12034318Q0172
1. REQUEST NO.
5a. ISSUED BY
NAME
a. NAME
c. STREET ADDRESS
d. CITY
10. PLEASE FURNISH QUOTATIONS TO
THE ISSUING OFFICE IN BLOCK 5a ON
OR BEFORE CLOSE OF BUSINESS (Date)
2. DATE ISSUED 3. REQUISITION/PURCHASE REQUEST NO. 4. CERT. FOR NAT. DEF.
UNDER BDSA REG. 2
AND/OR DMS REG.1
RATING
6. DELIVERY BY (Date)
7. DELIVERY
9. DESTINATION
a. NAME OF CONSIGNEE
b. STREET ADDRESS
PAGE OF PAGES
5b. FOR INFORMATION CALL: (No collect calls)
TELEPHONE NUMBER
AREA CODE NUMBER
8. TO:
b. COMPANY
e. STATE f. ZIP CODE
c. CITY
d. STATE e. ZIP CODE
IMPORTANT: This is a request for information, and quotations furnished are not offers. If you are unable to quote, please so indicate on this form and return it to the address in Block 5a. This request does not commit the Government to pay any costs incurred in the preparation of the submission of this quotation or to contract for supplies or services. Supplies are of domestic origin unless otherwise indicated by quoter. Any representations and/or certifications attached to this Request for Quotations must be completed by the quoter.
11. SCHEDULE (Include applicable Federal, State and local taxes)
THIS RFQ
REQUEST FOR QUOTATION
(THIS IS NOT AN ORDER)
IS IS NOT A SMALL BUSINESS SET ASIDEX
05/04/2018
1 52
R1 AQM EAST SIDE ACQUISITION TEAM
DANA BANGART - CONTRACT SPECIALIST
3710 FALLON STREET SUITE C
USDA FOREST SERVICE
BOZEMAN MT 59718
09/30/2018
USDA FOREST SERVICE
CUSTER GALLATIN NATIONAL FOREST
10 EAST BABCOCK AVENUE
BOZEMAN
MT 59715
406 624-3442DANA BANGART
05/25/2018 1630 MT
FOB DESTINATION
OTHER
(See Schedule)X
ITEM NO.
(a)
SUPPLIES/SERVICES
(b)
QUANTITY
(c)
UNIT
(d)
UNIT PRICE
(e)
AMOUNT
(f)
Period of Performance: 06/15/2018 to 09/30/2018
001 Storm Castle Road Surfacing Project Product/Service Code: Z2QA Product/Service Description: REPAIR OR ALTERATION
OF RESTORATION OF REAL PROPERTY (PUBLIC OR
PRIVATE)
Delivery: 09/30/2018 There is no formal site visit for this project.
For information regarding the site, please contact Grant Morrison, Civil Engineer, Custer Gallatin National Forest at 406-587-6724 or gmorrison@fs.fed.us.
For information regarding the solicitation, Continued ...
12. DISCOUNT FOR PROMPT PAYMENT
a. 10 CALENDAR DAYS (%) b. 20 CALENDAR DAYS (%) c. 30 CALENDAR DAYS (%) d. CALENDAR DAYS
NUMBER PERCENTAGE
NOTE: Additional provisions and representations
13. NAME AND ADDRESS OF QUOTER
b. STREET ADDRESS
c. COUNTY
d. CITY e. STATE f. ZIP CODE
14. SIGNATURE OF PERSON AUTHORIZED TO
SIGN QUOTATION
16. SIGNER
a. NAME (Type or print)
c. TITLE (Type or print)
a. NAME OF QUOTER
AREA CODE
NUMBER
15. DATE OF QUOTATION
b. TELEPHONE are are not attached
AUTHORIZED FOR LOCAL REPRODUCTION
Previous edition not usable
STANDARD FORM 18 (REV. 6-95)
Prescribed by GSA - FAR (48 CFR) 53.215-1(a)
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
NAME OF OFFEROR OR CONTRACTOR
2 52
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
12034318Q0172 please contact Dana Bangart, Contract Specialist, R1 AQM East Side Acquisition Team at 406-624-3442 or dbangart@fs.fed.us.
Please read Section L regarding what documents are to be returned with the quotation package.
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
12034318Q0172 – RFQ
Storm Castle Road #132 Surfacing Bozeman Ranger District, Custer Gallatin National Forest
B –SERVICES AND PRICES
Gallatin County, Montana
B-1 SCHEDULE OF ITEMS
BASE – Mile 0.04 – 3.74
ITEM
NO.
DESCRIPTION
Measure ment
PAY
UNIT
EST.
QTY.
UNIT
PRICE
TOTAL
PRICE
151-01 Mobilization LSQ Lump Sum 1
301-01
Roadway Aggregate, 4in thick, compaction method C* Government
Furnished
CQ
Cubic
Yard
301-02
Turnouts/Sideroads/Parking Areas
Aggregate, 4in thick, compaction method C* Government Furnished
CQ
Cubic
602-01 18 Inch Corrugated Steel Pipe, Government Furnished
CQ
Linear
Feet
619-01 Cattle Guard Install, Government
Furnished AQ Each 1
*Item 301-01 and 301-02 - Roadway Aggregate is measured as compacted, in-place quantity.
TOTAL BASE PRICE $ _
ADDITIVE #1 - Mile 3.74 -5.72
ITEM
NO.
DESCRIPTION
Measure ment
PAY
UNIT
EST.
QTY.
