901 - Terms, Format, Abbreviations and Definitions

905 – Quality Assurance and Quantity Measurement

906 – Measurement and Payment

907 - Mobilization

908 - Construction Staking, Flagging, and Cleanup

911 – Trail and Prism

912 - Clearing Limits

915 – Talus Section

917 - Fords

927 – Drain Dips

931 - Switchbacks

901 - Terms, Format, Abbreviations and Definitions

901.04_sawtooth_02_15_2018

901.04 Definitions.

Add the following:

Adjustment in Contract Price--“Equitable adjustment,” as used in the Federal Acquisition

Regulations.

Bid Schedule--The Schedule of Items.

Change--“Change” means “change order” as used in the Federal Acquisition Regulations.

Contractor--The individual or legal entity contracting with the Government for performance of prescribed work.

Neat Line--A line defining the proposed or specified limits of an excavation or structure.

Schedule of Items--A schedule in the contract that contains a listing and description of construction items, quantities, units of measure, unit price, and amount.

905 – Quality Assurance and Quantity Measurement

905.01_sawtooth_02_15_2018

905.01 Description

Replace this subsection in its entirety with the following:

This work consists of providing certification that the quality and quantity of construction conform to the plans, specifications, and requirements of the contract.

Contractors shall be Professional Trail Builder Association (PTBA) certified or equivalent.

Proof of certification shall be included as part of proposal submittal for evaluation prior to awarding the project.

Follow the requirements of FAR Clause 52.246-12 Inspection of Construction.

Perform all work to the lines, grades, cross-sections, dimensions, and processes or material requirements shown on the plans or specified in the contract.

Incorporate manufactured materials into the work according to the manufacturer’s recommendations or to these specifications, whichever is more strict.

Plan dimensions and contract specification values are the values to be strived for and complied with as the design values from which any deviations are allowed. Perform work and provide material that is uniform in character and reasonably close to the prescribed value or within the specified tolerance range. The purpose of a tolerance range is to accommodate occasional minor variations from the median zone that are unavoidable for practical reasons.

The Government may inspect, sample, or test all work at any time before final acceptance of the project. When the Government tests work, copies of test reports are furnished to the Contractor upon request. Government tests may or may not be performed at the work site. If Contractor testing and inspection is verified by the Government, the Contractor’s results may be used by the Government to evaluate work for acceptance. Do not rely on the availability of Government test results for process control.

Acceptable work conforming to the contract will be paid for at the contract unit bid price.

Remove and replace work that does not conform to the contract, or to prevailing industry standards where no specific contract requirements are noted, at no cost to the Government.

(a) Disputing Government test results. If the accuracy of Government test results is disputed, promptly inform the CO. If the dispute is unresolved after reasonable steps are taken to resolve the dispute, further evaluation may be obtained by written request.

Include a narrative describing the dispute and a proposed resolution protocol that addresses the following:

(1) Sampling method;

(2) Number of samples;

(3) Sample transport;

(4) Test procedures;

(5) Testing laboratories;

(6) Reporting;

(7) Estimated time and costs; and

(8) Validation process.

If the evaluation requires additional sampling or testing be performed, mutually agree with the Government on witnessing procedures and on sampling and testing by a third party laboratory. Use a third party laboratory accredited by the AASHTO accreditation program.

Provide proof of the laboratory’s accreditation for the test procedures to be used. Do not use the same laboratory that produced the disputed Government test results or that produced the test results used as a basis for the dispute.

The CO will review the proposed resolution protocol and may modify it before final approval and execution.

The Government will use the approved resolution protocol test results to determine the validity of the disputed testing. If the Government test results are validated, the Contractor will be responsible for all costs associated with developing and performing the resolution protocol. If the Government test results are not validated, the Government will be responsible for all costs associated with developing and performing the resolution protocol.

If the validity of the Government test results cannot be determined, the Contractor and

Government will equally share all costs associated with developing and carrying out the resolution protocol.

