This is a Statement of Work (SOW) from the U.S. Department of Agriculture (USDA) for the professional electrical installation of office cubicles at the Cereal Crops Research Unit (CCRU) located at 502 Walnut Street, Madison, Wisconsin 53726.

The contractor shall procure and professionally install five complete cubicle workstations and one hoteling desk arrangement with integrated electrical and data capabilities. Each station requires two duplex electrical outlets and two data ports (RJ45), both integrated into the cubicle spine or panel. The contractor must provide a licensed electrician to hardwire the cubicles into existing electrical infrastructure, with wires running through spine or corner sections installed by the contractor's personnel. The contractor is responsible for all labor, supervision, materials, supplies, tools, equipment, and transportation necessary to complete the installation in a professional, safe, and environmentally responsible manner in compliance with applicable federal, state, and local regulations. The contractor must also remove all packaging materials, debris, and waste generated during installation and provide project completion documentation including a signed acceptance form. The government will furnish building access and have USDA personnel escort the contractor on-site. No security clearance is required. The work will be inspected periodically by the government point of contact and must meet industry-accepted standards of quality and aesthetics, with any identified deficiencies corrected at no additional cost. Points of contact are Mark Cumming (mark@cumming@usda.gov) and Brittney Jones (brittney.jones@usda.gov).

View the file

Other files

File Type Posted
C05 Sol_1232SA27Q0021_Amd_0001.pdf PDF
C04b SCA WD 2015-4897_1232SA27Q0021.pdf PDF
C04 Sol_1232SA27Q0021.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

US Department of Agriculture (USDA)

Statement of Work

Contents

Project

General Information

1.0 Scope of Work

2.0 Background

Contractor Requirements

3.0 Technical Requirements / Tasks

4.0 Government Furnished

5.0 Deliverables / Schedule

6.0 Travel

7.0 Contractor’s Key Personnel

8.0 Security Requirements

9.0 Data Rights

10.0 Section 508 – Electronic and Information Technology Standards

11.0 Point of Contact

Project

This Statement of Work (SOW) defines the requirements for the procurement and professional electrical installation of a 5-station cubicle and one single hotel desk arrangement. This would include the electrical connection required to hardwire the new cubicles into the existing wall outlets. The purpose of this project is to create a functional, efficient, and aesthetically pleasing workspace within Cereal Crops Research Unit (CCRU) located at 502 Walnut Street Madison, WI. This SOW outlines the scope of work, deliverables, responsibilities, and acceptance criteria for the selected contractor.

General Information

1.0 Scope of Work

The Contractor shall provide all necessary labor, supervision, materials, supplies, tools, equipment, and transportation required to perform the installation as described herein. All work shall be performed in a professional, safe, and environmentally responsible manner, adhering to all applicable federal, state, and local regulations.

1.1 General Requirements Applicable:

• Power and Data Integration: Integrate power and data raceways/channels within the cubicle system, ready for connection by Agency IT/Facilities personnel.

• Site Cleanup: Remove all packaging materials, debris, and waste generated during the installation process, leaving the site clean and ready for use.

2.0 Background

The Location Support Staff required new cubicles to accommodate five (5) employees and (1) hoteling location in an open office environment. The new workstations are intended to provide dedicated, semi-private workspaces that support productivity and collaboration while maximizing the efficient use of available office space.

Contractor Requirements

3.0 Technical Requirements / Tasks

Upon successful completion of the project, the Contractor shall deliver the following:

• Electrical outfitting for Five (5) complete and (1) hoteling fully installed cubicle workstations. All cubicles will be hardwired by licensed electrician provided by the vendor into existing electrical, and wires will run through spine or corner sections of cubicles by installers.

• Waste removal and site cleanup, leaving the installation area free of debris.

• Project completion documentation, including a signed acceptance form

The Government POC will conduct periodic inspections to ensure compliance with the SOW requirements.

Work shall be performed to industry-accepted standards of quality and aesthetics. Any deficiencies identified by the Government POC shall be corrected by the Contractor within a mutually agreed-upon timeframe at no additional cost. Services will be accepted upon satisfactory completion of all tasks as verified by the

Government POC. Acceptance will be based on the work being performed to a professional standard, meeting all specifications outlined in this SOW, and achieving the desired aesthetic and functional outcomes.

4.0 Government Furnished

Government will provide access to DFRC building.

5.0 Deliverables / Schedule

Components per Station:

• Power/Data:

• Two (2) Duplex Electrical Outlets per station, integrated into the cubicle spine or panel.

• Two (2) Data Ports (RJ45) per station, integrated into the cubicle spine or panel (Contractor to provide raceway/faceplates; Agency IT to run and connect data cables).

6.0 Travel

The vendor will need to travel to the CCRU-Madison at 502 Walnut Street, Madison WI 53726.

7.0 Contractor’s Key Personnel

N/A

8.0 Security Requirements

The contractor does not require a security clearance to complete the work. The contractor will be escorted by

USDA personnel during the work on site.

9.0 Data Rights

10.0 Section 508 – Electronic and Information Technology Standards

11.0 Point of Contact

Mark Cumming mark@cumming@usda.gov and Brittney Jones brittney.jones@usda.gov mailto:mark@cumming@usda.gov mailto:brittney.jones@usda.gov

Project
General Information
1.0 Scope of Work
2.0 Background
Contractor Requirements
3.0 Technical Requirements / Tasks
4.0 Government Furnished
5.0 Deliverables / Schedule
6.0 Travel
7.0 Contractor’s Key Personnel
8.0 Security Requirements
9.0 Data Rights
10.0 Section 508 – Electronic and Information Technology Standards
11.0 Point of Contact