114520 KRR_Dwnstrm_Scour_Rpr_Schedule_apprvd_2024-01-17.pdf

PDF 205 KB Posted

Attached to
Kissimmee River Restoration S-69 Weir Permanent Repair Scour
Solicitation number
W912EP24Z0026
Issued by

About this file

This document contains a federal contract opportunity announcement and project schedule for the Kissimmee River Restoration S-69 Weir Permanent Repair Scour project. The U.S. Army Corps of Engineers seeks a contractor to install scour countermeasures downstream of an existing weir structure, including placement of riprap stone and geotextile fabric, removal and replacement of existing riprap, backfilling scour holes, and regrating the channel. The estimated value is $5-10 million with a 480-day period of performance. Interested parties must submit capability statements by March 26, 2024 detailing relevant experience, technical skills, subcontracting experience, and bonding capacity. The NAICS code is 237990 and small business size standard is $45 million. The solicitation is expected to be issued on June 28, 2024 as a firm-fixed-price contract.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ID %

Complete

Task Name Duration Start Finish Baseline Start Baseline Finish Predecessors Responsible

Party

0 7% 114520 Kissimmee River Restoration S-69 Downstream Scour

Hole Repair

253 days Fri 8/25/23 Fri 9/6/24 Fri 8/25/23 Fri 9/6/24

1 34% PROJECT SETUP 67 days Mon 9/18/23 Wed 1/3/24 Mon 9/18/23 Wed 1/3/24

2 44% INITIAL SCOPING 26 days Mon 9/18/23 Tue 10/24/23 Mon 9/18/23 Tue 10/24/23

3 100% Attend PDT Kick-Off Meeting 1 day Mon 9/18/23 Mon 9/18/23 Mon 9/18/23 Mon 9/18/23 PDT

4 100% Coordinate/Establish SOW with PDT 5 days Tue 9/19/23 Mon 9/25/23 Tue 9/19/23 Mon 9/25/23 3 TL

5 100% Conduct Site Visit 10 days Tue 9/26/23 Tue 10/10/23 Tue 9/26/23 Tue 10/10/23 4 PDT

6 0% Develop Acquisition Strategy 20 days Tue 9/26/23 Tue 10/24/23 Tue 9/26/23 Tue 10/24/23 4 PDT

7 88% SCHEDULE 17 days Tue 9/26/23 Thu 10/19/23 Tue 9/26/23 Thu 10/19/23

8 100% Prepare Schedule and Coordinate with PDT 5 days Tue 9/26/23 Mon 10/2/23 Tue 9/26/23 Mon 10/2/23 4 TL

9 100% SUBMIT SCHEDULE FOR EN REVIEW 0 days Mon 10/2/23 Mon 10/2/23 Mon 10/2/23 Mon 10/2/23 8 TL

10 100% Review and Approve Schedule 10 days Tue 10/3/23 Tue 10/17/23 Tue 10/3/23 Tue 10/17/23 9 Chiefs

11 0% Update Schedule 2 days Wed 10/18/23 Thu 10/19/23 Wed 10/18/23Thu 10/19/23 10 TL

12 0% BASELINE SCHEDULE 0 days Thu 10/19/23 Thu 10/19/23 Thu 10/19/23 Thu 10/19/23 11 QM

13 7% REVIEW PLAN 45 days Thu 10/19/23 Wed 1/3/24 Thu 10/19/23 Wed 1/3/24

14 100% Prepare RP 3 days Thu 10/19/23 Mon 10/23/23 Thu 10/19/23 Mon 10/23/23 4 TL

15 0% SUBMIT RP FOR PRELIMINARY SAD REVIEW 0 days Mon 10/23/23 Mon 10/23/23 Mon 10/23/23Mon 10/23/23 14 TL

16 0% Review RP 10 days Tue 10/24/23 Mon 11/6/23 Tue 10/24/23 Mon 11/6/23 15 SAD

10/2

10/19

Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

114520 Kissimmee River Restoration S-69 Downstream Scour Hole Repair

Project: 114520 Kissimmee River R

Date: Wed 1/17/24

Task Name Duration Start Finish Baseline Start Baseline Finish Predecessors Responsible

Party

17 0% Update RP 2 days Tue 11/7/23 Wed 11/8/23 Tue 11/7/23 Wed 11/8/23 16 TL

18 0% ISSUE RP REQUEST MEMO TO SAD 0 days Wed 11/8/23 Wed 11/8/23 Wed 11/8/23 Wed 11/8/23 17 RM

