Attachment 8 - RFI Submittal Form with Answers.pdf
PDF 48 KB Posted
- Attached to
- Replace Headhouse Roof - Columbus, MO Federal contract opportunity
- Solicitation number
- 1232SA25R0006
About this file
This document is a Questions and Answers (Q&A) form for Solicitation 1232SA25R0006 for Replacing Headhouse Roof in Columbia, MO. The Q&A addresses several key points, including a substitution request for DMI's standing metal roof panel (DL2016), which is recommended for approval. The contract is a new requirement with specific performance timelines: the base period is 45 calendar days after Notice to Proceed, with two additional option periods of 20 calendar days each. The Period of Non-Performance shall not exceed 180 days after contract award, and work is expected to be performed consecutively if options are exercised. The document directs potential bidders to sam.gov for site visit details and suggests reviewing the website for additional information about the solicitation.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 1232SA25R0006 Amd 00001 Final.pdf | ||
| Attachment 9 - Substitution Request.pdf | ||
| Sol_1232SA25R0006.pdf | ||
| Attachment 4 - Past Perfromance Questionnaire.pdf | ||
| Attachment 1 - Wage Determination MO20250084 04112025 Rev5.pdf | ||
| Attachment 3 - Drawings.pdf | ||
| Attachment 6 - ARS-372.pdf | ||
| Attachment 7 - RFI Submittal Form.xlsx | XLSX spreadsheet | |
| Attachment 2 - Statement of Work.pdf | ||
| Attachment 5 - ARS-371.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Question Answer
Substitution Request - Approval for DMI's Standing Metal Roof Panel -DMI's DL2016 - Review Attachment 9 - Substitution Request DMI
The proposed material substitution appears to meet the technical requirements of the basis of design material. Recommend approval of the proposed substitution.
2 Who is the incumbent? This is a new requirement.
3 Past Contract Award? This is a new requirement.
4 Is there a site visit? Review sam.gov for site visit details. https://sam.gov/opp/9bb4ea24db2d48e1986ab58d44e41338/view
5 Is there a pricing template? Review sam.gov for site visit details. https://sam.gov/opp/9bb4ea24db2d48e1986ab58d44e41338/view
Can the number of days be extended due to the large volume of roofing construction underway secondary to storm damage and seasonal requirements in the local area.
Period of Non-Performance shall not exceed 180 days after contract award. Period of Performance remains unchanged after notice to proceed. 0001 – Base: 45 calendar days after Notice to Proceed is issued.
0002 – Option 1: 20 calendar days after Notice to Proceed is issued.
0003 – Option 2: 20 calendar days after Notice to Proceed is issued.
The expectation for delivery timeframes is that the work will be consecutive, based on the awarded items. If any options are exercised after award the listed delivery timeframe will be added to the timeframe of the already awarded Line Items.