This document is a Statement of Work (SOW) for the removal and replacement of a 52-ton greenhouse chiller at the Dale Bumpers National Rice Research Center (DBNRRC) in Stuttgart, Arkansas. The project is being solicited by the U.S. Department of Agriculture (USDA), Agricultural Research Service (ARS) Southeast Area under Solicitation Number 12405B24Q0315.

The SOW requires the contractor to furnish all personnel, equipment, tools, materials, supervision, and quality control necessary to remove the existing chiller and replace it with a new 52-ton chiller. The work includes crane use for chiller placement, replacement of temperature sensors, connection of water supply and return piping, connection of electrical components, proper disposal of the old chiller, factory startup, and a 5-year warranty. The new chiller must be a tier 1 grade unit from a reputable manufacturer. The project must be completed within 90 calendar days from the Notice to Proceed. The contractor is required to submit a project schedule, safety plan, and material submittals. A pre-quote site visit is encouraged. The contractor must comply with requirements for use of biobased products, hazardous materials assessment, and disposal of removed materials and debris. Temporary utilities may be provided by the government.

View the file

Other files for this federal contract opportunity

Other files attached to 52-Ton Chiller Replacement, newest first.
File Type Posted
12405B24Q0315_0001 Photos.pdf PDF
Section J Attachment 1 SOW RFQ.docx DOCX document
Section J Attachment 3 ARS-371.pdf PDF
Section J Attachment 2 WD.pdf PDF
Section J Attachment 4 ARS-372.pdf PDF
12405B24Q0315.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Agricultural Research Service

U.S. DEPARTMENT OF AGRICULTURE

12405B24Q0315 – Greenhouse Chiller Replacement, Stuttgart, AR Page 2 of 2

STATEMENT OF WORK

52 TON CHILLER REMOVAL, REPLACEMENT,

AND INSTALLATION

Southeast Area Dale Bumper National Rice Research Center 2890 Highway 130 E Stuttgart, Arkansas 72160

1. PROJECT INTRODUCTION

1.1. PROJECT TITLE

Removal and Replacement of 52-Ton Greenhouse Chiller.

1.2. PROJECT BACKGROUND AND PURPOSE

The USDA, Agricultural Research Service (ARS), Dale Bumpers National Rice Research Center (DBNRRC) in Stuttgart, Arkansas is the largest facility withing ARS with the sole focus on rice research. The mission of the DBNRRC is to improve the competitiveness of the US rice industry in global and domestic markets.

The existing Trane chiller requires replacement; it is the chiller that provides cooling to the DBNRRC greenhouses 4 and 5. The chiller was installed during the building’s initial construction in 1990. The purpose of this project is to remove the current chiller at DBNRRC and replace it with a new 52-ton chiller.

1.3. PROJECT CONTACTS

Contracting Officer’s Representative (COR)

TBD

Contract Specialist (CS) Amanda Somerville USDA, ARS, Southeast Area amanda.somerville@usda.gov

Contracting Officer (CO) Frank Palmer, Contract Specialist USDA, ARS, Southeast Area frank.palmer@usda.gov

Area Safety and Health Manager (ASHM)

TBD

Engineering Project Manager (EPM)

TBD

Administrative Officer (AO)

TBD

2. SCOPE AND OBJECTIVES

2.1. DESCRIPTION OF WORK

The Contractor must furnish all personnel, equipment, tools, materials, supervision, and quality control necessary to remove and replace the 52-ton Trane chiller. Installation of chiller will include, but is not limited to:

2.1.1. Removal of existing chiller and placement new chiller on established concrete pad; crane use will be required.

2.1.2. Replacement of all temperature sensors.

2.1.3. Connection of existing water supply and return piping including required repairs or replacement of plumbing.

2.1.4. Connection of all high and low voltage electrical components.

2.1.5. Proper disposal of old chiller.

2.1.6. Chiller factory start up.

2.1.7. Provide 5-year warranty on all parts and labor on chiller.

2.1.8. The new chiller must be a tier1 grade chiller from a reputable manufacturer.

2.1.9. The installer must be able to provide a 24-hour on-site response time if needed for chiller failures during warranty period.