UNIT
PRICE
TOTAL
PRICE
301-03
Roadway Aggregate, 4in thick, compaction method C* Government
Furnished
CQ
Cubic
301-04
Turnouts/Sideroads/Parking Areas
Aggregate, 4in thick, compaction method C* Government Furnished
CQ
Cubic
*Item 301-03 and 301-04 - Roadway Aggregate is measured as compacted, in-place quantity.
ADDITIVE #2 - Mile 0.04 – 0.33
ITEM
NO.
DESCRIPTION
Measure ment
PAY
UNIT
EST.
QTY.
UNIT
PRICE
TOTAL
PRICE
404-01 Minor Hot Asphalt CQ TON 423
TOTAL BASE +1 & 2 PRICE $ _
DESIGNATED METHOD OF MEASUREMENT
AQ Actual Quantities
LSQ Lump Sum Quantities
DQ Design Quantities
CQ Contract Quantities
SPECIAL NOTES:
a. The bidder must bid on all items. Round to the nearest cent.
b. In the event of an error in extending the bid prices, unit prices will govern unless otherwise determined by the Contracting Officer in accordance with applicable regulations.
c. Offers for quantities less than those listed in the numbered items may be rejected.
d. Payment for bond premiums in accordance with Clause 52.232-5. Payments under Fixed-Price
Construction Contracts shall not be in addition to the contract price but can be included under
Mobilization.
e. The pay items in the Schedule of Items have suffixes that do not appear on the pay items in the specifications. They pertain only to sizes, classes, and/or types indicated in the item
"Descriptions,” and are used by the Government for computer tabulation of bid schedules.
There is no formal site visit for this project. Interested vendors are highly encouraged to visit the site prior to submitting a quotation. For information regarding the site, please contact Grant Morrison, Civil Engineer, Custer
Gallatin National Forest at 406-587-6724.
This is a Request for Quotation (RFQ); therefore, no public opening will be held. The results will not be made public prior to award. Quotes submitted in response to this RFQ will not be returned, but will be retained by the U.S. Forest Service for official record purposes. The RFQ does not commit the Government to pay any costs incurred in the preparation or the submission of this quote, or to make any award.
Vendor shall have a DUNS number and be registered in the System for Award Management (www.sam.gov) prior to award.
The Forest Service utilizes an electronic invoice system called Invoice Processing Platform (IPP). Awardee is required to set-up an account at www.ipp.gov in order to submit invoices.
Price Quotation furnished by:
Name: _______________________________ Phone: ____________________________
Address: ______________________________ Cell: ____________________________
______________________________ FAX: ____________________________
E-Mail: ________________________________ DUNS # ___________________________ http://www.ipp.gov/
C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK
C-1 PROJECT DESCRIPTION AND LOCATION
(a) Scope of Contract. The scope of this project is to prepare the road surface (by grading, watering, and rolling) and install government-furnished aggregate surfacing on the Storm Castle Road #132 and associated turnouts, sideroads, campgrounds, and trailheads on the Bozeman Ranger District, Custer
Gallatin National Forest. Work also includes installing government-furnished cattleguard and culvert.
Contract includes an additive for paving the first section of the Storm Castle Road. Work includes furnishing all labor, equipment, supervision, transportation, operating supplies, and incidentals necessary to perform road work on the road specified herein. All work and equipment shall be in compliance with the terms, specifications, and provisions of this contract. All equipment shall be in good operating condition and shall be operated by competent, experienced operators experienced in the work.
(b) Project Location. The beginning of the project is located approximately 11 miles south of Gallatin
Gateway, MT. See drawings for a detailed map.
C-2 GENERAL SPECIFICATIONS
a) Existing Facilities. In addition to the requirements of the Use of Premises Clause, AGAR 452.236-70, all existing facilities such as signs, cattleguards, and drainage structures damaged by the Contractor shall be replaced or repaired by the Contractor at no additional cost to the Government. This includes any facilities inside or outside the project limits, including along any access routes.
b) Pollution and Erosion Control. During all operations under this contract, the Contractor shall exercise reasonable measures to prevent or minimize soil erosion and pollution of water and other resources. All refuse, including garbage, rubbish, and solid or liquid wastes, from the Contractor's operations, including camps, parking areas, and equipment maintenance areas shall be stored, collected, and disposed of in a sanitary and nuisance-free manner. Refuse shall be disposed of in State-approved landfills unless otherwise approved by the Contracting Officer's Representative (COR).
During all of the work, the Contractor shall make every reasonable effort to direct surface runoff water to stabilized waterways and to keep the drainage systems functioning effectively to minimize soil erosion and water pollution.
c) Material Sources. Material source is indicated on plans. Contractor shall leave material not utilized for this project in the government stockpile in the location within the pit as staked by COR. Material shall be in one stockpile with no aggregate remaining on the pit floor.
C-3 TECHNICAL SPECIFICATIONS
a) Equipment Specifications. Equipment shall be in good mechanical and operating condition, fully capable of performing all phases of the specified work.
b) Winter Conditions. Winter shutdown in the project area due to cold and snow conditions typically occurs between November 1 and May 1 of each year but can vary considerably depending on the specific year.
c) Traffic Control. Contractor is allowed two 4 hour closures for culvert/cattle guard installation, provide
COR 7 days notification before closures. Contractor is allowed to have 20 minute closures on the road for all other work.
d) C-4 STANDARD SPECIFICATIONS
Standard Specifications are found in Standard Specifications for Construction of Roads and Bridges on Federal
Highway Projects (FP-03 US Customary Units) are included in this solicitation by reference only. The requirements contained in these Specifications are hereby made a part of this solicitation and any resultant
Contract. https://flh.fhwa.dot.gov/resources/specs/fp-03/
C-5 SPECIAL PROJECT SPECIFICATIONS
Preface
Delete all but the first paragraph and add the following:
The Forest Service, US Department of Agriculture has adopted FP-03 for construction of National Forest System
Roads.
https://flh.fhwa.dot.gov/resources/specs/fp-03/
101 - Terms, Format, and Definitions
101.01 Meaning of Terms
Delete all references to the FAR (Federal Acquisition Regulations) in the specifications.
