This is a fee sheet for a Construction Manager at Risk (CMAR) contract with the Atlanta Independent School System for the Coan Building Administrative Consolidation Site Improvements project located in Georgia. The contract, identified as 26-040326-60-P-AW, outlines the scope of pre-construction and construction services to be provided by the selected construction manager. The pre-construction phase includes four deliverables: Schematic Design, Design Development, 100% Construction Documents, and Bidding/GMP Negotiations with Award of GMP Amendment. These tasks have tentative completion dates ranging from June 5, 2026, through August 10, 2026, establishing a timeline for design and procurement phases prior to construction execution.

The fee structure for pre-construction services is established as lump sum payments per task, with each of the four pre-construction phases compensated at $7,500.00, resulting in a total pre-construction fee of $30,000.00. The construction phase compensation structure includes a Construction Manager's Fee calculated as either a percentage of general conditions or as a percentage fee, though specific percentages and the final construction phase cost are not completed in this fee sheet. No additional information regarding set-asides, incumbent contractors, funding sources, or contract renewal options is provided in this document.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FEE SHEET

Construction Manager at – Risk

26-040326-60-P-AW Coan Building Administrative Consolidation Site Improvements

FIRM NAME:

DATE:

PRE-CONSTRUCTION

SERVICES

As compensation for pre-construction services, the CM shall receive a fee as negotiated below:

LUMP SUM FEE

(PER TASK)

COMPLETION/

DUE DATES

1. Schematic Design $7,500.00 6/05/2026 (Tentative)

2. Design Development. $7,500.00 6/15/2026 (Tentative)

3. 100% Construction Documents $7,500.00 7/10/2026 (Tentative)

4. Bidding / GMP, Submittal / GMP, Negotiations / Award of

GMP Amendment $7,500.00 8/10/2026 (Tentative)

TOTAL PRE- CONSTRUCTION FEE $30,000.00

CONSTRUCTION PHASE

6. Construction Manager’s Fee:

a. percent of general conditions

b. percent fee