2.2. LOCATION OF WORK

The project is located at 2890 Highway 130 East, Stuttgart, Arkansas.

2.3. PRE-QUOTE SITE VISIT

Interested vendors are encouraged to visit the site and be escorted by a government representative to confirm locations, dimensions, and conditions of the project before a quote is submitted. The purpose of a site visit is to observe conditions relevant to the completion of this project. No consideration will be given to claims based on lack of knowledge of existing conditions, except where contract documents detail definite provisions for adjustment in cost or extension due to existing conditions not readily foreseeable. See Section L.4 of the solicitation for site visit information.

2.4 Site Photographs

a.

b.

c.

3. PROJECT SCHEDULE

3.1. The completion of the project must not exceed ninety (90) calendar days from the date of the Notice to Proceed (NTP).

3.2. The Contractor must prepare an overall project schedule including milestone dates for all phases of work and completion date; submit to the COR for approval. This schedule is due fourteen (14) days after contract award. The Contractor must track all work progress to ensure that the project is completed according to the schedule. Include work week schedule with daily starting and stopping time.

3.3. The Contractor must coordinate and confirm the dates for all work with the COR. If necessary, any request for a time extension must be submitted to the Contracting Specialist in writing. Each request must include specific and detailed reasons in support of the schedule alteration and provide an updated schedule for completion. No extension of the period of performance may be given without the written authority of the CO.

3.4. Project work hours are 7:00 am and 4:00 pm, local time, Monday through Friday; federal holidays excluded. The contractor is not required to provide services on recognized Federal holidays established by Federal law (5 U.S.C. 6103). Any changes to work schedule must be submitted to CO for written approval prior to any schedule change.

4. GENERAL REQUIREMENTS

4.1. PERMITS

The Contractor must obtain all building and trade permits necessary to include any drawings, plans, permit and inspection fees, utility location, site surveys, and any other items necessary for compliance with state, local, and federal building authorities.

4.2. SAFETY

The Contractor must submit a Site Safety Specific Plan/Accident Prevention Plan (SSSP) in industry recognizable format to the COR within fourteen (14) of contract award. The SSSP must include phone numbers and maps to local physician offices and the nearest hospital. The Government will review and approve the SSSP before issuance of the NTP.

4.3. EXISTING INSTALLATIONS/DEMOLITION

Coordinate removal of existing installations with COR. All disturbances of existing systems must be coordinated with the COR to prevent disconnecting equipment that may jeopardize on-going research.

4.4. QUALITY CONTROL

Provide quality control to ensure that all components of project work meet the requirements of the contract specifications. Ensure that all work not acceptable or compliant with the specifications is corrected prior to inspection or review by the COR. Quality control is the exclusive responsibility of the Contractor.

4.5. PROTECTION OF WORK AND PROPERTY/SAFETY REQUIREMENTS

4.5.1. The Contractor must protect the work, the site, and all existing property and structures within the limits of the construction activities or that may be affected until acceptance of the work. Any damage to property must be repaired at the Contractor’s expense to pre-damaged condition to the satisfaction of the COR.

4.5.2. Safety and health matters, as they relate to the work, are the exclusive responsibility of the Contractor. The Contractor must furnish, erect, and maintain barricades, warning lights, signs, guards, or take other precautions as may be required by law or local authorities of the protection and security.

4.5.3. Open depressions and excavations occurring as part of this work must be adequately barricaded or fenced to prevent vehicle or pedestrian traffic into the work area.

4.5.4. Provide continuous noise and dust abatement as required to prevent disturbance and nuisance to the public and workers and to the occupants of adjacent premises and surrounding areas. Dampen or cover areas affected by demolition operations as necessary to prevent dust nuisance.

4.5.5. The contract documents may not represent all surface conditions at the site and adjoining areas. The known surface conditions are as indicated and must be compared with actual conditions before commencement of work and the cost must be included in the Contractor’s quote.

4.5.6. The Government will not furnish any labor or equipment to unload or move materials or supplies.

5. UTILIZATION OF BIOBASED PRODUCTS

5.1. The Contractor must utilize products and material based from bio-based materials as applicable, (e.g. bio-based greases; bio-based hydraulic fluids, bio-based absorbents), to the maximum extent possible without jeopardizing the intended end use or detracting from the overall quality delivered to the Government. All supplies and materials must be of a type and quality that conform to the applicable federal specifications and standards. All supplies and materials to be used in the performance of work described herein are subject to the approval of the Contracting Officer Representative (COR). Products can be found at: www.biopreferred.gov.

