Text version
SOLICITATION, OFFER,
AND AWARD
2. TYPE OF SOLICITATION
6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.
PAGE OF PAGES
7. ISSUED BY CODE 8. ADDRESS OFFER TO
SOLICITATION
(Construction, Alteration, or Repair)
1. SOLICITATION NO. 3. DATE ISSUED
IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.
9.
INFORMATION
a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."
CALL:
FOR
SEALED BID (IFB)
NEGOTIATED (RFP)
966950
ALASKA REGIONAL OFFICE
709 WEST 9TH STREET
JUNEAU AK 99802
See body of SF-1442
MARI MEINERS 907-586-8746
108/14/2019
12010919R0008
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)
11. The Contractor shall begin performance
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and is not required.is, b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
d. Offers providing less than
12b. CALENDAR DAYSYES NO
(If "YES", indicate within how many calendar days after award in Item 12b.)
10 0 calendar days and complete it within ________________ ________________ calendar days after receiving
Section F.1
09/13/2019
NSN 7540-01-155-3212
x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________
STANDARD FORM 1442 (Rev. 4-85)
Prescribed by GSA
FAR(48 CFR) 53.236-1(d)
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)
16. REMITTANCE ADDRESS (Include only if different than item 14.)
CODE FACILITY CODE
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGEMENT OF AMENDMENTS
OFFER (Must be fully completed by offeror)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this document and return (Contractor is not required to sign this document.)
Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award.
No further contractual document is necessary.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31a. NAME OF CONTRACTING OFFICER (Type or print)
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE
BY
2PAGE OF
ALASKA REGIONAL OFFICE
709 WEST 9TH STREET
JUNEAU AK 99802
28. NEGOTIATED AGREEMENT 29. AWARD
Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, copies to issuing office.)
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
STANDARD FORM 1442 (REV. 4-85) BACK
Continued...
ITEM NO.
(A)
SUPPLIES/SERVICES
(B)
QUANTITY
(C)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
NAME OF OFFEROR OR CONTRACTOR
3 30
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
12010919R0008
This requirement is for improvements at the Lena
Beach Recreation Area.
A bid guarantee is required in accordance with
52.228-1. Offers may be hand delivered, mailed or emailed to mari.meiners@usda.gov. The bid guarantee must be delivered to the Contracting
Officer at one of the following addresses no later than the date and time set for receipt of offers:
US Postal Service Delivery:
US Forest Service
Attn: Mari Meiners
PO Box 21628
Juneau AK 99802
FedEx/UPS/DHL/Hand Delivery:
US Forest Service
Attn: Mari Meiners
709 W. 9th Street
5th Floor Mailroom
Juneau AK 99801
Bid guarantees must be delivered to one of the addresses listed above and may not be emailed or faxed. Offerors are advised that their SAM account must be active at the date and time set for receipt of proposals. If it is not active, the government cannot consider its offer.
No site visit is planned. Interested parties may visit the site at their convenience.
Delivery: 08/31/2020
Delivery Location Code: 0114
USDA FOREST SERVICE
TONGASS NF SITKA OFFICE
2108 HALIBUT POINT
SITKA AK 99835 US
0001 Lena Beach Recreation Area Improvements
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
12010919R0008 – Lena Beach Recreation Area Reconstruction Project, Juneau Ranger District, Tongass National Forest
PART 1 - THE SCHEDULE
SECTION B - SUPPLIES OR SERVICES AND PRICES/COSTS
Lena Beach Recreation Area Reconstruction Project, Phase II Juneau Ranger District, Tongass National Forest Juneau, Alaska
B.1 SCHEDULE OF ITEMS
Base Item
Item No.
Description Qty Unit Price
0001 BASE ITEMs 0001A Mobilization 1 Lump Sum $ 0001B Old Shelters 1 & 2 demolition, New Shelter 1 construction and associated work.
1 Lump Sum
0001C Old Shelter 5 demolition, New Shelter 5 construction and associated work.
1 Lump Sum
0001D Old Shelter 4 demolition, New Shelter 4 (group shelter) construction and associated work.
0001E Old Picnic Site 1 demolition, New picnic sites 1 & 2 construction and associated site work.
1 Lump Sum
0001F Host site water, electrical, site furnishings, and associated work; Public water faucet installation and associated work.
1 Lump Sum
0001G Asphalt concrete pavement, striping, wheel stops installation, and related work.
Total Base $
Option Items 0002 Resurface existing pathways and pads with crusher fines.
1 Lump Sum
0003 Install Hot Coal Bins at all 4 small shelters, located on the rear outside corner of the concrete grill pad.
4 EA
Total All Options
Total of Base and Options $
B-2 NOTE: Payment for bond premiums in accordance with Clause 52.232-5, Payments under Fixed- Price Construction Contracts, shall not be in addition to the contract price. Include bond premium under Mobilization. Offerors must submit prices for all items included in the schedule. Mobilization does not include on-site construction activities including the movement of personnel, materials or equipment within the project site.
Payment will be made on actual work performed as described in FP-14 109.01, unless otherwise noted.
