbing Code
• International Fire Code
• National Electric Code
• Applicable Federal and State laws, standards, and codes for disposal of hazardous waste
| ATTACHMENT 3 |
| Project: USFS, South Research Station, Athens North Building (NB) HVAC Repairs |
| 1.0 Scope of Work |
| 2.0 Background |
| Contractor Requirements |
| 3.0 Technical Requirements/Tasks |
| 3.1 North Building HVAC System Component Replacement |
| 3.5 Clean Up/Disposal |
| 4.0 Government Furnished |
| 5.0 Utilities: |
| 6.0 Deliverables/Schedule |
| 8.0 Contractor’s Key Personnel |
| 9.0 Security Requirements |
| 9.0 Data Rights: |
| 10.0 Section 508 – Electronic and Information Technology Standards: |
| 11.0 Safety: |
| 13.0 Applicable Licenses, Codes, and References: |
File details come from the government source that posted it. Updated .