(b) Alternatives to removing and replacing non-conforming work. As an alternative to removal and replacement, the Contractor may submit a written request to:

(1) Have the work accepted at a reduced price; or

(2) Be given permission to perform corrective measures to bring the work into conformity.

The request must contain supporting rationale and documentation. Include references or data justifying the proposal based on an evaluation of test results, effect on service life, value of material or work, quality, aesthetics, and other tangible engineering basis. The CO will determine disposition of the nonconforming work.

906 – Measurement and Payment

906.02_sawtooth_02_15_2018

906.02 Determination of Quantities

Replace the fifth paragraph under this subsections in its entirety, beginning with the word

“Deduct”, with the following:

Deduct lengths for stairways, turnpike, puncheon, retaining walls, wire baskets, bridges, and bridge approaches from the measurement of excavation in Section 911 unless these items are specified as incidental to excavation in Section 911.

907 - Mobilization

907.00_sawtooth_02_15_2018

Replace this section in its entirety with the following:

Description

907.01 This work consists of moving personnel, equipment, material, and incidentals to the project and performing all work necessary before beginning work at the project site; obtaining of permits, insurance, and bonds; providing sanitary facilities for the Contractor’s personnel; and performing all other required work necessary before beginning work on the Contract.

This work includes washing and treating construction equipment and vehicles necessary for equipment transport to remove seeds, plants, and plant fragments before the equipment is used on Forest Service lands, according to the requirements within.

This work includes submitting a Hazardous Spill Plan prior to beginning work. List actions to be taken in the event of a spill. Incorporate preventive measures to be taken, such as the location of mobile refueling facilities, storage and handling of hazardous materials, and similar information.

Immediately notify the CO of all hazardous material spills. Provide a written narrative report form no later than 24 hours after the initial report and include the following:

Description of the item spilled (including identity, quantity, manifest number, and other identifying information).

Whether amount spilled is EPA or state reportable, and if so whether it was reported, and to whom.

Exact time and location of spill including a description of the area involved.

Containment procedures.

Summary of any communications the Contractor had with news media, Federal, state and local regulatory agencies and officials, or Forest Service officials.

Description of clean-up procedures employed or to be employed at the site including final disposition and disposal location of spill residue.

When available provide copies of all spill-related clean up and closure documentation and correspondence from regulatory agencies.

The Contractor is solely responsible for all spills or leaks that occur during the performance of this contract. Contractor shall clean up spills or leaks to the satisfaction of the CO and in a manner that complies with Federal, state, and local laws and regulations.

Lastly, this work also include preparing and submitting a Project Fire Plan, prior to beginning any site work, in cooperation with the Contracting Officer, and providing for the prevention and control of fires in the project area. The Contractor shall certify compliance with all fire protection and suppression requirements, before beginning operations during the fire period and closed season. Required Tools and Equipment shall be kept currently in serviceable condition and immediately available for initial attack on fires.

Construction Requirements

907.02 Wash the sides, tops, and undercarriages of all construction equipment. Remove all seeds, plants, plant fragments, dirt, and debris from the construction equipment. Only equipment inspected by the Forest Service will be allowed to operate within the project area. All subsequent move-ins of equipment to the project area will be treated in the same manner as the initial move-in. This requirement does not apply to cars, pickup trucks, and other vehicles that regularly travel between the construction site and areas off the National Forest.

Equipment will be considered free of soil, seed, and other such debris when a visual inspection does not disclose such material. Disassembly of equipment, components or the need for specialized inspection tools is not required.

Notify the CO in writing at least 72 hours before moving any construction equipment onto the

National Forest. Notification will include an agreed upon location where the equipment will be available for inspection by the Forest Service. Inspection will be required after every cleaning.

Use methods of cleaning and locations for cleaning approved by the CO.

For work at a commercial washing facility, use an approved facility.

