Fawn Creek Revised RFP. Changes noted in yellow highlight.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Fawn_Creek_Amendment_003.pdf | ||
| Fawn_Creek_AOP_Amendment_002.pdf | ||
| Fawn_Creek_Amendment_001.pdf | ||
| Amendment_001_FAWN_CREEK-Final_AOP_Drawings.pdf | ||
| Amendment_001_FSSS_Fawn_Creek_AOP_19_Rd_MP_10-6.pdf | ||
| Fawn_Creek_AOP_Attachments_1-6.zip | ZIP file | |
| Fawn_Creek_AOP_RFP.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
OMB APPROVAL NO. 2700-0042
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NO.
1205GG19R0001
2. TYPE OF SOLICITATION
SEALED BID (IFB)
NEGOTIATED (RFP)
3. DATE ISSUED
4/1/2019
PAGE OF PAGES
IMPORTANT - The “offer” section on the reverse must be fully completed by offeror.
4. CONTRACT NO.
5. REQUISITION/PURCHASE REQUEST NO.
To be initiated prior to award
6. PROJECT NO.
7. ISSUED BY CODE 8. ADDRESS OFFER TO
USDA Forest Service Acquisition Management 215 Melody Lane Wenatchee WA 98801
USDA Forest Service Acquisition Management- Mariah Morris 215 Melody Lane Wenatchee WA 98801
9. FOR INFORMATION
CALL:
A. NAME
Mariah Morris Titus, CO Marge Hutchinson, COR
B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS) 509-664-9317 509-653-1430
SOLICITATION
NOTE: In sealed bid solicitations “offer” and “offeror” mean “bid” and “bidder.”
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date):
RFP 1205GG19R0001
Fawn Creek AOP – FSR 1900 MP 10.6
Naches Ranger District Yakima County
Price Range: The Government's estimate is between $250,000 and $500,000.
DUNS __________________________
TIN ____________________________
EMAIL _________________________
11. The Contractor shall begin performance within 10 calendar days after receiving award, notice to proceed. This performance period is mandatory, negotiable. (See Section F.)
12A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If “YES,” indicate within how many calendar days after award in Item 12B.)
YES NO
12B. CALENDAR DAYS
13. ADDITIONAL SOLICITATION REQUIREMENTS:
A. Sealed offers in original and 3 copies to perform the work required are due at the place specified in Item 8 by 1200 (hour) local time 5/6/2019 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror’s name and address, the solicitation number, and the date and time offers are due.
B. An offer guarantee is, is not required.
C. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
D. Offers providing less than 60 calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)
Computer Generated Prescribed by GSA FAR (48 CFR) 53.236-1(e)
OFFER (Must be fully completed by offeror)
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)
15. TELEPHONE NO. (Include area code)
16. REMITTANCE ADDRESS (Include only if different than Item 14)
CODE FACILITY CODE
17. The offeror agrees to perform the work at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government within calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each
AMENDMENT NO.
DATE
20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER
(Type or print)
20B. SIGNATURE
20C. OFFER DATE
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT
23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
Reference Block 27
ITEM
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c)( ) 41 U.S.C. 253(c)( )
26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY
INVOICE PROCESSING PLATFORM IPP
ALL INVOICES MUST BE SUBMITTED ELECTRONICALLY
THROUGH THE INVOICE PROCESSING PLATFORM (IPP)
VIA WWW.IPP.GOV
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return _3_ copies to issuing office.) Contractor agrees to furnish and deliver all items or perform all work, requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications or incorporated by reference in or attached to this contract.
29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.
30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED
TO SIGN (Type or print)
31A. NAME OF CONTRACTING OFFICER (Type or print)
30B. SIGNATURE
30C. DATE
31B. UNITED STATES OF AMERICA
BY
31C. AWARD DATE
Computer Generated STANDARD FORM 1442 BACK (REV. 4-85)
PART I—THE SCHEDULE
SECTION B--SUPPLIES OR SERVICES AND PRICES/COSTS
SCHEDULE OF ITEMS
Naches Ranger District
Okanogan-Wenatchee National Forest Yakima County, Washington
B- 1 - SCHEDULE OF ITEMS
BASE ITEMS
ITEM
NO.
DESCRIPTION
PAY
UNIT
MEAS.
METHO
D
EST.
QTY.
UNIT
PRICE
TOTAL
PRICE
15101 Mobilization LS CQ 1 15201 Construction Survey & Staking, Method
2, Tolerance A
LS CQ 1
15761 Dewatering Structures EA AQ 1
15713 Soil Erosion & Pollution Control LS CQ 1 20301 Removal of existing CMP, Disposal
Method A
EA CQ 1
20407 Roadway Excavation CY CQ 220 20417 Embankment Construction, Compaction method B
CY CQ 950
20801 Structural Excavation CY CQ 1892 20803 Structural Backfill CY CQ 736 25102 Placed Riprap – Class 05 Ton CQ 75 30202 Aggregate surface course, Method 1, Placement method 2 Ton CQ 390
40301 Asphalt Concrete, Type 1, Grading ¾” Ton CQ 230 55305 Precast concrete member, 60’ footings LS CQ 1 60205 32’ span, 8’ rise precast reinforced concrete box culvert
LF CQ 59
62552 Seeding & Mulching – Dry method LS CQ 1
63501 Temporary Traffic Control LS CQ 1
64802A Streambed Channel Rock, Class 1-3, Method C
Ton CQ 90
64802B Simulation Rock, Bed Class 12, Method A
Ton CQ 350
TOTAL BASE $___________
CONSTRUCTION RFP 1205GG19R0001
B-2 NOTE: Payment for bond premiums in accordance with Clause 52.232-5, Payments under Fixed- Price Construction Contracts, shall not be in addition to the contract price. Include bond payments under 151.01 Mobilization.
