a.RFQ_Crescent_Roads_Closure_.pdf
PDF 2 MB Posted
- Attached to
- Crescent Roads Closure
- Solicitation number
- 1204GG18Q0017
About this file
Crescent Roads Closure Solicitation
View the file
Other files
| File | Type | Posted |
|---|---|---|
| e.Past_Performance_Data_Sheet.docx | DOCX document | |
| b.Project_Maps_1-4.docx | DOCX document | |
| d.Fire_Specifications_R6-FS-6300-52.pdf | ||
| f.Equipment_Inspection-Cleaning_form.doc | DOC document | |
| c.SCA_Wage_Determination_77-0079.txt | TXT text file | |
| Project_Maps_1-4.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS 1. REQUISITION NUMBER PAGE 1 OF 46
OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, & 30 916978
2. CONTRACT NO. 3. AWARD/EFFECTIVE 4. ORDER NUMBER 5. SOLICITATION NUMBER 6. SOLICITATION ISSUE DATE:
DATE
1204GG18Q0017
June 28th, 2018
a. NAME b. TELEPHONE NUMBER(No collect
8. OFFER DUE DATE/ LOCAL
TIME
7. FOR SOLICITATION RaShauna Workman - CO calls) 541-383-5433 July 27th, 2018 INFORMATION CALL: Marcos Romero - COR 541-383-5624 @ 16:30 p.m. (PST)
9. ISSUED BY CODE 10. THIS ACQUISITON IS
DESCHUTES NATIONAL FOREST
63095 Deschutes Market Rd.
Bend, OR. 97701
UNRESTRICTED OR SET ASIDE: 100 % FOR
SMALL BUSINESS EMERGING SMALL
BUSINESS
HUBZONE SMALL
NAICS: 115310 BUSINESS
SERVICE-DISABLED VETERAN- 8(A)
SIZE STANDARD: 500 Employees OWNED SMALL BUSINESS
11. DELIVERY FOR FOB DESTINATION
UNLESS BLOCK IS MARKED
SEE SCHEDULE
12. DISCOUNT TERMS 13a. THIS CONTRACT
IS A RATED ORDER
UNDER DPAS (15 CFR 700)
13b. RATING
14. METHOD OF SOLICITATION
RFQ IFB RFP
15. DELIVER TO CODE
16. ADMINISTERED BY CODE
Same As Block 9
17a. CONTRACTOR/ CODE FACILITY
OFFEROR CODE
18a. PAYMENT WILL BE MADE BY CODE
Invoice Processing Platform (IPP)
DUNS_________________
TELEPHONE N0.__________________ Email ___________________
17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT SUCH ADDRESS IN 18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a UNLESS BLOCK BELOW
OFFER IS CHECKED
SEE ADDENDUM
19. 20. 21. 22. 23. 24.
ITEM N0. SCHEDULE OF SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
Crescent Roads Closure
Crescent Ranger District, Deschutes National Forest
All Quotes shall be submitted via email, mail, or hand delivered no later than July 27th, 2018 @ 16:30 (4:30) p.m.
(PST) to one of the following locations:
rworkman@fs.fed.us or Deschutes National Forest; 63095 Deschutes Market Rd.; Bend, OR. 97701.
25. ACCOUNTING AND APPROPRIATION DATA
26. TOTAL AWARD AMOUNT (For Govt. Use Only)
27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1, 52.212-4. FAR 52.212-3 AND 52.212-5 ARE
ATTACHED. ADDENDA
ARE ARE NOT ATTACHED
27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS
ATTACHED. ADDENDA
ARE ARE NOT ATTACHED
28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN
29. AWARD OF CONTRACT: REF. 1204GG18Q0016 OFFER
COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND
DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY DATED .. YOUR OFFER ON SOLICITATION ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED (BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE
SET FORTH HEREIN, IS ACCEPTED AS TO ITEMS: ____________________
30a. SIGNATURE OF OFFEROR/CONTRACTOR 31a. UNITED STATES OF AMERICA (SIGNATURE OF CONTRACTING OFFICER)
RaShauna Workman 30b. NAME AND TITLE OF SIGNER (Type or print) 30c. DATE SIGNED 31b. NAME OF CONTRACTING OFFICER (Type or print) 31c. DATE SIGNED
AUTHORIZED FOR LOCAL REPRODUCTION STANDARD FORM 1449 (REV.3/2005)
PREVIOUS EDITION IS NOT USABLE Prescribed by GSA - FAR (48 CFR) 53.212
04GG
mailto:rworkman@fs.fed.us
SCHEDULE OF ITEMS
ITEM NO. DESCRIPTION OF ITEM QUANTITY UNIT
UNIT
PRICE
AMOUNT
BASE ITEMS:
1 Road Travelway Obliteration (Subsoil) .96 Mile $ $
Entry Management Treatment (Barriers w/Boulder
Placement)* 10 Each $ $
3 Boulders – Contractor Shall Furnish 39 Each $ $
Total of All Base Items $
OPTION ITEMS:
Additional: Road Travelway Obliteration &
Closures in Two Rivers Project Area
2.8 Miles $ $
Additional: Entry Management Treatment
(Barriers w/Boulder Placement)* in Two Rivers
Project Area
2 Each $ $
Additional: Entry Management Treatment
(Barriers w/Berm & Native Materials) 15 Each $ $
7 Boulders – Contractor Shall Furnish 8 Each $ $
Total of All Option Items $
Required Delivery Date: All work shall be completed within 30 calendar days after issuance of Notice To Proceed. All work shall be completed by November 1st, 2018.
Period of Performance Date may be extended due to potentail fire danger if a waiver cannot be obtained at that time and/or because of unforseeable weather conditions at the project location in which reduces the quality or efficiency of work performed.