New infestations of noxious weeds of concern to Forest Service and identified by either

Contractor or Forest Service, in the Project Area or on the haul route, will be promptly reported to the other party. Contractor and Forest Service will agree on treatment methods to reduce or stop the spread of noxious weeds when new infestations are found. A current list of noxious weeds of concern to Forest Service is available at each Forest Service office.

Payment

907.03 The accepted quantity, measured as provided in Subsection 906.02, will be paid at the contract price per unit of measurement for the Section 907 pay item shown in the bid schedule.

Payment will be full compensation for the work prescribed in this Section. Include all costs associated with the cleaning of equipment, and Hazardous Spill Plan and Project Fire Plan preparation and implementation in the unit bid price for Mobilization.

Progress payments for mobilization lump sum will be paid as follows:

(a) Bond premiums will be reimbursed according to FAR Clause 52.232-5, Payments

Under Fixed-Price Construction Contracts, after receipt of the evidence of payment.

Reimburse for bond premiums before issuing the Notice to Proceed if evidence of payment is received.

(b) When 5 percent of the original contract amount is earned from other bid items, 50 percent of the mobilization item, or 5 percent of the original contract amount, whichever is less, will be paid.

(c) When 10 percent of the original contract amount is earned from other bid items, 100 percent of the mobilization item, or 10 percent of the original contract amount, whichever is less, will be paid.

(d) Any portion of the mobilization item in excess of 10 percent of the original contract amount will be paid after final acceptance. Pay any unpaid amount for mobilization upon final acceptance of all work items.

908 - Construction Staking, Flagging, and Cleanup

908.02_sawtooth_02_15_2018

Construction

Add the following to the end of the first paragraph under this subsection:

The Forest Service will provide a plan sheet that shows the flagged trail alignment, beginning and ending points, and known trail features to construct along the way. Contractor shall construct a new field-fit trail within a set distance either way of the flagged trail alignment, to be approved by the

CO prior to commencing any trail construction work.

911 – Trail and Prism

911.10.01_sawtooth_02_15_2018

Replace the second paragraph under subsection in its entirety with the following:

911.10.01.

Includes excavation, embankment, and backfill construction required to shape the trailbed, ditches, backslopes, fill slopes, drainage dips, trail passing sections, and turnouts. Also includes the excavation and embankment work required to construct culverts, trail bridges, shallow stream fords and gully crossings, talus and rubble rock sections, switchbacks, and climbing turns.

911.10.04_sawtooth_02_15_2018

911.10.04 Trailway Excavation and Embankment.

Contractor will have the creative freedom of fitting a new trail alignment within a set distance on either side of the Government flagged route, as approved ON THE GROUND by the CO prior to constructing new trail improvements. Contractor shall expect 30-40% side slopes throughout along with areas predominately comprised of rocks and talus sections. Any deviations to the approved ON

THE GROUND route shall be in writing from the CO.

Construct embankments with suitable compacted material. Compact all disturbed soil within the trailbed area.

When encountering rocks, remove surface rocks that are larger than 2 inches at their greatest dimension, and rocks that project more than 2 inches above the surface of the trail tread, when removal can be accomplished by hand or with a mini-excavator using reasonable effort, or when rocks can be pried out with a pick mattock, shovel, pry bar, or similar tool. Where the trailbed consists predominantly of rock with little or no soil present, remove loose rock in excess of 3 inches.

Protruding rocks in trail tread that are too large to be pried out with a pick, bar, or reasonable means with a mini excavator using reasonable effor, shall be removed using a hoe ram or other approved means in accordance with Section 912.60, unless these protruding rocks are approved in writing by the CO to remain in place to create a more desirable trail experience for users.

Contractor shall assume these “to remain in place” instances are limited and provide adequate equipment capable for removing protruding rocks down to the level of the tread surface. Fill any resulting depressions with suitable material and compact by tamping. Also remove any rock within or above the backslopes that is unstable. If rock removed is not needed for other items of work, scatter the rock by side-casting to the lower side of the trailway and beyond the clearing limits and distribute rock to ensure that no blockage of drainage or creation of windrow occurs.

