UNITED STATES DEPARTMENT OF AGRICULTURE

BELTSVILLE AGRICULTURAL RESEARCH CENTER

FACILITIES SERVICE

ENGINEERING AND CONSTRUCTION BRANCH

BUILDING 426A, BARC-EAST

10300 BALTIMORE AVENUE

BELTSVILLE, MARYLAND 20705-2350

STATEMENT OF WORK

FOR THE

PROCURE WITH INCIDENTAL INSTALLATION OF ONE 6 TON HOPPER BIN, TWO 13 TON HOPPER BINS AND OTHER SUPPORT STRUCTURES AT BUILDING #183

BELTSVILLE AGRICULTURAL RESEARCH CENTER

BELTSVILLE, MARYLAND

May 30, 2023

STATEMENT OF WORK

PROJECT NUMBER:

PROJECT LOCATION: Beltsville Agricultural Research Center (BARC), Bldg. #203, Beltsville, Maryland 20705 DESCRIPTION OF WORK: Procure with incidental installation of one 6-ton Hopper Bin and two 13 tons Hopper Bins next to Building B183. These shall also include providing the necessary power and controls for the bins. Contractor shall supply all necessary equipment, tools, and manpower to install the Hopper Bins in the Plans provided including electrical power, disconnects and any electrical wiring necessary.

In accordance with this contract, the Contractor shall provide all labor, material, equipment, and transportation to include all accessories and incidentals necessary to complete this job to government requirements. The facility under this contract may contain asbestos materials. The Contractor(s) is/are warned not to disturb any asbestos material during the performance of this work. Should the Contractor encounter any material that in his judgment may contain asbestos, he must stop work immediately and notify the Contracting Officer (CO) within 24 hours.

Prior to commencing work, the Contractor is required to obtain Construction Authorization, vehicle permits, and identification badges. These can be obtained from the Engineering and Construction Office, Building 426A, BARC-East, Beltsville, Maryland. Vehicle permits and identification badges shall be returned to the Government prior to the final payment being issued.

NOTE: THE CONTRACTOR SHALL NOTIFY THE GOVERNMENT TECHNICAL REPRESENTATIVE ON 301-504-9427 at least 48 HOURS BEFORE ANY WORK IS SCHEDULED TO START. All Contractor's work shall be monitored and inspected by BARC personnel and done in accordance with the Statement of Work and attached drawings, specifications, graphics, BARC Special Conditions, and performed in accordance with all federal, state, and local regulations as well as all applicable local building codes, Construction Standards and Codes, Americans with Disabilities Act, local and State traffic codes, Maryland Department of the Environment, the Maryland Highway Specifications, and the Maryland Department of the Environment Regulations concerning Clean Water Act. In the event of conflict, the most stringent regulation shall prevail.

SCOPE OF WORK:

Procure with incidental install one 6-ton Hopper Bin and two 13 tons Hopper Bins next to Building B183. These shall also include providing the necessary power and controls for the bins and accessories. Contractor shall supply all necessary equipment, tools, and manpower to install the Hopper Bins in the Plans provided including electrical power, disconnects and any electrical wiring necessary. Contractor shall restore damaged materials, equipment and or systems to their original condition affected by the Description of Work and cleanup the work site.

The following work shall be performed:

A. Mobilization

· Contractor is responsible for submission of material submittals and cut sheets for approval prior to commencement of work.

· Mobilize all necessary personnel, specialized tools and equipment, dumpsters, safety items, etc., to commence work after point of award of the contract and approval of submittals from the COR.

· Dumpster locations shall be coordinated with the Contracting Officer Representative (COR) as well as the final approval of that location.

· Contractor shall coordinate with the COR the location for the equipment and supplies Staging Area 10 business days prior to delivery.

· Contractor shall submit a Construction Schedule to the COR. Contractor shall coordinate with Using Activity through the COR for the construction schedule 10 business days after issuance of the Notice to Proceed and prior to beginning construction.

· The Contractor shall have a Bi-Weekly Project meeting with the CO and COR during the project duration. The Contractor will be responsible for sending out the invite to everyone, take minutes of the meeting and sending the meeting minutes to everyone within 3 days after the meeting.

· Hours of service shall be Monday – Friday between 7:00 a.m. – 4:00 p.m. Contractor shall not work on government holidays or weekends. Any work performed other than normal working hours shall be approved by the CO in advance.

· Contractor shall request, through the COR, an outage to any utility a minimum of five (5) days in advance. See general requirements and BARC Special Conditions.

B. Demolition

· In accordance with this contract, the contractor shall provide all labor, material, equipment, and transportation to include all accessories and incidentals necessary to complete this job to government requirements. The facility under this contract may contain Asbestos and Lead materials. The contractor(s) is/are warned not to disturb any asbestos or Lead materials during the performance of this work. Should the contractor encounter any material that in their judgment may contain Asbestos or Lead, they must stop work immediately and notify the contracting officer (CO) and (COR) within 24 hours.