*Contractor Furnished Materials
TOTAL Of BASE &
OPTION ITEMS:
32a. QUANTITY IN COLUMN 21 HAS BEEN
RECEIVED INSPECTED ACCEPTED, AND CONFORMS TO THE CONTRACT, EXCEPT AS NOTED: ________________________________________
32b. SIGNATURE OF AUTHORIZED GOVERNMENT
REPRESENTATIVE
32c. DATE 32d. PRINTED NAME AND TITLE OF AUTHORIZED GOVERNMENT
REPRESENTATIVE
32e. MAILING ADDRESS OF AUTHORIZED GOVERNMENT REPRESENTATIVE 32f. TELPHONE NUMBER OF AUTHORZED GOVERNMENT REPRESENTATIVE
32g. E-MAIL OF AUTHORIZED GOVERNMENT REPRESENTATIVE
33. SHIP NUMBER 34. VOUCHER NUMBER 35. AMOUNT VERIFIED
CORRECT FOR
36. PAYMENT 37. CHECK NUMBER
|PARTIAL | |FINAL
COMPLETE PARTIAL FINAL
38. S/R ACCOUNT NUMBER 39. S/R VOUCHER NUMBER 40. PAID BY
41a. I CERTIFY THIS ACCOUNT IS CORRECT AND PROPER
FOR PAYMENT
42a. RECEIVED BY (Print)
41b. SIGNATURE AND TITLE OF CERTIFYING OFFICER 41c. DATE
42b. RECEIVED AT (Location)
42c. DATE RECD (YY/MM/DD) 42d. TOTAL CONTAINERS
STANDARD FORM 1449 (REV.3/2005) BACK
1. SCOPE AND LOCATION
The desired outcome of this project is to address travel management issues an important wildlife habitat by reducing open road densities. Habitat quality is expected to improve by increasing refuge characteristics and habitat connectivity.
This requirement is set forth to accomplish the decommissioning and closure of unauthorized travel routes on the
Deschutes National Forest, Crescent Ranger District.
The work consists of Road Travelway Obliteration and Entry Management Treatments. Contractor shall provide all labor, materials, incidentals, and supplies needed to perform work as described in this contract, unless otherwise noted.
2. PROJECT LOCATION
The project work is located on the Deschutes National Forest, in Klamath County, Oregon.
Township 26S, Range 7E Section 11 and 12; Township 25S, Range 8E Sections 29, 30, 31, and 36.
See attached MAPS 1 – 4.
Note: Digital PDF maps of the project areas are available for use on tablets with the Avenza app for ease in locating specific work sites.
Deschutes National Forest, Crescent Ranger District
Klamath County, Oregon
Elevations – Approx. 4,453 ft. to 4,954 ft.
3. SYSTEM FOR AWARD MANAGEMENT (SAM)
Please Complete --- Is the Offeror currently registered in SAM (Yes / No): ___________
DUNS # _________________________
Prior to submitting a quote, contractors will be registered and have an active account with the System for Award
Management (SAM) pursuant to FAR 4.1102 and other applicable regulations and guidelines Any quote received from vendors not registered in SAM will be considered Non-Responsive and they will not be evaluated or considered for award.
The System for Award Management (SAM) is a Federal Government owned and operated FREE website that consolidates the capabilities in CCR/FedReg, Online Representations and Certifications Application (ORCA) and the
Excluded Parties List System (EPLS).
4. SPECIFICATIONS
Item 1: Road Obliteration
Activities shall include subsoiling for decompaction and surface cover, as outlined below. Activities shall occur on the entirety of the Road Prism identified in TABLES 1 - 3 and MAPS 1 - 4, or as modified by the Contracting Officer or their delegated representative. Road locations shall be flagged and numbered on the ground.
1. Subsoiling For Decompaction: Subsoiling will occur to a minimum depth of 18 inches (maximum 24 inches), except where the Government agrees to lesser depths. Soil shall be decompacted to the full depth, while preventing mixing or plowing. Surface disturbance of organics and vegetation, where present, will be minimized.
Once treated, the decompacted soil is slightly lifted and well-fractured rather than plowed, mixed, or displaced.
Treated areas shall span the entire length of the road and the total width of the compacted ground surface.
Subsurface rocks should not be pulled to the surface and large supportive roots should also not be severed.
Ground that cannot be effectively treated due to subsurface rock should be scarified to the extent possible – typically with the surface roughened and broken to a depth of 4-6 inches. The distance between subsoiled shank passes shall not exceed 24 inches.
Surface Cover: Available roadside material (such as downed wood, slash and root wads) shall be placed on the treated areas in conjunction with subsoiling to achieve a target effective ground cover of at least 50% by area. Where adequate material is not available to achieve 50% cover, at least one piece of roadside material per 20 linear feet of travelway distance is expected. The roadside material may include standing green trees under 7 inches DBH within 25 feet of the roads edge to achieve the desired surface coverage should other identified material not be available. Subsoiling and material placement shall be completed in one pass or in a way that would prevent compacting or displacing the treated area. Reference photos of subsoiling & slashing results are shown below in REFERENCE 1-3 (pages 4 and 5). All roads decommissioned will have barriers constructed at the entrance of each route to prevent future use and facilitate vegetative and soil recovery (see Item 2: Entry Management Treatment (Barrier Construction)). In some instances, one route may require two or more barriers if multiple intersections occur.
REFERENCE 1: Subsoil treatment result showing slightly lifted and well-fractured soil, rather than plowed, mixed, or displaced.
REFERENCE 2: Available roadside material such as downed wood, slash and root wads, shall be placed on the treated areas in conjunction with subsoiling
REFERENCE 3: Example of equipment used for subsoiling & slashing in one pass.
Item 2: Entry Management Treatment (Barrier Construction)
Activity shall occur on all roads identified in TABLES 1 and 2 (pages 6 and 7) and MAPS 1 – 3. In some instances, one route may require two or more barriers if multiple intersections occur. Barrier construction may extend beyond the road width if open conditions provide access around a road-width barrier. Barriers should not be passable by any 4WD passenger vehicle or ATV and should be discouraging to dirt bike use. Barriers shall be constructed from boulders
(minimum size of 3.0 feet in diameter in at least two dimensions) placed a maximum of 3.0 feet apart and partially buried and backfilled (minimum quarter depth) to discourage easy removal. To mimic a natural appearance, boulders will not be placed in an even, symmetrical pattern. Approximate number of boulders needed are identified in TABLES 1-2 (pages 6 and 7). Prior to hauling boulders, clearance from the Crescent District Botanist shall be given after assessing rock pits for weed contamination.
