QUESTION: Is the refrigerant lines and drain lines and starting up of units to be included in the installation?

ANSWER: All lines must be run. Does NOT include start up (MS State will be doing the final electrical connections.)

QUESTION: What are the electrical requirements?

ANSWER: There is a 500kW 3 phase in the building supplying the electricity, so that will be the limitation to work from.