Amendment_0001_122B4618Q0019.pdf
PDF 248 KB Posted
- Solicitation number
- 122B4618Q0019
About this file
Amendment 0001 122B4618Q0019 WRP Sumter County, SC
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SF1442_122B4618Q0019_WATSON_WRP.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
122B4618Q0019 x x
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT
THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
NRCS-PR-12F352
HATO REY PR 00918
Suite 604
654 MUNOZ RIVERA AVENUE
USDA-NRCS CARIBBEAN AREA OFFICE
WASHINGTON DC 20250
NRCS-HQ-122B46
ROOM 6801-S
1400 INDEPENDENCE AVENUE, SW
USDA-NRCS CONTRACTING TEAM 2
NRCS-HQ-122B46
04/13/20180001
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
04/06/2018
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not, is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
This amendment is issued to provide the list of contractors that participated from the site visit held on April 11, 2018 and provide the Questions and Answers:
- CP&G General Contractors
- LCS
- Lindlers construction of South Carolina
- Seed Slingers
- JT Owens Construction Co.
- Southern Wildlife Consulting Group
- Skippers Construction LLC
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
ORIEL VELEZ
STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA
FAR (48 CFR) 53.243
NSN 7540-01-152-8070
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
x 1
4/13/2018
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
NAME OF OFFEROR OR CONTRACTOR
2 2
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
122B4618Q0019/0001
2. Below are the Questions and Answers for this project:
Q1: Where will the excavated spoil be wasted?
Will it need to be transported offsite?
A1: Per Construction Specification 2, Section 7-A Item #2, "Excavated earth material shall be wasted on the roadway if it is approved by the Inspector. Excavated earth material not acceptable for road fill may be wasted on the sides and shoulders of the roadway as approved by the inspector".
Q2: Will the culverts need to be hauled offsite?
A2: Yes. Per Construction Specification 3, Section 7-A Item#2, "All culverts that are removed shall be hauled to an acceptable disposal site". (It is meant that the disposal site is offsite)
3. All terms and conditions remain unchanged.
There are no additional changes by reason of this amendment.
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
| 2018-04-13T10:48:05-0400 | |
| ORIEL VELEZ OLIVIERI |
File details come from the government source that posted it.