101.03 Abbreviations.
Add the following to (a) Acronyms:
AFPA
MSHA
NIST
NESC
WCLIB
American Forest and Paper Association
Mine Safety and Health Administration
National Institute of Standards and Technology
National Electrical Safety Code
West Coast Lumber Inspection Bureau
Add the following to (b) SI symbols:
mp Milepost ppm Part Per Million
101.04 Definitions.
Delete the following definitions and substitute the following:
Bid Schedule--The Schedule of Items.
Bridge--No definition.
Contractor--The individual or legal entity contracting with the Government for performance of prescribed work.
In a timber sale contract, the contractor is the “purchaser”.
Culvert--No definition.
Right-of-Way--A general term denoting (1) the privilege to pass over land in some particular line (including easement, lease, permit, or license to occupy, use, or traverse public or private lands), or (2) Real property necessary for the project, including roadway, buffer areas, access, and drainage areas.
Add the following:
Adjustment in Contract Price--“Equitable adjustment,” as used in the Federal Acquisition Regulations, or
“construction cost adjustment,” as used in the Timber Sale Contract, as applicable.
Change--“Change” means “change order” as used in the Federal Acquisition Regulations, or “design change” as used in the Timber Sale Contract.
Design Quantity--“Design quantity” is a Forest Service method of measurement from the FS-96 Forest Service
Specifications for the Construction of Roads and Bridges. Under these FP specifications this term is replaced by the term “Contract Quantities”.
Forest Service--The United States of America, acting through the Forest Service, U.S. Department of
Agriculture.
Neat Line--A line defining the proposed or specified limits of an excavation or structure.
Pioneer Road--Temporary construction access built along the route of the project.
Purchaser--The individual, partnership, joint venture, or corporation contracting with the Government under the terms of a Timber Sale Contract and acting independently or through agents, employees, or subcontractors.
Protected Streamcourse--A drainage shown on the plans or timber sale area map that requires designated mitigation measures.
http://www.nist.gov/
Road Order--An order affecting and controlling traffic on roads under Forest Service jurisdiction. Road Orders are issued by a designated Forest Officer under the authorities of 36 CFR, part 260.
Schedule of Items--A schedule in the contract that contains a listing and description of construction items, quantities, units of measure, unit price, and amount.
Utilization Standards--The minimum size and percent soundness of trees described in the specifications to determine merchantable timber.
Add Figure 101-1—Illustration of road structure terms:
Figure 101-1—Illustration of road structure terms.
101.04_nat_us_11_06_2007
101.04 Definitions.
Delete the following definitions:
Contract Modification
Day
Notice to Proceed
Solicitation
102 - Bid, Award, and Execution of Contract
102.00_nat_us_02_16_2005
102 Bid, Award, and Execution of Contract
Delete Section 102 in its entirety.
103 - Scope of Work
103.00_nat_us_02_16_2005
Deletions
Delete all but subsection 103.01 Intent of Contract.
104 - Control of Work
104.00_nat_us_06_16_2006
Deletions
Delete Sections 104.01, 104.02, and 104.04.
104.03_nat_us_01_22_2009
104.03 Specifications and Drawings.
Delete 104.03.
105 - Control of Material
105.02 Material Sources.
105.02(a) Government-provided sources.
Add the following:
Comply with the requirements of 30 CFR 56, subparts B and H. Use all suitable material for aggregate regardless of size unless otherwise designated. When required, re-establish vegetation in disturbed areas according to section
625.
106 - Acceptance of Work
106.07 Delete
Delete subsection 106.07.
107 - Legal Relations and Responsibility to the Public
107.05 Responsibility for Damage Claims.
Delete the entire subsection.
107.06 Contractor’s Responsibility for Work.
Delete the following from the first paragraph.
“except as provided in Subsection 106.07”.
107.08 Sanitation, Health, and Safety.
Perform all operations in a prudent, conscientious, safe and professional manner. Ensure that all personnel involved in handling and packaging the hazardous waste are trained for the level of expertise required for the proper performance of the task and, in particular, in the areas of chemical incompatibility, general first aid procedures, and spills. Provide handling and personal protective equipment appropriate to ensure safe handling of the hazardous waste according to 29 CFR 1910.120). Notify the Forest Service of all hazardous material that may be brought onto the National Forest.
107.09 Legal Relationship of the Parties.
Delete the entire subsection.
107.10 Environmental Protection.
Design and locate equipment repair shops, stationary refueling sites, or other facilities to minimize the potential and impacts of hazardous material spills on Government land.
Before beginning any work, submit a Hazardous Spill Plan. List actions to be taken in the event of a spill.
Incorporate preventive measures to be taken, such as the location of mobile refueling facilities, storage and handling of hazardous materials, and similar information. Immediately notify the CO of all hazardous material spills. Provide a written narrative report form no later than 24 hours after the initial report and include the following:
Description of the item spilled (including identity, quantity, manifest number, and other identifying information).