Payment will be made only for those items listed in the Schedule. All other work is incidental.
Additional Vendor Information for Contract Administration
Contact Name:
Phone No:
Signature:
Cell Phone No:
DUNS No:
Email:
SAM Account Expiration Date:
SECTION C - DESCRIPTION/SPECIFICATIONS/WORK STATEMENT
C.1 PROJECT DESCRIPTION AND LOCATION
(a) Description: This contract is for site improvements at the Lena Beach Recreation Area in Juneau, Alaska.
(b) Work Items: Major work items are site work including asphalt surfacing, aggregate pathways and pads;
demolition including picnic shelters, picnic sites and concrete staircase; construction work including picnic shelters, concrete work, site furnishings, utilities, and signs; and other miscellaneous work.
Specific Schedule Items include:
Base Item:
1. Mobilization
2. Old Shelters 1 & 2 demolition, New Shelter 1 construction and associated work.
3. Old Shelter 5 demolition, New Shelter 5 construction and associated work.
4. Old Shelter 4 demolition, New Shelter 4 (group shelter) construction and associated work.
5. Old Picnic Site 1 demolition, New Picnic sites 1 & 2 construction and associated site work
6. Host site water, electrical, site furnishings, and associated work; Public water faucet installation and associated work.
7. Asphalt concrete pavement, striping, wheel stops installation and related work
Option Items:
8. Resurface existing pathways and pads with crusher fines.
9. Install Hot Coal Bins at all 4 small shelters, located on the rear outside corner of the concrete grill pad.
(c) Location and Utilities: The project is located in Juneau, AK approximately 7 miles northwest of the Juneau airport. The project may be accessed from State Glacier Highway and Lena Loop Road.
Utilities are not available at the site but are in the vicinity; the Contractor is responsible for connection.
(d) Climate: Southeast Alaska including Juneau has a cool and moist maritime climate. This maritime climate results in cool summers, moderate winters, considerable precipitation distributed throughout the year, and a high percentage of overcast days. Precipitation amounts vary widely throughout Southeast Alaska. All field workers should be prepared for wet, cool conditions. Interested parties are encouraged to independently research weather conditions for the area.
(e) Access: Juneau is located in the Southeast Alaska Panhandle with no road access. Vehicles and equipment can be brought to Juneau by barge or the Alaska Marine Highway System (check with AMHS for schedules and size/weight restrictions). Air service is currently provided by Alaska Airlines year round, Delta Airlines in the summer only and several commuter air carriers.
(e) Price Range: Between $500,000 and $750,000
(f) Pre-Proposal Tour: A preproposal site visit is not anticipated. Interested parties may visit the site at their convenience – no advance notice is required.
(g) Period of Performance: See Section F, Clause 52.211-10.
C.2 TECHNICAL SPECIFICATIONS
(a) The technical specifications included in Section J are hereby made part of this solicitation and any resultant contract.
(b) The requirements contained in the following documents are hereby made a part of this solicitation and any resultant contract.
1. The Federal Highways Administration Standard Specifications for Construction of Roads and
Bridges on Federal Highway Projects, FP-14 (abbreviated in these specifications as FP-14), are included by reference. An electronic copy is available upon request.
2. FOREST SERVICE STANDARD SPECIFICATIONS FOR CONSTRUCTION OF TRAILS AND
TRAIL BRIDGES ON FOREST SERVICE PROJECTS, 10/30/2014. Note that this version supersedes EM-7720-103, Standard Specification for Construction and Maintenance of Trails (1996). Copies of the Forest Service Specifications can be purchased from: Government Printing Office, 915 Second Ave. Seattle, WA 98174, (206) 553-4270.Or may be viewed online at:
FS/Trail_Specifications.pdf
3. The Forest Service Outdoor Recreation Accessibility Guidelines 2013 (FSORAG), available online at: FSORAG.
4. The Architectural Barrier Act Standards. ABA Accessibility Standards may be viewed online at:
ABAAS.
5. Forest Service Handbook Alaska Region (R10) Juneau AK. FSH2509.22 Soil and Water Conservation Handbook for National Forest System Lands in Alaska. R-10 Amendment 2509.22- 2006-2.
6. USDA Forest Service National Best Management Practices (BMPs) for Water Quality Management on National Forest System Lands. Vol 1: National Core BMP Technical Guide, FS-990a.
7. MUTCD Manual on Uniform Traffic Control Devices, 2009 (including 2012 revisions)
8. EM 7100-15, Sign and Poster Guideline for the Forest Service.
C.3 AGAR 452.211-72 Statement of Work/Specifications
The Contractor shall furnish the necessary personnel, material, equipment, services, and facilities to perform the Statement of Work/Specifications referenced in Section J.
http://www.fs.fed.us/recreation/programs/trail-management/documents/plans/supporting_documents/Trail_Specifications.pdf http://www.fs.fed.us/recreation/programs/trail-management/documents/plans/supporting_documents/Trail_Specifications.pdf https://www.fs.fed.us/recreation/programs/accessibility/FSORAG_2013%20Update.1.docx https://www.fs.fed.us/recreation/programs/accessibility/FSORAG_2013%20Update.1.docx https://www.access-board.gov/guidelines-and-standards/buildings-and-sites/about-the-aba-standards/aba-standards https://www.access-board.gov/guidelines-and-standards/buildings-and-sites/about-the-aba-standards/aba-standards
C.4 Additional Contract Requirements
(a) Historic Properties. This area does not contain known historic properties. If a previously unidentified archaeological or historic site(s) is encountered, the contractor shall discontinue work in the general area of the site(s) and notify the contracting officer immediately. See also AGAR 452.236-73 (Section I)
(b) Landscape Preservation
1. The Contractor shall give attention to the effect of contract operation upon the landscape, shall take care to maintain natural surroundings undamaged, and shall conduct the work at all times in compliance with the following requirements.