For barrier construction on routes also identified for road travelway obliteration, barriers require additional deep mixing of soil to roughen the surface to an unpassable condition beyond the limitations of the subsoiling treatment for sight distance
(approximately 12 feet by 300 feet) and should incorporate on-site material such as downed wood and root wads that can be reached without leaving the road surface with equipment. Subsoiled surfaces shall not be trafficked after treatment.
Subsoiling should not occur when the ground is frozen. Subsoiling should not occur when roads are wet - there should not be standing water on the road surface and free water should be completely drained from the soil profile.
Item 3. Optional Item: Additional Road Obliteration In Two Rivers Project Area
Activity shall occur on all roads identified in TABLE 2 (Page7) and MAP 4. Work shall be conducted as described for
Item 1: Road Obliteration.
Item 4. Optional Item: Additional Entry Management Treatment in Two Rivers Project Area (Barriers With
Boulder Placement)
Activity shall occur on all roads identified in TABLE 2 (Page 7) and MAP 4. Work shall be conducted as described for
Item 2: Entry Management Treatment (Barrier Construction).
Item 5. Optional Item: Additional Entry Management (barriers With Berm and Native Materials)
Activity shall occur on all roads identified in TABLE 2 (page 7) and MAP 4. Barriers shall be constructed by moving soil to create a berm at a minimum 4ft. to 5ft. high and spanning the width of the road closure. Native materials found on site such as root wads, woody debris, and downed trees shall be used to reinforce the berm and to deter vehicle traffic over the berm. Native materials shall also be placed behind the berm on the subsoiled road to further deter vehicle use.
For barrier construction on routes also identified for road travelway obliteration, barriers require additional deep mixing of soil to roughen the surface to an unpassable condition beyond the limitations of the subsoiling treatment for sight distance
(approximately 12 feet by 300 feet) and should incorporate on-site material such as downed wood and root wads that can be reached without leaving the road surface with equipment. Subsoiled surfaces shall not be trafficked after treatment.
Subsoiling shall not occur when the ground is frozen, roads are wet, and/or has standing water on the road surface. Free standing water should be completely drained from the soil profile.
TABLE 1. RAILROAD (RR) PROJECT AREA
Travel Route
Number
WORK NEEDED
RR 0
1500 ft. of road travelway obliteration; 2 barriers constructed (approximately 4 boulders each)
RR 15
780 ft. road travelway obliteration; 1 barrier constructed with berm (approximately 3 boulders) and woody debris; start work at FS property boundary 150 ft. down from junction with FS 5825 road
RR 23
1240 ft. of road travelway obliteration; 2 barriers constructed (approximately 4 boulders each)
FS 092 Road Close 092 road with 350 ft. of subsoiling from junction with 090 road, 1 barrier constructed
(with 4 boulders)
RR 40 664 ft. of road travelway obliterated and 1 barrier constructed (approximately 4 boulders)
RR 42 –
EROSION SLOPE
1 barrier constructed with 4 boulders
TOTAL
4534 ft. (.82 miles) road travelway obliteration; 8 barriers constructed
(approximately 31 boulders)
TABLE 2. TWO RIVERS (TR) PROJECT AREA
Number
WORK NEEDED
TR 15 and 14 400 ft. of travel route obliteration; 1 barrier constructed (approximately 4 boulders)
FS 400 road 350 ft. of travel route subsoiling; berm and 1 barrier (approximately 4 boulders) at junction with 5830 road
TOTAL
750 ft. (.14 miles) of road travelway obliteration; 2 barriers constructed
(approximately 8 boulders)
Totals: .96 miles of road obliteration, 10 barriers, and 39 boulders
TABLE 3. OPTIONAL WORK TWO RIVERS (TR) PROJECT AREA
Number
WORK NEEDED
TR 5
402 ft. road obliteration; 1 barrier to be constructed with berm and native materials at junction with FS 5830 road
TR 6
350 ft. of road obliteration; 1 barrier to be constructed with berm and native materials at junction with FS 200 road
TR 10
628 ft. road obliteration; 1 barrier to be constructed berm and native materials at the junction with the FS 220 road
TR 11
750 ft. of road obliteration; 1 barrier to be constructed with berm and native materials at junction with FS 220 road
TR 20
250 ft. of road obliteration; 1 barrier to be constructed with berm and native materials at junction with FS 100 road
TR 21
350 ft. of road subsoiling; 1 barrier to be constructed with berm and native materials at junction with FS 100 road
TR 22 1726 ft. of road obliteration
TR 23
1839 ft. of road obliteration; 1 barrier to be constructed with berm and native materials at junction with FS 200 road
TR 25
450 ft. of road obliteration; 1 barrier to be constructed with berm and native materials at junction with FS 200 road
TR 27
2330 ft. of road obliteration; 2 barriers to be constructed with berm and native materials at junction with FS 200 road
TR 28
2640 ft. of road obliteration; 2 barriers to be constructed with berms and 4 boulders
(each) at the junctions with FS 100 and 200 roads
TR 29
350 ft. of road obliteration; 1 barrier to be constructed with berm and native materials at junction with FS 100 road
TR 38
1380 ft. of road obliteration 1 barriers constructed with berms and native materials at junction with FS 200 road
TR 40
1340 ft. with 1 barrier constructed with berm and native materials at junction with FS
200 road
TOTAL 14,785 ft. ( miles) of road obliteration; 17 barriers constructed, 8 boulders
Total: 2.8 miles road obliteration, 17 barriers, and 8 boulders
5. CONTRACTOR OBLIGATIONS
The Contractor shall furnish, all labor, equipment, supervision, transportation, supplies, and incidentals. All Federal and State rules and regulations shall be followed as well as appropriate Federal Agency Jurisdictional Guidelines unique to each agency.