Also ensure that rocks are nested into adjacent soil to render stable condition to prevent rolling down the hillside. Do not dispose any waste material in water courses.

When encountering roots, remove exposed tree roots on or in the trail tread that are greater than

1 inch in diameter, unless these protruding roots are approved in writing by the CO to remain in place to create a more desirable trail experience for users. Contractor shall assume these “to remain in place” instances are limited and remove embedded roots that project more than 2 inches above the trail tread flush with the trail tread. Scatter removed roots on the lower side of the trailway beyond the clearing limits and outside of water courses.

Leave the finished slope in a uniform and roughened condition.

911.10.05_sawtooth_02_15_2018

911.10.05 Trailbed Finish.

Contractor shall render entire trailbed excavated to the required slopes/grades AS SHOWN ON THE

PLANS and compacted so no vertical displacement or rutting is observed. With the exception of talus trail sections and shallow ford crossings, all remaining work associated with finishing the trailbed to have a smooth, uniform finish will be performed by others.

912 - Clearing Limits

912.00.01_sawtooth_02_15_2018

Delete the last subsection reference under this section and replace it with the following:

Section 912.60. Rock Removal

912.10.01_sawtooth_02_15_2018

912.10.01 This work consists of grubbing, and removing trees, logs, limbs, branches, stumps, brush, plants, and other vegetation within the limits of disturbance (clearing limits). Work also includes the protection from injury or defacement of trees and other objects not designated for removal.

All tree felling and tree limbing-related work will be done by others. Contractor shall coordinate having this “by others” work completed a minimum of 48 hours prior to commencing work on new trail elements.

912.60_sawtooth_02_15_2018

Replace this subsection in its entirety and with the following:

912.60 – Rock Removal

912.60.01. This work consists of the removal and disposal of rock outcroppings or other large rocks from the trail tread that require a hoe ram or other specialized equipment to remove to accommodate the new trail alignment, not including talus trail section work.

912.60.02. Contractor shall notify the CO prior to commencing work on trail sections through rock outcropping or locations where large rocks are present. The CO will make the determination as to whether this rock removal work exceeds the customary reasonable removal effort noted in Section 911.10.04. If so, limits will be determined and agreed to by the CO and the Contractor ON THE GROUND prior to beginning work.

Following rock removal, fill any resulting depressions with suitable material and compact by tamping. If rocks removed are not needed for other items of work, scatter the rock by side-casting to the lower side of the trailway and beyond the clearing limits and distribute rock to ensure that no blockage of drainage or creation of windrow occurs. Also ensure that rocks are nested into adjacent soil to render stable condition to prevent rolling down the hillside. Do not dispose any waste material in water courses.

Maintain trail tread to the width as SHOWN ON THE PLANS.

Measurement

912.60.04 Measure Rock Removal according to subsection 906. Both the CO and Contractor shall mutually agree on the Rock Removal quantity prior to commencing with any required hammering or specialized removal equipment use/work.

912.60.05 The accepted quantities for Rock Removal will be paid at the contract price per unit of measurement listed in the bid schedule. Payment will be full compensation for the work prescribed in this section. See Subsection 906.04.

915 – Talus Section

915.00_sawtooth_02_15_2018

Replace this section in its entirety with the following:

915.00.01 This work consists of constructing a talus trail section utilizing in situ material and includes hauling, placing of rock and leveling course aggregate, compacting through talus or rubble rock sections of trail, and all finishing related work.

Materials

915.00.02 Materials. Use materials meeting the requirements of the following sections:

Rock, Grid Pavement Units, and Aggregate 991

Geosynthetics 994

Material for Timber Structures 995

915.00.03 Preparation of Subgrade. Prepare trailbed as required under section 911. Obtain written approval of the CO before placing leveling course aggregate.