· The contractor shall excavate an area of 9’0” Wide x 30’-0” Long x 1’-3” Deep to remove the existing grass and topsoil. Then remove debris from the Government’s site per the SOW.

· The contractor shall excavate an area of approximately 1’-0” Wide x 120’-0” Long x 2’-6” Deep from the General Electric Small Stainless Steel Electrical Panel to 2’-6” passed proposed concrete pad. Note: Refer to Attachment #1 for details.

· The Contractor shall remove and dispose all items not related to this Scope Of Work in the Work area. Contractor shall Lock Out Tag Out (LOTO) the electrical power supply prior to Demolition work. Contractor shall coordinate with COR for any LOTO request five calendar days prior to electrical work.

· The contractor shall remove and dispose of Government property, all items indicated as to be removed. Such items become the property of the contractor and shall be loaded, transported per applicable DOT regulations, and disposed of at approved landfills.

· The Contractor shall control the dust from entering the adjacent building workspaces, remove and discard all debris off site at an approved land fill. The Contractor shall not at any time use the USDA, ARS, BARC Waste Disposal System such as trash can nor dumpsters to discard project debris.

C. Installation

· The Contractor shall supply all materials, equipment, and perform all labor required to install and operate one 6-ton Hopper Bin and two 13 tons Hopper Bins next to Building B183 and all relevant local and national codes whichever one is most stringent.

· The Contractor shall procure (One) 6-ton Hopper Bin and (Two) 13 tons Hopper Bins with the following specifications.

HOPPER BIN UNITS: 6-ton Hopper Bin - Capacity rated at 6.1 tons at 40 pounds per cubic foot materials, designed for free-flowing materials, Feed Bin style roof system and 60-degree hopper system. Bin shall have outside ladder with safety cage and outdoor lock system. Auger shall be 4” boot with 20-foot x 4” rigid auger with each with (One) (1 HP), 208 Volt, 4.6 Amp, 3 Phase motor and drive.

13-ton Hopper Bins - Capacity rated at 13 tons at 40 pounds per cubic foot materials, designed for free-flowing materials, Feed Bin style roof system and 67-degree hopper system. Bin shall have outside ladder with safety cage and outdoor lock system. Auger shall be 4” boot with 20-foot x 4” rigid auger with each with (One) (1 HP), 208 Volt, 4.6 Amp, 3 Phase motor and drive.

Hopper bin shall be assembled and set on Contractor prepared concrete pads. Hopper Bin units may match TAM Systems Model 45 bin or approved equal. Refer to Attachment #2 for sample hopper bin installation.

Approved Equal Vendor:

Brock Grain Systems A Division of CTB, Inc.

· The Contractor shall supply and install Electrical feeder that is approximately 140’-0” long of (4) THHN #6 Copper Wire places in 1 ½” Grey PVC piping that shall be places in the excavated trench that starts from the existing General Electric Small Stainless Steel Electrical Panel to 1’-0” passed proposed concrete pad. Then Connect the 4 wires to the existing General Electric Small Stainless Steel Electrical Panel that is landed on the contractor supplied (1) 3 phase 50 Amp General Electric Breaker. Then the (4) THHN #6 Copper Wire shall be connected to the contractor supplied 3 Phase 50 Amp Breaker in the contractor supplied Sub-Panel with a 50 Amp, 208 Volt, 3 Phase Main Breaker with 16 spaces minimum in a NEMA 3R Stainless Steel Enclosure.

· The Contractor shall Supple and install Stainless Steel Vertical and Horizontal Support Structs that is bolted to the concrete pad with corrosion proof steel anchor bolts that are 4” long and 1/4 “ in diameter. The Vertical structs shall be raise the Electrical Panel Approximately 4’-0” from the concrete pad to the bottom of the electrical panel. Note: There shall be (2) Vertical Steel Support Struts no less than 7” apart extending to 2” above the Electrical Panel. The Horizontal Steel Support Struts shall extend 2’-0” in front and 2’-0” of the rear of the Electrical Sub-Panel with each strut having (3) Corrosion Proof Steel Anchor Bolts that are 4” long and 1/4 “ in diameter anchored in the concrete pad.

· The contractor shall supply and install (1) 5/8” Dia. 10’-0” long Copper Grounding Rod buried a minimum 8’-0” in the Earth and Grounding wire Bonded to the Ground Bar in the Electrical Sub-Panel.