6. BIOBASED PRODUCTS
The Contractor must comply with the Agricultural Act of 2014; the Food, Conservation and Energy Act of 2008 (FCEA), 7 U.S.C. 8102; the Farm Security and Rural Investment Act of 2002 (FSRIA), 7 U.S.C. 8102; the Federal Acquisition
Regulation; Executive Order (EO) 13514, “Federal Leadership in Environmental, Energy and Economic Performance,” dated October 5, 2009; EO 13423, “Strengthening Federal Environmental, Energy, and Transportation Management,” dated January 24, 2007; and Presidential Memorandum, “Driving Innovation and Creating Jobs in Rural America through Biobased and Sustainable Product Procurement,” dated February, 2012 to provide biobased products.
All supplies and materials shall be of a type and quantity that conform to applicable Federal specifications and standards, and to the extent feasible and reasonable; include the exclusive use of biobased and recycled products.
The following is a list of categories for biopreferred products that may be available or required for performance of this contract.
Equipment Lubricants, Hydraulic Fluids, Fuel Additives, Engine Oils.
For more information regarding the Department of Agriculture Biobased Program go to: http://www.biopreferred.gov.
7. INSPECTION
A. CONTRACTOR’S QUALITY CONTROL PLAN
The Contractor shall provide a detailed Quality Control Plan. In General, the Quality Control Plan must demonstrate how the contractor will assure quality, and meet the requirements and specifications of the project work. Plan shall describe: how quality will be monitored to assure the performance standards are met; the supervision of the work;
and personnel that will be performing the quality control. In addition, the Contractor shall address industry standard guidelines, and any applicable State or Federal specifications, protection to the environment and wildlife habitat, and public safety in constructing a Quality Control Plan.
B. GOVERNMENT QUALITY ASSURANCE SURVEILLANCE PLAN
The Contracting Officer or the Contracting Officer’s duly authorized representative (COR) shall inspect and accept the services and/or supplies to be provided under this contract.
The Government shall use the following plan to assure quality control.
Item 1 – Extent of roadbed treated, depth of subsoiling.
Item 2 - Correct depth placement and horizontal spacing between boulders.
8. FAR 52.211-10COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)
The Contractor shall be required to (a) commence work under this contract within 5 calendar days after the date the
Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than November 1st. 2018. The time stated for completion shall include final cleanup of the premises.
9. MEASUREMENT AND PAYMENT
Item 1 - Payment per mile of work completed
Item 2 - Payment per barrier constructed http://www.biopreferred.gov./
10. FAR 52.246-4 INSPECTION OF SERVICES—FIXED-PRICE (AUG 1996)
Definition. “Services,” as used in this clause, includes services performed, workmanship, and material furnished or utilized in the performance of services.
The Contractor shall provide and maintain an inspection system acceptable to the Government covering the services under this contract. Complete records of all inspection work performed by the Contractor shall be maintained and made available to the Government during contract performance and for as long afterwards as the contract requires.
The Government has the right to inspect and test all services called for by the contract, to the extent practicable at all times and places during the term of the contract. The Government shall perform inspections and tests in a manner that will not unduly delay the work.
If the Government performs inspections or tests on the premises of the Contractor or a subcontractor, the Contractor shall furnish, and shall require subcontractors to furnish, at no increase in contract price, all reasonable facilities and assistance for the safe and convenient performance of these duties.
If any of the services do not conform to contract requirements, the Government may require the Contractor to perform the services again in conformity with contract requirements, at no increase in contract amount. When the defects in services cannot be corrected by re-performance, the Government may—
(1) Require the Contractor to take necessary action to ensure that future performance conforms to contract requirements; and
(2) Reduce the contract price to reflect the reduced value of the services performed.
If the Contractor fails to promptly perform the services again or to take the necessary action to ensure future performance in conformity with contract requirements, the Government may—
(1) By contract or otherwise, perform the services and charge to the Contractor any cost incurred by the
Government that is directly related to the performance of such service; or
(2) Terminate the contract for default.
11. AGAR 452.215-73 POST AWARD CONFERENCE (NOV 1996)
A post award conference with the successful offeror is required. It will be scheduled and held within _7 days after the date of contract award. The conference may be held at the Deschutes National Forest; 63095 Deschutes Market Rd; Bend, OR. 97701, conference call, or a mutually agreed upon location.
12. CONTRACTOR FURNISHED PROPERTY
The Contractor shall provide the following item(s) of property for use in accordance with the Specifications and Terms &
Conditions contained elsewhere in the contract to complete the described work.
These materials shall be of a quality and type customarily utilized on similar projects performed on the Deschutes
National Forest.
Item
No.
Property Description Qty. Location
Date
Available
Boulders For Base Items:
(Shall be a minimum size of 3.0 feet in diameter in at least two dimensions)
39 See Tables 1, 2, & 3 TBD
Boulders For Optional Items:
(Shall be a minimum size of 3.0 feet in diameter in at least two dimensions)
8 See Tables 1, 2, & 3 TBD
13. DESIGNATION OF CONTRACTING OFFICER'S REPRESENTATIVE (COR) AND GOVERNMENT
INSPECTORS
The Contracting Officer will designate the Contracting Officer's Representative.
The COR is responsible for administering the performance of work under this contract. In no event, however, will any understanding, agreement, modification, change order, or other matter deviating from the terms of this contract will be effective or binding upon the Government unless formalized by proper contractual documents executed by the Contracting
Officer prior to completion of the contract.
Government Inspectors: The Inspector(s) are designated by the Contracting Officer to represent the COR in securing compliance of contract requirements. The Designation of Inspector Form (form FS-6320-32) will be used to designate the inspector and provides the responsibilities. The inspector(s) will monitor Contractor performance and inform the
Contractor of contract deviations. The inspector(s) will monitor thinning in progress, and conduct quality verification plots. The inspector(s) will not direct the operations of the crew but rather keep in direct contact with the foreman stressing the requirement of Contractor quality control as well as to protect the Governments interest by assessing the adequacy of thinning and stand improvement activities.
The Contracting Officer should be informed as soon as possible of any actions or inactions by the Contractor, or the
Government will change the required delivery or completion times stated in the contract and the contract will be modified accordingly. (This does not apply to individual task assignments which were issued by the COR provided they do not affect the delivery schedule or performance period stated in the contract.)
On all matters that pertain to the contract terms the Contractor must communicate with the Contracting Officer.