19 0% Review and Approve RP 30 days Thu 11/9/23 Wed 1/3/24 Thu 11/9/23 Wed 1/3/24 18 SAD

20 0% ISSUE RP APPROVAL MEMO 0 days Wed 1/3/24 Wed 1/3/24 Wed 1/3/24 Wed 1/3/24 19 SAD

21 0% VALUE MANAGEMENT PLAN 10 days Tue 9/26/23 Tue 10/10/23 Tue 9/26/23 Tue 10/10/23

22 0% Prepare VMP 5 days Tue 9/26/23 Mon 10/2/23 Tue 9/26/23 Mon 10/2/23 4 VEO

23 0% Route VMP for Signature 5 days Tue 10/3/23 Tue 10/10/23 Tue 10/3/23 Tue 10/10/23 22 VEO

24 0% VMP APPROVED 0 days Tue 10/10/23 Tue 10/10/23 Tue 10/10/23 Tue 10/10/23 23 VEO

25 63% SCOPE OF WORK VERIFICATION 8 days Tue 9/26/23 Thu 10/5/23 Tue 9/26/23 Thu 10/5/23

26 100% Verify Project Authorization 5 days Tue 9/26/23 Mon 10/2/23 Tue 9/26/23 Mon 10/2/23 4 TL

27 0% Approve SOW 3 days Tue 10/3/23 Thu 10/5/23 Tue 10/3/23 Thu 10/5/23 26 TL

28 0% CONCEPTUAL PLANNING 33 days Mon 9/11/23 Thu 10/26/23 Mon 9/11/23 Thu 10/26/23

29 0% CONDUCT DESIGN CHARRETTE WITH SFWMD 1 day Fri 10/27/23 Fri 10/27/23 Fri 10/27/23 Fri 10/27/23 28

30 6% DATA ACQUISITION 86 days Tue 9/19/23 Thu 2/1/24 Tue 9/19/23 Thu 2/1/24

31 6% DEVELOPMENT 86 days Tue 9/19/23 Thu 2/1/24 Tue 9/19/23 Thu 2/1/24

32 100% Request and Establish ProjectWise Directory 5 days Tue 9/19/23 Mon 9/25/23 Tue 9/19/23 Mon 9/25/23 3 TL

33 0% SURVEY DATA ACQUISITION (A-E) 72 days Tue 10/10/23 Thu 2/1/24 Tue 10/10/23 Thu 2/1/24

34 0% Request 27 days Tue 10/10/23 Thu 11/16/23 Tue 10/10/23 Thu 11/16/23

11/8

1/3

10/10

Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

114520 Kissimmee River Restoration S-69 Downstream Scour Hole Repair

Task Name Duration Start Finish Baseline Start Baseline Finish Predecessors Responsible

Party

35 0% Develop SOW/IGE 5 days Tue 10/10/23 Mon 10/16/23 Tue 10/10/23 Mon 10/16/23 27 TL

36 0% Route RFP for Review and Approval 3 days Tue 10/17/23 Thu 10/19/23 Tue 10/17/23 Thu 10/19/23 35 PDT

37 0% Process RFP 3 days Fri 10/20/23 Tue 10/24/23 Fri 10/20/23 Tue 10/24/23 36 CT

38 0% Issue RFP 1 day Wed 10/25/23 Wed 10/25/23 Wed 10/25/23Wed 10/25/23 37 CT

39 0% Proposal 31 days Thu 10/26/23 Tue 12/12/23 Thu 10/26/23 Tue 12/12/23

40 0% Contracting 30 days Thu 10/26/23 Mon 12/11/23 Thu 10/26/23 Mon 12/11/23 38 A-E

41 0% Issue NTP 1 day Tue 12/12/23 Tue 12/12/23 Tue 12/12/23 Tue 12/12/23 40 CT

42 0% Performance 29 days Wed 12/13/23 Thu 2/1/24 Wed 12/13/23Thu 2/1/24

43 0% Execute Survey SOW 20 days Wed 12/13/23 Fri 1/19/24 Wed 12/13/23Fri 1/19/24 41 A-E

44 0% Perform Quality Assurance of Products 8 days Mon 1/22/24 Wed 1/31/24 Mon 1/22/24 Wed 1/31/24 43 A-E