2. The Contractor shall not remove, deface, injure, or destroy trees, shrubs, lawns, or other natural features or any other improvements in the work area unless specifically authorized by the Contracting Officer.
3. Confine operations to within the clearing limits or other areas designated in contract documents, and prevent the depositing of rocks, excavated materials, stumps, or other debris outside of these limits. Unless otherwise agreed to by the CO, retrieve material which falls outside of these limits and either incorporate the material in the work or dispose of the material as directed by the CO.
4. Protection of Streams, Lakes, and Reservoirs. Submit a stream protection plan and receive approval from the CO, in writing, prior to the beginning of construction. The Contractor shall take sufficient precautions, including providing all necessary materials and labor, to prevent pollution of streams (wet or dry), lakes, small ponds, and reservoirs with fuels, oils, bitumens, calcium chloride, silt, or other harmful materials. Mechanical equipment shall not be operated in live streams without written approval of the Contracting Officer.
5. Do not discharge pollutants such as raw sewage, and other harmful materials into or near rivers, streams, and impoundments or into natural or manmade channels leading thereto. Do not allow wash water or waste water from concrete or aggregate operations to enter live streams prior to treatment by filtration, settling, or other means sufficient to reduce the sediment content to not more than that of the stream into which it is discharged.
6. Collect and return waste motor oils, fuels, lubricants, bitumens and similar hydrocarbons to the supplier. Comply with the requirements of 40 CFR 279, Standards for the Management of Used Oil.
Do not discharge hydrocarbon products on the ground, use them for road oiling, or bury them in a landfill.
7. Do not operate mechanized equipment in live streams without written approval of the Contracting Officer.
(c) Use of Premises
1. Use of Site: Limit use of premises to work in areas indicated. Do not disturb portions of site beyond areas in which the Work is indicated.
2. Limits: Confine construction operations to designated work areas or as approved by the CO.
3. Government Access: Allow for Government access to the site.
4. Driveways and Entrances: Keep driveways and entrances serving premises clear and available to
Government employees and emergency vehicles at all times. Do not use these areas for parking or storage of materials unless approved by CO.
5. Camping is not permitted at the project site.
6. Areas for staging operations and storage of materials shall be approved by the CO. The Contractor must request in writing for approval from the CO to stage work trailers on site.
7. Sanitation Facilities: Provide and maintain the following facilities for the work force at the work site, unless provided otherwise.
8. Handwashing and other potable water facilities are not currently available but potable water sources will be installed under this contract. Meet State of Alaska drinking water regulations 18 AAC 80 regarding potable water supplies for drinking and washing prior to installation of potable water facilities.
9. Fuel and hazardous material storage: Meet the requirements of 40 CFR 112 (Oil Pollution Prevention) for fuel storage. Meet the requirements of 33 CFR 150 and 33 CFR 154 for facilities transferring oil or hazardous materials in bulk.
(d) Availability and Use of Utility Services. Utilities are not available at the site for construction purposes. If needed, the Contractor will be responsible for coordinating with the City and Borough of Juneau or applicable utility company for the installation of temporary power for the site and the cost for the service.
(e) Notification of Work Schedule
1. At the pre-work meeting provide a proposed schedule of work showing dates of major work items, camp establishment, sample work and subgrade approval, helicopter operations and other main items of work.
2. Call the COR on the telephone each week when work is proceeding to discuss the work for the upcoming week and onsite inspection requirements. Call on Monday morning or at another mutually agreeable time.
(f) Equipment Cleaning
1. All construction equipment shall be pressure washed before entering National Forest System lands. The removal of mud and debris from treads, tracks and undercarriage, with emphasis on axles, frame, cross-members, motor mounts, and underneath steps, running boards, and front bumper/brushguard assemblies will be required. The purpose is to reduce or eliminate the transportation of noxious weeds, which is required by Federal and State regulations.
2. Contractor shall advise Forest Service of its cleaning measures and make the equipment available for inspection prior to mobilization to project site. Forest Service shall have 2 days, excluding weekends and Federal holidays, to inspect equipment after it has been made available. After satisfactory inspection or after such 2 day period, Contractor may move the equipment as planned.
Equipment shall be considered clean when a visual inspection does not disclose seeds, soil, vegetative matter, and other debris that could contain or hold seeds. Contractor shall not be required to disassemble equipment unless directed to do so by CO.