Whether amount spilled is EPA or state reportable, and if so whether it was reported, and to whom.
Exact time and location of spill including a description of the area involved.
Containment procedures.
Summary of any communications the Contractor had with news media, Federal, state and local regulatory agencies and officials, or Forest Service officials.
Description of clean-up procedures employed or to be employed at the site including final disposition and disposal location of spill residue.
When available provide copies of all spill related clean up and closure documentation and correspondence from regulatory agencies.
The Contractor is solely responsible for all spills or leaks that occur during the performance of this contract. Clean up spills or leaks to the satisfaction of the CO and in a manner that complies with Federal, state, and local laws and regulations.
108 - Prosecution and Progress
108 Delete.
Delete Section 108 in its entirety.
109 - Measurement and Payment
109 Deletions
Delete the following entire subsections:
109.06 Pricing of Adjustments.
109.07 Eliminated Work.
109.08 Progress Payments.
109.09 Final Payment.
109.02 Measurement Terms and Definitions.
(b) Contract quantity.
Add the following:
Contract quantities will be adjusted only when there are errors in the original design of 15% or more.
Change the following:
“(b) Cubic yard” to “(c) Cubic yard”.
155 - Schedules for Construction Contracts
155.00_nat_us_05_11_2004
155 Delete.
Delete Section 155 in its entirety.
301 - Untreated Aggregate Courses
301.00_nat_us_03_03_2005
301 Title Change.
Change the title to: Section 301 Aggregate Courses
301.03 General.
Prepare the surface on which the aggregate course is placed by grading, adjusting moisture content, and rolling:
After grading the roadway:
o will have been bladed shoulder to shoulder o will be free of berms, both sides o existing crowned roads will be crowned(4%-6% from centerline) o no surfacing or road material will be wasted o will have ruts/potholes cut out o all ditches and lead-out ditches will be free of obstructions and functioning properly o This shall consist of reshaping and finish blading the roadbed, including shoulders and turnouts, to provide adequate water runoff and restore/maintain the original cross section and grade of the road. Work includes removing ruts, washes, slough, and other irregularities that prevent normal runoff from the road surface. Ditches shall be cleaned where they are plugged or full of debris and need to be pulled to maintain drainage.
o Upon completion of the last pass with the grader, the finished road will be crowned and free of rock 2 inches or greater in diameter.
Adjust for optimum moisture content by applying water to the roadway
Compact roadway according to 301.05 - Compaction C
Written approval of the roadbed is required before placing aggregate.
After approval of roadbed apply Government furnished aggregate as staked and according to the plans.
301.05 Compacting
Delete and replace with the following:
Compact each layer full width. Roll from the sides to the center, parallel to the centerline of the road. Along curbs, headers, walls, and all places not accessible to the roller, compact the material with approved tampers or compactors.
Compact the aggregate using one of the following methods as specified:
Compaction A. Operating spreading and hauling equipment over the full width of the travelway.
Compaction B. Operate rollers and compact as specified in Subsection 204.11(a)(1).
Compaction C. Moisten or dry the aggregate to a uniform moisture content between 5 and 7 percent based on total dry weight of the mixture. Operate rollers and compact as specified in Subsection 204.11(a)(1).
Compaction D. Compact to a density of at least 95 percent of the maximum density, as determined by AASHTO
T 99, method C or D.
Compaction E. Compact to a density of at least 96 percent of the maximum density, as determined by the
Modified Marshall Hammer Compaction Method (available upon request from USDA Forest Service, Regional
Materials Engineering Center, P.O. Box 7669, Missoula, MT 59807).
Compaction F. Compact to a density of at least 95 per-cent of the maximum density, as determined by AASHTO
T 180, method C or D.
Compaction G. Compact to a density of at least 100 percent of the maximum density as determined by the
Modified Marshall Hammer Compaction Method (available upon request from USDA Forest Service, Regional
Materials Engineering Center, P.O. Box 7669, Missoula, MT 59807).
For all compaction methods, blade the surface of each layer during the compaction operations to remove irregularities and produce a smooth, even surface. When a density requirement is specified, determine the in place density and moisture content according to AASHTO T 310 or other approved test procedures.
301.06_nat_us_03_03_2005
301.06 Surface Tolerance.
Add the following:
Thickness and Width requirements:
The maximum variation from the compacted specified thickness is ½ inch. The compacted thickness is not consistently above or below the specified thickness and the average thickness of 4 random measurements for any
½ mile of road segment is within + ¼ inch of the specified thickness.
The maximum variation from the specified width will not exceed +12 inches at any point. The compacted width is not consistently above the specified width and the average of any four random measurements along any ½ mile of road segment is within +4 inches of the specified width.
301.08(b) Plasticity Index.
Add the following to the first sentence:
“and under 703.05(c)(1)
301.09 Measurement.
Replace the second paragraph with the following:
Measure aggregate by cubic yard compacted in place when payment is by contract quantities.
301.10 Payment
Delete the following:
adjusted according to Subsection 106.05
C-7 CLEANUP AND DISPOSAL
The Contractor shall be responsible for solid waste disposal. The Contractor shall at all times keep the area in a clean, neat, and orderly condition. Construction related debris, including but not limited to used motor oil, oil cans, grease cartridges and refuse shall be removed promptly from the site and disposed of in a lawful manner off
National Forest System lands. Fees for the use of landfills or transfer stations shall be paid for by the Contractor if there is a charge.
