AMEND 1_07082020.pdf
PDF 235 KB Posted
- Solicitation number
- 1224H820Q0021
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 1224H820Q0021_06102020.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
Previous edition unusable
AMENDMENT 01: Q&A
North East Acquisition Team 4 Farm Colony Drive Warren PA 16365
See block 6.
1224H820Q0021
07/08/2020
06/10/2020
Solicitation: 1224H820Q0021
Date: 8 July 2020
AMENDMENT 01:
QUESTIONS AND ANSWERS:
1. QUESTION: Can you please tell me what forms are required to be submitted with the request for quotation? I went to the website but it doesn’t say what forms are actually to be submitted. I did find the Bid Bond Form SF-24-16d. Anything else besides the Standard Form 18 and the Schedule of Items?
RESPONSE: The instructions can be found in Section L and M of the solicitation
2. QUESTION: What is the correction period for this project? Usually it is 1 year, can you clarify?
RESPONSE: It appears you are asking about the warranty. Reference FAR clause 52.246-21 Warranty of Construction (MAR 1994) as included in the solicitation.
3. QUESTION: I was just completing the solicitation documents for 1224H820Q0021 – Red Bridge Wastewater System Rehabilitation and I have a question regarding Section K. What Paragraph (d) are the documents referring to? On page 29 of 41 it states (i) Paragraph (d) applies or (ii) Paragraph (d) does not apply. I do not see a Paragraph (d).
RESPONSE: It appears you are referring to paragraph (d) of the solicitation provision, FAR 52.204-8 Annual Representations and Certifications (MAR 2020). Paragraph (d) of the provision starts on page 32 and carries over to page 33 of 41.
4. QUESTION: I have a question regarding The Sustainable Acquisition Plan, can you tell me if this is specific to this job only or our company in general?
RESPONSE: Reference section C.1 of the solicitation.
5. QUESTION: The specs call for hauling the existing filter media to a Forest Service stone pit. Do you know how far from the work site that this FS stone pit is?
RESPONSE: Reference Section 017320-Selective Demolition, Part 3.4. This section in the contract states that filter sand material shall be placed in the stone pit located on Forest Road
587. The pit location is 4.31 miles from the Red Bridge Wastewater Treatment Plant.
6. QUESTION: Under what bid item does the site pipe work go?
RESPONSE: If it is “Prep” not pipe then it would be line items 2 and 3: Remove existing sand filter media, Remove existing sand filter structure & liner
If it is pipe, then it would be line item 7, Install new effluent piping.