Payment will be made on actual work performed as described in FP-03 109.01 unless otherwise noted.
B-3 NOTE: Notice to Offeror(s)/Supplier(s): Funds are not presently available for this effort. No award will be made under this solicitation until funds are available. The Government reserves the right to cancel this solicitation, either before or after the solicitation’s closing date. In the event the Government cancels this solicitation, the Government has no obligation to reimburse an offeror for any costs incurred.
B-4 NOTE: No award shall be made to a Contractor not registered in the System for Award Management (www.sam.gov) database. (Section I)(Previously CCR) Contract award with a value of $100,000 or more, the Contractor must also be registered with VETS-100 (https://vets100.vets.dol.gov/).
SECTION C--DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK
C.1 Scope of Contract: The project will consist of removal of existing 60” x 38” x 60’ elliptical CMP and installation of a new 32’ x 9’ x 60’ precast concrete (3-sided) box culvert placed on precast concrete footings on a two lane asphalt road. The stream channel shall be constructed using streambed simulation rock and construction of rock ribs. Contractor shall be responsible for providing all labor, tools, material and equipment necessary to perform all work in strict accordance with the specifications and drawings. Payment for contract work will be made only for and under those pay items included in the Schedule of Items. All other work and materials will be considered as incidental to and included in the payment for the items shown.
The Contractor shall utilize products and material made from biobased materials to the maximum extent possible without jeopardizing the intended end use or detracting from the overall quality delivered to the end user. All supplies and materials shall be of a type and quality that conform to applicable Federal specifications and standards. All supplies and materials to be used in the performance of work described herein are subject to the approval of the Contracting Officer Representative (COR). It is desirable that vendors be able to supply the greatest number of biobased products listed meeting the health and environmental specifications.
C.2 Project Location: The project is located on the Naches Ranger District of the Okanogan- Wenatchee National Forest. To access the project area, from Naches, WA, take US Highway 12 W for approximately 4.4 miles to WA-410 W. Follow WA-410 W for 24.2 miles to Forest Service Road (FSR) 19 (Little Naches Road). Follow FSR 19 for 10.6 miles to the Fawn Creek crossing and the project site.
C.3 Price Range: The government estimate is between $250,000 and $500,000
C.4 Description of Work: The contract includes excavation of fill and roadway material, and https://vets100.vets.dol.gov/ removal of an existing 60” x 38” x 60’ squash culvert. The existing pipe is under approximately 5 feet of fill on a two lane asphalt surfaced road. Precast concrete footing to be furnished and installed according to the drawings. The new streambed shall be constructed using various sizes of rock and through construction of rock ribs as shown in the drawings. Construction of pools and riffles will also be necessary. A new 32’ x 9’ x 60’ precast concrete 3-sided box culvert is to be furnished and installed.
Backfill shall be done carefully to ensure proper compaction. Riprap shall be machine placed as bank stabilization. The exiting road grade will be raised approximately one foot with a crushed aggregate base course placed and compacted under new HMAC surfacing placed on the roadway. Dewatering will be required during removal of the existing 60” x 38” squash culvert and during installation of the box culvert. To dewater the site, the contractor may divert the majority of the water along the toe of the fillslope of the 1900 to the bridge at mile post 10.4.
For assigned activities, the Contractor shall provide the CO with an accurate construction schedule.
C.5 Performance Period: It is anticipated that this contract will be awarded by May 31, 2019.
Normal operating season is June through mid November. All instream work must be completed between July 16 and August 15 of 2019 or 2020. Work must be begin within 5 days of the Notice to Proceed and all contract work shall be completed by September 2, 2020. The total closure of the road shall not exceed 19 calendar days. It is the intent of the Government to complete at least some contract work in 2019. For example, at a minimum, order and have the precast concrete box culvert delievered in 2019 with construction work to follow in 2020.
C.6 Project Control: Contractor shall submit a proposed work schedule, prior to beginning construction, for approval by the Contracting Officer.
The contractor will be allowed to close FSR 19 – Naches Pass Road from mile post 10.4 to mile post
10.8 to all traffic for a maximum of 19 days from 0600 on Monday till 1200 Friday (including 2 weekends) during the in-water work window. Otherwise the road may be closed to all traffic for up to 2 hours with 15 minute open periods. The road must be left in a condition to pass traffic at the end of each work day and during weekends outside of the complete closure window. A minimum of three weeks notice must be given to the CO prior to any closures and the closures must be included in the schedule provided to the CO prior to starting any work. Road Closures and delays should be minimized. In the event of a wildfire or emergency, contractor maybe asked to provide access as possible.