· The contractor shall compact the existing soil to 95% compaction. Then install 6 Mil. Vapor Barrier, 4” of CR6 stone, 3,500 psi 9” thick Concrete Pad. The concrete pad shall be 9’-0” Wide x 30’-0” Long and 11” Thick. It shall have 5” from the Top of the concrete pad a continues layer of Welded Wire Fabric 6x6 W2.9/W2.9 within 3” of all edges of the concrete pad along with on top of the welded Wire Fabric. The concrete mix design is listed below with specifications.

The Low-Shrinkage, Crack-Free Mix (per cubic yard)

Cement - 530 lbs.
Macro Synthetic Fiber: Tuf-Strand SF - 4 lbs
Sand - 1,240 lbs
Air Content - 2.5%
Coarse Aggregate #67 - 1,750 lbs
water-cement ratio - 0.49
Coarse Aggregate #8 - 450 lbs
Slump - 7 inches
Water - 261 lbs
Shrinkage @ 28 days - 0.032%

High Range Water Reducer: Eucon 37 - 74 oz

· Heavy Duty Concrete Pad

· Construct a heavy duty reinforced concrete pad.

· Construct heavy duty floor by placing a heavy-duty bonded topping on a bases lab which has had a rough slab finish left 50 mm 2 inches below final grade. Concrete in the base slab must be thoroughly hardened but not more than 30 hours old. The temperature of the fresh concrete topping must not vary more than 5 degrees C 10 degrees F plus or minus from the temperature of the base slab. The ambient temperature of the space adjacent to the concrete placement and of the base slab must be between 10 and 30 degrees C50- and 90-degrees F.

· The contractor shall provide the following:

· Preparation Slab

· Keep the base slab continuously damp until topping is placed. Thoroughly clean the surface of the base slab with an air-water jet immediately before placing the topping. Thoroughly scrub a thin coat of neat cement grout of about the consistency of thick cream into the existing surface immediately ahead of the overlay placing. At the time the neat cement grout is placed, the existing concrete surface must be damp but no free water present.

Deposit the overlay concrete before the grout coat has had time to stiffen.

CONCRETE PAD HARDENER

· Treat the concrete pad with a hardener applied after the concrete has been cured and then air dried for 14 days. Apply three coats, each the day after the preceding coat was applied. For the first application, dissolve 0.5 kg one pound of the silicofluoride in 4 liters one gallon of water. For subsequent applications, the solution must be 1.0 kg two pounds of silicofluoride to each 4 liters gallon of water. Mop the floor with clear water shortly after the preceding application has dried to remove encrusted salts. Apply proprietary hardeners in accordance with the manufacturer's instructions. Ventilate the area during application. Take precautions when applying silicofluoride due to the toxicity of the salts. Immediately remove any compound that contacts glass or aluminum with clear water.

EXTERIOR SLAB AND RELATED ITEMS TESTING AND INSPECTION FOR CQC

· Perform the inspection and tests described below and, based upon the results of these inspections and tests, take the action required. Submit certified copies of laboratory test reports, including mill tests and all other test data, for Portland cement, blended cement, pozzolan, ground granulated blast furnace slag, silica fume, aggregate, admixtures, and curing compound proposed for use on this project.

· When, in the opinion of the Contracting Officer, the concreting operation is out of control, cease concrete placement and correct the operation.

· The laboratory performing the tests must be onsite and conform with

ASTM C1077. Materials may be subjected to check testing by the

Government from samples obtained at the manufacturer, at transfer points, or at the project site.

· The Government will inspect the laboratory, equipment, and test procedures prior to start concreting operations and at least once for conformance with ASTM C1077.

· Grading and Corrective Action.

· Fine Aggregate.

· Concrete Mixture.

· Air Content Testing

Perform air content tests when test specimens are fabricated. In addition, make at least two tests for air content on randomly selected batches of each separate concrete mixture produced during each 8-hour period of concrete production. Perform additional tests when excessive variation in workability is reported by the placing foreman or Government inspector.

Conduct tests in accordance with ASTM C231/C231M for normal weight concrete and ASTM C173/C173M for lightweight concrete. [Plot test results on control charts. Submit the control charts weekly and make them readily available to the Government. Keep copies of the current control charts in the field by testing crews and results plotted as tests are made. When a single test result reaches either the upper or lower action limit, perform a second test immediately. Average the results of the two tests and use this average as the air content of the batch to plot on both the air content and the control chart for range, and for determining need for any remedial action. Plot the result of each test, or average as noted in the previous sentence, on a separate control chart for each mixture on which an

"Average line" is set at the midpoint of the specified air content range from paragraph AIR ENTRAINMENT. Set an upper warning limit and a lower warning limit line 1.0 percentage point above and below the average line, respectively. Set an upper action limit and a lower action limit line 1.5 percentage points above and below the average line, respectively. Plot the range between each two consecutive tests on a secondary control chart for range where an upper warning limit is set at 2.0 percentage points and an upper action limit is set at 3.0 percentage points. Samples for air content may be taken at the mixer, however, the Contractor is responsible for delivering the concrete to the placement site at the stipulated air content. If the materials or transportation methods cause air content loss between the mixer and the placement, take correlation samples at the placement site as required by the Contracting Officer/COR, and the control the air content at the mixer as directed.

