This is a Performance Work Statement (PWS) for roadway vegetation maintenance services on the Wallowa-Whitman National Forest in Baker and Union Counties, Oregon, issued by the U.S. Department of Agriculture.
The contractor shall provide roadway vegetation maintenance on an estimated 55.8 base miles of forest roads, with an additional 44.4 optional miles available. The base period runs from 1 August 2026 to 30 November 2027, with an option period from 1 October 2026 to 30 November 2027. Work includes removing vegetation and trees from the road prism, cutting vegetation less than or equal to 9 inches in diameter, providing 14 feet of overhead clearance, removing debris from road surfaces and ditches, and mechanically thinning and scattering woody debris to no greater than 1 foot in depth with an average piece size of 12 inches. The contractor shall NOT remove vegetation within 10 feet of fish-bearing streams. Specific road segments are identified in four charts: 38.8 base miles in Baker County, 17.0 base miles in Union County, 32.1 option miles in Baker County, and 12.3 option miles in Union County. The contractor must comply with Acceptable Quality Levels 842 for Roadway Vegetation Maintenance as outlined in the Quality Assurance Surveillance Program (QASP). The contractor shall submit four deliverables within 14 calendar days of award: a Work Plan (including Traffic Control, Safety, and Fire Plans), a Quality Control Plan, a Property Storage Plan, and key personnel contact information. The contract manager must be available during regular government working hours and on-site within one hour after hours. The solicitation number is 1240BE26Q0046-0001, with the purchase order number to be determined. Change 1 modified the Period of Performance section on page 3.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ATCH-02_PWS_1240BE26Q0046-0001 Page 1 of 7 Pages
US Department of Agriculture (USDA)
Performance Work Statement
Wallowa-Whitman National Forest
2026 Roadway Vegetation Maintenance Service Baker and Union Counties
Solicitation: 1240BE26Q0046-0001 Purchase Order: TBD
Changes are in Blue
Change 1: Page 3, Period of Performance
ATCH-02_PWS_1240BE26Q0046-0001 Page 2 of 7 Pages
Contents Project General Information
1.0 Scope of Work
Contractor Requirements
3.0 Performance Tasks
4.0 Property
4.1 Government Furnished
4.2 Contractor Property
5.0 Deliverables / Schedule
6.0 Travel. Not used
7.0 Contractor’s Key Personnel
8.0 Security Requirements. Not Used
9.0 Data Rights. Not Used
10.0 Section 508 – Electronic and Information Technology Standards. Not Used Attachments
ATCH-02_PWS_1240BE26Q0046-0001 Page 3 of 7 Pages
Project Baker and Union County Road Brushing
General Information
1.0 Scope of Work
The Wallowa-Whitman National Forest requires road maintenance on the Whitman and La Grande Ranger District road systems in Baker and Union counties. Services shall include Roadway Vegetation Maintenance. The contractor shall provide services in accordance with (IAW) this Performance Work Statement (PWS), and all federal, state, and local laws and regulations. Specific performance tasks are listed in paragraph 3.
2.0 Background
2.1 Project Location
The project is throughout the Wallowa-Whitman National Forest in Baker and Union counties.
Wallowa-Whitman N. F. Supervisor’s Office 1550 Dewey Avenue, Suite A Baker City, OR 97814-3825 541-426-5509 Attn: Dan Story, P: 541-519-8384, danny.story@usda.gov
2.2 Period of Performance Change 1
Base Period: 1 August 2026 to 30 Nov 2027 Option Period: 1 October 2026 to 30 Nov 2027
2.3 Acceptance: Government
Contractor Requirements
3.0 Performance Tasks
3.1 General:
3.1.a. This is a non-Personnel Services Contract. The Contractor shall furnish all labor, supervision, equipment, transportation, (except those designated as Government-furnished), and incidentals for roadway vegetation maintenance services within the Whitman District of the Wallowa-Whitman National Forest. The work scope includes an estimated 55.8 miles with an additional 44.4 optional miles. See Para 3.2.a below.
3.1.b. Contractor Work Plan: The contractor shall submit a work plan for acceptance to the COR within 14 calendar days of award. (Deliverable 01). At a minimum the work plan shall include: 1) Traffic Control Plan iaw FSSS 156. 2) Safety Plan. 3) Fire Plan.
3.1.c. Contractor Quality Control Plan: The Contractor shall develop and maintain a QCP Plan iaw FP- 03 153.02 to ensure services are performed in accordance with this PWS. (Deliverable 02) mailto:danny.story@usda.gov
ATCH-02_PWS_1240BE26Q0046-0001 Page 4 of 7 Pages
3.2 Specific Tasks: The contractor shall provide road vegetation maintenance on the Wallowa-Whitman NF Road system. The following establishes the required tasks (pay items) and the minimum acceptable levels of service.
3.2.a. Task 1 – Roadway Vegetation Maintenance (842): Remove vegetation, including trees, from entirety of road prism. Roadway vegetation maintenance is complete when the vegetation has been removed from the designated treatment area which interferes with traffic, obscures signs, impedes the flow of water or diverts water from drainage structures. Cut all vegetation within treatment area which is less than or equal to 9 inches in diameter measured 6 inches above the ground. Cut all vegetation within 5 feet of culvert inlets. Cut all vegetation, including tree branches, to provide overhead clearance of 14 feet above road surface. Cut all vegetation horizontally within 6 feet of cut slope ditch line and 6’ of fill slope hinge point. Remove debris from road surface, ditches, and cut slope above road. Refer to Typical Clearing Limits drawing (QASP Appendix B).