Whenever, in the opinion of the Contractor, the COR requests effort outside the scope of the contract, the Contractor should so advise the COR. If the COR persists and there still exists a disagreement as to proper contractual coverage, the
Contracting Officer should be notified immediately, preferably in writing if time permits. Proceeding with the work without proper contractual coverage could result in nonpayment or necessitate submittal of a contract claim.
14. CONTRACTING OFFICER’S REPRESENTITIVE
Name: Marcos Romero
Address: 63095 Deschutes Market Rd.
Telephone: 541-383-5624
Email: mromero@fs.fed.us
15. APPROVAL OF SUBCONTRACTING
The Contractor shall request approval from the Contracting Officer prior to entering into any subcontract arrangement.
The subcontractor shall have the experience and be equipped for such work. The written notification shall include as a minimum:
a) The name, address, and telephone number(s) of the subcontractor.
b) The date upon which the subcontract was entered into and its duration.
c) A detailed description of the work being subcontracted including a listing of contract items, units, etc., as appropriate.
d) Documentation of the subcontractor's representative authority.
Subcontracting any portion of the contract shall not relieve the Prime Contractor of any responsibility under this contract.
Any subcontract agreement shall contain all terms and conditions of the prime contract.
16. SUSPENSION FOR OTHER THAN GOVERNMENT CONVENIENCE
The Contracting officer may issue orders to suspend work wholly or in part for such periods of time as deemed necessary because of : 1) Weather or ground conditions when further prosecution of the work might cause environmental or resource damage to the project, access roads, or adjacent property. Such actions would include but are not limited to instances such as siltation of streams, damage to access roads, rutting of project roads which causes otherwise suitable soils to become muddy or unsuitable for further work; or 2) failure of the Contractor to comply with specifications such as but not limited to placement of frozen materials in fills, seeding on frozen ground, operating equipment not meeting fire requirements, performing work prior to prerequisite approvals, or when conditions exist which do not meet safety requirements.
Whether or not a suspend work notice is issued, the Contractor shall be responsible for correcting any damage caused by his/her operation, whether inside or outside project limits, at no cost to the government. Such suspensions shall not be considered as suspensions for the Convenience of the Government under FAR 52.242-14, Suspension of Work, and shall not qualify for equitable adjustment.
17. TRAFFIC CONTROL
Contractor will provide traffic control devices and/or flaggers as appropriate for the road and conditions. Unless otherwise agreed in writing, when permittee's operations are in progress adjacent to or on Forest Service controlled roads and trails open to public travel, permittee shall provide the use with adequate warning of hazardous or potentially hazardous conditions associated with permittee's Operation. Devices shall be appropriate to current conditions and shall be covered or removed when not needed. Except as otherwise agreed, flaggers and devices shall be as specified in the "Manual on Uniform Traffic Control Devices for Streets and Highways" (MUTCD).
18. SAFETY
Services for this project will involve many types of equipment operating in varying terrain, possibly in adverse conditions. Individuals performing diverse jobs may be working throughout the project at any given time. A field meeting will be scheduled daily to discuss safety and planned daily operations.
The contractor shall submit a written site specific safety plan to ensure safety compliance when coordinating work activities. The intent is to use this plan as a discussion at the post award and subsequent meetings to insure safe contractor operations. It will also be used as the safety standard during the course of the project.
19. POTENTIAL SAFETY HAZARDS
(a) Data and information furnished or referred to below is for the Contractor's information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor. This list shall not be deemed to be all-inclusive. The Contractor shall bear the sole responsibility for taking all appropriate actions necessary to prevent accidents and injuries to individuals at the worksite.
(b) The following activities have been identified by the Government as potential safety hazards when performing complex restoration activities over a large project area. Contractor shall provide a job-specific safety plan addressing these hazards as well as any other potential hazards the Contractor has encountered in this type of work.
1) Working around heavy equipment and trucks, blind spots, backing, visibility, etc.
2) Working in semi-remote locations
3) Working on uneven terrain.
The job-specific safety plan should at a minimum address the following:
1) Job specific Personal Protective Equipment (PPE) for all individuals on the job site, safety vests, glasses, hardhats, foot wear, hearing protection, etc.
2) Job and equipment specific first-aid kits, spill kits for fuel, hydraulic fluid, etc.
3) Evacuation plan in case of injury, include EMS, and hospitals/clinics with directions, phone numbers, and additional contact information as needed.
20. NOXIOUS WEEDS
(a) In order to prevent the potential spread of noxious weeds onto Federal lands, the Contractor shall be required to furnish the Forest Service with proof of weed-free equipment.
(b) Noxious weeds are defined as any exotic plant species established or that may be introduced in the State, which may render the land unfit for agriculture, forestry, livestock, wildlife, or other beneficial uses and which is designated by the Oregon/Washington Department of Agriculture, County Weed Boards, or by other appropriate agencies having jurisdiction.
(c) All equipment and vehicles to be used at the job site shall be cleaned and certified free of noxious weeds and their seeds prior to entrance onto the National Forest. The restriction shall include equipment and vehicles intended for off-road use as well as on road use, whether they are owned, leased, or borrowed by the contractor or subcontractor.
(d) Cleaning shall consist of the removal of all dirt, grease, debris, and materials that may harbor noxious weeds and their seeds. This may require the use of a pressure hose. Cleaning shall occur off Federal lands.
(d) Equipment, materials and vehicles shall be visually inspected by a designated Forest Service Officer, and certified in writing to be reasonably clean and weed free. Inspections will take place at a location designated by the Forest Officer in advance of equipment and material arrival. Equipment and vehicles are expected to proceed directly to the job site following the inspection. Materials to be used on the project will be delivered to the project.
Certification shall remain valid for each identified piece of equipment or vehicle only for the duration of the specified project and only as long as the vehicle or equipment remains at the job site. Equipment and vehicles (excepting passenger vehicles - this includes pickups and vans) that leave the job site will need to be recertified as weed free before they are allowed to return to the job site or re-enter the National Forest.