C-8 EXISTING UTILITIES
Utilities present on site. Contractor is responsible for location of utilities if excavation is planned. No excavation is anticipated on this project.
AGAR 452.211-72 Statement of Work/Specifications (FEB 1988)
The Contractor shall furnish the necessary personnel, material, equipment, services and facilities (except as otherwise specified), to perform the Statement of Work/Specifications referenced in Section J.
AGAR 452.211-73 Attachments to Statement of Work/Specifications (FEB 1988)
The attachments to the Statement of Work/Specifications listed in Section J are hereby made part of this solicitation and any resultant contract.
D - PACKAGING AND MARKING
{For this solicitation there are NO Clauses.}
E - INSPECTION AND ACCEPTANCE
52.246-1 Contractor Inspection Requirements. (APR 1984)
52.246-12 Inspection of Construction. (APR 1996)
F - DELIVERIES OR PERFORMANCE
52.211-10 Commencement, Prosecution, and Completion of Work (Apr 1984) Alternative I
The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than September 30, 2018. The time stated for completion shall include final cleanup of the premises.
The completion date is based on the assumption that the successful offeror will receive the notice to proceed by
June 15, 2018. The completion date will be extended by the number of calendar days after the above date that the
Contractor receives the notice to proceed, except to the extent that the delay in issuance of the notice to proceed results from the failure of the Contractor to execute the contract and give the required performance and payment bonds within the time specified in the offer.
(End of Clause)
NOTE: Notify the Contracting Officer’s Representative (COR) of intent to begin work at least seven (7) days in advance.
G - CONTRACT ADMINISTRATION DATA
452.215-73 Postaward Conference. (NOV 1996)
A post award conference with the successful offeror is required. It will be scheduled after the date of contract award. The conference will be held at a date and time to be determined later.
(End of Clause)
GOVERNMENT-FURNISHED PROPERTY
The Government will provide the following item(s) of Government property to the Contractor for use in the performance of this contract. This property shall be used and maintained by the Contractor in accordance with the provisions of the "Government Property" FAR clause contained elsewhere in the contract.
1. Roadway Aggregate – Stockpiled in the Cascade Pit (along Highway 191) as indicated on plans.
H - SPECIAL CONTRACT REQUIREMENTS
H-1 NOXIOUS WEED CONTROL
Prior to mobilizing onto National Forest lands, roads, or trails, the contractor shall sufficiently clean any equipment by removing all visible dirt and plant materials. All subsequent move-outs/move-ins by the same piece of equipment shall be equally cleaned.
Prior to any equipment move-in, the Contractor shall make the equipment available for a Forest Service inspection at an agreed location.
H-2 LANDSCAPE PRESERVATION
(a) The Contractor shall confine operations to within the clearing limits or other areas designated in contract documents, and prevent the depositing of rocks, excavated materials, stumps, or other debris outside of these limits.
Material, which falls outside of these limits, shall be retrieved, disposed of, or incorporated in the work as directed by the Contracting Officer.
(b) Operation shall be scheduled and conducted to minimize erosion of soils and to prevent silting and muddying of streams, rivers, irrigation systems, and impoundments (lakes, reservoirs, etc.).
Pollutants such as fuels, lubricants, bitumens, raw sewage, and other harmful materials shall not be discharged into or near rivers, streams, and impoundments or into natural or manmade channels leading thereto. Wash water or waste water from concrete or aggregate operations shall not be allowed to enter live streams prior to treatment by filtration, settling, or other means sufficient to reduce the sediment content to not more than that of the stream into which it is discharged.
Mechanized equipment shall not be operated in live streams without written approval by the Contracting Officer.
H-3 SECURITY AND PROTECTION
(a) Security and Protection – Security is the Contractor’s responsibility. Limit access to the construction area to persons involved in the work. Provide secure storage for materials that are stored on site. Secure completed work as required to prevent loss.
Barricades, warning signs and light shall comply with standards and code requirements for erection of structurally adequate barricades. All road warning signs, barricades, and traffic control devices shall conform to MUTCD. Paint with appropriate colors, graphics, and warning signs to inform personnel and the public of the hazard being protected against. Where appropriate and needed, provide lighting, including flashing red or amber lights.
(b) Maintenance of Traffic – The Contractor is authorized to use roads under the jurisdiction of the Forest
Service, and open to public travel, for all activities necessary to complete this contract, subject to limitations and authorizations shown on the drawings or specified under this contract when such use will not damage the roads or national forest resources and when traffic can be accommodated safely.
Except as allowed in the contract, trailheads and roads shall remain open throughout the construction project. Perform no work that interferes or conflicts with traffic or existing access to the roadway surface until a plan for satisfactorily handling the traffic has been approved.
Before shutting down operations, take all necessary precautions to prevent damage to the project, such as temporary detours, approaches, crossings, or intersections; and provide for normal drainage and minimization of erosion. Leave all travel ways in a condition suitable for traffic.
(c) Protection of Improvements – The Contractor shall complete sequences of construction activity in order to prevent damage to equipment, material, and articles incorporated into the work covered by this contract.
H-4 CAMPING
(a) Before camping, the Contractor shall obtain a District Camping Permit, if required, from each District the
Contractor is working on through the Contracting Officer/Contracting Officer's Representative.
(b) A camp is interpreted to include a campsite or trailer parking area of any employee working on the project for the Contractor.
(c) Contractor is to bring a proposed campsite location to the prework for review and approval and prior to camping.
(d) In bear country follow all food storage orders.
(e) The Government will make no special camping allowances for the Contractor within or near the project area.
