AMEND_1_04082019.pdf

PDF 78 KB Posted

Attached to
Robert Frost Interpretive Trail Reconstruction Green Mountain National Forest
Solicitation number
12168119R0003
Issued by

About this file

Amendment 1 Q&A

View the file

Other files

File Type Posted
12168119R0003.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

12168119R0003 GMNF Robert Frost Interpretive Trail Reconstruction

AMENDMENT 1

Q&A

1. QUESTION: Can you confirm the preferred start date and end date for this project?

RESPONSE: Reference Box 11 on the SF 1442 for the period of performance and number of calendar days to begin performance upon receipt of a notice to proceed. The period of performance is 120 days after receipt of the notice to proceed. The earliest start date could be middle of May 2019. That is based on when snow is gone off the ground and when a contract is awarded.

2. QUESTION: Is the site visit on April 12th mandatory?

RESPONSE: No, but in accordance with provision 52.236-27, offerors are urged and expected to inspect the site where the work will be performed. Also reference clauses 52.236-3-Site Investigation and Conditions Affecting Work and 52.236-2-Differing Site Conditions.