Nez Perce-Clearwater National Forest 12034319Q0101 Newsome Creek Trail Bridge

REQUEST FOR QUOTATION

PAGE OF PAGES

(THIS IS NOT AN ORDER)
THIS RFQ
x
IS
IS NOT A SMALL BUSINESS SET- ASIDE
1
47
1. REQUEST NO.
2. DATE ISSUED
3. REQUISITION/PURCHASE REQUEST NO.
4. CERT. FOR NAT.DEF.
RATING
12034319Q0101
05/13/2019
955739
UNDER BDSA REG. 2

AND/OR DMS REG. 1

5a. ISSUED BY
6. DELIVER BY (Date)

USDA - Forest Service

Region 1, Acquisition Management

North Fork Office 12730 HWY 12, Orofino, ID 83544 See Contract Time

5b. FOR INFORMATION CALL (NO COLLECT CALLS)
7. DELIVERY

FOB DESTINATION

NAME
TELEPHONE NUMBER
X
OTHER (See Schedule)
AREA CODE
NUMBER
9. DESTINATION
DARREN ZYCHEK
208
476-8224
a. NAME OF CONSIGNEE
8. TO:
Section C - Location & Description
a. NAME
b. COMPANY
b. STREET ADDRESS
c. STREET ADDRESS
c. CITY
d. CITY
e. STATE
f. ZIP CODE
d. STATE
e. ZIP CODE
10. PLEASE FURNISH QUOTATIONS TO THE ISSUING OFFICE IN BLOCK 5a ON OR BEFORE CLOSE OF BUSINESS (Date)
IMPORTANT: This is a request for information, and quotations furnished are not offers. If you are unable to quote, please so indicate on this form and return it to the address in BLOCK 5a. This request does not commit the Government to pay any costs incurred in the preparation of the
05/29/2017 2:30 pm (PDT)
submission of this quotation or to contract for supplies or services. Supplies are of domestic origin unless otherwise indicated by quoter. Any representations and/or certifications attached to this Request for Quotations must be completed by the quoter.

11. SCHEDULE (Include applicable Federal, State and local taxes)

ITEM NO.
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
(a)
(b)
(c)
(d)
(e)
(f)

NEWSOME CREEK TRAIL BRIDGE

Red River Ranger District

Nez Perce-Clearwater National Forest Idaho County, Idaho

PLEASE PLACE YOUR QUOTE IN SECTION B-1 SCHEDULE OF ITEMS

FURNISHING QUOTATION: Complete Standard Form 18, Section B, Section K, Technical Package, and Requirements of Section L as your quote. Return to the address shown in Block 5a. Please place “Solicitation No. 120343119Q0101” on the envelope.

a. 10 CALENDAR DAYS (%)
b. 20 CALENDAR DAYS
c. 30 CALENDAR DAYS
d. CALENDAR DAYS

12. DISCOUNT FOR PROMPT PAYMENT

(%)
(%)
NUMBER
PERCENTAGE
NOTE: Additional provisions and representations
X
are

are not attached.

13. NAME AND ADDRESS OF QUOTER
14. SIGNATURE OF PERSON AUTHORIZED TO
15. DATE OF
a. NAME OF QUOTER
SIGN QUOTATION
QUOTATION

DUNS NO. _____________

b. STREET ADDRESS
16. SIGNER
a. NAME (Type or print)
b. TELEPHONE

c. COUNTY

AREA CODE

d. CITY
e. STATE
f. ZIP CODE
c. TITLE (Type or Print)
NUMBER

NSN 7540-01-152-8084

Previous edition not usable

18-121
STANDARD FORM 18 (Rev. 6-95)

Prescribed by GSA-FAR (48 CFR) 53.215-1(a)

PART I - THE SCHEDULE

SECTION B - SUPPLIES OR SERVICES AND PRICES

Newsome Creek Trail Bridge Red River Ranger District

Nez Perce-Clearwater National Forest

Idaho County, Idaho B- 1 Schedule of Items

Item No.
Description
Method of Measurement
Unit
Quantity
Sub Total
15101
Mobilization
LSQ
Lump Sum
1
$
15713
Soil Erosion and Pollution Control
LSQ
Lump Sum
1
$
20417
Embankment Construction (Gov't Furnished)
CQ
Cubic Yard
80
$
20803
Structural Backfill (Commercial Source)
CQ
Cubic Yard
40
$
25101
Placed Riprap, Class 2 (Commercial Source)
CQ
Cubic Yard
49
$
27250
Geocell Abutment Stabilization, 6-inch Depth
CQ
Square Yard
8
$
30207
Aggregate Surface Course (Commercial Source)
CQ
Cubic Yard
4
$
553A01
Precast Concrete Grade Beam
AQ
Each
2
$
55707
Treated Timber Trail Bridge, Fabricate, Deliver and Install
LSQ
Lump Sum
1
$
62201
Hydraulic Excavator w/Thumb
AQ
Hour
8
$
62403
Furnish and Placing Topsoil (Gov't Furnished)
AQ
Cubic Yard
25
$
63313
Kiosk System
LSQ
Lump Sum
1
$
64808
Cross Vane Modifications and Bank Improvements
LSQ
Lump Sum
1
$
Total:
$

* Designated Method of Measurement:

AQ - Actual Quantities, LSQ - Lump Sum Quantities, CQ - Contract Quantities

Note: See Page 4 of 8 of drawings denoting “in-place quantities” and that the potential quoter is encouraged to verify all quantities prior to submitting quote.