Arrangements with the local private landowners will be at the discretion of the Contractor.
I - CONTRACT CLAUSES
52.252-2 Clauses Incorporated by Reference. (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): http://farsite.hill.af.mil/
(End of clause)
52.204-7 System for Award Management. (OCT 2016)
52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards. (OCT 2016)
52.204-13 System for Award Management Maintenance. (OCT 2016)
52.204-18 Commercial and Government Entity Code Maintenance. (JUL 2016)
52.209-6 Protecting the Governments Interest When Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment. (OCT 2015)
52.209-10 Prohibition on Contracting With Inverted Domestic Corporations. (NOV 2015)
52.211-10 Commencement, Prosecution, and Completion of Work. (APR 1984)
52.211-18 Variation in Estimated Quantity. (APR 1984)
52.219-6 Notice of Total Small Business Set-Aside. (NOV 2011)
52.219-28 Post Award Small Business Program Rerepresentation. (JUL 2013)
52.222-3 Convict Labor. (JUN 2003)
52.222-6 Construction Wage Rate Requirements. (MAY 2014)
52.222-7 Withholding of Funds. (MAY 2014)
52.222-8 Payrolls and Basic Records. (MAY 2014)
52.222-9 Apprentices and Trainees. (JUL 2005)
52.222-10 Compliance with Copeland Act Requirements. (FEB 1988)
52.222-11 Subcontracts (Labor Standards). (MAY 2014) http://farsite.hill.af.mil/
52.222-12 Contract Termination - Debarment. (MAY 2014)
52.222-13 Compliance with Construction Wage Rate Requirements and Related Regulations. (MAY 2014)
52.222-14 Disputes Concerning Labor Standards. (FEB 1988)
52.222-15 Certification of Eligibility. (MAY 2014)
52.222-21 Prohibition of Segregated Facilities. (APR 2015)
52.222-26 Equal Opportunity. (SEP 2016)
52.222-27 Affirmative Action Compliance Requirement for Construction. (APR 2015)
52.222-36 Equal Opportunity for Workers With Disabilities. (JUL 2014)
52.222-50 Combating Trafficking in Persons. (MAR 2015)
52.222-55 Minimum Wages Under Executive Order 13658. (DEC 2015)
52.222-62 Paid Sick Leave Under Executive Order 13706. (JAN 2017)
52.223-2 Affirmative Procurement of Biobased Products Under Service and Construction Contracts. (SEP
2013)
52.223-5 Pollution Prevention and Right-to-Know Information. (MAY 2011)
52.223-6 Drug-Free Workplace. (MAY 2001)
52.223-18 Encouraging Contractor Policies to Ban Text Messaging While Driving. (AUG 2011)
52.225-13 Restrictions on Certain Foreign Purchases. (JUN 2008)
52.228-2 Additional Bond Security. (OCT 1997)
52.228-11 Pledges of Assets. (JAN 2012)
52.228-12 Prospective Subcontractor Requests for Bonds. (MAY 2014)
52.228-14 Irrevocable Letter of Credit. (NOV 2014)
52.228-15 Performance and Payment Bonds – Construction. (OCT 2010)
52.232-5 Payments under Fixed-Price Construction Contracts. (MAY 2014)
52.232-23 Assignment of Claims. (MAY 2014)
52.232-27 Prompt Payment for Construction Contracts. (JAN 2017)
52.232-33 Payment by Electronic Funds Transfer - System for Award Management. (JUL 2013)
52.232-39 Unenforceability of Unauthorized Obligations. (JUN 2013)
52.232-40 Providing Accelerated Payments to Small Business Subcontractors. (DEC 2013)
52.233-1 Disputes. (MAY 2014)
52.233-3 Protest after Award. (AUG 1996)
52.233-4 Applicable Law for Breach of Contract Claim. (OCT 2004)
52.236-2 Differing Site Conditions. (APR 1984)
52.236-4 Physical Data. (APR 1984)
52.236-5 Material and Workmanship. (APR 1984)
52.236-6 Superintendence by the Contractor. (APR 1984)
52.236-7 Permits and Responsibilities. (NOV 1991)
52.236-8 Other Contracts. (APR 1984)
52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements. (APR
1984)
52.236-10 Operations and Storage Areas. (APR 1984)
52.236-11 Use and Possession Prior to Completion. (APR 1984)
52.236-12 Cleaning Up. (APR 1984)
52.236-13 Accident Prevention. (NOV 1991)
52.236-14 Availability and Use of Utility Services. (APR 1984)
52.236-15 Schedules. (APR 1984)
52.236-16 Quantity Surveys. (APR 1984)
52.236-17 Layout of Work. (APR 1984)
52.236-21 Specifications and Drawings for Construction. (FEB 1997)
52.236-26 Preconstruction Conference. (FEB 1995)
52.242-14 Suspension of Work. (APR 1984)
52.243-5 Changes and Changed Conditions. (APR 1984)
52.244-6 Subcontracts for Commercial Items. (FEB 2016)
52.245-1 Government Property. (JAN 2017)
52.245-9 Use and Charges. (APR 2012)
52.246-12 Inspection of Construction. (AUG 1996)
52.246-21 Warranty of Construction. (MAR 1994)
52.249-1 Termination for Convenience of the Government (Fixed-Price) (Short Form). Alternative I (APR
1984)
52.249-10 Default (Fixed-Price Construction). (APR 1984)
52.253-1 Computer Generated Forms. (JAN 1991)
452.232-70 Reimbursement for Bond Premiums – Fixed Price Construction Contracts. (NOV 1996)
452.236-71 Prohibition Against the Use of Lead-Based Paint. (NOV 1996)
452.236-73 Archaeological or Historic Sites. (FEB 1988)
452.236-74 Control of Erosion, Sedimentation, and Pollution. (NOV 1996)
452.236-77 Emergency Response (NOV 1996)
52.225-9 Buy American - Construction Materials. (MAY 2014)
(a) Definitions. As used in this clause-
Commercially available off-the-shelf (COTS) item- (1) Means any item of supply (including construction material) that is-
(i) A commercial item (as defined in paragraph (1) of the definition at FAR 2.101);
(ii) Sold in substantial quantities in the commercial marketplace; and
(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and
(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products.