(g) Construction Loads on Roadways. Contractors are cautioned that the roadway structure is designed so that the completed road will support highway legal loads during a limited use season. Construction equipment often subjects the uncompleted roadway structure to loadings it is not designed to support.
This is especially critical during periods of excessive moisture. Materials on this project are sensitive to excessive moisture and will require careful selection and scheduling of equipment to permit efficient operation. Any damage resulting from operations, which renders the material unsuitable for use or results in potential siltation of streams, will be corrected by the Contractor at Contractor's expense.
(h) Traffic Control
1. The Contractor shall provide, erect and maintain all necessary barricades, suitable and sufficient lights, danger signals, signs, and other traffic control devices, and shall take all necessary precautions for the protection of the work and safety of the public. When allowed by Section H.11 – Public Access to the Area, close the Lena Cove Road (FSR8451) and the Lena Beach Recreation Area to the public. Provide effective, professional-appear closure signs and barriers at typical points of public access to the site. Roads closed to traffic shall be protected by effective barricades, and obstructions shall be illuminated during the hours of darkness. Suitable warning signs shall be provided to properly control and direct traffic. Post signs along the Lena Loop Road and Glacier Highway indicating that the Lena Beach Recreation Area is closed during periods that construction requires closing the site.
2. The Contractor shall erect warning signs in advance to any place on the project where operations may interfere with the use of the road or trail by traffic and at all intermediate points where the new work crosses or coincides with an existing road or trail. All road barricades, warning signs, lights, temporary signals, flagman and pilot car operators and equipment, and other protective devices, except for special devices, shall conform with Part VI of the Manual on Uniform Traffic Control Devices for Streets and Highways, published by the Federal Highway Administration and applicable safety codes.
(i) Emergency Control (see also AGAR 452.236-77, Emergency Response)
1. Immediately extinguish, without expense to the Government, all fires on or in the vicinity of the project which are caused by the Contractor's employees, whether set directly or indirectly as a result of construction operations, with or without direction by the Forest Service. The Contractor may be held liable for all damages and costs of additional labor, subsistence, equipment, supplies, and transportation deemed necessary by the Government resulting from fires set or caused by Contractor's employees or resulting from construction operations.
2. Contractor's Responsibility for Controlling Other Emergencies - When requested by the Contracting Officer, allow the Forest Service to temporarily use employees and equipment for emergency control work. Payment will be made at not less than the current area rate established by the Forest Service.
3. Fire fighting equipment will be required during the fire season from May 10 to August 31, and during any other period of fire danger designated by the Contracting Officer.
4. Furnish rust-free fire tools to equip all workers employed in Contractor's operations at each separate work site. Maintain tools in serviceable condition and keep tools in one or more weather-tight fire tools boxes. Paint fire tools boxes red, mark "tools for Fire Only" with letters at least 3” high, and keep sealed. Post a list of the contents inside each fire tool box so as to be visible when opened.
5. Kind of tool:
Tool No. of People Working in Area 1-4 5-9 10-15 16-20 Axe, d, b chopping, 32 inch min handle
1 1 2 3
Shovels, LHRP, No 0 or Larger
1 3 6 7
Pulaski, 32 inch min handle
2 3 7 10
File, 10 inch mill bastard
1 1 1 2
Pumps, backpack cans, 5 gal filled with water
1 2 2 3
6. Equip each internal combustion engine with a spark arrester qualified and rated USDA-Forest
Service, Standard 5100-1, unless it is:
i. Equipped with a turbine-driven exhaust supercharger such as the turbocharger. There shall be no exhaust bypass.
ii. A multi-position engine, such as on a chain saw, which is equipped with screen arrester, as described in the Forest Service Spark Arrester guide.
iii. A spark arrester, which does not meet the requirements in this guide may be approved upon submission of acceptable proof that the arrester is at least 80 percent efficient in retention, attrition, or destruction of carbon particles. Such arrester may be required to meet higher standards as improvements in design and efficiency are discovered.
iv. A passenger-carrying vehicle or light truck intended primarily for use on roads, and equipped with a factory designed muffler and exhaust system.
v. A heavy duty truck, such as a dump or log truck, or other vehicle used for commercial hauling, used only on roads and equipped with a factory designed muffler and with a vertical stack exhaust system extending above the cab.
vi. Properly install and constantly maintain in serviceable condition all exhaust equipment described in this Subsection, including spark arresters and mufflers.
vii. Equip each unit of mobile or stationary power equipment, including trucks, with one shovel, and at least one fire extinguisher meeting one of the following specifications:
1. 2-1/2 pound size or larger dry chemical type.
2. 4-pound size or larger carbon dioxide type.
3. Test or check each extinguisher for proper functioning prior to the beginning of fire precautionary period.
4. Provide each gasoline power saw with one chemical-pressurized fire extinguisher of not less than 8-ounce capacity by weight. Maintain the extinguisher in good working order at all times.
viii. Do not burn camp refuse, brush, slash, or debris such as that resulting from clearing around camps or on rights-of-way, without the written approval of the Contracting Officer. Submit written requests for burning to the Contracting Officer at least 48 hours in advance of intended burning. The Contracting Officer will approve routine camp refuse disposal incineration in the camp development proposal.