915.00.04 Talus or Rubble Rock Sections. Through talus or rubble rock slide areas, fill all voids with suitable material. Use cap rocks that weigh a minimum of 130 lbs and have a length of at least twice their width. At least 50 percent of all hand-placed outer rocks should weigh a minimum of 130 lbs. Construct tread by building out rather than by removing material from the inner bank.

915.00.05 Measure the section 915 items listed in the bid schedule according to subsection 906.

915.00.06 The accepted quantities will be paid at the contract price per unit of measurement for the section 915 pay items listed in the bid schedule. Payment will be full compensation for the work prescribed in this section. See Subsection 906.04.

917 - Fords

917.00_sawtooth_02_15_2018

Delete this section in its entirety and replace it with the following:

917.00.01 This work consists of constructing armored fords utilizing in situ material and includes all required hauling, compaction, placement of rock/aggregate, rock retainers, rock check dams, and approach sections as required, and all finishing-related work.

917.00.02 Materials. Use materials meeting the requirements of the following sections:

917.00.03 Preparation of Subgrade. Prepare trailbed as required under section 911 and 912 and/or as SHOWN ON THE PLANS. Obtain written approval of the CO before placing rock features.

917.00.04 Rock Retainers and Check Dams Construct rock retainers and check dams in accordance with Section 911.70 and Section 928.10 respectively, and as SHOWN ON THE

PLANS.

917.00.05 Measure the section 917 items listed in the bid schedule according to subsection 906.

917.00.06 The accepted quantities will be paid at the contract price per unit of measurement for the Section 917 pay items listed in the bid schedule. Payment will be full compensation for the work prescribed in this section. See Subsection 906.04.

927 – Drain Dips

927.00_sawtooth_01_15_2018

927.00.01 This work consists of constructing drainage dips along the length of the new trail alignment where required. Work also includes constructing rock spillways on the downhill side of the drainage dips for erosion protection.

927.00.02 Materials. Use materials meeting the requirements of the following sections:

927.00.03 General. Construct drainage dips at locations SHOWN ON THE PLANS or

DESIGNATED ON THE GROUND. Use in situ gabion rock consisting of a mixture of 4” to 8” dimensional material to construct drainage spillways on the downhill side of drainage dips in accordance with Section 923.

927.00.04 Excavation and Embankment. Perform excavation and embankment in accordance with Section 911.

927.00.05 There will be no separate measurement for this item.

927.00.06 Drain dips and other required work will be considered incidental to Section 911 pay items list in the bid schedule, and additional payment will not be made.

931 - Switchbacks

931.00_sawtooth_01_15_2018

931.00.01 This work consists of constructing switchbacks having banked berm corners including construction of associated barriers, ditches, retaining walls, and approach drainage and grading as applicable.

931.00.02 Materials. Conform to the following Sections and Subsections:

931.00.03 Excavation and Embankment. Perform excavation and embankment in accordance with Section 911.

931.00.04 Retaining Walls. Construct retaining walls, if necessary, in accordance with Section

935.

931.00.05 Barriers. Construct stacked rock or timber barriers, if necessary, at each switchback in accordance with Section 933.

931.00.06 Ditches. Construct ditches in accordance with Section 925.

931.00.07 Berms. Construct berm along the in-sloped turn section of the switchback in accordance with Section 926. Compound berms may be needed depending upon presence of compound horizontal trail alignment entering and existing switchback. Coordinate layout with

CO prior to construction.

931.00.08 Limits of Switchback. Beginning and ending of switchback will be DESIGNATED

ON THE GROUND.

931.00.09 Measure the Section 931 items listed in the bid schedule according to section 906.

931.00.10 The accepted quantities will be paid at the contract price per unit of measurement for the Section 931 pay items listed in the bid schedule. Payment will be full compensation for the work prescribed in this Section. See Subsection 906.04.