Under Clause 52.236-7, Permits and Responsibilities, Contractors shall be responsible for complying with any Federal, State, and municipal laws, codes and regulations applicable to the performance of the work. Questions regarding assessment of Idaho Use Tax on Government Furnished Property should be directed to the Idaho State Tax Commission at (208) 799-3491.

B- 2 Quote on all items. Only quotes to the nearest cent will be accepted.

B- 3 Payment for Bond Premiums Payment for bond premiums in accordance with FAR Clause 52.232-5, Payments Under Fixed-Price Construction Contracts, shall not be in addition to the contract price. Bonding protection to 100% of the awarded contract total value, with corresponding legal power of attorney shall be due no later than 10 days following receipt of acceptance of award by the Contractor to the issuing office:

USDA North Fork Office

ATTN: Darren M. Zychek

12730 HWY 12

Orofino, ID 83544

B- 4 Written Acceptance Any contract resulting from this solicitation will require written acceptance within 10 days of receipt by the Contractor.

B- 5 Basis of Award

One award will be made. Offer of award will be made to the Quoter whose quote, as determined by the Contracting Officer, provides the best value to the Government, considering but not limited to, such factors as price, past performance, and capability to accomplish this type of work. Technical packages are required for a quote submission. See Section M for evaluation factors and subfactors for this requirement.

PART I - THE SCHEDULE

SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK

C- 1 Project Description and Location

(a) Description of Work: Newsome Creek Trail Bridge-Trail No. 825 – M.P. 0.0 The project consists of the construction of a new 60’ (centerline to centerline) span by 7’ wide glued-laminated timber stringer trail bridge with a timber deck and precast concrete foundations. Ancillary work to repair an upstream in-stream rock grade control structure is also included. The project site is located on Forest Service Trail No. 825, MP 0.0 and the bridge crosses Newsome Creek. Improvements consist of but are not limited to: structure excavation/backfill, geocell abutment stabilization, precast concrete grade beams, supply and installation of treated timber trail bridge, placement of riprap, aggregate surfacing, embankment construction, kiosk system improvements, and in-stream rock grade control/bank improvements.

(b) Project Location:

The project site is located in the Red River Ranger District of the Nez Perce-Clearwater National Forests, approximately 10 miles northwest of Elk City in Idaho County, Idaho (Section 5, Township 29 North, Range 7 East). Refer to the location map on the title sheet of the plans.

(c) Price Range The Government’s estimate for the project is between $25,000 and $100,000.

(d) Pre-Bid Tour None.

(e) Pre-Bid Conference None.

(f) Start Work: Work on the project site shall commence no earlier than June 1, 2019 and proceed in accordance with the contractor’s approved work schedule and run continuously till the end of the project no later than September 15, 2019. All in-stream work must take place between July 1 and August 15, 2019 unless otherwise approved by the Contracting Officer (CO).

(g) Period of Performance (See Part I, Section F, Clause 52.212-3)

(h) Government-Furnished Property (Also see Section I, FAR 52.245-4)

C- 2 Biobased Product Utilization The Contractor must comply with the Agricultural Act of 2014; the Food, Conservation and Energy Act of 2008 (FCEA), 7 U.S.C. 8102; the Farm Security and Rural Investment Act of 2002 (FSRIA), 7 U.S.C. 8102; the Federal Acquisition Regulation; Executive Order (EO) 13514, “Federal Leadership in Environmental, Energy and Economic Performance,” dated October 5, 2009; EO 13423, “Strengthening Federal Environmental, Energy, and Transportation Management,” dated January 24, 2007; and Presidential Memorandum, “Driving Innovation and Creating Jobs in Rural America through Biobased and Sustainable Product Procurement,” dated February 2012, to provide biobased products.

The Contractor shall utilize products and material made from biobased materials to the maximum extent possible without jeopardizing the intended end use or detracting from the overall quality delivered to the end user. All supplies and materials shall be of a type and quality that conform to applicable Federal specifications and standards. All supplies and materials to be used in the performance of work described herein are subject to the approval of the Contracting Officer’s Representative (COR).

The following is an example list of products that may be used in this contract for which biobased products are available. The list is not all inclusive. It is desirable that Contractors be able to supply the greatest number of biobased products listed meeting the health and environmental specifications.

Grease Removers Insulating Foam Concrete and Asphalt Release Fluids

Fluid-filled Transformers Wood and Concrete Sealers Composite Panels

Adhesive and Mastic Removers Carpets Roof Coatings

Hydraulic Fluid Water Tank Coatings

Biobased products that are designated for preferred procurement under USDA’s Biopreferred Program must meet the required minimum biobased content as stated in the USDA Final Rule available at www.biopreferred.gov. The Contractor should provide data for their biobased products such as biobased content and source of biobased material.

In addition to the biobased products designated by the U.S. Department of Agriculture in the Biopreferred Program, the Contractor is encouraged to use other commercially available biobased products.

The Contractor shall submit with the initial proposal a complete list of biobased products, indicating the name of the manufacturer, cost of each material, and the intended use of each of the materials that are to be used in carrying out the requirements of this contract.

Additionally, the winning Contractor on each anniversary date of the contract shall compile a complete list of biobased products, including the information above, purchased to carry out the contract requirements. The Contractor shall list volume to be used and total cost for each individual product. This information will be used for reporting purposes (see Section I, FAR Clause 52.223-2).

Within thirty (30) days of contract award, the Contractor shall submit an Operation Plan. This submittal will be approved by the COR in writing. The Contractor shall not commence work until this submittal is approved by the COR in writing. The Plan must be reviewed and updated annually, and as required by the COR. The Plan must contain and define the following elements:

· The Contractor’s written policy stating its commitment to the use of biobased products, employee health and safety, and sound environmental management practices.