(j) Public Access to the Area. The Lena Beach Recreation Area, including all site elements (shelters, picnic areas, paths, toilet buildings, roadway, and parking areas), which are not actively under construction, will remain open to the public throughout the duration of the project. Ensure traffic control measures (per Section C.4(h) Traffic Control) are implemented to protect public health and safety, and to provide notice. Schedule operations to minimize disruption to visitors and to minimize area and time period during which areas are closed for construction. The Contractor may close the entire site for up to 14 consecutive days to allow for road base preparation and paving.
(k) Public Notification. Contractor is responsible for posting weekly Juneau Empire notifications, to be approximately 100 words and run for 4 weeks prior to start of construction through project completion.
Submit notices to the Contracting Officer for review at least 6 weeks prior to start of construction.
Juneau Empire notification of site closure, prior to paving preparation and paving, to run for at least 2 weeks prior to start of site closure.
(l) Special Note. The U.S. Department of Agriculture (USDA) prohibits discrimination in all its programs and activities on the basis of race, color, national origin, age, disability, and where applicable, sex, marital status, familial status, parental status, religion, sexual orientation, genetic information, political beliefs, reprisal, or because all or part of an individual’s income is derived from any public assistance program. (Not all prohibited bases apply to all programs.) Persons with disabilities who require alternative means for communication of program information (Braille, large print, audiotape, etc.)
should contact USDA's TARGET Center at (202) 720-2600 (voice and TDD). To file a complaint of discrimination, write to USDA, Director, Office of Civil Rights, 1400 Independence Avenue, S.W., Washington, DC 20250-9410, or call (800) 795-3272 (voice) or (202) 720-6382 (TDD). USDA is an equal opportunity provider and employer.
SECTION D--PACKAGING AND MARKING
D.1 PROJECT LABELING FOR OFFICIAL CORRESPONDENCE
The Government singularly identifies each project with a contract number at time of award. The contract number is a unique identifier to purposely and permanently represent an awarded project. The Government issued contract number is to be referenced on all official communication, to include emails, starting upon notice of award.
NOTE: Forest Service solicitation and contract identifiers are new effective 01 Oct 2017. The solicitation number, for this requirement, will include an “R” in the identifier. Solicitation numbers look like this:
12010918R0003. Contracts will have a similar identifier but will have a “C” in place of the “R”. Contract numbers look like this: 12010918C0010.
SECTION E--INSPECTION AND ACCEPTANCE
FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES
52.246-12 Inspection of Construction (AUG 1996)
Juneau Ranger District, Tongass National Forest
SECTION F--DELIVERIES OR PERFORMANCE
FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES
F.1 FAR 52.211-10 Commencement, Prosecution, and Completion of Work (APR 1984) The Contractor shall be required to commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed (anticipated for October 1, 2019), (b) prosecute the work diligently, and (c) complete the onsite work ready for use by August 31, 2020. The time stated for completion shall include final cleanup of the premises, and removal of all equipment.
F.2 NOTIFICATION OF WORK SCHEDULE
At the pre-work meeting provide a proposed schedule of work showing dates of major work items.
SECTION G--CONTRACT ADMINISTRATION DATA
G.1 AGAR 452.215-73 Post Award Conference (NOV 1996) A post award or pre-work conference with the successful offeror is required. It will be scheduled and held within a reasonable time after award and prior to any on-site work commences. Contractor will arrange this meeting with the Contracting Officer’s Representative (COR) and the Contracting Officer at a mutually agreeable date and time.
G.2 Electronic Invoicing and Payment Requirements – Invoice Processing Platform (IPP)
a. Payment requests must be submitted electronically through the U. S. Department of the Treasury's
Invoice Processing Platform (IPP). "Payment request" means any request for contract financing payment or invoice payment by the Contractor. To constitute a proper invoice, the payment request must comply with the requirements identified in the applicable Prompt Payment clause included in the contract. The IPP website address is: https://www.ipp.gov. The Contractor must use the IPP website to register, access and use IPP for submitting requests for payment. Contractor assistance with enrollment can be obtained by contacting the IPP Production Helpdesk via email IPPCustomerSupport@fms.treas.gov or phone (866) 973-3131.
b. Progress Payments. Along with each request for progress payments as authorized in 52.232-5(b), the contractor shall submit the contractor certification statement in paragraph (c) of the clause. Failure to provide the required certification will result in progress payment requests being rejected.
c. Final Payment. The final invoice must be accompanied by a release of claims against the Government arising by virtue of this contract, other than claims, in stated amounts, that the Contractor has specifically accepted from the operation of the release. Final payment will not be approved without a properly executed Contract Release.
d. In addition, when submitting the invoice, the Contractor shall submit payrolls, subcontractor payment information and a spreadsheet detailing the payment breakdown in accordance with the Items in the Schedule of Items, Section B.1 (either electronically in IPP, hard copy, or via email) to the Contracting Officer (see FAR 52.232-5 Payments Under Fixed Price Construction Contracts).
https://www.ipp.gov/ https://www.ipp.gov/ mailto:IPPCustomerSupport@fms.treas.gov mailto:IPPCustomerSupport@fms.treas.gov
G.3 Contract Administration
a. This contract will be administered by the Contracting Officer located at:
Alaska Region, Acquisition Management Attn: Mari Meiners 709 W 9th Street Juneau AK 99802-1628
b. All matters related to the performance of this contract shall be coordinated through the Contracting
Officer.