All equipment including, but not limited to, vehicles, tools, hydro-seeders, mulch blowers/spreaders, tractors, trailers, excavators, and dozers shall be clean and free of mud, debris, seed, fertilizer, mulch, or any hydro seeding products used on prior jobs including both internal and external surfaces. Equipment will be inspected prior to any project work at a mutually agreed upon location(s) by the COR and/or Inspector. If equipment does not pass inspection, the contractor will be required to clean equipment off-site at an approved facility before returning to the project site. The Government is not liable for lost time due to re-cleaning of equipment.
21. CONTRACT RELEASE
When submitting final payment, Contractor shall provide a signed and dated contract release that includes the following information: "In consideration of receipt of final payment in the amount of $__________ Contractor hereby releases the
United States of America from any and all obligations arising under this contract and any modifications thereof except as reserved herein. Reservations:______________"
SPECIAL REQUIREMENTS
22. FAR 52.236-9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND IMPROVEMENTS (APR 1984)
(a) The Contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs, and grass) on or adjacent to the work sites, which are not to be removed and which do not unreasonably interfere with the work required under this contract. The Contractor shall only remove trees when specifically authorized to do so, and shall avoid damaging vegetation that will remain in place. If any limbs or branches of trees are broken during contract performance, or by the careless operation of equipment, or by workman, the Contractor shall trim those limbs or branches with a clean cut and paint the cut with a tree-pruning compound as directed by Contracting Officer.
(b) The Contractor shall protect from damage all existing improvements and utilities (1) at or near the work site and (2) on adjacent property of a third party, the location of which are made know to or should be known by the Contractor. The
Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the Contractor fails or refuses to repair the damage promptly, the Contracting Officer may have the necessary work performed and charge the cost to the Contractor.
23. LANDSCAPE PRESERVATION
The Contractor shall give attention to the effect of contract operation upon the landscape, shall take care to maintain natural surroundings undamaged, and shall conduct the work at all times in compliance with the following requirements.
a. Prevention of the Landscape Defacement. The Contractor shall not remove, deface, injure, or destroy trees, shrubs, lawns, or other natural features or any other improvements in the work area unless specifically authorized by the Contracting Officer. Unless otherwise provided herein, the Contractor shall confine contract operations to within the areas designated in contract documents.
b. Protection of Streams, Lakes, and Reservoirs. The Contractor shall take sufficient precautions to prevent pollution of streams, lakes, small ponds, and reservoirs with fuels, oils, bitumen’s, calcium chloride, silt, or other harmful materials. Mechanical equipment shall not be operated in live streams without written approval of the Contracting Officer.
24. CONTRACTOR’S USE OF EXISTING ROADS
The Contractor is authorized to use roads in the immediate construction project area for performance of work under this contract. The authorization is limited to roads necessary for direct access between the construction area and storage sites, disposal areas, and other work areas designated in the contract.
The roads authorized for use will be subject to the following general conditions:
(1) State laws governing traffic rules and equipment requirements on State and County Highways.
(2) Federal Regulations contained in 36 CFR 261.12. These regulations prohibit use in excess of State
Codes for weight and size, damaging a road while using it, and blocking a road open to use by others.
The Contractor shall be responsible for and perform road maintenance commensurate with his use of Forest
Service roads in the construction area.
25. ROAD MAINTENANCE REQUIREMENTS
In order to fulfill the obligation to protect existing facilities, material source, and disposal site access roads from seasonal weather damage, to safeguard soil and water quality, and to repair damage commensurate with his use, the Contractor shall perform road maintenance work on these roads in accordance with the following:
1. While performing ordinary road maintenance work, the Contractor shall avoid permanent fouling of gravel or bituminous surfaces through covering them with earth or debris from side ditches, slides, or other sources. The Contractor shall avoid blading surface material off the surface of roads.
2. While performing all phases of construction, the Contractor shall minimize damage to ditches, slopes and road surfaces. Where damage does occur, the Contractor shall restore the road to its prior condition within a reasonable period of time.
3. The Contractor shall remove all excess materials and debris from asphalt roadways and trails immediately after backfilling has been completed. This may require brooming and hosing down with water.
4. On completion and acceptance of work requirements, including acceptance of road maintenance by the
Forest Service, Contractor road maintenance responsibility shall terminate.
26. TRAFFIC CONTROL
The Contractor shall provide, erect and maintain all necessary barricades, suitable and sufficient lights, danger signals, signs, and other traffic control devices, and shall take all necessary precautions for the protection of the work and safety of the public. Roads closed to traffic shall be protected by effective barricades, and obstructions shall be illuminated during the hours of darkness. Suitable warning signs shall be provided to properly control and direct traffic.
The Contractor shall erect warning signs in advance to any place on the project where operations may interfere with the use of the road or trail by traffic and at all intermediate points where the new work crosses or coincides with an existing road or trail. All road barricades, warning signs, lights, temporary signals, flagman and pilot car operators and equipment, and other protective devices, except for special devices, shall conform to Part VI of the
Manual on Uniform Traffic Control Devices for Streets and Highways, published by the Federal Highway
Administration and applicable safety codes.
The Contractor shall furnish, erect, maintain, and remove when notified any project identification signs shown on the drawings
Necessary warning signs and guards shall be posted during blasting operations to safeguard the public.
27. SUSPENSIONS FOR OTHER THAN GOVERNMENT CONVENIENCE
The Contracting Officer may issue orders to suspend the work wholly or in part for such period of time as deemed necessary because of: (1) Weather or ground conditions when further prosecution of the work might cause environmental or resource damage to the project, access roads to the project, or adjacent property. Such action would include but not be limited to instances such as siltation of streams, damage to access roads, rutting of project roads which causes otherwise suitable soils to become muddy or unsuitable; or (2) Failure of the Contractor to comply with Specifications such as but not limited to placement of frozen material in fills, placing of asphalts at temperatures lower than those specified, performing work prior to prerequisite approvals, operating equipment not meeting fire requirements, or when conditions exist which do not meet safety requirements. Whether or not a suspend work notice is issued, the Contractor shall be responsible for correcting any damage caused by his/her operation, whether inside or outside project limits, at no cost to the Government. Such suspensions shall not be considered as suspensions for the Convenience of the Government under
FAR 52.242-14, Suspension of Work, and shall not qualify for equitable adjustment.