· Air Content Corrective Action

Whenever points on the control chart for percent air reach either warning limit, immediately make an adjustment in the amount of air-entraining admixture batched. As soon as practical after each adjustment, make another test to verify the result of the adjustment. Whenever a point on the secondary control chart for range reaches the warning limit, recalibrate the admixture dispenser to ensure that it is operating accurately and with good reproducibility. Whenever a point on either control chart reaches an action limit line, the air content is considered out of control and the concreting operation immediately halted until the air content is under control. Make additional air content tests when concreting is restarted.

· Slump Testing

In addition to slump tests which are made when test specimens are fabricated during concrete placement/discharge, make at least four slumps tests on randomly selected batches in accordance with ASTM C143/C143M for each separate concrete mixture produced during each 8-hour or less period of concrete production each day. Also, make additional tests when excessive variation in workability is reported by the placing foreman or

Government inspector. Plot test results on control charts. Submit the control charts and make them readily available to the Government. Keep copies of the current control charts in the field by testing crews and results plotted as tests are made. When a single slump test reaches or goes beyond either the upper or lower action limit, immediately perform a second test. Average the results of the two tests and use this average as the slump of the batch to plot on both the control charts for slump and the chart for range, and for determining need for any remedial action. Set limits on separate control charts for slump for each type of mixture. Set the upper warning limit at 12.5 mm 1/2 inch below the maximum allowable slump specified in paragraph SLUMP in PART 1 for each type of concrete and, set an upper action limit line and lower action limit line at the maximum and minimum allowable slumps, respectively, as specified in the same paragraph. Plot the range between each consecutive slump test for each type of mixture on a single control chart for range on which an upper action limit is set at 50 mm 2 inches. Take samples for slump at the mixer. However, the Contractor is responsible for delivering the concrete to the placement site at the stipulated slump. If the materials or transportation methods cause slump loss between the mixer and the placement, take correlation samples at the placement site as required by the Contracting Officer, and the slump at the mixer controlled as directed.

· Slump Corrective Action

Whenever points on the control charts for slump reach the upper warning limit, make an adjustment immediately in the batch weights of water and fine aggregate. The adjustments are to be made so that the total water content does not exceed that amount allowed by the maximum w/c ratio specified, based on aggregates which are in a saturated surface dry condition. When a single slump reaches the upper or lower action limit, deliver no further concrete to the placing site until proper adjustments have been made. Immediately after each adjustment, make another test to verify the correctness of the adjustment. Whenever two consecutives individual slump tests, made during a period when there was no adjustment of batch weights, produce a point on the control chart for range at or above the upper action limit, halt the concreting operation immediately, and take appropriate steps to bring the slump under control. Make additional slump tests as directed.

· Temperature

Measure the temperature of the concrete when compressive strength specimens are fabricated in accordance with ASTM C1064/C1064M. Report the temperature along with the compressive strength data.

Strength Specimens

Perform on at least one set of test specimens, for compressive strength as appropriate, on each different concrete mixture placed during the day for each 380 cubic meters 500 cubic yards or portion thereof of that concrete mixture placed each day. Perform on additional sets of test specimens, as directed by the Contracting Officer when the mixture proportions are.

changed or when low strengths have been detected. Develop a truly random

(Not haphazard) sampling plan for approval by the Contracting Officer prior to the start of construction. Show in the plan that sampling is done in a completely random and unbiased manner.

· A set of test specimens for concrete with a 28-day specified strength in accordance with paragraph STRENGTH REQUIREMENTS in PART 2 consists of five specimens, two to be tested at 7 days, two at 28 days, and one cylinder held in reserve.[ A set of test specimens for concrete with a

[56-day] [90-day] strength in accordance with the same paragraph consists of eight specimens, two tested at 7 days, two at 28 days, two at [56] [90] days, and two held in reserve.

· A strength test is the average of the strengths of at least two 150 mm by 300 mm 6 inch by 12-inch cylinders or at least three 100 mm by 200 mm

4 inches by 8-inch cylinders made for the same sample of concrete.

· Mold and cure test specimens in accordance with ASTM C31/C31M, and test in accordance with ASTM C39/C39M for test cylinders. Immediately report results of all strength tests to the Contracting Officer.