· Detail on how the Contractor intends to keep abreast of the development and increasing availability of designated and non-designated biobased products and how any new or improved products will be incorporated on an ongoing basis into contract performance.

· Proposed biobased construction products which must be selected in accordance with the criteria included above. At a minimum, the Plan must identify products by brand name for each of the product types.

NOTE: A Contractor may propose more than one product within a product category and/or propose a product or products addressing more than one product category.

· The product guides which define standard operating procedures for instructing staff in the proper use, storage, and disposal of biobased products; proper maintenance of equipment; and other procedures/instructions to accomplish work under this contract.

The Contractor shall provide data on the quantity and dollar values of biobased products used in this contract. The data shall be submitted to the COR quarterly.

A demonstration of proper use, an effective training program, and technical assistance are essential to the success of the purchase and use of some biobased products that may function differently than a conventional product.

C- 3 Government-Furnished Property See Section G within solicitation for full description, location map, etc.

C- 4 Standard Specifications - General Specifications "Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects" (FP-03, U.S. Customary Units) are included in this solicitation by reference only. The requirements contained in these Specifications are hereby made a part of this solicitation and any resultant contract.

“Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects” (FP-14) are included in this solicitation by reference only. The requirements contained in these Specifications are hereby made a part of this solicitation and any resultant contract.

Copies are available electronically on the U.S. DEPARMENT OF TRANSPORTATION Federal Highways Administration website at: http://flh.fhwa.dot.gov/resources/specs/fp-14/fp14.pdf.

C- 4 Supplemental Specifications – Special Project Specifications

SUPPLEMENTAL PROJECT SPECIFICATIONS

The Supplemental Project Specifications listed in the Supplemental Specification List are applicable to this contract and are physically included in this section (C).

NOTE THAT THE SPECIFICATION LIST INCLUDES THE MAJOR SPECIFICATIONS APPLICABLE TO THIS PROJECT. OTHER SPECIFICATIONS REFERRED TO WITHIN THESE SPECIFICATIONS (EVEN THOUGH NOT SPECIFICALLY LISTED HEREIN) ARE ALSO FULLY APPLICABLE TO THIS REQUEST FOR PROPOSALS AND ANY RESULTANT CONTRACT.

SUPPLEMENTAL SPECIFICATION LIST

Newsome Creek Trail Bridge

SPEC. No.
SPECIFICATION TITLE
FSSS101
Terms, Format, and Definitions
FSSS102
Bid, Award, and Execution of Contract
FSSS103
Scope of Work
FSSS104
Control of Work
FSSS105
Control of Materials
FSSS106
Acceptance of Work
FSSS107
Legal Relations and Responsibility to the Public
FSSS108
Prosecution and Progress
FSSS109
Measurement & Payment
FSSS152
Construction Survey and Staking
FSSS153
Contractor Quality Control
FSSS155
Schedules for Construction Contracts
FSSS157
Soil Erosion Control
FSSS 201
Clearing and Grubbing
FSSS 204
Excavation and Embankment
FSSS 208
Structural Excavation and Backfill for Selected Major Structures
FSSS 251
Riprap
FSSS 272
Geocell Abutment Stablization
FSSS 553A
Precast Concrete Structures
FSSS 622
Rental Equipment
FSSS 703
Aggregate
FSSS 736
Geocell

PART I - THE SCHEDULE

SECTION E - INSPECTION AND ACCEPTANCE

E- 1 FAR 52.252-2 Clauses Incorporated by Reference (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): Federal Acquisition Regulations - http://www.acquisition.gov/far and the Agriculture Acquisition Regulations – http://www.dm.usda.gov/procurement/policy/agar.html.

FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES

52.246-12 Inspection of Construction (AUG 1996)

PART I - THE SCHEDULE

SECTION F - DELIVERIES OR PERFORMANCE

F- 1 FAR 52.252-2 Clauses Incorporated by Reference (FEB 1998) This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): Federal Acquisition Regulations - http://www.acquisition.gov/far and the Agriculture Acquisition Regulations – http://www.dm.usda.gov/procurement/policy/agar.html.

FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES

52.242-14 Suspension of Work (APR 1984) F- 2 FAR 52.211-10 Commencement, Prosecution, and Completion of Work (APR 1984) The Contractor shall be required to (a) commence work under this contract within 10-calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than _15 September 2019___. The time stated for completion shall include final cleanup of the premises.

F-3 AGAR 452.211-3 Statement of Work/Specifications.

The Contractor shall furnish the necessary personnel, material, equipment, services and facilities (except as otherwise specified), to perform the Statement of Work/Specifications referenced in Section J.

(End of Clause)

F-4 452.211-4 Attachments to Statements of Work/Specifications.

The attachments to the Statement of Work/Specifications listed in Section J are hereby made part of this solicitation and any resultant contract.

(End of Clause)

F- 5 AGAR 452.211-74 Period of Performance (FEB 1988) The period of performance of this contract is from ____Date of Award_______________ through ___15 September 2019_____________.

PART I - THE SCHEDULE

SECTION G - CONTRACT ADMINISTRATION DATA

G-1- GOVERNMENT-FURNISHED PROPERTY

52.245-1 Government Property (JAN 2017) 52.245-9 Use and Charges (APR 2012)

The Government will provide the following item(s) of Government property to the Contractor for use in the performance of this contract. This property shall be used and maintained by the Contractor in accordance with the provisions of the “Government Property” FAR clause contained elsewhere in the contract.

Government-provided sources for this project are identified as follows:

Government-provided mandatory sources.