PART II - CONTRACT CLAUSES
28. FAR 52.212-4 CONTRACT TERMS AND CONDITIONS--COMMERCIAL ITEMS (JAN 2017)
ALTERNATE I (JAN 2017).
29. FAR 52.212-5 -- CONTRACT TERMS AND CONDITIONS REQUIRED TO IMPLEMENT
STATUTES OR EXECUTIVE ORDERS -- COMMERCIAL ITEMS (JAN 2017)
(a) The Contractor shall comply with the following Federal Acquisition Regulation (FAR) clauses, which are incorporated in this contract by reference, to implement provisions of law or Executive orders applicable to acquisitions of commercial items:
(1) 52.203-19, Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements (JAN 2017)
(section 743 of Division E, Title VII, of the Consolidated and Further Continuing Appropriations Act, 2015 (Pub. L. 113-
235) and its successor provisions in subsequent appropriations acts (and as extended in continuing resolutions)).
(2) 52.209-10, Prohibition on Contracting with Inverted Domestic Corporations (Nov 2015).
(3) 52.233-3, Protest After Award (AUG 1996) (31 U.S.C. 3553).
(4) 52.233-4, Applicable Law for Breach of Contract Claim (OCT 2004)(Public Laws 108-77 and 108-78 (19 U.S.C.
3805 note)).
(b) The Contractor shall comply with the FAR clauses in this paragraph (b) that the Contracting Officer has indicated as being incorporated in this contract by reference to implement provisions of law or Executive orders applicable to acquisitions of commercial items:
[Contracting Officer check as appropriate.]
__ (1) 52.203-6, Restrictions on Subcontractor Sales to the Government (Sept 2006), with Alternate I (Oct 1995) (41
U.S.C. 4704 and 10 U.S.C. 2402).
__ (2) 52.203-13, Contractor Code of Business Ethics and Conduct (Oct 2015) (41 U.S.C. 3509)).
__ (3) 52.203-15, Whistleblower Protections under the American Recovery and Reinvestment Act of 2009 (June
2010) (Section 1553 of Pub. L. 111-5). (Applies to contracts funded by the American Recovery and Reinvestment Act of
2009.)
__ (4) 52.204-10, Reporting Executive Compensation and First-Tier Subcontract Awards (Oct 2016) (Pub. L. 109-
282) (31 U.S.C. 6101 note).
__ (5) [Reserved].
_X_ (6) 52.204-14, Service Contract Reporting Requirements (Oct 2016) (Pub. L. 111-117, section 743 of Div. C).
__ (7) 52.204-15, Service Contract Reporting Requirements for Indefinite-Delivery Contracts (Oct 2016) (Pub. L.
111-117, section 743 of Div. C).
_X_ (8) 52.209-6, Protecting the Government’s Interest When Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment. (Oct 2015) (31 U.S.C. 6101 note).
__ (9) 52.209-9, Updates of Publicly Available Information Regarding Responsibility Matters (Jul 2013) (41 U.S.C.
2313).
__ (10) [Reserved].
__ (11)(i) 52.219-3, Notice of HUBZone Set-Aside or Sole-Source Award (Nov 2011) (15 U.S.C. 657a).
__ (ii) Alternate I (Nov 2011) of 52.219-3.
__ (12)(i) 52.219-4, Notice of Price Evaluation Preference for HUBZone Small Business Concerns (OCT 2014) (if the offeror elects to waive the preference, it shall so indicate in its offer) (15 U.S.C. 657a).
__ (ii) Alternate I (JAN 2011) of 52.219-4.
https://www.acquisition.gov/sites/default/files/current/far/html/52_200_206.html#wp1158787 https://www.acquisition.gov/sites/default/files/current/far/html/52_207_211.html#wp1146366 https://www.acquisition.gov/sites/default/files/current/far/html/52_233_240.html#wp1113329 http://uscode.house.gov/uscode-cgi/fastweb.exe?getdoc+uscview+t29t32+1665+30++%2831%29%20%20AND%20%28%2831%29%20ADJ%20USC%29%3ACITE%20%20%20%20%20%20%20%20%20 https://www.acquisition.gov/sites/default/files/current/far/html/52_233_240.html#wp1113344 http://uscode.house.gov/ http://uscode.house.gov/ https://www.acquisition.gov/sites/default/files/current/far/html/52_200_206.html#wp1137622 http://uscode.house.gov/ http://uscode.house.gov/ http://uscode.house.gov/ https://www.acquisition.gov/sites/default/files/current/far/html/52_200_206.html#wp1141983 http://uscode.house.gov/ https://www.acquisition.gov/sites/default/files/current/far/html/52_200_206.html#wp1144881 https://www.acquisition.gov/sites/default/files/current/far/html/52_200_206.html#wp1141649 http://uscode.house.gov/ https://www.acquisition.gov/sites/default/files/current/far/html/52_200_206.html#wp1151163 https://www.acquisition.gov/sites/default/files/current/far/html/52_200_206.html#wp1151299 https://www.acquisition.gov/sites/default/files/current/far/html/52_207_211.html#wp1140926 https://www.acquisition.gov/sites/default/files/current/far/html/52_207_211.html#wp1145644 https://www.acquisition.gov/sites/default/files/current/far/html/52_217_221.html#wp1135955 http://uscode.house.gov/uscode-cgi/fastweb.exe?getdoc+uscview+t13t16+492+90++%2815%29%20%20AND%20%28%2815%29%20ADJ%20USC%29%3ACITE%20%20%20%20%20%20%20%20%20 https://www.acquisition.gov/sites/default/files/current/far/html/52_217_221.html#wp1135955 https://www.acquisition.gov/sites/default/files/current/far/html/52_217_221.html#wp1135970 http://uscode.house.gov/uscode-cgi/fastweb.exe?getdoc+uscview+t13t16+492+90++%2815%29%20%20AND%20%28%2815%29%20ADJ%20USC%29%3ACITE%20%20%20%20%20%20%20%20%20 https://www.acquisition.gov/sites/default/files/current/far/html/52_217_221.html#wp1135970
__ (13) [Reserved]
_X_ (14)(i) 52.219-6, Notice of Total Small Business Set-Aside (Nov 2011) (15 U.S.C. 644).