· Maintain quality control charts for individual strength "tests", ("test" as defined in paragraph STRENGTH REQUIREMENTS) moving average of last 3 "tests" for strength, and moving average for range for the last 3 "tests" for each mixture. Provide charts similar to those found in ACI 214R.

Inspection Before Placing

Inspect foundations, construction joints, forms, and embedded items in sufficient time prior to each concrete placement in order to certify too the

Contracting Officer/COR that they are ready to receive concrete. Report the results of each inspection in writing.

Placing

The placing foreman must supervise placing operations, determine that the correct quality of concrete or grout is placed in each location as specified and as directed by the Contracting Officer/COR, and be responsible for measuring and recording concrete temperatures and ambient temperatures hourly during placing operations, weather conditions, time of placement, volume placed, and method of placement. The placing foreman must not permit batching and placing to begin until it has been verified that an adequate number of vibrators in working order and with competent operators are available. Do not continue placing if any pile of concrete is inadequately consolidated. If any batch of concrete fails to meet the temperature requirements, take immediate steps to improve temperature controls.

Concrete Finish

· The Contractor shall provide a broom Finish with Chamfered Edge/Beveled edge at a 45 Degree angle.

· Cold-Weather Protection

At least once each shift and once per day on non-workdays, inspect all areas subject to cold-weather protection. Note any deficiencies, correct, and report.

· Mixer Uniformity

Stationary Mixers

Prior to the start of concrete placing and once every 6 months when concrete is being placed, or once for every 60,000 cubic meters 75,000 cubic yards of concrete placed whichever results in the shortest time interval, determine uniformity of concrete mixing in accordance with

ASTM C94/C94M.

· Truck Mixers

Prior to the start of concrete placing and at least once every 6 months when concrete is being placed, determine uniformity of concrete mixing in accordance with ASTM C94/C94M. Select the truck mixers randomly for testing. When satisfactory performance is found in one truck mixer, the performance of mixers of substantially the same design and condition of the blades may be regarded as satisfactory.

· Mixer Uniformity Corrective Action

When a mixer fails to meet mixer uniformity requirements, either increase the mixing time, change the batching sequence, reduce the batch size, or adjust the mixer until compliance is achieved.

· Reports

Report all results of tests or inspections conducted, informally as they are completed and in writing daily. Prepare a weekly report for the updating of control charts covering the entire period from the start of the construction season through the current week. During periods of cold-weather protection, prepare daily reports of pertinent temperatures. These requirements do not relieve the Contractor of the obligation to report certain failures immediately as required in preceding paragraphs. Confirm such reports of failures and the action taken in writing in the routine reports. The Contracting Officer has the right to examine all contractor quality control records.

· The Contractor shall install the (3) Hopper Bins evenly spaced on the concrete Pad with the Rigid Augers facing the road which is East facing side of the Concrete Pad. The Hoper Bins shall be installed in accordance to the Brock Construction Manual requirements.

· The Contractor shall install the (3) Auger with 4” boot with 20-foot x 4” rigid auger with each with (One) (1 HP), 208 Volt, 4.6 Amp, 3 Phase motor and drive to the Hopper Bins. They shall be installed in accordance with the Brock Construction Manual requirements. The contractor supply and install on one of the front legs of each Bin a Motor Starter with Weather Tight Metal Start/Stop Double Push Button with an Emergency Stop Push Button and Reset Switch, 208 volt 20 Amps, 3 Phase, Rated for 600V AC, 50-60Hz, with each switch connected to the new Auger motor and the New Electrical Sub Panel 20 Amps, 208 Volt, 3 Phase Circuit Breaker Supplied by the contractor. The Contractor shall supply for each switch the required (4 Wire) THHN #10 Copper Wire inside of ½” Grey Electrical PVC Piping that is anchored the metal leg of the Auger and the top of the Concrete Pad in accordance with the current NFPA 70 National Electrical Code. Refer to Attachment #3 for sample hopper bin and control.

· The Contractor Shall supply and install at each Hopper Bin one of the East leg and one of the West legs a Grounding Connection Totaling (Six) connections for the (Three) Hopper Bins. The Contractor Shall supply and install (1) 5/8” Dia. 10’-0” long Copper Grounding Rod buried a minimum 8’-0” in the Earth and Grounding Wire Bonded to one East Leg and one Bonded to the West Leg of the Hopper Bins then Bonded to the Concrete Pad Steel Wire Steel Reinforcing. The Bin Copper Grounding System shall comprise of (1) 5/8” Dia. 10’-0” long Copper Grounding Rod, (2) grounding Clamps, (1) Copper Wire, (1) Swivel Cable Clamp and (1) Heavy Duty Metal Bonding Plate for (6) Hopper Bin Metal Legs. Refer to Attachment #2 for sample hopper bin installation.