Pay Item
Description
Material source number or name
20417
Trail Embankment
Source adjacent to Road 1858 approximately 1.4 miles north of project site, as directed by CO.
62403
Topsoil
Source adjacent to access road off Road 1858, as shown in the map below. Road improvements to the access road will be necessary and will include clearing of woody debris and removal of drainage dips. Once topsoil has been removed, site restoration to pre-existing conditions will occur. All topsoil hauling, access road clearing and restoration included in 62403 bid item.

*Note: Page 1 of 8 of drawings “Waste Disposal Site” not to be used at time of award. All project waste must be removed from the project site and disposed of offsite.

G-2 - CONTRACTING OFFICER'S REPRESENTATIVE

The Contracting Officer (CO) will designate a representative, hereinafter referred to as the Contracting Officer's Representative (COR) or, alternatively, as the Engineer, who will provide on-the-ground administration for the Government. The COR will be designated in writing and a copy of the designation will be furnished to the Contractor before or at the prework conference. The Contractor is cautioned to read the COR designation because certain authority under the contract is reserved solely for the Contracting Officer. The term "Contracting Officer" as used throughout the Specifications, shall be interpreted to include the Contracting Officer's designated representative(s) acting within the limits of their delegation of authority.

G-3 - SUBMITTAL/NOTIFICATION TIMELINES

Required Submittal/Notification
Deadline for Receipt by the Government
Applicable Specification
Hazardous Spill Plan
Prior to work
107 –Legal Relations and Responsibility to the Public
Equipment Mobilization Notification
24 hours prior to moving equipment onto Nez Perce N.F
H-4, 151 - Mobilization
Preliminary Construction Schedule
7-days prior to preconstruction conference.
151- Mobilization
Traffic Control Plan
14-days prior to preconstruction conference.
156 – Public Traffic
Road Closure Notice
3-weeks prior to construction
156 – Public Traffic
Erosion Control Plan
7-days prior to preconstruction conference.
157 – Soil Erosion Control
Excavator Size Approval
Prior to use
622- Rental Equipment
Straw Bales Certification
Prior to use
H-4
Backfill Proctor and Density Testing
Prior to and during backfill.
FP-03 208.11, FSSS 208

*See FSSS 153 for the entire submittal log.

G-4 Invoice Processing Platform (IPP)

The Forest Service is utilizing the Invoice Processing Platform (IPP) for the electronic submission and tracking of contracts/purchase orders, invoices, and payment information. IPP is a secure Government-wide, Web-based invoice processing service. Visit http://www.ipp.gov to learn more.

Upon award of a contract, Contractors will be enrolled automatically. Contractor will subsequently receive electronic notification from IPP of enrollment. IPP password will be delivered electronically to allow first login to IPP. Contractors shall submit all invoices electronically via IPP. Paper copies of invoices will no longer be accepted.

PART I - THE SCHEDULE

SECTION H - SPECIAL CONTRACT REQUIREMENTS

H- 1 FAR 52.252-2 Clauses Incorporated by Reference (FEB 1998) This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): Federal Acquisition Regulations - http://www.acquisition.gov/far and the Agriculture Acquisition Regulations – http://www.dm.usda.gov/procurement/policy/agar.html.

AGRICULTURE ACQUISITION REGULATION (48 CFR CHAPTER 4) CLAUSES

H- 2 FAR 52.236-4 Physical Data (APR 1984) Data and information furnished or referred to below is for the contractor's information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the contractor.

(a) The indications of physical conditions on the drawings and in the specifications are the result of site investigations by the U.S. Department of Agriculture, Forest Service. Features shown on the plan & profile sheets were identified by visual observation during the preliminary location and survey and during a "plans in hand" review.

(b) Weather Conditions - The project is subject to seasonal limitations from November thru June. Wet weather commonly limits construction operations in October and June.

H - 3 AGAR 452.237-74 Key Personnel (FEB 1988)

(a) The Contractor shall assign to this contract the following key personnel: __Site Superintendent & or Senior Equipment Operator________________

(b) During the first ninety (90) days of performance, the Contractor shall make no substitutions of key personnel unless the substitution is necessitated by illness, death, or termination of employment. The Contractor shall notify the Contracting Officer within 15 calendar days after the occurrence of any of these events and provide the information required by paragraph (c) below. After the initial 90-day period, the Contractor shall submit the information required by paragraph (c) to the Contracting Officer at least 15 days prior to making any permanent substitutions.

(c) The Contractor shall provide a detailed explanation of the circumstances necessitating the proposed substitutions, complete resumes for the proposed substitutes, and any additional information requested by the Contracting Officer. Proposed substitutes should have comparable qualifications to those of the persons being replaced. The Contracting Officer will notify the Contractor within 15 calendar days after receipt of all required information of the decision on substitutions. The contract will be modified to reflect any approved changes of key personnel.

H- 5 AGAR 452.236-77 Emergency Response (NOV 1996)

(a) Contractor’s Responsibility for Fire Fighting.

(1) The Contractor, under the provisions of FAR clause 52.236-9, Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements, shall immediately extinguish all fires on the work site other than those fires in use as a part of the work.

(2) The Contractor may be held liable for all damages and for all costs incurred by the Government for labor, subsistence, equipment, supplies, and transportation deemed necessary to control or suppress a fire set or caused by the Contractor or the Contractor’s agents or employees.

(b) Contractor’s Responsibility for Notification in Case of Fire. The Contractor shall immediately notify the Government of any fires sighted on or in the vicinity of the work site.