Construction material means an article, material, or supply brought to the construction site by the
Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.
Cost of components means-
(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or
(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.
Domestic construction material means-
(1) An unmanufactured construction material mined or produced in the United States;
(2) A construction material manufactured in the United States, if-
(i) The cost of its components mined, produced, or manufactured in the United States exceeds 50 percent of the cost of all its components. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic; or
(ii) The construction material is a COTS item.
Foreign construction material means a construction material other than a domestic construction material.
United States means the 50 States, the District of Columbia, and outlying areas.
(b) Domestic preference. (1) This clause implements 41 U.S.C. chapter 83, Buy American, by providing a preference for domestic construction material. In accordance with 41 U.S.C. 1907, the component test of the Buy American statute is waived for construction material that is a COTS item. (See FAR
12.505(a)(2)). The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.
(2) This requirement does not apply to information technology that is a commercial item or to the construction materials or components listed by the Government as follows:
NONE
(3) The Contracting Officer may add other foreign construction material to the list in paragraph
(b)(2) of this clause if the Government determines that-
(i) The cost of domestic construction material would be unreasonable. The cost of a particular domestic construction material subject to the requirements of the Buy
American statute is unreasonable when the cost of such material exceeds the cost of foreign material by more than 6 percent;
(ii) The application of the restriction of the Buy American statute to a particular construction material would be impracticable or inconsistent with the public interest; or
(iii) The construction material is not mined, produced, or manufactured in the United
States in sufficient and reasonably available commercial quantities of a satisfactory quality.
(c) Request for determination of inapplicability of the Buy American statute. (1)(i) Any Contractor request to use foreign construction material in accordance with paragraph (b)(3) of this clause shall include adequate information for Government evaluation of the request, including-
(A) A description of the foreign and domestic construction materials;
(B) Unit of measure;
(C) Quantity;
(D) Price;
(E) Time of delivery or availability;
(F) Location of the construction project;
(G) Name and address of the proposed supplier; and
(H) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(3) of this clause.
(ii) A request based on unreasonable cost shall include a reasonable survey of the market and a completed price comparison table in the format in paragraph (d) of this clause.
(iii) The price of construction material shall include all delivery costs to the construction site and any applicable duty (whether or not a duty-free certificate may be issued).
(iv) Any Contractor request for a determination submitted after contract award shall explain why the Contractor could not reasonably foresee the need for such determination and could not have requested the determination before contract award. If the Contractor does not submit a satisfactory explanation, the Contracting Officer need not make a determination.
(2) If the Government determines after contract award that an exception to the Buy American statute applies and the Contracting Officer and the Contractor negotiate adequate consideration, the Contracting Officer will modify the contract to allow use of the foreign construction material.
However, when the basis for the exception is the unreasonable price of a domestic construction material, adequate consideration is not less than the differential established in paragraph (b)(3)(i) of this clause.
(3) Unless the Government determines that an exception to the Buy American statute applies, use of foreign construction material is noncompliant with the Buy American statute or Balance of
Payments Program.
(d) Data. To permit evaluation of requests under paragraph (c) of this clause based on unreasonable cost, the Contractor shall include the following information and any applicable supporting data based on the survey of suppliers:
Foreign and Domestic Construction Materials Price Comparison
Construction material description Unit of Quantity Price measure (dollars)* Item 1:
Foreign construction material ________ ________ ________
Domestic construction material ________ ________ ________
Item 2:
Foreign construction material ________ ________ ________
Domestic construction material ________ ________ ________
* Include all delivery costs to the construction site and any applicable duty (whether or not a duty-free entry certificate is issued).
List name, address, telephone number, and contact for suppliers surveyed. Attach copy of response; if oral, attach summary.
Include other applicable supporting information.
52.228.13 Alternative Payment Protections. (JUL 2000)
(a) The Contractor shall submit one of the following payment protections:
SF-25A, Payment Bond
Irrevocable Letter of Credit (Portion of SF-25A shall be completed when utilizing ILC)
Tripartite Escrow Agreement
Certified or Cashier’s Check, Bank Drafts, Money Orders or Currency.
(b) The amount of the payment protection shall be 100 percent of the contract price.
(c) The submission of the payment protection is required within 10 days of contract award.
(d) The payment protection shall provide protection for the full contract performance period plus a one-year period.
(e) Except for escrow agreements and payment bonds, which provide their own protection procedures, the
Contracting Officer is authorized to access funds under the payment protection when it has been alleged in writing by a supplier of labor or material that a nonpayment has occurred, and to withhold such funds pending resolution by administrative or judicial proceedings or mutual agreement of the parties.
(f) When a tripartite escrow agreement is used, the Contractor shall utilize only suppliers of labor and material that signed the escrow agreement.