· The contractor shall supply and install (1) 5/8” Dia. 10’-0” long Copper Grounding Rod buried a minimum 8’-0” in the Earth and Grounding wire Bonded to the Ground Bar in the Electrical Sub-Panel.

· The Contractor shall install on each of the (3) Hopper Bins outside ladder with safety cage and outdoor lock system. They shall be installed in accordance with the Brock Construction Manual requirements.

· The Government shall fill the Hopper Bins from the top hatch of the Hopper Bin.

· The Contents to be stored in the Hopper Bins is grain for animals that is suitable for the specified Hopper Bins.

· No Soil or any other Debris shall be stockpiled on site for future use. The Soil is hazardous chemical free.

· This Project has no As-Built Drawings available.

· The Contractor shall provide for crane and rigging services. Contractor shall coordinate with COR the proposed location for the crane and rigging 10 business days prior to commencement of Work.

· Contractor shall coordinate with Vendor for the installation and location of equipment and accessories Refer to Attachment #1 for details.

· The Contractor shall ensure Work performed in accordance with the manufacturer's published diagrams, recommendations, and equipment warranty requirements.

· The Contractor shall floor mount equipment on a raised 6 inches reinforced concrete pad. Pad shall extend beyond equipment a minimum of six inches on each side. Refer to Attachment #2 for sample hopper bin installation.

· Reinforcement, detailing, and placement of concrete shall be as specified in Section 03 30 00 CAST-IN-PLACE CONCRETE of the UNIFIED FACILITIES GUIDE SPECIFICATIONS. Compressive strength in 28 days shall be 3000 psi; concrete shall be cured for seven days after placement.

· Contractor shall provide vibration isolation for all mechanical equipment to prevent transmission of vibration to building structure.

· Foundation drawings, details, bolt-setting information, and foundation bolts shall be furnished prior to concrete foundation construction for all equipment indicated or required to have concrete foundations. Anchor and fasten per manufacturer’s specifications/recommendations.

· Contractor shall coordinate with the COR all penetrations to existing exterior walls of the building. Individual wall penetration shall not exceed a maximum of six square feet.

· Equipment shall be properly leveled, aligned, and secured in place in accordance with manufacturer's instructions.

· The Contractor shall supply all necessary equipment, tools, and manpower to install the electrical power feeds, disconnects and electrical wiring.

· Electrical Power, Schedules, and Riser Plans shall be furnished prior to Electrical Work.

· Contractor shall provide on-site presence on the duration of equipment prep and start up once equipment is connected to all building systems required. On-site presence shall be maintained until equipment passes Vendor Commissioning/Field Testing as required.

· DEVICES/MATERIAL/EQUIPMENT: Refer to Attachment #2 for the list of equipment to be installed.

· POWER CONNECTION: The Contractor shall make available all necessary equipment, tools, and manpower to provide disconnects and stub out for Vendor connection to each equipment requiring power. Contractor shall coordinate with COR for LOTO request within five calendar days prior to electrical work.

· QUALITY ASSURANCE: Materials shall comply with manufacturers specifications.

· CLEAN-UP & FINAL PUNCH LIST: The Contractor shall clean the site of any loose debris and schedule a final walk thru with the COR. Upon completion of all punch list items, the parking passes and badges remitted to the COR. The Contractor and the COR will instruct the CO that the contract has been to the completed in its entirety.

· Contractor shall coordinate with the COR the new equipment tag prior to labelling the equipment.

· Contractor shall provide all the equipment cut sheets, warranties, and O&M manual in a three (3) binder and electronic PDF formats as part of Close-Out items.

· The Contractor shall provide at least a one-year warranty on the Work/Labor. The Contractor shall indicate the years of the warranty upon submission of proposal.

· The Contractor shall note that all mechanical installations shall comply with the current 2018 International Mechanical Code.

· The Contractor shall field verify all field conditions, measurements, quantities, and safety constraints prior to bidding and forward any discrepancies or concerns to the COR. Otherwise, it is BARC intent that all is inclusive of everything regardless of quantity, measurement or level of protection required to accomplish scope of work.

General:

A. Demolition: The Contractor shall remove and dispose of Government property, all items indicated as TO BE REMOVED. Such items become the property of the Contractor and shall be loaded, transported per applicable DOT regulations, and disposed at approved landfills.

B. Field Verification: The Contractor is responsible for field verification of all measurements, quantities, and field conditions prior to commencing work.

C. Staging: All equipment, supplies and materials for this contract shall be stored in the work area at the Contractor’s risk. The buildings and grounds at BARC will be secured at the end of each day by BARC Security. The security at BARC is not responsible for any of the Contractor's stored material, equipment, either inside or outside the building at any time.