Contractor is responsible for protecting workers from injury. Refer to FAR 52.236-13, Accident Prevention, for full text.
The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. The Government is not responsible for loss of or damage to materials or supplies stored on-site during performance of this contract.
Unless otherwise agreed, to prevent the introduction of seeds of noxious weeds onto National Forest land, Contractor shall ensure all equipment moved onto National Forest land is free of soil, seeds, vegatative matter or other debris that could contain or hold seeds. Contractor shall employ whatever cleaning methods necessary to insure compliance with this provision, and shall notify the Forest Service prior to moving each piece of equipment onto National Forest land.
Upon request of Forest Service, arrangements will be made for Forest Service to inspect each piece of equipment prior to being moved onto National Forest land.
C.7 Technical Specifications:
References to Standard Specifications in the contract refer to the U.S. Department of Transportation, “Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects: FP-14 U.S. Customary Units,” hereafter refered to as FP-14, and are included by reference. The requirements contained in Section 101 through 158 are hereby made a part of this solicitation and any resultant contract.
Supplemental Specifications that amend FP-14 are given on the Supplemental List but are physically attached in Section J. The attachments to the Statement of Work and the Supplemental Specifications listed in Section J are hereby made part of this solicitation and any resultant contract.
Specifications not on the list but referenced by other Standard Specifications, shall also be applicable to this document.
Offerors can access the FP-14 specifications from the website below:
http://www.wfl.fha.dot.gov/design/specs/fp14.htm
C.8 AGAR 452.211-72 Statement of Work/Specifications (FEB 1988)
The Contractor shall furnish the necessary personnel, material, equipment, services and facilities (except as otherwise specified), to perform the Statement of Work/Specifications referenced in Section J.
C.9 AGAR 452.211-73 Attachments to Statement of Work/Specifications (FEB 1988)
The attachments to the Statement of Work/Specifications listed in Section J are hereby made part of this solicitation and any resultant contract.
http://www.wfl.fha.dot.gov/design/specs/fp14.htm
SECTION D--PACKAGING AND MARKING
{For this Solicitation, there are NO clauses in this Section}
SECTION E--INSPECTION AND ACCEPTANCE
E.1 FAR 52.252-2 Clauses Incorporated by Reference (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): www.arnet.gov/far/
FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES
Clause Number Title Date 52.246-12 Inspection of Construction AUG 1996
E.2 Inspection and Acceptance (AGAR 452.246-70) (FEB 1988)
(a) The Contracting Officer or the Contracting Officer's duly authorized representative will inspect and accept the supplies and/or services to be provided under this contract.
(b) Inspection and acceptance will be performed at the project site.
E.3 Inspection and Testing Performed By Government
The Government will perform sampling, testing and inspection of work in progress where these responsibilities are not expressly assigned to the Contractor by the Forest Service specifications or by the Special Project Specifications.
E.4 Conformity With Drawings And Specifications
Unless working tolerances are specified, all work performed and materials furnished shall be in reasonably close conformity with lines, grades, cross sections, dimensions, and material requirements shown on the Drawings, indicated in the specifications, or designated on the ground. "Reasonably close conformity" is in compliance with reasonable and customary manufacturing and construction tolerances.
http://www.arnet.gov/far/
SECTION F--DELIVERIES OR PERFORMANCE
F.1 FAR 52.252-2 Clauses Incorporated by Reference (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): www.arnet.gov/far/
FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES
Clause Number
Title Date
52.242-14 Suspension of Work APR 1984
F.2 FAR 52.211-10 Commencement, Prosecution, and Completion of Work (APR 1984)
The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use within 60 calendar days. The time stated for completion shall include final cleanup of the premises.
SECTION G--CONTRACT ADMINISTRATION DATA
G.1 AGAR 452.215-73 Post Award Conference (NOV 1996)
A post award conference with the successful offeror is required. It will be scheduled and held within 15 days after the date of contract award. The conference will be held at a mutually agreed upon location.
G.2 Contract Release
When submitting final payment, Contractor shall provide a signed and dated contract release that includes the following information: "In consideration of receipt of final payment in the amount of $__________ Contractor hereby releases the United States of America from any and all obligations arising under this contract and any modifications thereof except as reserved herein.
Reservations:______________"
G.3 DESIGNATION OF CONTRACTING OFFICER’S REPRESENTATIVE
The Contracting Officer will designate a Contracting Officer's Representative (COR) at the time of contract award.
The COR is responsible for administering the performance of work under this contract. In no event, however, will any understanding, agreement, modification, change order, or other matter deviating from the terms of this contract be effective or binding upon the Government unless formalized by proper contractual documents executed by the Contracting Officer prior to completion of the contract.
The Contracting Officer should be informed as soon as possible of any actions or inactions by the Contractor or the Government which will change the required delivery or completion times stated in the contract, and the contract will be modified accordingly. (This does not apply to individual task assignments which were issued by the COR provided they do not affect the delivery schedule or performance period stated in the contract).
On all matters that pertain to the contract terms the Contractor must communicate with the Contracting Officer. Whenever, in the opinion of the Contractor, the COR requests effort outside the scope of the contract, the Contractor should so advise the COR. If the COR persists and there still exists a disagreement as to proper contractual coverage, the Contracting Officer should be notified immediately, preferably in writing if time permits. Proceeding with work without proper contractual coverage could result in nonpayment or necessitate submittal of a contract claim.