(c) Contractor’s Responsibility for Responding to Emergencies. When directed by the Contracting Officer, the Contractor shall allow the Government to temporarily use employees and equipment from the work site for emergency work (anticipated to be restricted to fire fighting). An equitable adjustment for the temporary use of employees and equipment will be made under the Changes Clause, FAR 52.243-4.

H- 5 Fire Control

(a) Contractor's Responsibility for Contractor-Caused Fires. The Contractor, whether or not directed by the Forest Service, shall immediately extinguish, without expense to the Government, all fires on or in the vicinity of the project which are caused by Contractor's employees, whether set directly or indirectly as a result of Contractor operations. The Contractor may be held liable for all damages and costs of additional labor, subsistence, equipment, supplies, and transportation resulting from fires set or caused by the Contractor's employees or resulting from contract operations.

(b) Other Fires. For the purpose of fighting forest fires on or in the vicinity of the project which are not caused by the Contractor or the Contractor’s employees, the Contractor when requested by the Contracting Officer shall place the employees and equipment temporarily at the disposal of the Forest Service. Payment for such services will be made by the Government at not less than the current rate for fire-fighting services established by the Forest Service in the area concerned.

Any employees and equipment furnished will be relieved from fire fighting as soon as the Forest Service finds that it is practicable to employ other labor and equipment adequate for the protection of the area.

An equitable adjustment in contract time may be made for this period.

(c) Fire Protection Requirements - Fire Plan. At all times during closed fire season period, as specified by State law, the Contractor shall comply with each of the following provisions to the extent applicable to the Contractor’s operation under the contract.

(1) Fire Tools. The Contractor will provide for each employee in the contract area at least one approved handtool of a type appropriate in the contract area, such as shovel, pulaski, or ax. Tools required and furnished under (2) and (4) below, shall count toward fulfillment of the above requirement. Where additional tools, beyond those required under (2) and (4) below, are to be provided, the Contractor shall seal such tools in one or more boxes painted red and marked "Tools for Fire Only." All tools required herein shall be kept sharp and in good serviceable condition and maintained at locations to be designated by the Forest Service.

(2) Fire Extinguishers and Tools on Mobile or Stationary Equipment. Each unit of powered equipment used in connection with this contract, including automobiles, trucks, tractors, etc., shall be equipped with serviceable tools and fire extinguishers as follows:

One - fire extinguisher, dry chemical type of not less than 2-1/2 pound capacity with 4 BC or higher rating.

One - shovel, round point #0 lady or equal.

One - ax, 2 pounds or over, 26-inch minimum length, or one pulaski.

One - water container (at least 1-gallon capacity), not required with stationary equipment.

(3) Spark Arresters. Each internal combustion engine shall be provided with a spark arrester or spark arresting device approved by the Forest Service. Exceptions where the Forest Service may approve mufflers, or other equipment in lieu of spark arresters qualified and rated under Forest Service Standard 5100-1a are: (a) small multiposition engines, such as chain saws, shall meet Society of Automotive Engineers J335b standards; (b) passenger-carrying vehicles and light trucks may have baffle-type mufflers with tail pipe; (c) heavy-duty trucks may have a vertical stack exhaust system and muffler, provided the exhaust stack extends above the cab of the vehicle. An exhaust-driven turbocharger is considered to be a satisfactory spark arrester. Internal combustion engine exhaust systems, arresters, and other devices must be properly installed and maintained.

(4) Powersaws. For each powersaw used in connection with this contract, the following will be provided:

One - shovel, round point #0 lady or equal. Shovel must be immediately available for use.

One - Fire extinguisher, containing not less than 8 ounces of extinguisher fluid, or a dry chemical powder-type of not less than 1-pound capacity. The extinguisher must be immediately accessible to the saw operator at all times.

Any fueling or refueling of a powersaw shall only be done in an area which has first been cleared or is free of all material capable of carrying fire; powersaw shall be moved at least 10 feet from place of fueling before starting.

(5) Blasting. Fuse or prima cord shall not be used unless authorized in writing by the COR with special precautions stated.

(6) Smoking. Smoking shall not be permitted within the contract area except on surfaced or dirt roads, at landings, within closed vehicles, in camps, or at other posted places, and shall never be allowed while working or traveling on foot.

(7) Storage of Petroleum and Other Highly Flammable Products. Gasoline, oil, grease, or other highly flammable material will be stored either in a separate building used exclusively for such storage, or at a site where all combustible debris and vegetation is cleared away within a radius of 25 feet. Fire extinguishers and/or sand barrels may be required at such locations specified by the Forest Service when unusually hazardous conditions exist.

(8) Debris Burning and Warming Fires. Burning permits will be required for all debris burning fires. Lunch and warming fires may be allowed in fireproofed areas during periods of low fire danger if and as specified in the fire plan. Such fires must not be left burning unattended.

(9) Precautions for Stoves. Stovepipes on all temporary buildings, trailers, and tents using wood burning stoves, will be equipped with roof jacks and serviceable spark arresters of mesh with openings no larger than 5/8 inch.

All stovepipes, inside and out, will not be closer than 2 feet from any wood or other flammable material or 1 foot if the combustible material is protected by a metal or asbestos shield.

(10) Welding. Welding or use of cutting torches will be permitted only in areas that have been cleared or are free of all material capable of carrying fire. Flammable debris and vegetation must be removed from within a minimum of 10 feet radius of all welding and cutting torch operations. A shovel and a 5-gallon standard backpack water container (filled) with handpump attached, shall be immediately available for use in the event of a fire start.