D. Construction Project Schedule: See contract, FAR 52.236-15 Schedules for Construction Contracts. The Contractor will not begin actual work until the construction project schedule has been approved by the CO. The Contractor shall submit one electronic copy of the updated construction project schedule with each progress payment request.

E. Contract Inspector’s Daily Report: Contractor shall submit to the CO a daily report listing the names of all those present on the job site each day, along with their Job Classification, hours of work and a brief description of the work performed by each on that day. The Contract Inspector’s Daily Report is to be submitted at the beginning of work each day for the previous day’s work and shall be maintained throughout the term of the contract.

F. Formal Meetings: Any meeting (deemed formal by the Contractor, the COR, or the CO) will have the minutes of said meeting prepared by the Contractor (and a copy provided to the CO). The minutes will include: Date, Name of Attendees (with contact info), Old Business, and New Business subjects (or narratives). Regardless of who requests a meeting (the COR or the Contractor or the CO) the Contractor may be required to provided hard copy pictures of the issues to be discussed. Each issue will be linked to a contract specification section number and/or subject area by page number. Issues discussed will also include an action/completion date.

G. Safety Submittals: Contractor shall submit a "site specific" Safety Plan to the CO that describes how the Contractor is to comply with all applicable OSHA standards and NFPA codes pertaining to construction work to include, but not limited to: General Safety and Health Provisions, Occupational Health and Environmental Controls, Personal Protective and Life Saving Equipment, Hand and Power Tools, Welding and Cutting, Electrical, Scaffolds, Fall Protection, Excavations, Demolition, Stairways and Ladders, Toxic and Hazardous Substances, Confined Space Entry, Lockout/Tagout, Respiratory Protection, Hearing Protection. Safety Plan shall identify Contractor and sub-Contractor employees who are authorized/qualified to perform electrical work. No work shall proceed until written approval of the Safety Plan by the CO. Safety Plan shall describe how the Contractor and/or sub-Contractors are to secure equipment, supplies, tools, and chemical products. Contractor and/or sub-Contractor equipment, supplies, tools, and chemical products are to be under the control of the Contractor at all times, equipment, supplies tools, and chemical products found not to be under the control of the Contractor or sub-Contractor are subject to confiscation and will be reported to the CO.

H. The Contractor shall inspect the entire construction site daily, including days without construction work if there are NFPA 101 Life Safety Code deficiencies existing while construction work is shut down, the results of that inspection shall be documented on the attachment “DAILY INSPECTION FORM”, and the form is to be signed and submitted to the CO.

I. Contractor shall provide continuous monitoring for noise, dust, chemical vapor generation, volatile organic compounds, and vibration. At no time shall noise exposure to any ARS staff exceed 75 dB. Contractor shall provide to the CO a written weekly update of the all test results and also for proposed work for the subsequent two weeks (a two week “look-ahead”)involving any construction activity that will produce loud noises, heavy vibrations, strong smells, or significant dust inside ARS staff occupied space.

J. Contractor and sub-Contractors shall notify in writing the CO at least one week prior to executing high risk work (this may be included in the two week “look-ahead” update). High risk work includes, but is not limited to, tasks requiring Lockout/Tag Out, live electrical work, hot work, work at heights, trenching/ shoring, crane operations, and confined space entry. Contractor’s Competent Person shall provide the CO written weekly documented safety inspection results.

K. Contractor shall provide to the CO for approval, copies of Safety Data Sheets (SDS) for EVERY CHEMICAL WITHOUT EXCEPTION prior to bringing such chemical on the work site.

L. Hot and Grinding Work Permits: The Contractor will not be permitted to work without this permit when performing Hot and Grinding Work.

M. Scheduling: The total contract period shall be 130 calendar days from the point of contract award. A period of 5 calendar days shall be allotted for the submittal, 5 calendar days for review and re-submit process. A period of 75 days shall be allotted for ordering materials and the delivery of those ordered materials. The final inspection shall be scheduled a maximum of 125 calendar days from point of contract award, leaving 5 days for punch list remedies. The Contractor shall submit a copy of his proposed schedule to the CO for approval.

N. Submittals: The Contractor shall submit the manufacturer’s technical data sheets and shop drawings for the items listed in the Submittal Registry five (5) calendar days from the point of contract award. Each submittal shall be attached to a Submittal Transmittal Form (enclosed), signed by the Contractor, and delivered to the CO. Provide 6 copies of each material submittal.

O. Coordination: The Contractor shall coordinate with the COR, with adequate notice, all work which will require an inconvenience or work stoppage to Government personnel due to noise, dust, extreme temperatures, or interruption in utilities.

P. Complete Work: It is the intent of this project to contract for a complete, functioning mechanical and or electrical system, finished in all respects, accomplished by mechanics skilled in the trades involved and performed in the highest standards of workmanship.

