Amend1.doc

DOC document 82 KB Posted

Attached to
Nez Perce-Clearwater NFs - Joe Springs Pit Crushing and Aggregate Extraction
Solicitation number
12034320Q0001
Issued by

About this file

Amendment 1, SF-30 (3 pages)

View the file

Other files

File Type Posted
Amendment1_SolicitationAttachment5_FlowerPhotos.docx DOCX document
Amendment1_SolicitationAttachment6_TSRoads.pdf PDF
MandatorySiteVisitNotes.docx DOCX document
Attachment2_FS_SupplementalSpecifications.doc DOC document
Attachment3_Drawings.pdf PDF
RFQ_withAttachments1and4.doc DOC document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

1. CONTRACT ID CODE
PAGE OF PAGES
1
3
2. AMENDMENT/MODIFICATION NO.
3. EFFECTIVE DATE
4. REQUISITION/PURCHASE REQ. NO.
5. PROJECT NO. (If applicable)
1
10/21/2019
982515
6. ISSUED BY
CODE
7. ADMINISTERED BY (If other than Item 6)
CODE

USDA - Forest Service Region 1, Acquisition Management Idaho Montana Acquisition Team Grangeville Office, 104 Airport Road Grangeville, ID 83530 USDA - Forest Service Region 1, Acquisition Management Idaho Montana Acquisition Team Grangeville Office, 104 Airport Road Grangeville, ID 83530

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State, and ZIP Code)
(X)
9A. AMENDMENT OF SOLICITATION NO.
X
12034320Q0001

9B. DATED (SEE ITEM 11)

10/03/2019

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

CODE
FACILITY CODE

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in item 14. The hour and date specified for receipt of Offers is extended, FORMCHECKBOX is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: 52.211.18 THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN

THE CONTRACT ORDER NO. IN ITEM 1 and 2.

FORMCHECKBOX

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

FORMCHECKBOX

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor FORMCHECKBOX is not, FORMCHECKBOX is required to sign this document and return 1 copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.

JOE SPRING PIT CRUSHING & AGGREGATE EXTRACTION

Nez Perce-Clearwater National Forests; Salmon River Ranger District

1. Amend Attachment 2, FSSS 105 Control of Materials, Subpart 105.02(a) - Government Provided Sources as follows. Add the following paragraph: “Import of clay or bentonite into the source to meet the plasticity requirement shall not be required without formal contract modification. The plasticity requirement shall be waived if necessary fines are not found on-site. A smaller class of rip rap may be substituted for some of the currently required Class 3 if standard crushing practices result in the manufacture of smaller material.” Continue Amendment on pages 2-3.

Except as provided herein, all terms and conditions of the documents referenced in item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

KAREN RUKLIC

15B. CONTRACTOR/OFFEROR
15C. DATE SIGNED
16B. UNITED STATES OF AMERICA
16C. DATE SIGNED

(Signature of person authorized to sign)

(Signature of Contracting Officer)

NSN 7540-01-152-8070

Previous edition unusable

30-105
STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA

FAR (48 CFR) 53.243

SOLICITATION: 12034320Q0001

JOE SPRINGS PIT CRUSHING & AGGREGATE EXTRACTION

Amendment 1, Page 2 of 3 Dated 10/21/2019

2. Amend paragraph 3 under the Statement of Work section on page 4 of the solicitation. Strike the final completion deadline of August 31, 2020 and replace it with September 30, 2020. Further, amend FAR 52.211-10 Commencement, Prosecution, and Completion of Work (APR 1984) Alt I, paragraph 1, page 14 of the solicitation. Strike the final completion deadline of August 31, 2020 and replace it with September 30, 2020.

Given the site development required, the government determined that it was reasonable to provide one additional month of contract time.