(End of Clause)
52.236-3 Site Investigation and Conditions Affecting the Work. (APR 1984)
(a) The Contractor acknowledges that it has taken steps reasonably necessary to ascertain the nature and location of the work, and that it has investigated and satisfied itself as to the general and local conditions which can affect the work or its cost, including but not limited to (1) conditions bearing upon transportation, disposal, handling, and storage of materials; (2) the availability of labor, water, electric power, and roads; (3) uncertainties of weather, river stages, tides, or similar physical conditions at the site; (4) the conformation and conditions of the ground; and (5) the character of equipment and facilities needed preliminary to and during work performance. The Contractor also acknowledges that it has satisfied itself as to the character, quality, and quantity of surface and subsurface materials or obstacles to be encountered insofar as this information is reasonably ascertainable from an inspection of the site, including all exploratory work done by the Government, as well as from the drawings and specifications made a part of this contract. Any failure of the Contractor to take the actions described and acknowledged in this paragraph will not relieve the Contractor from responsibility for estimating properly the difficulty and cost of successfully performing the work, or for proceeding to successfully perform the work without additional expense to the
Government.
(b) The Government assumes no responsibility for any conclusions or interpretations made by the Contractor based on the information made available by the Government. Nor does the Government assume responsibility for any understanding reached or representation made concerning conditions which can affect the work by any of its officers or agents before the execution of this contract, unless that understanding or representation is expressly stated in this contract.
J - LIST OF DOCUMENTS, EXHIBITS, AND OTHER ATTACHMENTS
J-1: Wage Rate Requirements (Construction), Wage Determination: General Decision Number, MT180080, dated
03/16/2018, MT80
J-2: Experience Questionnaire
J-3: Signed Cover Sheet (1 page, separate attachment)
J-4: Project Plans (5 pages, separate attachment)
K - REPRESENTATIONS, CERTIFICATIONS, AND OTHER STATEMENTS OF OFFERORS OR
RESPONDENTS
52.252-1 Solicitation Provisions Incorporated by Reference. (Feb 1998)
This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es): http://farsite.hill.af.mil/
(End of provision)
52.204-19 Incorporation by Reference of Representations and Certifications. (DEC 2014)
52.204-8 Annual Representations and Certifications. (JAN 2017)
(a)
(1) The North American Industry classification System (NAICS) code for this acquisition is 237310 –
Highway, Street, and Bridge Construction.
(2) The small business size standard is $36.5 Million.
(3) The small business size standard for a concern which submits an offer in its own name, other than on a construction or service contract, but which proposes to furnish a product which it did not itself manufacture, is 500 employees.
(b)
(1) If the provision at 52.204-7, System for Award Management, is included in this solicitation, paragraph (d) of this provision applies.
(2) If the provision at 52.204-7 is not included in this solicitation, and the offeror is currently registered in the System for Award Management (SAM), and has completed the Representations and Certifications section of SAM electronically, the offeror may choose to use paragraph (d) of this provision instead of completing the corresponding individual representations and certification in the solicitation. The offeror shall indicate which option applies by checking one of the following boxes:
[_] (i) Paragraph (d) applies.
[_] (ii) Paragraph (d) does not apply and the offeror has completed the individual representations and certifications in the solicitation.
(c)
(1) The following representations or certifications in SAM are applicable to this solicitation as indicated:
http://farsite.hill.af.mil/
(i) 52.203-2, Certificate of Independent Price Determination. This provision applies to solicitations when a firm-fixed-price contract or fixed-price contract with economic price adjustment is contemplated, unless—
(A) The acquisition is to be made under the simplified acquisition procedures in Part 13;
(B) The solicitation is a request for technical proposals under two-step sealed bidding procedures; or
(C) The solicitation is for utility services for which rates are set by law or regulation.
(ii) 52.203-11, Certification and Disclosure Regarding Payments to Influence Certain Federal
Transactions. This provision applies to solicitations expected to exceed $150,000.
(iii) 52.203-18, Prohibition on Contracting with Entities that Require Certain Internal
Confidentiality Agreements or Statements—Representation. This provision applies to all solicitations.
(iv) 52.204-3, Taxpayer Identification. This provision applies to solicitations that do not include the provision at 52.204-7, System for Award Management.
(v) 52.204-5, Women-Owned Business (Other Than Small Business). This provision applies to solicitations that—
(A) Are not set aside for small business concerns;
(B) Exceed the simplified acquisition threshold; and
(C) Are for contracts that will be performed in the United States or its outlying areas.
(vi) 52.209-2, Prohibition on Contracting with Inverted Domestic Corporations—Representation.
(vii) 52.209-5; Certification Regarding Responsibility Matters. This provision applies to solicitations where the contract value is expected to exceed the simplified acquisition threshold.
(viii) 52.209-11, Representation by Corporations Regarding Delinquent Tax Liability or a Felony
Conviction under any Federal Law. This provision applies to all solicitations.
(ix) 52.214-14, Place of Performance--Sealed Bidding. This provision applies to invitations for bids except those in which the place of performance is specified by the Government.
(x) 52.215-6, Place of Performance. This provision applies to solicitations unless the place of performance is specified by the Government.
(xi) 52.219-1, Small Business Program Representations (Basic & Alternate I). This provision applies to solicitations when the contract will be performed in the United States or its outlying areas.
(A) The basic provision applies when the solicitations are issued by other than DoD, NASA, and the Coast Guard.
(B) The provision with its Alternate I applies to solicitations issued by DoD,…