5.2. The Contractor must comply with the Farm Security and Rural Investment Act of 2002 (FSRIA), 7 U.S.C. 8102; the Food, Conservation and Energy Act of 2008 (FCEA), 7 U.S.C. 8102; the Federal Acquisition Regulation; Executive Order (EO) 13514, “Federal Leadership in Environmental, Energy and Economic Performance,” dated October 5, 2009; EO 13423, “Strengthening Federal Environmental, Energy, and Transportation Management,” dated January 24, 2007; and Presidential Memorandum, “Driving Innovation and Creating Jobs in Rural America through Biobased and Sustainable Product Procurement,” dated February, 2012 to provide biobased products.

6. HAZARDOUS MATERIAL

The equipment is believed to be free of asbestos containing materials. Existing conditions are reflected correctly to the best of USDA’s knowledge. The USDA makes no representation, warranty, or guaranty that the conditions indicated either are representative of those conditions existing throughout the area, or that unforeseen developments may not occur, or that materials other than, or proportions different from those indicated may not exist. The Contractor must include costs for hazardous materials assessment in the quote. If hazardous materials are found to be present, it must be reported to the CO & COR for further action.

7. DISPOSAL OF REMOVED MATERIALS AND DEBRIS

7.1. The Contractor must dispose of removed materials, waste, trash, and debris in a safe, acceptable manner, in accordance with applicable laws and ordinances and as prescribed by authorities having jurisdiction.

7.2. Burying of trash and debris on the site is prohibited. Burning of trash and debris at the site is prohibited.

7.3. Remove trash and debris from the site at frequent intervals so that its presence will not delay the progress of the work or cause hazardous conditions for workers and the public.

7.4. Removed materials, trash, and debris must become the property of the Contractor and must be removed from the project site and be disposed of in a legal manner. Location of disposal site and length of haul are the Contractor's responsibility.

7.5. The Contractor should make every effort to recycle as much of the construction debris as possible.

7.6. Any waste materials encountered during the demolition that are found to contain lead, asbestos, polychlorinated biphenyls (PCB), fluorescent lamps, or any hazardous substances are to be handled and removed in accordance with local, state, and federal laws and requirements concerning hazardous waste as well as any specific hazardous waste requirements stated in different sections.

7.7. Comply with hauling and disposal regulations of authorities having jurisdiction, per federal, state, and local requirements.

8. TEMPORARY FACILITIES

Temporary utilities (water and electricity) may be furnished to the Contractor by the Government, if requested. The Contractor must maintain and protect all such utilities during the course of construction and must repair or replace any items damaged through its own negligence. Should the Contractor require any power or utility shutdowns during construction, the Contractor must obtain approval for such shutdown from the COR three (3) working days prior to the need.

9. CLEANUP

The construction site must be kept clean and free of debris at all times. Restore areas disturbed as nearly as possible to the original appearance and condition. Upon completion of the project, and prior to final inspection, the Contractor must remove from the premises all unused material, trash, and debris resulting from the work to the satisfaction of the COR.

10. SUBMITTALS

Submittals on all material incorporated into the work, including shop drawings and specifications, used on this project must be submitted to the COR and Contracting Specialist. Electronic submittals are acceptable, otherwise three (3) written submittals are required.

10.1 Project Schedule within fourteen (14) days of award (see Section 3.2).

10.2 SSSP within fourteen (14) days of award (see Section 4.2).

10.3 Any project material, including shop drawings and specifications, used on this project.

11. INSPECTION AND ACCEPTANCE

A government representative will inspect and approve the work performed on this project. The Contractor must schedule inspection a minimum of ten (10) days in advance, in writing, to the COR and CO.

12. FINAL PAYMENT/CONTRACT CLOSEOUT

The following documents are required prior to final payment (other documents may also be required): Release of Liens, Release of Claims, Employee Payroll\Timesheets, and Invoice.