G.4 Designation of Contracting Officer's Representative
a. The Contracting Officer designates the Contracting Officer's Representative(s) (COR). The COR is responsible for administering the performance of work under this contract. In no event, however, will any understanding, agreement, modification, change order, or other matter deviating from the terms of this contract be effective or binding upon the Government unless formalized by proper contractual documents executed by the Contracting Officer prior to completion of the contract.
b. The Contracting Officer should be informed as soon as possible of any actions or inactions by the
Contractor or the Government which will change the required delivery or completion times stated in the contract, and the contract will be modified accordingly. (This does not apply to individual task assignments which were issued by the COR provided they do not affect the delivery schedule or performance period stated in the contract.)
c. On all matters that pertain to the contract terms, the Contractor must communicate with the Contracting
Officer. Whenever, in the opinion of the Contractor, the COR requests effort outside the scope of the contract, the Contractor should so advise the COR. If the COR persists and there still exists a disagreement as to proper contractual coverage, the Contracting Officer should be notified immediately, preferably in writing if time permits. Proceeding with work without proper contractual coverage could result in nonpayment or necessitate submittal of a contract claim.
G.5 Contractor’s Designated Representative It is required that the Contractor have a designated representative available on the project during the entire project and that the representative be able to speak and understand English. When designating a representative, the Contractor shall furnish a copy of the designation in writing to the Contracting Officer.
Such designation shall clearly indicate the name and limitations (if any) of authority of the representative. If the Contractor intends to designate a representative prior to the pre-work meeting, the representative is strongly encouraged to attend that meeting.
SECTION H--SPECIAL CONTRACT REQUIREMENTS
RESERVED
PART II--CONTRACT CLAUSES
SECTION I--CONTRACT CLAUSES
FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES
52.202-1 Definitions (NOV 2013) 52.203-3 Gratuities (APR 1984) 52.203-5 Covenant Against Contingent Fees (MAY 2014) 52.203-6 Restrictions on Subcontractor Sales to the Government (SEP 2006) 52.203-7 Anti-Kickback Procedures (MAY 2014) 52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity (MAY 2014) 52.203-10 Price or Fee Adjustment for Illegal or Improper Activity (MAY 2014) 52.203-12 Limitation on Payments to Influence Certain Federal Transactions (OCT 2010) 52.203-13 Contractor Code of Business Ethics and Conduct (OCT 2015) 52.203-17 Contractor Employee Whistleblower Rights and Requirement to Inform Employees of Whistleblower Rights (APR 2014) 52.204-4 Printed or Copied Double-Sided on Postconsumer Fiber Content Paper (May 2011) 52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards (OCT 2018) 52.204-13 System for Award Management Maintenance (OCT 2018) 52.204-14 Service Contract Reporting Requirements (OCT 2016) 52.204-18 Commercial and Government Entity Code Maintenance (JUL 2016) 52.204-19 Incorporation by Reference of Representations and Certifications (Dec 2014)
The Contractor’s representations and certifications, including those completed electronically via the System for Award Management (SAM), are incorporated by reference into the contract.
52.209-6 Protecting the Government's Interest when Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment (OCT 2015)
52.209-10 Prohibition on Contracting with Inverted Domestic Corporations (NOV 2015) 52.215-2 Audit and Records – Negotiation (OCT 2010) 52.217-7 Option for Increased Quantity – Separately Priced Line Item (Mar 1989) (Fill-in: Option Item #1- February 1, 2020; Option Item #2 – March 1, 2020) 52.219-6 Notice of Total Small Business Set-Aside (NOV 2011) 52.219-8 Utilization of Small Business Concerns (NOV 2016) 52.219-14 Limitations on Subcontracting (OCT 2018) 52.219-28 Post-Award Small Business Program Representation (JUL 2013) 52.222-3 Convict Labor (JUN 2003) 52.222-4 Contract Work Hours and Safety Standards -- Overtime Compensation (MAY 2018) 52.222-6 Construction Wage Rate Requirements (AUG 2018) 52.222-7 Withholding of Funds (MAY 2014) 52.222-8 Payrolls and Basic Records (AUG 2018) 52.222-9 Apprentices and Trainees (JUL 2005) 52.222-10 Compliance with Copeland Act Requirements (FEB 1988) 52.222-11 Subcontracts (Labor Standards) (MAY 2014) 52.222-12 Contract Termination - Debarment (MAY 2014) 52.222-13 Compliance with Construction Wage Requirements and Related Regulations (MAY 2014) 52.222-14 Disputes Concerning Labor Standards (FEB 1988) 52.222-15 Certification of Eligibility (MAY 2014) 52.222-21 Prohibition of Segregated Facilities (Apr 2015)
52.222-26 Equal Opportunity (Sep 2016) 52.222-27 Affirmative Action Compliance Requirements for Construction (Apr 2015) 52.222-35 Equal Opportunity for Veterans (OCT 2015) 52.222-36 Equal Opportunity for Workers With Disabilities (JUL 2014) 52.222-37 Employment Reports on Veterans (FEB 2016) 52.222-40 Notification of Employee Rights Under the National Labor Relations Act (DEC 2010) 52.222-50 Combating Trafficking in Persons (JAN 2019) 52.222-54 Employment Eligibility Verification (OCT 2015) 52.222-55 Establishing a Minimum Wage for Contractors (DEC 2015) 52.223-2 Affirmative Procurement of Biobased Products under Service and Construction Contracts
(SEP 2013)
52.223-3 Hazardous Material and Material Safety Data (JAN 1997) 52.223-5 Pollution Prevention and Right-to-Know Information (MAY 2011) 52.223-6 Drug-Free Workplace (MAY 2001) 52.223-9 Estimate of percentage of Recovered Material Content for EPA-Designated Products
(May 2008)
(a) Definitions. As used in this clause— “Postconsumer material” means a material or finished product that has served its intended use and has been discarded for disposal or recovery, having completed its life as a consumer item. Postconsumer material is a part of the broader category of “recovered material.”