__ (ii) Alternate I (Nov 2011).
__ (iii) Alternate II (Nov 2011).
__ (15)(i) 52.219-7, Notice of Partial Small Business Set-Aside (June 2003) (15 U.S.C. 644).
__ (ii) Alternate I (Oct 1995) of 52.219-7.
__ (iii) Alternate II (Mar 2004) of 52.219-7.
_X_ (16) 52.219-8, Utilization of Small Business Concerns (Nov 2016) (15 U.S.C. 637(d)(2) and (3)).
__ (17)(i) 52.219-9, Small Business Subcontracting Plan (Jan 2017) (15 U.S.C. 637(d)(4)).
__ (ii) Alternate I (Nov 2016) of 52.219-9.
__ (iii) Alternate II (Nov 2016) of 52.219-9.
__ (iv) Alternate III (Nov 2016) of 52.219-9.
__ (v) Alternate IV (Nov 2016) of 52.219-9.
_X_ (18) 52.219-13, Notice of Set-Aside of Orders (Nov 2011) (15 U.S.C. 644(r)).
__ (19) 52.219-14, Limitations on Subcontracting (Jan 2017) (15 U.S.C. 637(a)(14)).
__ (20) 52.219-16, Liquidated Damages—Subcon-tracting Plan (Jan 1999) (15 U.S.C. 637(d)(4)(F)(i)).
__ (21) 52.219-27, Notice of Service-Disabled Veteran-Owned Small Business Set-Aside (Nov 2011) (15 U.S.C.
657 f).
_X_ (22) 52.219-28, Post Award Small Business Program Rerepresentation (Jul 2013) (15 U.S.C. 632(a)(2)).
__ (23) 52.219-29, Notice of Set-Aside for, or Sole Source Award to, Economically Disadvantaged Women-Owned
Small Business Concerns (Dec 2015) (15 U.S.C. 637(m)).
__ (24) 52.219-30, Notice of Set-Aside for, or Sole Source Award to, Women-Owned Small Business Concerns
Eligible Under the Women-Owned Small Business Program (Dec 2015) (15 U.S.C. 637(m)).
_X_ (25) 52.222-3, Convict Labor (June 2003) (E.O. 11755).
_X_ (26) 52.222-19, Child Labor—Cooperation with Authorities and Remedies (Oct 2016) (E.O. 13126).
__X (27) 52.222-21, Prohibition of Segregated Facilities (Apr 2015).
_X_ (28) 52.222-26, Equal Opportunity (Sept 2016) (E.O. 11246).
__ (29) 52.222-35, Equal Opportunity for Veterans (Oct 2015)(38 U.S.C. 4212).
_X_ (30) 52.222-36, Equal Opportunity for Workers with Disabilities (Jul 2014) (29 U.S.C. 793).
__ (31) 52.222-37, Employment Reports on Veterans (FEB 2016) (38 U.S.C. 4212).
__ (32) 52.222-40, Notification of Employee Rights Under the National Labor Relations Act (Dec 2010) (E.O.
13496).
_X_ (33)(i) 52.222-50, Combating Trafficking in Persons (Mar 2015) (22 U.S.C. chapter 78 and E.O. 13627).
__ (ii) Alternate I (Mar 2015) of 52.222-50 (22 U.S.C. chapter 78 and E.O. 13627).
__ (34) 52.222-54, Employment Eligibility Verification (OCT 2015). (Executive Order 12989). (Not applicable to the acquisition of commercially available off-the-shelf items or certain other types of commercial items as prescribed in
22.1803.)
__ (35) 52.222-59, Compliance with Labor Laws (Executive Order 13673) (OCT 2016). (Applies at $50 million for solicitations and resultant contracts issued from October 25, 2016 through April 24, 2017; applies at $500,000 for solicitations and resultant contracts issued after April 24, 2017).
Note to paragraph (b)(35): By a court order issued on October 24, 2016, 52.222-59 is enjoined indefinitely as of the date of the order. The enjoined paragraph will become effective immediately if the court terminates the injunction. At that time, GSA, DoD and NASA will publish a document in the Federal Register advising the public of the termination of the injunction.
__ (36) 52.222-60, Paycheck Transparency (Executive Order 13673) (OCT 2016).
https://www.acquisition.gov/sites/default/files/current/far/html/52_217_221.html#wp1136004 http://uscode.house.gov/uscode-cgi/fastweb.exe?getdoc+uscview+t13t16+492+90++%2815%29%20%20AND%20%28%2815%29%20ADJ%20USC%29%3ACITE%20%20%20%20%20%20%20%20%20 https://www.acquisition.gov/sites/default/files/current/far/html/52_217_221.html#wp1136017 http://uscode.house.gov/uscode-cgi/fastweb.exe?getdoc+uscview+t13t16+492+90++%2815%29%20%20AND%20%28%2815%29%20ADJ%20USC%29%3ACITE%20%20%20%20%20%20%20%20%20 https://www.acquisition.gov/sites/default/files/current/far/html/52_217_221.html#wp1136017 https://www.acquisition.gov/sites/default/files/current/far/html/52_217_221.html#wp1136017 https://www.acquisition.gov/sites/default/files/current/far/html/52_217_221.html#wp1136032 http://uscode.house.gov/uscode-cgi/fastweb.exe?getdoc+uscview+t13t16+492+90++%2815%29%20%20AND%20%28%2815%29%20ADJ%20USC%29%3ACITE%20%20%20%20%20%20%20%20%20 https://www.acquisition.gov/sites/default/files/current/far/html/52_217_221.html#wp1136058 http://uscode.house.gov/uscode-cgi/fastweb.exe?getdoc+uscview+t13t16+492+90++%2815%29%20%20AND%20%28%2815%29%20ADJ%20USC%29%3ACITE%20%20%20%20%20%20%20%20%20 https://www.acquisition.gov/sites/default/files/current/far/html/52_217_221.html#wp1136058…
This is the start of the file's text. The full file is on GovTribe.