This is a Scope of Work attachment for Request for Proposals Number 3717-27.11 issued by Amarillo Independent School District (AISD) for Optical Transport Modernization and Routed Optical Network Deployment. The project entails modernizing the District's core telecommunications backbone by migrating from an end-of-life Cisco NCS 2006 DWDM optical transponder ring to a next-generation Routed Optical Network operating over District-owned single-mode dark fiber. The scope encompasses 6 Core Hub Sites (including 2 Primary Data Centers) and 47 Remote School Campuses. Equipment requirements include 4 modular DC core routers (NCS-57C3-MOD-SYS or equivalent), 8 hub core routers (8011-32Y8L2H2FH or equivalent), 6 hub local switches (C9550-48L4CD or equivalent), 47 campus switches (C9550-24L4CD or equivalent), coherent optical transceivers (400G ZR/ZR+ and DR4/LR4 variants), and associated licensing for a total of 53 campus switches. The proposal deadline is 4:00 PM on December 17, 2026, with hardware delivery authorized February 1 through May 31, 2027, on-site cutover scheduled June 1 through August 6, 2027, and all work completion required by September 30, 2027. The contract term includes five years of manufacturer hardware support and software licensing for Core Hub Sites and one year hardware/three years software support for Remote Campuses upon final system cutover.
The procurement qualifies for Universal Service Administrative Company (USAC) E-Rate discounts under Funding Year 2027 (July 1, 2027 - June 30, 2028) with Category One (C1) eligible scope covering network electronics to light WAN, and billing via Service Provider Invoice (SPI). Vendors may propose Cisco specified products or functionally equivalent solutions from industry-recognized manufacturers, with mandatory submission of side-by-side specification matrices, optical link budget compliance charts, OSPF/BFD/telemetry feature parity documentation, and equivalent warranty/TAC support evidence. The awarded vendor must provide comprehensive deliverables including Low-Level Design documentation, pre-staging and burn-in certification, optical test certification, interim NCS configuration playbooks, and as-built documentation with 8-hour technical training. The contract requires zero interruption to school operations with parallel staging methodology, achievement of sub-50ms dynamic routing convergence, and successful completion of a 14-day operational stability period with Severity 1 and 2 incident protocols. Final payment is contingent upon successful completion of Network Acceptance Testing approved by the AISD Chief Technology Officer, with 10% retainage withheld until completion of the stability period and delivery of all required documentation.
View the file
Other files
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMARILLO INDEPENDENT SCHOOL DISTRICT (AISD)
ATTACHMENT A - SUMMARY OF WORK
Request for Proposals Number: 3717-27.11
Optical Transport Modernization & Routed Optical Network Deployment
1. Purpose
Amarillo ISD is modernizing its core telecommunications backbone by migrating from an end-of-life Cisco NCS
2006 DWDM optical transponder ring to a next-generation Routed Optical Network (RON) operating natively over District-owned single-mode dark fiber. The scope encompasses 6 Core Hub Sites (including 2 Primary
Data Centers) and 47 Remote School Campuses.
The turnkey engagement requires the awarded vendor to furnish, stage 'on top' of existing infrastructure, pre-test, rack, patch, tune, cutover, and operationalize all routing, switching, coherent transceivers, and dynamic OSPF routing.
1.1 E-Rate Program Governance, Funding Year, & Eligibility Scope
This procurement will be submitted for Universal Service Administrative Company (USAC) E-Rate discounts under Funding Year 2027 (July 1, 2027 – June 30, 2028) pursuant to FCC Form 470. Billing should be done via
Servicer Provider Invoice (SPI).
Category One (C1) Eligible Scope: All core routing chassis, modular port adapters (MPAs), coherent optical transceivers (400G ZR/ZR+), intra-hub optical modules (QDD-400G-DR4-S=), base operating software, and initial-term manufacturer technical support lighting the District-owned dark fiber ring across the 6 Core Hubs and 47 Remote Campuses are designated strictly as Category One (C1) —
Network Electronics to Light WAN.
Authorized Delivery & Execution Schedule: The implementation timeline is established as follows:
Pre-Staging Hardware Delivery Window:
o February 1, 2027 – May 31, 2027 (equipment delivery to contractor staging facility authorized prior to July 1 in compliance with USAC rules).
On-Site Cutover Window:
o June 1, 2027 – August 6, 2027 (all campus ring cutovers and stabilization must be completed prior to the 2027–2028 academic school year).
Contract Completion Deadline:
o All work, stability testing, and invoicing must conclude on or before September 30, 2027
(consistent with USAC non-recurring service deadline).
2. Equipment
The equipment listed below defines the baseline standard of performance, port density, optical reach, and system throughput. Vendors may propose the specified Cisco products or functionally equivalent solutions from industry-recognized networking manufacturers.
Manufacturer Support & Service Level Agreement (SLA):
Core Hub Site Support & Licensing (5-Year): Bidders must include a baseline five (5) year manufacturer hardware support and software licensing contract (Cisco SmartNet / DNA Advantage or approved manufacturer equivalent) for all routing, switching, and optical equipment deployed at the 6 Core Hub Sites, starting upon final system cutover.