“Recovered material” means waste materials and by-products recovered or diverted from solid waste, but the term does not include those materials and by-products generated from, and commonly reused within, an original manufacturing process.
(b) The Contractor, on completion of this contract, shall—
(1) Estimate the percentage of the total recovered material content for EPA-designated item(s) delivered and/or used in contract performance, including, if applicable, the percentage of postconsumer material content; and
(2) Submit this estimate to Mari Meiners at mari.meiners@usda.gov in the following certification statement:
Certification I, _______________ (name of certifier), am an officer or employee responsible for the performance of this contract and hereby certify that the percentage of recovered material content for EPA-designated items met the applicable contract specifications or other contractual requirements.
[Signature of the Officer or Employee] [Typed Name of the Officer or Employee] [Title] [Name of Company, Firm, or Organization] [Date]
52.223-17 Affirmative Procurement of EPA-designated Items in Service and Construction Contracts
(AUG 2018)
52.223-18 Encouraging Contractor Policies to Ban Text Messaging While Driving (AUG 2011) 52.225-9 Buy American Act-Construction Materials (MAY 2014)
(a) Definitions. As used in this clause— mailto:mari.meiners@usda.gov mailto:mari.meiners@usda.gov
“Commercially available off-the-shelf (COTS) item”—
(1) Means any item of supply (including construction material) that is—
(i) A commercial item (as defined in paragraph (1) of the definition at FAR 2.101);
(ii) Sold in substantial quantities in the commercial marketplace; and
(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and
(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products.
“Component” means an article, material, or supply incorporated directly into a construction material.
“Construction material” means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.
“Cost of components” means--
(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or
(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.
“Domestic construction material” means—
(1) An unmanufactured construction material mined or produced in the United States;
(2) A construction material manufactured in the United States, if—
(i) The cost of its components mined, produced, or manufactured in the United States exceeds 50 percent of the cost of all its components. Components of foreign origin of the same class or kind for which non-availability determinations have been made are treated as domestic; or
(ii) The construction material is a COTS item.
“Foreign construction material” means a construction material other than a domestic construction material.
“United States” means the 50 States, the District of Columbia, and outlying areas.
(b) Domestic preference.
(1) This clause implements the 41 U.S.C. chapter 83, Buy American, by providing a preference for domestic construction material. In accordance with 41 U.S.C. 1907, the component test of the Buy American statute is waived for construction material that is a COTS item. (See FAR 12.505(a)(2)).
The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.
(2) This requirement does not apply to information technology that is a commercial item or to the construction materials or components listed by the Government as follows: _none_ [Contracting Officer to list applicable excepted materials or indicate “none”]
(3) The Contracting Officer may add other foreign construction material to the list in paragraph
(b)(2) of this clause if the Government determines that
(i) The cost of domestic construction material would be unreasonable. The cost of a particular domestic construction material subject to the requirements of the Buy American statute is unreasonable when the cost of such material exceeds the cost of foreign material by more than 6 percent;
(ii) The application of the restriction of the Buy American statute to a particular construction material would be impracticable or inconsistent with the public interest; or
(iii) The construction material is not mined, produced, or manufactured in the United States in sufficient and reasonably available commercial quantities of a satisfactory quality.
(c) Request for determination of inapplicability of the Buy American statute.
(1)
(i) Any Contractor request to use foreign construction material in accordance with paragraph (b)(3) of this clause shall include adequate information for Government evaluation of the request, including--
(A) A description of the foreign and domestic construction materials;
(B) Unit of measure;
(C) Quantity;
(D) Price;
(E) Time of delivery or availability;
(F) Location of the construction project;
(G) Name and address of the proposed supplier; and
(H) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(3) of this clause.
