This document is a Statement of Work (SOW) for the construction of 17 sets of stainless-steel hanging poultry cages and racks for the USDA, Agricultural Research Service (ARS) facility in Athens, GA.
The SOW provides detailed specifications for the cages and racks, including dimensions, materials, and required features. It outlines the contractor requirements, including the need to be registered in the System for Award Management (SAM) and to submit material submittals and shop drawings. The period of performance is 180 days from the notice to proceed, and the contractor must provide a 10-year guarantee on the work. The related federal contract opportunity, Solicitation Number 12405B24Q0374, seeks quotations from responsible offerors to provide the required poultry cages and racks. The solicitation states that the award will be made on a best value basis, with technical capability and past performance being more important than price.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Clauses and Provisions (supply Solicitation).pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work USDA, Agricultural Research Service
United States Department of Agriculture Agricultural Research Service
STATEMENT OF WORK
Hanging Poultry Cages
USNPRC SEPRL
950 College Station Road Athens GA, 30605
Prepared by:
Melissa Scott
| Version 2.8, Page - |
| Page 10 of 10 |
Scope of Work The contractor shall provide professional services, labor and material to construct 17 sets of stainless-steel hanging poultry cages and rack for USDA, ARS, USNPRC SEPRL on 950 College Station Road Athens GA, 30605.
Base Bid The contractor shall provide a detailed proposal and cost breakdown for the entire project as specified in this statement of work and Project Requirements Document.
Contractor must be registered in System for Award Management, (SAM), prior to submitting a bid. Registration can be completed at www.sam.gov/portal/public/SAM
Codes and Standards Applicable Codes and Standards apply and are not limited to the following
| ANSI - | American National Standards Institute. |
| ASME - | American Society of Mechanical Engineers. |
| NEC - | National Electrical Code, NFPA 72. |
| OSHA - | Occupational Safety and Health Administration |
| ADA – | Americans with Disabilities Act |
All work must meet ARS 242.1M “ARS Facilities Design Standards” for the defined scope of this project in addition to meeting all Local, State and Federal codes, and latest International Building Code (IBC).
Project Summary The contractor will provide materials and labor to construct Stainless steel poultry cages.
Description for one set:
(2) 4-Bay Stainless steel welded wire cages
- 120”L x 23”D x 24” H
- 1” x 1” x .080’ diameter SS Wire
- 14”W x 9”H Spring hinged doors
- Plastic trim to cover bottom of doorway and waterer openings
Stainless steel rack/frame w/ leveling feet
| -2”x3”x1/8” SS tubing frame |
| - (3) ¼”x “ SS flat Bar hangers |
We will need 17 sets.
Contractor Requirements The project fabrications work shall be performed on the contractor’s premises.
Material Submittals Submittals are required for all materials used for this project.
Shop Drawings Shop drawings of cages and racks are required for this project.
Inspection and Acceptance A government representative shall inspect and approve the work performed on this project. The Contractor shall schedule inspection a minimum of 2 days in advance with the TPOC.
Period of Performance The completion of this project shall not exceed 180 days from date of notice to proceed. A request for time extension must be submitted to the Contracting Specialist in writing. Each request must include specific and detailed reasons in support of the schedule alteration.
Guaranty The contractor shall provide and submit a single guarantee stating that all portions of the work are in accordance with Contract requirements. Guarantee all work against faulty and improper material and workmanship for a period not less than ten (10) years from date of final acceptance by the USDA, except where manufacturer guarantees or warranties are for longer terms. The contractor shall correct any deficiencies which occur during the guarantee period within 24 hours after notification.