SECTION H--SPECIAL CONTRACT REQUIREMENTS
H.1 FAR 52.236-4 Physical Data (APR 1984)
Data and information furnished or referred to below is for the Contractor’s information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor.
A. The indications of physical conditions on the drawings and in the specifications are the result of site investigations by observations and measurements.
B. Weather conditions: Typical for East Slopes of the Cascades and Central Washington. The elevation of this project is approximately 3100 feet. Typical day time temperatures are in the 60’s to 70’s and typical night time temperatures are in the 40’s to 50’s. The typical work season is June to mid- November.
H.2 WA Use Tax Clause for Construction Contracts: The Contractor is liable for Use Tax, in accordance with State of Washington Code 458-20-173, Sub-paragraph (8), which states: “Thus the use tax applies to all property provided by the federal Government to the Contractor for installation or inclusion in the contract work as well as to all Government provided tooling”.
H.3 Conformity with Drawings and Specifications: Unless working tolerances are specified, all work performed and materials furnished shall be in reasonably close conformity with lines, grades, cross sections, dimensions, and material requirements shown on the drawings, indicated in the specifications, or designated on the ground. “Reasonably close conformity” is compliance with reasonable and customary manufacturing and construction tolerance.
H.4 Warning Signs and Restrictions: Contractor shall be totally responsible for safety signing, barricades and other signing to maintain a safe site to the public and Government employees.
H.5 Traffic Control: The Contractor shall provide, erect, and maintain all necessary barricades, suitable and sufficient lights, danger signals, signs, and other traffic control devices, and shall take all necessary precautions for the protection of the work and safety of the public. Roads closed to traffic shall be protected by effective barricades, and obstructions shall be illuminated during the hours of darkness. Suitable warning signs shall be provided to properly control and direct traffic.
The Contractor shall erect warning signs in advance to any place on the project where operations may interfere with the use of the road or trail by traffic and at all intermediate points where the new work crosses or signs, lights, temporary signals, flagmen and pilot car operators and equipment, and other protective devices, except for special devices, shall conform with Part VI of the Manual on Uniform Traffic Control Devices for Streets and Highways, published by the Federal Highway Administration and applicable safety codes.
The contractor will be allowed to close FSR 19 – Naches Pass Road at mile post 10.6 to all traffic for a maximum of 19 days from 0600 on Monday till 1200 Friday (including 2 weekends) during the in-water work window. Otherwise the road may be closed to all traffic for up to 2 hours with 15 minute open periods. The road must be left in a condition to pass traffic at the end of each work day and during weekends outside of the complete closure window. A minimum of three weeks notice must be given to the CO prior to any closures and the closures must be included in the schedule provided to the CO prior to starting any work. Road Closures and delays should be minimized. In the event of a wildfire or emergency contractor, maybe asked to provide access as possible.
H.6 Emergency Control:
A. Contractor's Responsibility for Fighting Fire.
1. The Contractor, under the provisions of FAR clause 52.236-9, Protection of Existing Vegetation, Structures, Equipment, Utilities and Improvements, shall immediately extinguish all fires on the work site other than those fires in use as a part of the work.
2. The Contractor may be held liable for all damages and for all costs incurred by the Government for labor, subsistence, equipment, supplies and transportation deemed necessary to control or suppress a fire set or caused by the Contractor or the Contractor' agents or employees.
B. Contractor's Responsibility for Notification in Case of Fire. The Contractor shall immediately notify the Government of any fires sighted on or in the vicinity of the work site.
C. Contractor's Responsibility for Responding to Emergencies.
When directed by the Contracting Officer, the Contractor shall allow the Government to temporarily use employees and equipment form the work site for emergency work (anticipated to be restricted to fire fighting). An equitable adjustment for the temporary use of employees and equipment will be made under the Change clause, or under an Emergency Equipment Rental Agreement. Payment will be made at not less than the current area rates established by the Government. Employees and equipment will be released from emergency operations when other labor and equipment adequate for the protection of the area are obtained.
NOTE: See Fire Plan Requirements referenced in Section J.
H.7 Legal Relations and Responsibilities: Contractor's Responsibility for Utilities - In the event of interruption to utility services because of accidental breakage the Contractor shall promptly notify the utility authority and shall cooperate with that authority in the restoration of service.
H.8 Job Specific Safety Plan: Prior to the prework meeting, the Contractor shall provide a written job specific safety plan that recognizes the inherently hazardous conditions that will exist on this contract. Some of these hazardous conditions are, but not limited to: fall protection, heavy equipment operation, permitted confine space entry, traffic control on haul routes, loading an unloading of materials, site security, noises and dust contract and the use of personal protective equipment (PPE) in the work area. The plan shall be in accordance with OSHA Regulations. The plan shall include all tasks and related activities anticipated to successfully complete the work.
H.9 Accident Prevention: The Contractor shall provide and maintain work environments and procedures, which will (1) safeguard the public and Government personnel, property, materials, supplies, and equipment exposed to Contractor operations and activities; (2) avoid interruptions of Government operations and delays in project completion dates; and (3) control costs in the performance of this contract. A Safety Plan will be requested before starting work.