45 0% Deliver Survey Products 1 day Thu 2/1/24 Thu 2/1/24 Thu 2/1/24 Thu 2/1/24 44 A-E

46 0% VALUE ENGINEERING STUDY (CONDUCT AS SOON AS P&S

DEVELOPMENT SUPPORTS)

45 days Wed 10/11/23 Fri 12/15/23 Wed

10/11/23

Fri 12/15/23

51 0% COST ESTIMATE 88 days Fri 3/29/24 Fri 8/2/24 Fri 3/29/24 Fri 8/2/24

52 0% Update Current Working Estimate 15 days Fri 3/29/24 Thu 4/18/24 Fri 3/29/24 Thu 4/18/24 70 PDT

53 0% Prepare Preliminary Time and Cost Estimate 15 days Thu 5/23/24 Thu 6/13/24 Thu 5/23/24 Thu 6/13/24 80 PDT

54 0% Develop Independent Government Estimate 15 days Mon 7/15/24 Fri 8/2/24 Mon 7/15/24 Fri 8/2/24 53,113FS-15 days,88PDT

55 0% FINAL PLANS & SPECIFICATIONS/DESIGN DOCUMENTATION REPORT142 days Fri 10/27/23 Thu 5/30/24 Fri 10/27/23 Thu 5/30/24

2/1

Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

114520 Kissimmee River Restoration S-69 Downstream Scour Hole Repair

Task Name Duration Start Finish Baseline Start Baseline Finish Predecessors Responsible

Party

56 0% DEVELOPMENT 85 days Fri 10/27/23 Mon 3/11/24 Fri 10/27/23 Mon 3/11/24

57 0% Review Water Resources Branch Input 10 days Fri 10/27/23 Thu 11/9/23 Fri 10/27/23 Thu 11/9/23 28

58 0% Draft Design Branch Input 20 days Fri 2/2/24 Fri 3/1/24 Fri 2/2/24 Fri 3/1/24 45 PDT

59 0% Draft Geotechnical Branch Input 20 days Fri 2/2/24 Fri 3/1/24 Fri 2/2/24 Fri 3/1/24 45 PDT

60 0% Team Review of Plans and Specifications 5 days Mon 3/4/24 Fri 3/8/24 Mon 3/4/24 Fri 3/8/24 58,59 PDT

61 0% COMPLETE DRAFT FINAL PLANS &

SPECIFICATIONS/DESIGN DOCUMENTATION REPORT

1 day Mon 3/11/24 Mon 3/11/24 Mon 3/11/24 Mon 3/11/24 58,59,60 TL

62 0% REVIEWS 100 days Tue 1/9/24 Thu 5/30/24 Tue 1/9/24 Thu 5/30/24

63 0% Notify Review Manager of ATR Review 1 day Tue 1/9/24 Tue 1/9/24 Tue 1/9/24 Tue 1/9/24 75FS-60 daysTL

64 0% CAD Compliance Review and Printing Plans 3 days Tue 3/12/24 Thu 3/14/24 Tue 3/12/24 Thu 3/14/24 61

65 0% Quantities and Measurement/Payment Review 3 days Tue 3/12/24 Thu 3/14/24 Tue 3/12/24 Thu 3/14/24 61

66 0% DQC 13 days Thu 3/14/24 Tue 4/2/24 Thu 3/14/24 Tue 4/2/24

67 0% QCR (Combined DQCR/PQCR) 13 days Thu 3/14/24 Tue 4/2/24 Thu 3/14/24 Tue 4/2/24

68 0% SUBMIT FOR QCR (FINAL P&S) 0 days Thu 3/14/24 Thu 3/14/24 Thu 3/14/24 Thu 3/14/24 65,64 PDT

69 0% Perform QCR (Comment Period) 5 days Fri 3/15/24 Thu 3/21/24 Fri 3/15/24 Thu 3/21/24 68 PDT

70 0% Incorporate QCR Comments 5 days Fri 3/22/24 Thu 3/28/24 Fri 3/22/24 Thu 3/28/24 69 PDT

71 0% Route QCR Certification 3 days Fri 3/29/24 Tue 4/2/24 Fri 3/29/24 Tue 4/2/24 70 TL

72 0% CERTIFY QCR (FINAL P&S) 0 days Tue 4/2/24 Tue 4/2/24 Tue 4/2/24 Tue 4/2/24 71 Chiefs

