AMENDMENT OF SOLICITATION 1. CONTRACT ID CODE Page of Pages

1 4

2. Amendment/Modification No. 3. Effective Date 4. Requisition/Purchase Req. No. 5. Project No.

TWO 03/02/2018

6. Issued By: Code 7. Administered By: Code

USDA Forest Service

Mt. Hood National Forest

16400 Champion Way

Sandy, Oregon 97055

See Block 6

8. Name and Address of Contractor

(X) 9A. Amendment of Solicitation No.

AG-046W-18-R-0001

9B. Dated (See Item 11)

02/09/2018

10A. Modification of Contract No.

10B. Date Issued (See Item 13)

Code Facility Code

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods: (a) By completing Items 8 and 15, and returning ___1___ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE

RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. Accounting and Appropriation Data (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS, IT MODIFIES THE

CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. This Change Order is issued pursuant to: (specify authority) The changes set forth in item 14 are made in the Contract

Order No. in item 10A.

B. The above numbered contract/order is modified to reflect the administrative changes set forth in Item 14. pursuant to the authority of FAR 43.103(b).

C. This supplemental agreement is entered into pursuant to authority of:

D. Other (specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return _1__ copies to the issuing office.

14. Description of Amendment/Modification (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Solicitation 12046W18R0001 (Underground water line system at Zigzag RD) is hereby amended as follows:

The drawings show the existing pipe under the highway to be transite. This is not the case, when the highway was widened, the pipe was changed to 4” C-900. Since it is C-900, this pipe can be re-used if after a video inspection it is confirmed that it is still in good condition. Please take this information into account when submiting your bids.

Additional vendor questions:

1. Is there a soils report for this project? No, the soil is made up of sand and cobbles

2. If the ground has too much cobbles, boring may not be possible? Engineers who designed this talked to the telephone and other companies who have been boring in the area along Hwy 26 and there is a layer under the cobbles that is clear for boring. This should not be an issue.

A signed copy of the amendment is required with your quote package.

By signature in Block 15B Contractor releases the Government from all claims relating to this modification. This settlement is complete accord and satisfaction. Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. Name and Title of Signer 16A. Name and Title of Contracting Officer

Leslie Solberg 15B. Contractor/Offeror Date Signed 16B. United States of America Date Signed

(Authorized Signature) (Signature of Contracting Officer)

NSN 7540-01-152-8070

PREVIOUS EDITION UNUSABLE

30-105 STANDARD FORM 30 (REV.10-83)

PRESCRIBED BY GSA

FAR (48CFR) 53.243

File details come from the government source that posted it.