(11) Fire Plan. Prior to initiating work on the contract area, during the closed fire season period, a fire prevention and suppression plan will usually be prepared. The Contractor and the Forest Service will jointly prepare this plan. Such plan shall include a detailed list of men and equipment at the Contractor's disposal for implementing the plan. The fire plan shall also specify additional measures and/or special requirements, such as Hoot Owl restrictions, necessary during periods of critical fire weather conditions.

When Hoot Owl restrictions are invoked, the Forest Service may curtail or shut down all or portions of a Contractor's operations. The following requirements may be imposed:

(i) All high fire risk operations could be terminated at 1300 local time.

(ii) All burning could be stopped, including debris burning fires.

(iii) Patrolman may be required for a period of 2 hours after high fire risk operations and 1 hour after end of work shift. The Contractor shall provide the patrolman unless the contract is for equipment rental, in which case the Government will provide the patrolman.

(12) Pump and Trailer. The Contractor shall provide at a location satisfactory to the Contracting Officer, a serviceable truck or trailer, equipped with a fire fighting tanker unit to be kept ready for instant use for suppressing forest fires. The unit shall consist of a tank of not less than 100-gallon capacity upon which shall be mounted a live hose reel or live hose basket with 250 feet of at least ¾-inch I.D. heavy-duty rubber hose; a portable or power takeoff pump with discharge capacity of at least 10 gallons per minute at 150 P.S.I. pressure. Gear type pumps shall be provided with a bypass or pressure relief valve so that the hose nozzle may be shut while the pump is operating. Each tanker unit shall have a hose nozzle of the shut-off type, adjustable for straight stream, spray or fog, at least 12 feet of 1-inch suction hose with an intake screen, and additional 250 feet of 3/4 –inch heavy-duty rubber hose or 1-inch cotton jacket rubber-lined or linen hose to be carried on the unit for use as needed. Tools, adapters, accessories and fuel necessary to operate the pump and truck or trailer shall be provided. If a trailer is used, a serviceable vehicle with proper trailer tow hitch shall be located at a point satisfactory to the Contracting Officer. Where water is available, a supply sufficient for rapidly filling the water tank shall be provided at one or more accessible points along or adjacent to the main truck roads.

(13) Burning. Before starting any open burning, the Contractor shall comply with the following:

(i) Submit a burning plan, subject to approval by the Contracting Officer, designed to minimize the impact on air quality and to lessen any fire damage.

(ii) Obtain a burning permit from the District Ranger.

(iii) Use weather forecasts as far as possible in scheduling burning for more favorable dispersal of smoke.

(iv) Fuel shall be reasonably free of dirt and piled to facilitate rapid and complete combustion. Piles shall be tended during burning operations to maintain combustion and to eliminate unnecessary smudges. Piles shall be patrolled during off-work hours to avoid wildfires.

(v) Unless fire season controls dictate otherwise, burning shall be scheduled, as far as practicable, for the most favorable conditions during the burning period.

(vi) Under certain atmospheric conditions, smoke accumulations may become excessive and in these cases, the Regional Forester may, at his/her discretion, prohibit all open burning for definite periods within specific areas of the National Forest.

H- 6 Loss, Damage, or Destruction

(a) Equipment furnished with operator. The Government shall not be liable for loss, damage, or destruction of equipment furnished under this contract except for such loss, damage, or destruction resulting from the negligent or wrongful act(s) of Government employee(s) while acting within the scope of their employment.

All claims arising under this clause will be submitted to the Contracting Officer.

H- 7 Incidental Payment Items

The intent of the contract is to provide for the complete construction of the project described in the contract. Unless otherwise provided, the Contractor shall furnish all labor, materials, equipment, tools, transportation, and supplies and perform all work required to complete the project in accordance with drawings, specifications, and provisions of the contract. Payment for contract work will be made only for and under those pay items included in the Schedule of Items. All other work and materials will be considered as incidental to and included in the payment for items shown.

H- 8 Conformity With Drawings and Specifications

Unless working tolerances are specified, all work performed and materials furnished shall be in reasonably close conformity with lines, grades, cross sections, dimensions, and material requirements shown on the drawings, indicated in the specifications, or designated on the ground. "Reasonably close conformity" is compliance with reasonable and customary manufacturing and construction tolerances.

H- 9 Local Material Sources

(a) Designated Sources--Sources of local materials will be designated on the drawings or Section G. The Government assumes responsibility for the quality and quantity of material in the source. The Contractor shall determine the equipment and work required to produce the specified product.

The Contractor shall utilize all suitable material in the source. The designation of source will include the rights of the Contractor to use certain area(s) for plant site, stockpiles, and haul roads. Any Contractor royalty payment requirements will be stated below.

When materials are subject to weight measurement, the weight/volume relationship used for determination of designed quantities will be shown on the Drawings.

Should the designated source, due to causes beyond the control of the Contractor, contain insufficient suitable material, the Government will provide another source with an equitable adjustment in accordance with the Differing Site Conditions and Changes clauses.

(b) Contractor-Furnished Sources--When the material sources are not designated as provided above or the Contractor elects not to use designated sources, the Contractor shall be responsible for providing the specified product with no adjustment in contract price, unless weight/volume relationship differences between designated source material and Contractor-furnished source material result in financial disadvantage to the Government. Quality testing shall be the responsibility of the Contractor. Test results shall be furnished to the Contracting Officer.

H-10 Barricades, Warning Signs, and Other Devices The Contractor shall provide, erect, and maintain all necessary barricades, suitable and sufficient lights, danger signals, signs, and other traffic control devices, and shall take all necessary precautions for the protection of the work and safety of the public. Roads closed to traffic shall be protected by effective barricades, and obstructions shall be illuminated during the hours of darkness. Suitable warning signs shall be provided to properly control and direct traffic.