H.10 Storage of Materials and Equipment: Materials shall be stored to assure the preservation of their quality and fitness for work. Approved portions of the right-of-way or other areas on Government land may be used for storage purposes. All storage sites approved by the Government shall be restored to a satisfactory condition at the Contractor's expense.
H.11 Landscape Preservation and Hazardous Materials:
A. The Contractor shall confine operations to within the clearing limits or other areas designated in contract documents, and prevent the depositing of rocks, excavated materials, stumps, or other debris outside of these limits. Material which falls outside of these limits shall be retrieved, disposed of, or incorporated in the work as directed by the Contracting Officer, and damage to vegetation or structures outside the clearing limits shall be repaired as directed by the Contracting Officer.
B: Contractor shall notify the Government of any hazardous materials and or waste (as defined in 29
CFR 1910.1200) to be used on the job and will have Material Safety Data Sheets (MSDS's) for those materials available on the job. All such materials shall be labeled in accordance with Federal and State regulations.
C: Operations shall be scheduled and conducted to minimize erosion of soils and to prevent silting and muddying of streams, rivers, irrigation systems, and impoundments (lakes, reservoirs, etc.).
Pollutants such as fuels, lubricants, bitumen, raw sewage, and other harmful materials shall not be discharged into or near rivers, streams, and impoundments or into natural or manmade channels leading thereto. Wash water or waste from concrete or aggregate operations shall not be allowed to enter live streams prior to treatment by filtration, settling, or other means sufficient to reduce the sediment content to not more than that of the stream into which it is discharged.
Mechanized equipment shall not be operated in live streams without written approval by the
Contracting Officer.
D. Prevention of Oil Spills - If the Contractor maintains storage facilities for oil or oil products on the
Project Area, Contractor shall take appropriate preventive measures to ensure that any spill of such oil or oil products does not enter any stream or other waters of the United States or any of the individual States and shall conform to Federal, State, and Local regulations.
If the total oil or oil products storage exceeds 1,320 gallons or if any single container exceeds a capacity of 660 gallons, Contractor shall prepare a Spill Prevention Control and Countermeasure (SPCC) Plan. Such plan shall meet applicable EPA requirements (40 CFR 112) including certification by a registered professional engineer.
All petroleum products or other hazardous substances shall not be released on or into land or into rivers, streams, and impoundments, or into natural or manmade channels leading thereto. Servicing of all equipment shall be done only in the areas approved by Contracting Officer or designated representative. Contractor shall properly dispose of vehicle oil filters (drained of free-flowing oil), oily rags, and waste oil in accordance with Local, State, and Federal regulations off of Government property and shall transport such material in accordance with State and Federal regulations.
Contractor shall immediately take action to notify appropriate agencies including Contracting Officer, or designated representative, contain, and cleanup without expense to the Government, all petroleum products or other hazardous substance (as defined in 29 CFR 1910.120) releases on/or in the vicinity of the project of construction operations. Contractor shall be held liable for all damages and costs of additional labor, subsistence, equipment, supplies and transportation deemed necessary by the Government for the containment and cleanup of petroleum products releases caused by Contractor’s employees or resulting from construction operations.
H.12 Contractor Camps: Forest Service regulations for Use of Campgrounds prohibit occupancy of developed recreation sites for other than primarily recreation purposes. No contractor camping will be authorized at these sites. A special use permit is required on National Forest land for contractor camps.
These permits are to be obtained by the Contractor through the Contracting Officer. Such permission, if granted, will be without charge to the Contractor but may include use restrictions. One self-contained camp unit will be allowed at each staging area and equipment or supply dump for use by a watchman.
H.13 Use of Premises:
A. The Contractor shall comply with the regulations governing the operation of premises which are occupied and shall perform this contract in such a manner as not to interrupt or interfere with the conduct of Government business.
B. Before any camp, quarry, borrow pit, storage, detour, or bypass site, other than shown on the drawings, is opened or operated on Forest Service land or lands administered by the Forest Service, the Contractor shall obtain written permission from the appropriate Ranger District. A camp is interpreted to include a campsite or trailer parking area of any employee working on the project for the Contractor. If permission is granted, a work order will specify all conditions and requirements.
Sanitation facilities shall be provided for all employees of the Contractor and members of the campsite.
C. It is further stipulated that in addition to clean-up of any campsites, the Contractor shall remove his equipment from National Forest Service land before final acceptance and payment of the contract.
D. The Contractor shall provide and maintain sanitary facilities. There shall be a minimum of one toilet for each ten employees. Solid waste shall be dispose of in accordance with applicable Federal, State and local regulations.
H.14 Use of Water: The Contractor may use water from an agreed upon location within 6 miles of the project site. Location will depend on volume of water needed and timing of need. Pumping from other locations must be approved by the Contracting Officer. All pump intakes shall be equipped with a screen meeting the National Marine Fisheries Service criteria, mesh size (3/32 inch) and at least one square inch of functional screen area per each gallon per minuite (gpm) of pump capacity and no more than 10% of the flow may be used.
H.15 Contractor’s Use of Existing Roads: The Contractor is authorized to use roads in the immediate construction project area for performance of work under this contract. The authorization is limited to roads necessary for direct access between the construction area and storage sites, disposal areas, and other work areas designated in the contract.