3. Amend Attachment 2, FSSS 320 – Stockpiled Aggregates, Subpart 320.03 Quarry Site as follows. Strike sentence 3 starting with the words “Place all merchantable logs” with the following language: “A merchantable tree is defined as a tree measuring 7 inches DBH or greater for which an 8 foot or longer piece may be manufactured. Merchantable trees shall be cut from the stump at a height of less than or equal to 1 foot from the ground. To ensure that merchantable trees don’t break, contractors shall not push merchantable trees over with heavy equipment. Merchantable logs need not be limbed, bucked or topped. Place all merchantable logs into decks adjacent to the stockpile(s) or existing roads (see Attachment 5).”

After conferring with contractors and USFS timber professionals, this specification was written to balance the need for aggregate production with timber sale operational needs.

4. Amend Attachment 4 – LOCAL FOREST – SPECIAL CONDITIONS, Clause entitled LANDSCAPE PRESERVATION as follows. Add the following section to the end of the clause.

(c) The Contractor shall conduct operations in a manner to minimize effects to the Broadfruit Mariposa, a USFS sensitive plant species. This species has been recorded within the meadow above Joe Springs Pit (see attachment 6 for photos) and is known to bloom in July. Contractors may position a mobile crushing unit within the pit or in the crushing area shown on Sheet 4 of the plans. As this site is on the margin of the pit and at the edge of the meadow, it may be leveled and developed for placement of a mobile crushing unit so long as it is restored in a like manner to the pit floor; graded to drain, edges of the excavation sloped back, spread with topsoil and seeded. If developing the crushing site at this location requires blasting, that would be acceptable. Contractors are prohibited from locating mobile crushing units within the center of the meadow. To minimize effects to the Broadfruit Mariposa, developing crushing and stockpile sites in locations currently covered by trees is preferred. Contractors shall also minimize ground disturbance within the meadow by selecting haul routes carefully and/or utilizing conveyors.

5. Amend solicitation to add Attachment 5 – Broadfruit Mariposa photos.

6. Amend the solicitation by adding Attachment 6 entitled Joe Springs Pit – Adjacent Timber Sale Roads. This map identifies a second alternate stockpile site that has been approved by the government as well as existing timber sale roads.

SOLICITATION: 12034320Q0001

JOE SPRINGS PIT CRUSHING & AGGREGATE EXTRACTION

Amendment 1, Page 3 of 3 Dated 10/21/2019

7. Amend Attachment 2, FSSS 320 – Stockpiled Aggregates, Subpart 320.04 Aggregate Haul as follows. Add the following sentence: “Restrict aggregate haul to roads 9339 and 420, US Forest Service system roads.”

8. Amend Attachment 2, FSSS 156 - Public Traffic, Subpart 156.05 - Temporary Closures as follows. Strike sentence 1 and replace with the following: “Road segments may be closed temporarily for items such as blasting and equipment mobilization and demobilization.” Further, Amend FAR 52.211-10 Alt I on page 14 of the solicitation as follows. Strike sentence 3 under the first bullet statement and replace with the following. “Requests for US Forest Service road closures must be submitted to the CO at least two weeks prior to the closure; closure of Idaho County Road 493 shall be coordinated with the Deer Creek Highway District.”

9. Amend Addendum FAR 52.212-1 Instructions to Quoters Tailored, Section (b)(9) 2. Work Plan/Proposed Schedule to add the following bullet under the words “Specifically address:”

· General Plan of Operations outlining planned locations for crushing and stockpile locations and haul routes.

Further, strike the last paragraph of this section and replace with the following: “In addition, the government will assess the strengths, weaknesses and risks of the plan as it relates to meeting the project specifications, minimizing erosion and damage to Broadfruit Mariposa plants, managing public traffic and meeting performance deadlines.”

RESPONDENT SHALL ACKNOWLEDGE RECEIPT OF THIS AMENDMENT BY ONE OF THE METHODS OUTLINED IN BLOCK 11 OF THE SF-30 FORM. DEADLINE FOR RECEIPT OF QUOTES REMAINS UNCHANGED.