The Contractor shall erect warning signs in advance to any place on the project where operations may interfere with the use of the road or trail by traffic and at all intermediate points where the new work crosses or coincides with an existing road or trail. All road barricades, warning signs, lights, temporary signals, flagmen and pilot car operators and equipment, and other protective devices, except for special devices, shall conform with Part VI of the Manual on Uniform Traffic Control Devices for Streets and Highways, published by the Federal Highway Administration and applicable safety codes.

Necessary warning signs and guards shall be posted during blasting operations to safeguard the public.

H-12 Weed-Free Equipment In order to prevent the potential spread of noxious weeds into the project area, the Contractor shall be required to furnish the Contracting Officer with proof of weed-free equipment.

The following is considered proof of weed-free equipment:

The Contractor will be required to clean all construction equipment (equipment that operates off existing roads) prior to entry on the project area. This cleaning shall remove all dirt and plant parts and material that may carry noxious weed seeds into the project area. Only construction equipment inspected by the Contracting Officer will be allowed to operate within the project area. All subsequent move-ins of construction equipment shall be treated the same as the initial move-in.

Prior to initial move-in of all construction equipment, and all subsequent move-ins, the Contractor shall make equipment available for inspection at an agreed location.

H-13 Landscape Preservation

(a) The Contractor shall confine operations to within the clearing limits or other areas designated in contract documents, and prevent the depositing of rocks, excavated materials, stumps, or other debris outside of these limits. Material, which falls outside of these limits, shall be retrieved, disposed of, or incorporated in the work as directed by the Contracting Officer.

(b) Operation shall be scheduled and conducted to minimize erosion of soils and to prevent silting and muddying of streams, rivers, irrigation systems, and impoundments (lakes, reservoirs, etc.).

Pollutants such as fuels, lubricants, bitumens, raw sewage, and other harmful materials shall not be discharged into or near rivers, streams, and impoundments or into natural or manmade channels leading thereto. Wash water or waste water from concrete or aggregate operations shall not be allowed to enter live streams prior to treatment by filtration, settling, or other means sufficient to reduce the sediment content to not more than that of the stream into which it is discharged.

Mechanized equipment shall not be operated in live streams without written approval by the Contracting Officer.

H-14 Idaho Workers’ Compensation Law

(a) Prior to award of any contract subject to Idaho Workers' Compensation Laws, the Contractor must provide a completed State of Idaho Certificate of Verification of Workers’ Compensation Insurance form to the Government. This form will be submitted to the Idaho Industrial Commission by the Government in order to assure that the Contractor in line for award has the required worker’s compensation coverage or is exempt from the requirement for coverage. Contact: suretyrequest@iic.idaho.gov for the form.

(b) A copy of the State of Idaho Certificate of Verification of Workers' Compensation Insurance form has been provided for use in Section J and shall be completed and submitted as part of the offer.

(c) This certificate of verification shall be fully executed by the Contractor and signed by the Industrial Commission Compliance Officer prior to award of the contract.

PART II - CONTRACT CLAUSES

SECTION I - CONTRACT CLAUSES

I- 1 FAR 52.252-2 Clauses Incorporated by Reference (FEB 1998) This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): Federal Acquisition Regulations - http://www.acquisition.gov/far and the Agriculture Acquisition Regulations – http://www.dm.usda.gov/procurement/policy/agar.html.

FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES

52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements (JAN 2017)

52.204-7 System for Award Management. (OCT 2016) 52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards (OCT 2016)

52.204-13 System for Award Management Maintenance (OCT 2016)

52.204-18 Commercial and Government Entity Code Maintenance (JUL 2016) 52.209-6 Protecting the Government's Interest When Subcontracting With Contractors Debarred, Suspended, or Proposed for Debarment. (OCT 2015) 52.209-10 Prohibition on Contracting with Inverted Domestic Corporations (NOV 2015) 52.211-18 Variation in Estimated Quantity. (APR 1984)

52.219-27 Notice of Service-Disabled Veteran-Owned Small Business Set-Aside (NOV 2011)

52.222-3 Convict Labor. (JUN 2003)

52.222-6 Construction Wage Rate Requirements. (MAY 2014)

52.222-7 Withholding of Funds. (MAY 2014)

52.222-8 Payrolls and Basic Records. (MAY 2014)

52.222-9 Apprentices and Trainees. (JUL 2005)

52.222-10 Compliance with Copeland Act Requirements. (FEB 1988)

52.222-11 Subcontracts (Labor Standards). (MAY 2014)

52.222-12 Contract Termination - Debarment. (MAY 2014)

52.222-13 Compliance With Construction Wage Rate Requirements and Related Regulations. (MAY 2014)

52.222-14 Disputes Concerning Labor Standards. (FEB 1988)

52.222-15 Certification of Eligibility. (MAY 2014)

52.222-21 Prohibition of Segregated Facilities. (APR 2015)

52.222-26 Equal Opportunity. (SEP 2016)

52.222-27 Affirmative Action Compliance Requirements for Construction. (APR 2015)

52.222-36 Equal Opportunity for Workers with Disabilities. (JUL 2014) 52.222-40 Notification of Employee Rights Under the National Labor Relations Act (DEC 2010)

52.222-50 Combating Trafficking in Persons (MAR 2015)

52.222-55 Minimum Wages Under Executive Order 13658 (DEC 2015) 52.223-2 Affirmative Procurement of Biobased Products Under Service and Construction Contracts. (SEP 2013)