The roads authorized for use will be subject to the following general conditions:
(1) State laws governing traffic rules and equipment requirements on State and County Highways.
(2) Federal Regulations contained in 36 CFR 261.12. These regulations prohibit use in excess of
State Codes for weight and size, damaging a road while using it, and blocking a road open to use by others.
(3) The current National Forest Road Use Rules Document is applicable to all commercial road users. This document is available for inspection at the office of the Forest Supervisor and shall be applicable except when modified by provisions of this contract.
Load Limits --All vehicles and equipment shall not exceed State legal highway loads and widths or posted limits without valid State and Forest Service overload, overwidth permits. Forest Service overload permit applications for this project may be obtained from the COR and must be submitted at least 30 days in advance to the COR for regional review.
H.16 Washing of Equipment: Pollutants such as fuels, lubricants, bitumen, raw sewage, and other harmful materials shall not be discharged on the ground; into or nearby rivers, streams, or impoundments; or into natural or man-made channels. Wash water or waste from concrete or aggregate operations shall not be allowed to enter live streams prior to treatment by filtration, settling, or other means sufficient to reduce the sediment content to not more than that of the stream into which it is discharged.
The Contractor shall wash all equipment except for hauling vehicles prior to entering National Forest Land. Remove all soil which could contain noxious weeds. Remove grease and oil from drive mechanisms which would be discharged into the stream when equipment is operating. Prior to transporting equipment to the site, assure that the equipment's hydraulic, lubrication and fuel systems are free from leaks.
H.17 Product Substitution, Shop Drawings and Material Certification: Product Substitution. Any modification of other items, designs, materials, products or equipment (including Government- Furnished Property), made necessary because of a substitution, will be the responsibility of the Contractor without adjustment in contract price or time. The Contracting Officer’s approval of any substitute will not affect the Contractor’s responsibility for such modification. All substitutions shall be requested by the Contractor after award of the contract has been made. No approvals will be made prior to award. Shop drawing of the precast concrete box culvert and the precast concrete footings must be submitted for review to the Contracting Officer at least 21 days prior to fabrication.
H.18 Material Certifications and Testing Reports: The following material certifications and/or testing reports shall be submitted on this project: See List of Required Submittals
Noxious Weeds: All materials transported onto or incorporated into the work will be certified noxious weed free, either through visual inspection or commercial certification. The Contracting Officer will request written documentation of the methods used to determin the weed free status of any and all materials furnished by the contractor. Contractor-provided expertise and methods to establish weed free status must be appropriate for the weeds of concern in the local area.
A Forest Service weed specialist will inspect sources to determine weed free status. Provide the Contracting Officer written notification of proposed material sources 10 days prior to use. Written approval of the specific source will be provided to the contractor. If weed species are present in the proposed source, appropriate mitigation measures as requried by the Contracting Officer may allow conditional use of the source.
H.19 Payments for Incidental Items: The intent of the contract is to provide for the complete construction of the project described in the contract. Unless otherwise provided, the Contractor shall furnish all labor, materials, equipment, tools, transportation, and supplies and perform all work required to complete the project in accordance with drawings, specifications, and provisions of the contract.
Payment for contract work will be made only for and under those pay items included in the Schedule of Items. All other work and materials will be considered incidental to and included in the payment for items shown.
H.20 Costing of Claims or Modifications: The cost principles and procedures in Subpart 31.2 of the Federal Acquisition Regulations shall be used in the pricing of contract claims and modifications, and for determining costs under terminated contracts, except, where actual costs can be determined from the Contractor's accounting records. Allowable ownership and operating costs for owned or rented equipment shall be determined from “The Construction Equipment Ownership and Operating Expense Schedule”, U.S. Army Corps of Engineers Publication EP 1110-1-8, published by the U.S. Government Printing Office, to the extent that this publication contains a listing of the equipment being priced, or of similar equipment. During periods of suspension of work pursuant to a contract clause, the allowance for equipment ownership shall not exceed the amount for standby cost as determined by this schedule.
H.21 Construction Stakes, Lines and Grades:
A. The Forest Service shall flag or mark on the ground the location of the control points. The contractor is responsible for any additional staking needed for specific items.
B. These flags/marks shall constitute the field control from which the Contractor shall establish other necessary controls and execute the work. The Contractor shall furnish, without additional compensation, all additional stakes and other materials and supplies necessary.
C. The Contractor is responsible for the preservation of all stakes and control points. The cost of replacing them will be charged to the Contractor when destroyed due to Contractor's negligence or operation.