3/14

4/2

Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

114520 Kissimmee River Restoration S-69 Downstream Scour Hole Repair

Task Name Duration Start Finish Baseline Start Baseline Finish Predecessors Responsible

Party

73 0% ATR/SPONSOR REVIEW 41 days Wed 4/3/24 Thu 5/30/24 Wed 4/3/24 Thu 5/30/24

74 0% Apply CUI/EXEMPT Markings to P&S 1 day Wed 4/3/24 Wed 4/3/24 Wed 4/3/24 Wed 4/3/24 72 TL

75 0% SUBMIT FOR ATR/Sponsor Review (FINAL P&S) 0 days Wed 4/3/24 Wed 4/3/24 Wed 4/3/24 Wed 4/3/24 74 TL

76 0% Perform ATR/Sponsor Review (Comment Period) 15 days Thu 4/4/24 Wed 4/24/24 Thu 4/4/24 Wed 4/24/24 75 ATR Team

77 0% Evaluate/Incorporate ATR/Sponsor Review Comments 10 days Thu 4/25/24 Wed 5/8/24 Thu 4/25/24 Wed 5/8/24 76 PDT

78 0% Provide Updated Documents/Check-Set to Review Team10 days Thu 5/2/24 Wed 5/15/24 Thu 5/2/24 Wed 5/15/24 77FS-5 daysPDT

79 0% Backcheck/Close ATR/Sponsor Review Comments 10 days Thu 5/16/24 Thu 5/30/24 Thu 5/16/24 Thu 5/30/24 78 PDT

80 0% Incorporate Late Sponsor Comments 10 days Thu 5/9/24 Wed 5/22/24 Thu 5/9/24 Wed 5/22/24 77 PDT

81 0% Issue ATR Report 1 day Thu 5/9/24 Thu 5/9/24 Thu 5/9/24 Thu 5/9/24 77 ATR Team

82 0% Route ATR Certification 5 days Fri 5/10/24 Thu 5/16/24 Fri 5/10/24 Thu 5/16/24 81 RM

83 0% CERTIFY ATR (FINAL P&S) 0 days Thu 5/16/24 Thu 5/16/24 Thu 5/16/24 Thu 5/16/24 82 Chiefs

84 0% BCOES 41 days Wed 4/3/24 Thu 5/30/24 Wed 4/3/24 Thu 5/30/24

85 0% Prepare VE Certification Memo 10 days Wed 4/3/24 Tue 4/16/24 Wed 4/3/24 Tue 4/16/24 50,24,72 TL

86 0% SUBMIT FOR BCOES (FINAL P&S) 1 day Wed 4/3/24 Wed 4/3/24 Wed 4/3/24 Wed 4/3/24 72 TL

87 0% Perform BCOES (Comment Period) 15 days Thu 4/4/24 Wed 4/24/24 Thu 4/4/24 Wed 4/24/24 86 BCOES Team

88 0% Evaluate/Incorporate BCOES Comments 10 days Thu 4/25/24 Wed 5/8/24 Thu 4/25/24 Wed 5/8/24 87 PDT

89 0% Provide Updated Documents/Check-Set to Review Team10 days Thu 5/2/24 Wed 5/15/24 Thu 5/2/24 Wed 5/15/24 88FS-5 daysPDT

90 0% Backcheck/Close BCOES Comments 10 days Thu 5/16/24 Thu 5/30/24 Thu 5/16/24 Thu 5/30/24 89 PDT

4/3

5/16

Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

114520 Kissimmee River Restoration S-69 Downstream Scour Hole Repair

Task Name Duration Start Finish Baseline Start Baseline Finish Predecessors Responsible

Party

91 0% VE CERTIFICATION MEMO COMPLETE 0 days Tue 4/16/24 Tue 4/16/24 Tue 4/16/24 Tue 4/16/24 85 VEO

92 0% Route BCOES Certification 10 days Thu 5/9/24 Wed 5/22/24 Thu 5/9/24 Wed 5/22/24 88,91,50 EN-DC

93 0% CERTIFY BCOES (FINAL P&S) 0 days Wed 5/22/24 Wed 5/22/24 Wed 5/22/24 Wed 5/22/24 92 Chiefs