52.223-5 Pollution Prevention and Right-to-Know Information. (MAY 2011)

52.223-6 Drug-Free Workplace. (MAY 2001)

52.223-18 Encouraging Contractor Policies to Ban Text Messaging (AUG 2011) 52.224-1 Privacy Act Notification (APR 1984) 52.225-13 Restrictions on Certain Foreign Purchases. (JUN 2008)

52.228-2 Additional Bond Security. (OCT 1997)

52.228-11 Pledges of Assets. (JAN 2012)

52.228-12 Prospective Subcontractor Requests for Bonds. (MAY 2014)

52.228-14 Irrevocable Letter of Credit. (NOV 2014)

52.232-5 Payments Under Fixed-Price Construction Contracts. (MAY 2014)

52.232-23 Assignment of Claims. (MAY 2014)

52.232-27 Prompt payment for construction contracts. (JAN 2017)

52.232-33 Payment by Electronic Funds Transfer - System for Award Management. (JUL 2013) 52.232-39 Unenforceability of Unauthorized Obligations (JUN 2013)

52.232-40 Providing Accelerated Payments to Small Business Subcontractors (DEC 2013) 52.233-1 Disputes. (MAY 2014)

52.233-3 Protest after Award. (AUG 1996)

52.233-4 Applicable Law for Breach of Contract Claim. (OCT 2004)

52.236-2 Differing Site Conditions. (APR 1984)

52.236-5 Material and Workmanship. (APR 1984)

52.236-6 Superintendence by the Contractor. (APR 1984)

52.236-7 Permits and Responsibilities. (NOV 1991)

52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements. (APR 1984)

52.236-10 Operations and Storage Areas. (APR 1984)

52.236-11 Use and Possession Prior to Completion. (APR 1984)

52.236-12 Cleaning Up. (APR 1984)

52.236-13 Accident Prevention. (NOV 1991)

52.236-16 Quantity Surveys. (APR 1984)

52.236-17 Layout of Work. (APR 1984)

52.236-21 Specifications and Drawings for Construction. (FEB 1997)

52.236-26 Preconstruction Conference. (FEB 1995)

52.243-5 Changes and Changed Conditions. (APR 1984)

52.244-6 Subcontracts for Commercial Items. (NOV 2017)

52.246-21 Warranty of Construction. (MAR 1994)

52.249-1 Termination for Convenience of the Government (Fixed-Price) (Short Form). (APR 1984)

52.249-10 Default (Fixed-Price Construction). (APR 1984) 52.251-1 Government Supply Sources (APR 2012)

52.253-1 Computer Generated Forms (JAN 1991)

AGRICULTURE ACQUISITION REGULATION (48 CFR CHAPTER 4) CLAUSES

452.224-70 Confidentiality of Information (FEB 1988)

452.232-70 Reimbursement for Bond Premiums - Fixed-Price Construction Contracts. (NOV 1996)

452.236-72 Use of Premises. (NOV 1996)

452.236-73 Archaeological or Historic Sites. (FEB 1988)

452.236-74 Control of Erosion, Sedimentation, and Pollution. (NOV 1996)

452.236-76 Samples and Certificates (FEB 1988) I- 2 FAR 52.219-28 Post-Award Small Business Program Rerepresentation (JUL 2013)

(a) Definitions. As used in this clause—

Long-term contract means a contract of more than five years in duration, including options. However, the term does not include contracts that exceed five years in duration because the period of performance has been extended for a cumulative period not to exceed six months under the clause at 52.217-8, Option to Extend Services, or other appropriate authority.

Small business concern means a concern, including its affiliates, that is independently owned and operated, not dominant in the field of operation in which it is bidding on Government contracts, and qualified as a small business under the criteria in 13 CFR part 121 and the size standard in paragraph (c) of this clause. Such a concern is “not dominant in its field of operation” when it does not exercise a controlling or major influence on a national basis in a kind of business activity in which a number of business concerns are primarily engaged. In determining whether dominance exists, consideration shall be given to all appropriate factors, including volume of business, number of employees, financial resources, competitive status or position, ownership or control of materials, processes, patents, license agreements, facilities, sales territory, and nature of business activity.

(b) If the Contractor represented that it was a small business concern prior to award of this contract, the Contractor shall rerepresent its size status according to paragraph (e) of this clause or, if applicable, paragraph (g) of this clause, upon the occurrence of any of the following:

(1) Within 30 days after execution of a novation agreement or within 30 days after modification of the contract to include this clause, if the novation agreement was executed prior to inclusion of this clause in the contract.

(2) Within 30 days after a merger or acquisition that does not require a novation or within 30 days after modification of the contract to include this clause, if the merger or acquisition occurred prior to inclusion of this clause in the contract.

(3) For long-term contracts—

(i) Within 60 to 120 days prior to the end of the fifth year of the contract; and

(ii) Within 60 to 120 days prior to the date specified in the contract for exercising any option thereafter.

(c) The Contractor shall rerepresent its size status in accordance with the size standard in effect at the time of this rerepresentation that corresponds to the North American Industry Classification System (NAICS) code assigned to this contract. The small business size standard corresponding to this NAICS code can be found at http://www.sba.gov/content/table-small-business-size-standards.

(d) The small business size standard for a Contractor providing a product which it does not manufacture itself, for a contract other than a construction or service contract, is 500 employees.

(e) Except as provided in paragraph (g) of this clause, the Contractor shall make the rerepresentation required by paragraph (b) of this clause by validating or updating all its representations in the Representations and Certifications section of the System for Award Management (SAM) and its other data in SAM, as necessary, to ensure that they reflect the Contractor’s current status.