PART II--CONTRACT CLAUSES
SECTION I--CONTRACT CLAUSES
I.1 FAR 52.252-2 Clauses Incorporated by Reference (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):
www.arnet.gov/far/ www.usda.gov/procurement/policy/agar.html
FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES
52.202-1 Definitions (NOV 2013) 52.203-3 Gratuities (APR 1984) 52.203-5 Covenant Against Contingent Fees (MAY 2014) 52.203-6 Restrictions on Subcontractor Sales to the Government (SEP 2006) 52.203-7 Anti-Kickback Procedures (MAY 2014) 52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity
(MAY 2014)
52.203-10 Price or Fee Adjustment for Illegal or Improper Activity (MAY 2014) 52.203-12 Limitation on Payments to Influence Certain Federal Transactions (OCT 2010) 52.203-17 Contractor Employee Whistleblower Rights and Requirement to Inform Employees of
Whistleblower Rights (APR 2014) 52.204-4 Printed or Copied Double-Sided on Recycled Paper (MAY 2011) 52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards (JUL 2013) 52.204-13 System for Award Management Maintenance (JUL 2013) 52.204-19 Incorporation by Reference of Representations and Certifications (DEC 2014) 52.209-6 Protecting the Government's Interest when Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment (AUG 2013) 52.209-9 Updates of Publicly Available Information Regarding Responsibility Matters (JUL 2013) 52.211-18 Variation in Estimated Quantity (APR 1984) 52.215-2 Audit and Records -- Negotiation (OCT 2010) 52.219-6 Notice of Total Small Business Set-Aside (NOV 2011) 52.219-8 Utilization of Small Business Concerns (OCT 2014) 52.219-14 Limitations on Subcontracting (NOV 2011) 52.222-3 Convict Labor (JUN 2003) 52.222-4 Contract Work Hours and Safety Standards -- Overtime Compensation (MAY 2014) 52.222-6 Construction Wage Rate Requirements (MAY 2014) 52.222-7 Withholding of Funds (MAY 2014) 52.222-8 Payrolls and Basic Records (MAY 2014) 52.222-9 Apprentices and Trainees (JUL 2005) 52.222-10 Compliance with Copeland Act Requirements (FEB 1988) 52.222-11 Subcontracts (Labor Standards) (MAY 2014) 52.222-12 Contract Termination - Debarment (MAY 2014) 52.222-13 Compliance with Construction Wage Requirements and Related Regulations (FEB 1988) http://www.usda.gov/procurement/policy/agar.html
52.222-14 Disputes Concerning Labor Standards (FEB 1988) 52.222-15 Certification of Eligibility (MAY 2014) 52.222-21 Prohibition of Segregated Facilities (FEB 1999) 52.222-26 Equal Opportunity (MAR 2007) 52.222-27 Affirmative Action Compliance Requirements for Construction (FEB 1999) 52.222-35 Equal Opportunity for Veterans (JUL 2014) 52.222-36 Affirmative Action for Workers with Disabilities (JUL 2014) 52.222-37 Employment Reports on Veterans (JUL 2014) 52.222-40 Notification of Employee Rights under the National Labor Relations Act (DEC 2010) 52.222-50 Combating Trafficking in Persons (FEB 2009) 52.222-55 Minimum Wages Under Executive Order 13658 (DEC 2014) 52.223-2 Affirmative Procurement of Biobased Products under Service and Construction Contracts
(SEP 2013)
52.223-6 Drug-Free Workplace (MAY 2001) 52.223-15 Energy Efficiency in Energy-Consuming Products (DEC 2007) 52.223-18 Encouraging Contractor Policies to Ban Text Messaging While Driving (AUG 2011) 52.225-13 Restrictions on Certain Foreign Purchases (JUN 2008) 52.227-1 Authorization and Consent (DEC 2007) 52.227-2 Notice and Assistance Regarding Patent and Copyright Infringement (DEC 2007) 52.227-4 Patent Indemnity -- Construction Contracts (DEC 2007) 52.228-2 Additional Bond Security (OCT 1997) 52.228-11 Pledges of Assets (JAN 2012) 52.228-12 Prospective Subcontractor Requests for Bonds (MAY 2014) 52.228-14 Irrevocable Letter of Credit (NOV 2014) 52.228-15 Performance and Payment Bonds – Construction (OCT 2010) 52.229-3 Federal, State, and Local Taxes (FEB 2013) 52.232-5 Payments under Fixed-Price Construction Contracts (MAY 2014) 52.232-17 Interest (MAY 2014) 52.232-18 Availability of Funds (APR 1984) 52.232-23 Assignment of Claims (MAY 2014) 52.232-27 Prompt Payment for Construction Contracts (MAY 2014) 52.232-33 Payment by Electronic Funds Transfer – System for Award Management (JUL 2013) 52.232-39 Unenforceability of Unauthorized Obligations (JUN 2013) 52.232-40 Providing Accelerated Payments to Small Business Subcontractors (DEC 2013) 52.233-1 Disputes (MAY 2014) 52.233-3 Protest after Award (AUG 1996) 52.233-4 Applicable Law for Breach of Contract Claim (OCT 2004) 52.236-2 Differing Site Conditions (APR 1984) 52.236-3 Site Investigation and Conditions Affecting the Work (APR 1984) 52.236-5 Material and Workmanship (APR 1984) 52.236-6 Superintendence by the Contractor (APR 1984) 52.236-7 Permits and Responsibilities (NOV 1991) 52.236-8 Other Contracts (APR 1984) 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements
(APR 1984)
52.236-10 Operations and Storage Areas (APR 1984) 52.236-11 Use and Possession Prior to Completion (APR 1984) 52.236-12 Cleaning Up (APR 1984)
52.236-13 Accident Prevention (NOV 1991) Alternate I (NOV 1991)
52.236-15 Schedules for Construction Contracts (APR 1984) 52.236-16 Quantity Surveys (APR 1984)
Alternate I (APR 1984) 52.236-17 Layout of Work (APR 1984) 52.236-21 Specifications and Drawings for Construction (FEB 1997) 52.236-26 Preconstruction Conference (FEB 1995) 52.242-13 Bankruptcy (JUL 1995) 52.243-4 Changes (JUN 2007) 52.244-6 Subcontracts for Commercial Items (OCT 2014) 52.245-1 Government Property (APR 2012) 52.246-21 Warranty of Construction (MAR 1994) 52.248-3 Value Engineering – Construction (OCT 2010) 52.249-2 Termination for Convenience of the Government (Fixed-Price) (APR 2012)--Alternate I
