Amendment 1 Q&A

View the file

Other files

File Type Posted
12168119R0002.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

12168119R0002 General Construction IDIQ on the Green Mountain National Forest

AMENDMENT 1

Questions & Answers:

1. QUESTION 1: What is the date and time this package is due?

RESPONSE: The date and time due is on the solicitation on www.fbo.gov . Proposals are due by 1:00 PM (EST) on March 29, 2019.

2. QUESTION 2: On the schedule of items, concerning item #60201, spell out CPP

RESPONSE: FP-14, Section 708, Corrugated Polyethylene Pipe

3. QUESTION 3. Also on the schedule of items, should pricing include installation labor and equipment costs? The hourly rates used to be separate.

RESPONSE: Pay Items are in accordance with FP-14. Labor and Equipment are included in each pay item (no separate).

4. QUESTION: On page 45 3.(a) What do we need to include in our bid from Section-K

RESPONSE: Section K-Offerors Reps and Certs.

5. QUESTION: where is the bid tabulation, so we can submit unit rates, and is this a multi year bid as before?

RESPONSE: This is RFP does not contain a schedule of items. The task orders will be sent out for pricing each time. The sample task order needs to be priced as it will be used to evaluate pricing. The sample task order starts around page 172

Resulting contracts will be for a base period and four, one-year option periods.