J3_Work_Items.pdf

PDF 91 KB Posted

Attached to
CUSTER GALLATIN NATIONAL FOREST - Hyalite Lake Loop Trail - Phase III
Solicitation number
12034318Q0328
Issued by

About this file

Attachment J3

View the file

Other files

File Type Posted
StandardSpecs_forTrails.pdf PDF
J6_Project_Map.pdf PDF
J5_Special_Project_Specs.pdf PDF
SF_18.pdf PDF
J4_Project_Drawings.pdf PDF
Q0328.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

H y a l i t e L a k e L o o p T r a i l – P h a s e I I I H y a l i t e C a n y o n T r a i l # 6 2

W o r k I t e m s

Custer Gallatin National Forest Page 1

Beginning Station

Ending Station

Task Drawing Standard Spec

Special Spec

Pay Item Group

Pay Item Unit Quantity

0+00 Begin Work on Trail #62 at Blackmore Trailhead

0+00 1+50 Trail crosses parking lot – no work this contract

1+50 1+80 Recondition existing trailbed 915-1 915 Additive #2

915(01) LF 30

1+50 1+80 Apply aggregate base surfacing 941-1 941 Additive #2

941(02) CY 2

1+80 2+00 Trail crosses Hyalite Canyon Road #62 – no work this contract

2+00 22+50 Recondition existing trailbed 915-1 915 Additive #2

915(01) LF 2050

2+00 48+20 Apply aggregate base surfacing 941-1 941 Additive #2

941(02) CY 278

11+50 11+70 Place 50 CY borrow from Hyalite Canyon Road #62 milepost 3.0 (landslide spoils) as directed across trainer dike none 915 Additive #2

915(04) CY 50

14+50 20+50 Trail across dam. Use caution when working around monitoring well manhole covers.

Government will mark with lathe & flagging.

none none Additive #2

Incidental to other Items

22+50 26+50 Construct 400 LF of new trail. Includes clearing, grubbing and excavation. Excavation from Station 25+50 to 26+50 hauled & placed between 23+50 to 25+50 including over culvert at Station 23+80

911-1 912-1 912-2

Additive #2

911(02) 912(01)

LF

LF

23+50 Install 18” x 20’ Corrugated Metal Culvert with Rock Headwalls

921-1 921 Additive #2

921(01) LF 20

22+50 48+20 Recondition existing trailbed 915-1 915 Additive #2

915(01) LF 2570

26+50 27+50 Construct 100 LF Turnpike, Log Retainers. Final top of turnpike flush with existing ground

913-2 913 Additive #2

913(01)c LF 100

H y a l i t e C a n y o n T r a i l # 6 2

Custer Gallatin National Forest Page 2

Ending Station

Task Drawing Standard Spec

Special Spec

Pay Item Group

Pay Item Unit Quantity

2+00 48+20 Equipment Rental – Hydraulic Excavator with Thumb. Excavator will be used along the project minor unspecified work such as area restoration, site drainage, and other minor directed work.

Additive #2

990(01) HR 8

48+20 80+00 Recondition 3180 LF existing trailbed 915-1 915 Base 915(01) LF 3180

48+20 92+00 Apply aggregate base surfacing 941-1 941 Base 941(02) CY 263

80+00 92+00 Construct 1200 LF of new trail. Includes clearing, grubbing, and excavation.

911-1 912-1 912-2

Base 911(02) 912(01)

LF

LF

80+00 92+00 Obliterate 1200 LF if existing abandoned trail 954-1 954 Base 954(01) LF 1200

48+20 92+00 Equipment Rental – Hydraulic Excavator with Thumb. Excavator will be used along the project minor unspecified work such as area restoration, site drainage, and other minor directed work.

Base 990(01) HR 4

210+50 270+82 Recondition existing trailbed 915-1 915 Base 915(01) LF 6032

210+50 270+82 Apply aggregate base surfacing 941-1 941 Base 941(02) CY 363

210+50 270+82 Equipment Rental – Hydraulic Excavator with Thumb. Excavator will be used along the project minor unspecified work such as area restoration, site drainage, and other minor directed work.

Base 990(01) HR 4

270+82 End Project

W e s t s h o r e T r a i l # 4 3 1

Ending Station

Task Drawing Standard Spec

Special Spec

Pay Item Group

Pay Item Unit Quantity

0+00 Begin Work on Westshore Trail #431

0+00 19+30 Recondition 1930 LF of Trail 915-1 915 Additive #1

915(01)a LF 1930

0+00 19+30 Apply Aggregate Base Surfacing 941-1 941 301

Additive #1

941(02) CY 116

0+00 19+30 Equipment Rental – Hydraulic Excavator with Thumb. Excavator will be used along the project minor unspecified work such as area restoration, site drainage, and other minor directed work.

Additive #1

990(01) HR 4

19+30 End Work on Trail #431

G r o t t o F a l l s T r a i l # 4 3 2

Ending Station

Task Drawing Standard Spec

Special Spec

Pay Item Group

Pay Item Unit Quantity

0+00 Begin Work on Grotto Falls Trail #432

0+00 13+00 Recondition 1300 LF of Trail 915-1 915 Base 915(01)a LF 1300

0+00 13+00 Apply Aggregate Base Surfacing 941-1 941 301

Base 941(02) CY 78

0+00 13+00 Equipment Rental – Hydraulic Excavator with Thumb. Excavator will be used along the project minor unspecified work such as area restoration, site drainage, and other minor directed work.

Base 990(01) HR 4

13+00 End Work on Trail #432

HyaliteLakeLoopIII_TR62_WorkItems
HyaliteLakeLoopIII_TR431_WorkItems
HyaliteLakeLoopIII_TR432_WorkItems
HyaliteLakeLoopIII_TR676_WorkItems