(SEP 1996)
52.249-10 Default (Fixed-Price Construction) (APR 1984) 52.253-1 Computer Generated Forms (JAN 1991)
AGRICULTURE ACQUISITION REGULATION (48 CFR CHAPTER 4) CLAUSES
452.232-70 Reimbursement for Bond Premiums – Fixed-Price Construction Contracts (NOV 1996) 452.236-71 Prohibition Against the Use of Lead-Paint (NOV 1996) 452.236-72 Use of Premises (NOV 1996) 452.236-73 Archeological or Historic Sites (FEB 1988) 452.236-74 Control of Erosion, Sedimentation and Pollution (NOV 1996) 452.236-76 Samples and Certificates (FEB 1988) 452.236-77 Emergency Response (NOV 1996)
I.2 AGAR 452.209-71 Assurance Regarding Felony Convictions or Tax Delinquent Status for Corporate Applicants (FEB 2012) Alternate I (FEB 2012)
(a) This award is subject to the provisions contained in section As prescribed in 25.1102(d)(2), substitute the following paragraph (b) for paragraph (b) of the basic provision:
(b) Requests for determination of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American statute shall submit the request with its offer, including the information and applicable supporting data required by paragraphs (c) and (d) of FAR clause 52.225-11.
s 433 and 434 of the Consolidated Appropriations Act, 2012 (P.L. No. 112-74), Division E, as amended and/or subsequently enacted, regarding corporate felony convictions and corporate federal tax delinquencies. Accordingly, by accepting this award the contractor acknowledges that it –
(1) does not have a tax delinquency, meaning that it is not subject to any unpaid Federal tax liability that has been assessed, for which all judicial and administrative remedies have been exhausted or have lapsed, and that is not being paid in a timely manner pursuant to an agreement with the authority responsible for collecting the tax liability, and https://acquisition.gov/far/current/html/Subpart%2025_11.html#wp1078063 https://acquisition.gov/far/current/html/52_223_226.html#wp1193406
(2) has not been convicted (or had an officer or agent acting on its behalf convicted) of a felony criminal violation under any Federal law within 24 months preceding the award, unless a suspending and debarring official of the United States Department of Agriculture has considered suspension or debarment of the awardee, or such officer or agent, based on these convictions and/or tax delinquencies and determined that suspension or debarment is not necessary to protect the interests of the Government.
(b) If the awardee fails to comply with these provisions, the Forest Service may terminate this contract for default and may recover any funds the awardee has received in violation of sections 433 or 434.
I.3 FAR 52.219-28 Post-Award Small Business Program Rerepresentation (JUL 2013)
(a) Definitions. As used in this clause—
Long-term contract means a contract of more than five years in duration, including options. However, the term does not include contracts that exceed five years in duration because the period of performance has been extended for a cumulative period not to exceed six months under the clause at 52.217-8, Option to Extend Services, or other appropriate authority.
Small business concern means a concern, including its affiliates, that is independently owned and operated, not dominant in the field of operation in which it is bidding on Government contracts, and qualified as a small business under the criteria in 13 CFR part 121 and the size standard in paragraph (c) of this clause. Such a concern is “not dominant in its field of operation” when it does not exercise a controlling or major influence on a national basis in a kind of business activity in which a number of business concerns are primarily engaged. In determining whether dominance exists, consideration shall be given to all appropriate factors, including volume of business, number of employees, financial resources, competitive status or position, ownership or control of materials, processes, patents, license agreements, facilities, sales territory, and nature of business activity.
(b) If the Contractor represented that it was a small business concern prior to award of this contract, the Contractor shall rerepresent its size status according to paragraph (e) of this clause or, if applicable, paragraph (g) of this clause, upon the occurrence of any of the following:
(1) Within 30 days after execution of a novation agreement or within 30 days after modification of the contract to include this clause, if the novation agreement was executed prior to inclusion of this clause in the contract.
(2) Within 30 days after a merger or acquisition that does not require a novation or within 30 days after modification of the contract to include this clause, if the merger or acquisition occurred prior to inclusion of this clause in the contract.
(3) For long-term contracts—
(i) Within 60 to 120 days prior to the end of the fifth year of the contract; and
(ii) Within 60 to 120 days prior to the date specified in the contract for exercising any option thereafter.
https://www.acquisition.gov/far/current/html/52_217_221.html#wp1135887
(c) The Contractor shall rerepresent its size status in accordance with the size standard in effect at the time of this rerepresentation that corresponds to the North American Industry Classification System…