The contractor shall mechanically thin, masticate and scatter standing live trees and standing snags under 9” DBH, so that the resulting woody debris bed is no greater than 1 foot in depth with an average piece size of 12”.
The contractor shall NOT remove any vegetation within 10 feet of fish bearing streams.
Scatter to fill slopes below road, no debris piles will be allowed at culvert outlets. Work activity will be measured along the centerline of the road regardless of the number of lanes. One mile of road includes treatment on both sides of the road. This task is paid by the Mile.
Work shall comply with Acceptable Quality Levels 842 ROADWAY VEGETATION MAINTENANCE, listed in the Quality Assurance Surveillance Program (QASP), Appendix A.
ATCH-02_PWS_1240BE26Q0046-0001 Page 5 of 7 Pages
Base Road Listing – Baker County
Chart 3.2.a.1 Road No. Segment Desc. Unit Quantity (Est.)
From 43 jct to the large pull out on the south side of the road at mile post 3.8
Mi. 3.8
1210 From the 2646-650 jct and ends at the Malheur NF boundary. Mi. 5
1900-160 From the 19 road to the 1940 jct Mi. 4 1040 From Hwy 7 to the 19 rd jct Mi. 8
1044 From the Greenhorn rd to the 1960 rd jct Mi. 2.5
1960 From the 1044 rd jct to the 19 rd jct Mi. 4.3 1920 From the 11 rd jct to the 081 rd jct Mi. 2.7
From double cattleguard to the switchback 0.3 miles from the trailhead
Mi. 6
11 From the 1145 rd jct to the 1140 rd jct Mi. 1.8
1140 From the 11 rd jct to the Forest Boundary Mi. 0.7
Total Miles: 38.8
Base Road Listing - Union County
Chart 3.2.a.2 Roadway Vegetation Maintenance (842)
62 MP 4.8 to MP 21.8 Mi. 17.0 Total Miles: 17.0
Option Road Listing - Baker County
Chart 3.2.a.3 Roadway Vegetation Maintenance
(842)
7380 From Granite Highway to the 19 rd jct
Mi. 8.3
7386 From Mp 0 to MP 4.6 at Pvt bndry Mi. 4.6
7386 From mp 5 at pvt bndry to mp 7.3 at 075 jct
Mi. 2.3
2665 From the end of the 105 rd to the 2646 jct.
Mi. 1.7
66 From Forest Boundary for 10.5 miles Mi 10.5 66 From Mile Post 10.5 to Fish Lake
C.G.
Mi. 4.7
Total Miles: 32.1
ATCH-02_PWS_1240BE26Q0046-0001 Page 6 of 7 Pages
Option Road Listing - Union County
Chart 3.2.a.4
6220 From the 62 jct to Moss Springs
C.G.
Mi. 12.3
Total Miles: 12.3
4.0 Property
4.1 Government Furnished (N/A)
4.2 Contractor Property
4.2.a. The contractor may store equipment and materials within the Wallowa-Whitman National Forest as approved by the COR. The contractor shall submit an equipment and materials storage to the COR for approval within 14 calendar days of contract award. (Deliverable 3)
4.2.b. The contractor stores equipment and material at its own risk and is responsible for the security of any contractor property stored on Government lands and facilities. The contractor holds the Government harmless for property security and damage.
5.0 Deliverables / Schedule
DELIVERABLE REFERENCE DUE SUBMIT TO
(1) Contractor Work Plan
PWS Paragraph 3.1.b. The contractor shall submit a work plan. At a minimum the work plan shall include: 1) Traffic Control Plan iaw FSSS 156. 2) Safety Plan. 3) Fire Plan.
Within fourteen
(14) calendar days after contract award and exercised option.
Contracting Officer’s Representative
(2) Contractor Quality Control Plan
PWS Paragraph 3.1.c. The Contractor shall develop and maintain a QCP to ensure services are performed in accordance with this PWS.
Within fourteen
(14) calendar days after contract award
Contracting Officer’s Representative
(3) Contractor Property Plan
PWS Paragraph 4.2, Contractor Property.
Within fourteen (14) calendar days after contract award
Contracting Officer’s Representative
(4) Key Personnel PWS Paragraph 7, Contractor’s Key Personnel.
Within fourteen (14) calendar days after contract award
Contracting Officer’s Representative
6.0 Travel
Not Used
7.0 Contractor’s Key Personnel
The Contractor shall provide a Contract Manager and designated alternate, as applicable, who has full
ATCH-02_PWS_1240BE26Q0046-0001 Page 7 of 7 Pages authority to act for the Contractor on all contract matters relating to this contract. The Contract Manager or alternate shall be available during the Government's regular working hours and shall be available on site within one hour after the Government's regular working hours. The Contractor shall submit the name and contact information of the contract manager in writing to the COR within 14 calendar days of award. (Deliverable 04)
8.0 Security Requirements
9.0 Data Rights
10.0 Section 508 – Electronic and Information Technology Standards
Enclosures:
ANNEX A, WW Road Vegetation Maintenance Maps
| Project |
| General Information |
| 1.0 Scope of Work |
| Contractor Requirements |
| 3.0 Performance Tasks |
| 4.0 Property |
| 5.0 Deliverables / Schedule |
| 7.0 Contractor’s Key Personnel |
| 8.0 Security Requirements |
| 9.0 Data Rights |
| 10.0 Section 508 – Electronic and Information Technology Standards |
| Enclosures: |
| ANNEX A, WW Road Vegetation Maintenance Maps |