94 0% ISSUE FINAL PLANS & SPECIFICATIONS/DESIGN

DOCUMENTATION REPORT

0 days Wed 5/22/24 Wed 5/22/24 Wed 5/22/24 Wed 5/22/24 93 TL

95 0% P2 MILESTONE DATE CERTIFY BCOES (CW320) 0 days Wed 5/22/24 Wed 5/22/24 Fri 11/3/23 Fri 11/3/23

96 0% PROCUREMENT DOCUMENTS 203 days Tue 9/5/23 Fri 7/5/24 Tue 9/5/23 Fri 7/5/24

97 0% Request Procurement Package from PM 1 day Tue 9/5/23 Tue 9/5/23 Tue 9/5/23 Tue 9/5/23 EN-DC

98 0% Request Liquidated Damages from CD 1 day Fri 6/14/24 Fri 6/14/24 Fri 6/14/24 Fri 6/14/24 53 EN-DC

99 0% Provide Procurement Package to CT 3 days Mon 6/17/24 Thu 6/20/24 Mon 6/17/24 Thu 6/20/24 97,98 EN-DC

100 0% Receive Preliminary Contracting Fronts 10 days Fri 6/21/24 Fri 7/5/24 Fri 6/21/24 Fri 7/5/24 99 EN-DC

101 0% Provide Final P&S and BCOES Certifications to CT 1 day Thu 5/23/24 Thu 5/23/24 Thu 5/23/24 Thu 5/23/24 94 TL

102 0% Conduct Preliminary Review 2 days Fri 5/24/24 Tue 5/28/24 Fri 5/24/24 Tue 5/28/24 101 CT

103 0% Conduct Business Oversight Branch (BOB) Review 5 days Wed 5/29/24 Tue 6/4/24 Wed 5/29/24 Tue 6/4/24 102 CT

104 0% Perform Legal/Compliance Review 5 days Wed 6/5/24 Tue 6/11/24 Wed 6/5/24 Tue 6/11/24 103 OC

105 0% Incorporate Legal/Compliance Review Comments 4 days Wed 6/12/24 Mon 6/17/24 Wed 6/12/24 Mon 6/17/24 104 EN-DC

106 0% ISSUE CORRECTED FINAL - RTA PLANS &

SPECIFICATIONS/DESIGN DOCUMENTATION REPORT

0 days Mon 6/17/24 Mon 6/17/24 Mon 6/17/24 Mon 6/17/24 105 TL

4/16

5/22

5/22

5/22

6/17

Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

114520 Kissimmee River Restoration S-69 Downstream Scour Hole Repair

Task Name Duration Start Finish Baseline Start Baseline Finish Predecessors Responsible

Party

107 0% ADVERTISEMENT/AWARD 253 days Fri 8/25/23 Fri 9/6/24 Fri 8/25/23 Fri 9/6/24

108 0% RTA 0 days Mon 6/17/24 Mon 6/17/24 Mon 6/17/24 Mon 6/17/24 106 TL

109 0% Acquisition Strategy Finalized and Approved 5 days Fri 8/25/23 Thu 8/31/23 Fri 8/25/23 Thu 8/31/23 93FS-180 daysCT

110 0% Source Selection Plan Prepared/Reviewed/Approved (RFP) 25 days Fri 9/1/23 Fri 10/6/23 Fri 9/1/23 Fri 10/6/23 109 CT

111 0% Synopsis Posted 1 day Mon 7/15/24 Mon 7/15/24 Mon 7/15/24 Mon 7/15/24 113FS-15 daysCT

112 0% KO / Business Operations Board Review 10 days Tue 6/18/24 Tue 7/2/24 Tue 6/18/24 Tue 7/2/24 105 CT

113 0% Advertise 22 days Wed 7/3/24 Fri 8/2/24 Wed 7/3/24 Fri 8/2/24 112 CT

114 0% Initiate Construction Survey Task Order with EN-DG 1 day Tue 6/11/24 Tue 6/11/24 Tue 6/11/24 Tue 6/11/24 113SS-15 daysTL

115 0% AWARD 0 days Fri 9/6/24 Fri 9/6/24 Fri 9/6/24 Fri 9/6/24 113FS+24 daysCT

116 0% P2 MILESTONE DATE RTA (CW400) 0 days Fri 9/6/24 Fri 9/6/24 Fri 9/6/24 Fri 9/6/24 115

6/17

9/6

9/6

Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

114520 Kissimmee River Restoration S-69 Downstream Scour Hole Repair