(ii) A request based on unreasonable cost shall include a reasonable survey of the market and a completed price comparison table in the format in paragraph (d) of this clause.
(iii) The price of construction material shall include all delivery costs to the construction site and any applicable duty (whether or not a duty-free certificate may be issued).
(iv) Any Contractor request for a determination submitted after contract award shall explain why the Contractor could not reasonably foresee the need for such determination and could not have requested the determination before contract award. If the Contractor does not submit a satisfactory explanation, the Contracting Officer need not make a determination.
(2) If the Government determines after contract award that an exception to the Buy American statute applies and the Contracting Officer and the Contractor negotiate adequate consideration, the Contracting Officer will modify the contract to allow use of the foreign construction material.
However, when the basis for the exception is the unreasonable price of a domestic construction material, adequate consideration is not less than the differential established in paragraph (b)(3)(i) of this clause.
(3) Unless the Government determines that an exception to the Buy American statute applies, use of foreign construction material is noncompliant with the Buy American statute.
(d) Data. To permit evaluation of requests under paragraph (c) of this clause based on unreasonable cost, the Contractor shall include the following information and any applicable supporting data based on the survey of suppliers:
Foreign and Domestic Construction Materials Price Comparison Construction material description Unit of measure Quantity Price (dollars) * Item 1 Foreign construction material Domestic construction material Item 2 Foreign construction material Domestic construction material [List name, address, telephone number, and contact for suppliers surveyed. Attach copy of response; if oral, attach summary.] [Include other applicable supporting information.] [*Include all delivery costs to the construction site and any applicable duty (whether or not a duty-free entry certificate is issued).]
52.225-13 Restrictions on Certain Foreign Purchases (JUN 2008) 52.227-1 Authorization and Consent (DEC 2007) 52.227-2 Notice and Assistance Regarding Patent and Copyright Infringement (DEC 2007) 52.227-4 Patent Indemnity – Construction Contracts (DEC 2007) 52.228-1 Bid Guarantee. (Sep 1996) Fill-in: twenty percent (20%) of the bid price or $3 million, whichever is less.
52.228-2 Additional Bond Security (OCT 1997) 52.228-11 Pledges of Assets (JAN 2012) 52.228-12 Prospective Subcontractor Requests for Bonds (MAY 2014) 52.228-14 Irrevocable Letter of Credit (Nov 2014) 52.228-15 Performance and Payment Bonds – Construction (OCT 2010) 52.229-3 Federal, State, and Local Taxes (FEB 2013) 52.232-5 Payments under Fixed-Price Construction Contracts (MAY 2014) 52.232-17 Interest (MAY 2014) 52.232-23 Assignment of Claims (MAY 2014) 52.232-27 Prompt Payment for Construction Contracts (JAN 2017) 52.232-33 Payment by Electronic Funds Transfer – System for Award Management (OCT 2018) 52.232-39 Unenforceability of Unauthorized Obligations. (Jun 2013) 52.232-40 Providing Accelerated Payments to Small Business Subcontractors. (Dec 2013) 52.233-1 Disputes (MAY 2014) 52.233-3 Protest After Award (AUG 1996) 52.233-4 Applicable Law for Breach of Contract Claim (OCT 2004) 52.236-2 Differing Site Conditions (APR 1984) 52.236-3 Site Investigation and Conditions Affecting the Work (APR 1984) 52.236-5 Material and Workmanship (APR 1984) 52.236-6 Superintendence by the Contractor (APR 1984) 52.236-7 Permits and Responsibilities (NOV 1991) 52.236-8 Other Contracts (APR 1984) 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements
(APR 1984)
52.236-10 Operations and Storage Areas (APR 1984) 52.236-11 Use and Possession Prior to Completion (APR 1984) 52.236-12 Cleaning Up (APR 1984)
52.236-13 Accident Prevention (NOV 1991) 52.236-17 Layout of Work (APR 1984) 52.236-21 Specifications and Drawings for Construction (FEB 1997) Alternate I (APR 1984) 52.236-26 Preconstruction Conference (FEB 1995) 52.242-13 Bankruptcy (JUL 1995) 52.242-14 Suspension of Work (APR 1984) 52.243-4 Changes (JUN 2007) 52.244-6 Subcontracts for Commercial Items (JAN 2019) 52.246-21 Warranty of Construction (MAR 1994)
Alternate I (APR 1984) 52.248-3 Value Engineering -- Construction (OCT 2015) 52.249-2 Termination for Convenience of the Government (Fixed-Price) (APR 2012);
Alternate I (SEP 1996) 52.249-10 Default (Fixed-Price Construction) (APR 1984) 52.252-2 Clauses Incorporated by Reference (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): www.acquisition.gov/far/ www.usda.gov/procurement/policy/agar.html
52.253-1 Computer Generated Forms (JAN 1991)
AGRICULTURE ACQUISITION REGULATION (48 CFR CHAPTER 4) CLAUSES
452.228-70 Alternative Forms of Security (NOV 1996)
If furnished as security, money orders, drafts, cashier's checks, or certified checks shall be drawn payable to: USDA…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it.