11-Coan Building - Fee Sheet.pdf
PDF 119 KB Posted
- Solicitation number
- 26-040326-60-P-AW
- Issued by
- Fulton County, Georgia
About this file
This is a fee sheet for a Construction Manager at Risk (CMAR) contract with the Atlanta Independent School System for the Coan Building Administrative Consolidation Site Improvements project located in Georgia. The contract, identified as 26-040326-60-P-AW, outlines the scope of pre-construction and construction services to be provided by the selected construction manager. The pre-construction phase includes four deliverables: Schematic Design, Design Development, 100% Construction Documents, and Bidding/GMP Negotiations with Award of GMP Amendment. These tasks have tentative completion dates ranging from June 5, 2026, through August 10, 2026, establishing a timeline for design and procurement phases prior to construction execution.
The fee structure for pre-construction services is established as lump sum payments per task, with each of the four pre-construction phases compensated at $7,500.00, resulting in a total pre-construction fee of $30,000.00. The construction phase compensation structure includes a Construction Manager's Fee calculated as either a percentage of general conditions or as a percentage fee, though specific percentages and the final construction phase cost are not completed in this fee sheet. No additional information regarding set-asides, incumbent contractors, funding sources, or contract renewal options is provided in this document.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FEE SHEET
Construction Manager at – Risk
26-040326-60-P-AW Coan Building Administrative Consolidation Site Improvements
FIRM NAME:
DATE:
PRE-CONSTRUCTION
SERVICES
As compensation for pre-construction services, the CM shall receive a fee as negotiated below:
LUMP SUM FEE
(PER TASK)
COMPLETION/
DUE DATES
1. Schematic Design $7,500.00 6/05/2026 (Tentative)
2. Design Development. $7,500.00 6/15/2026 (Tentative)
3. 100% Construction Documents $7,500.00 7/10/2026 (Tentative)
4. Bidding / GMP, Submittal / GMP, Negotiations / Award of
GMP Amendment $7,500.00 8/10/2026 (Tentative)
TOTAL PRE- CONSTRUCTION FEE $30,000.00
CONSTRUCTION PHASE
6. Construction Manager’s Fee:
a. percent of general conditions
b. percent fee
PPAB 7401255v1