Q. Manufacturer Warranty: Manufacturer shall warrant pipe and fittings for one (1) year to be free of defects in materials or workmanship. Warranty shall cover labor and material costs of repairing and/or replacing defective materials and repairing any incidental damage caused by failure of the piping system do to defects in materials or workmanship. Warranty shall be in effect only upon submission by the Contractor to the manufacturer valid pressure/leak test documentation indicating that the system was tested and passed the manufacturer’s pressure/leak test.

R. Contractor Guaranty and Warranty: All contracted work shall be guaranteed by the Contractor for a period of one (1) year for labor from the date of final acceptance against defective materials, design, and workmanship. The material shall be as specified in the manufacture’s specifications but at least one year. Upon receipt of notice from the Government of failure of part or parts of the guaranteed equipment during the warranty period, the affected part or parts shall be replaced within 48 hours with new parts by and at the expense of the Contractor. ALL WARRANTIES SHALL BE TURNED OVER TO THE COTR PRIOR TO FINAL INVOICING.

S. It shall be the Contractor’s responsibility to segregate the three identified waste streams (aluminum, plastic, and toner cartridges) and transport them to the two designated centralized collection points. Collection point number one will be located behind Building 003 and collection point number two will be located behind Building 200. The contracted recycler is scheduled to deliver collection containers to both centralized collection points within the next week. Once the collection containers have been delivered Contractor shall be notified and begin placing the identified waste streams into the collection containers.

T. Bio Preferred Materials: The Contractor must comply with Sections 9002 of the Farm Security and Rural Investment Act of 2002; the Food Conservation and Energy Act of 2008; and the Agricultural Act of 2014; and the Federal Acquisition Regulation to provide biobased products. The Contractor shall also comply with the clause at FAR 52.223-2, Affirmative Procurement of Biobased Products Under Service and Construction Contracts contained in Section I. The Contractor shall also comply with the provision at FAR 52.223-1, Biobased Product Certification contained in Section K.

The Contractor shall utilize products and material made from biobased materials (e.g., biobased insulating foam, biobased interior paints and coatings, and biobased wood and concrete sealers). All supplies and materials shall be of a type and quality that conform to applicable Federal specifications and standards. All supplies and materials to be used in the performance of work described herein are subject to the approval of the COR.

The following is a list of products that may be used in this minor construction contract for which biobased products are available and the designated biobased content. The list is not all inclusive. It is desirable that vendors can supply the greatest number of biobased products listed meeting the health and environmental specifications.

Composite Panels – Acoustical – 37 percent; Interior Panels – 55 percent; Plastic Lumber – 23 percent; Structural Interior Panels – 89 percent; Structural Wall Panels – 94 percent and Countertops and Solid Surface -_ 89 percent

Concrete and Asphalt Cleaners – 70 percent

Concrete and Asphalt Release Fluids – 87 percent

Dust Suppressants – 85 percent

Floor Coverings (Non-Carpet) – 91 percent

General Purpose Cleaners - 54 percent

Hand Soaps and Cleaners – 64 percent

Industrial Cleaners – 41 percent

Insulating Foam – 7 percent

Paint- Interior Paints and Coatings, Latex – 20 percent and Oil-based – 67 percent

Paint Removers – 41 percent

Wastewater Systems Coatings – 47 percent

Wood and Concrete Sealers – Membrane Concrete Sealers- 11 percent and Penetrating Liquids – 79 percent

Wood and Concrete Stains – 39 percent

Biobased products that are designated for preferential procurement under USDA’s Bio Preferred Program must meet the required minimum biobased content as stated in USDA’s Final Rules available at www.biopreferred.gov. The Contractor shall provide data for their biobased products such as biobased content. In addition to the biobased products designated by the USDA Bio Preferred Program, the Contractor is encouraged to use other commercially available biobased products such as biobased products certified with a label.

Within thirty (30) days of contract award, the Contractor shall provide a complete list of USDA’s designated biobased products that it intends to use or supply during performance of this contract, including products used or supplied by subcontractors. For each product, the Contractor shall identify the product and brand/manufacturer. For each designated product, the Contractor shall also identify the biobased content. The Contractor shall provide detail on how the Contractor intends to keep abreast of the development and increasing availability of designated and non-designated biobased products and how any new or improved products will be incorporated on an ongoing basis into contract performance. The list shall be approved by the COR in writing. The Contractor shall not commence work until this list is approved by the COR in writing.

Reporting is required by Sections 9002 of the Food Conservation and Energy Act of 2008 and the Agricultural Act of 2014. The Contractor shall provide quantities, product types and dollar value of any USDA-designated biobased product purchased by the Contractor. This important data shall be submitted to the COR for the current quarter and current contract year.