SOW.pdf
PDF 13 KB Posted
- Attached to
- Synthetic Shingle Roof Replacement Federal contract opportunity
- Solicitation number
- 1232SC18R0018
About this file
Statement of Work
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Responses_to_University_Park_Slate_Roof_Questions.pdf | ||
| 1232SC18R0018_Amend_2.pdf | ||
| 1232SC18R0018_Amd_0001.pdf | ||
| Attachment_2-_Head_House_Roof_Replacement_Plans.pdf | ||
| Attachment_1-_Aerial_View_of_PSWMRU_Head_House.pdf | ||
| 1232SC18R0018.pdf | ||
| Wage_Determination.pdf | ||
| Specifications.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REPLACE SYNTHETIC SLATE ROOFING AT HEAD HOUSE (BUILDING 005)
Pasture Systems and Watershed Management Research Unit University Park, PA
May 1, 2018
The Contractor shall provide all labor, material, and supervision to replace the existing deteriorated synthetic shingle roofing system at the head house building of the Pasture Systems and Watershed Management Research Unit (PSWMRU) on Curtin Road, University Park, PA 16802. The head house building (“Building 005”) is approximately 3,200 square feet. An aerial view of the work area is provided as an attachment (Attachment 1: Aerial view of PSWMRU Head House).
Plans prepared in 2001 for a previous re-roofing effort are available and provided as an attachment (Attachment 2: Head House Roof Replacement Plans) and shall apply to this re-roofing effort.
Project specifications are also provided as an attachment (Attachment 3- Replace Synthetic Slate Roofing at Head House Specifications).
All roofing and underlayment is to be removed and replaced with new per the plans and specifications provided. Existing building drains and flashing shall be re-used unless in need of replacement or otherwise indicated to be replaced on the plans.
All new flashing shall be copper to match existing. The tongue and groove sheathing is to be assumed to be intact and shall be replaced on a time and material basis at additional cost if required.
All aluminum guttering and downspouts are to be replaced in kind.
The intent of the replacement is to mimic the materials and installation approach of the roofing system installed on the Main Building in 2011. This building’s roofing system is the EcoStar Majestic Slate 12” Traditional in Midnight Grey. Approved equals shall be considered pending approval by the Contracting Officer.
Contractor’s working hours shall be scheduled to coincide with the working hours of the PSWMRU Campus which are 7:30 a.m. to 4:00 pm. Should it be necessary to work hours other than the regular working hours, the Contractor shall arrange for access to the area with the Contracting Officer.
Any questions or clarifications pertaining to this Statement of Work shall be addressed directly to the Contracting Officer.
Attachment 1- Aerial view of PSWMRU Head House Attachment 2- Head House Roof Replacement Plans Attachment 3- Replace Synthetic Slate Roofing at Head House Specifications