Remote Campus Support & Licensing (1-Year HW / 3-Year SW): Bidders must include a baseline one
(1) year manufacturer hardware support contract and a three (3) year software licensing contract for all equipment deployed at the 47 Remote School Campuses, starting upon final system cutover.
Coverage & Response Level: Support coverage must be 24x7x365 with Next Business Day (NBD) on-site advance hardware replacement and direct, unlimited 24x7 Tier-3 TAC/engineering support, including access to all minor/major operating system software patches and updates for the duration of the respective hardware terms. For equivalent manufacturer solutions, the bidder must demonstrate identical 24x7 engineering support and on-site hardware dispatch capabilities. All transceivers (including coherent ZR/ZR+ and intra-site DR4 modules) must carry full manufacturer support warranty coverage aligned with their host chassis.
Category Specified Part Number* Description & Minimum Functional Requirements
Total Qty
DC Core Routers NCS-57C3-MOD-SYS or equiv. Modular Carrier-Grade Chassis, RP2-E w/SyncE, MPA-2D4H (48x1/10/25G, 8x40/100G, 2x400G)
4 Units
Hub Core Routers 8011-32Y8L2H2FH or equiv. Fixed 1RU Carrier Router, 32x25G, 8x50G, 2x100G QSFP28, 2x400G QDD, 1.6Tbps throughput
8 Units
Hub Local Switches C9550-48L4CD or equiv. 48-Port 1/10/25/50G + 4x100G / 2x400G Line-Rate L3 Aggregation Switch (Local Campus handoff)
6 Units
Campus Switches C9550-24L4CD or equiv. 24-Port 1/10/25/50G + 4x100G / 2x400G Line-Rate L3 Switch (Remote School MDF edge)
47 Units
Core Coherent Optics with 5 years of HW support
QDD400GBRT-2-BUN or equiv. 400G Pluggable Bright ZR+ High-Tx Power QSFP- DD w/ SmartNet (Inter-Hub DWDM ring links) (Bundle of 2 DP04QSDD-HE0-A1)
5 Units
Core Intra-Site Optics QDD-400G-DR4-S= or equiv. 400GBASE-DR4 MPO-12 Transceivers w/ SmartNet (Intra-Site Router A/B & DC interconnects; dual links per hub + spares)
12 Units
Core Reach Optics QDD-400G-LR4-S= or equiv. 400GBASE-LR4 Duplex SMF Transceivers w/ SmartNet (10km Palo Duro - Caprock inter-hub link)
2 Units
Local Distribution Optics SFP-10G-SR-S= or equiv. 10GBASE-SR SFP+ Optical Transceivers w/ SmartNet (Hub to local campus LAN handoffs)
12 Units
NCS Software RTUs ADN-100G-RTU-2 or equiv. 100G RTU / Advantage SW Feature License for Modular DC Core Routers (NCS 57C3)
48 Lic
8000 Software RTUs ADN-NGA-10G-RTU or equiv. Access Network Advantage RTU (per 10G capacity) for Hub Routers (Cisco 8011)
800 Lic
Campus Switch Lic. LIC-CS-CO-M-A / ADV or equiv. Cisco DNA Advantage 3-Year Subscription Licenses (Must cover all required L3 functions for the 6 Hub Local Switches and 53 Campus Switches. Must be included in the itemized unit price.)
53 Lic
Equivalence Evaluation Requirements:
MANDATORY 'OR EQUIVALENT' SPECIFICATION CLAUSE: Catalog numbers and manufacturer references are descriptive, not restrictive, and define the standard of quality desired. Proposers submitting alternate manufacturers must demonstrate strict functional, optical, throughput, and protocol equivalence. Alternate submittals must include: (1) Side-by-side hardware specification matrices; (2) Optical link budget compliance charts (confirming unamplified 400G ZR+ coherent operation); (3) Complete OSPF, BFD, and telemetry feature parity; and (4) Equivalent 5/3-year base hardware warranty and TAC support with optional 4th and 5th year extensions. AISD reserves the sole authority to determine functional equivalence.
3. Architectural Hierarchy & Port Ingestion Boundaries
To guarantee deterministic wire-speed routing and protect packet forwarding hierarchies, interface connectivity is strictly partitioned as follows:
Dedicated Hub Local Switching Handoff: The six (6) Cisco Catalyst C9550-48L4CD (or equivalent) switches deployed at the 6 Hub Sites are dedicated exclusively to aggregating local facility traffic, local campus LAN distribution, and data center host services. Lateral school links SHALL NOT land on these switches.
Lateral School Uplink Ingestion: All lateral WAN fiber uplinks originating from the 47 remote school campuses will land directly into the core routing layer — terminating on the Cisco 8011 routers at hub sites or the Cisco NCS-57C3 modular routers at ESC and LDZ Data Centers (or approved equivalents).
Intra-Site Interconnect: At each of the 6 Hub Sites, Core Router A and Core Router B will be directly interconnected via 400G DR4 links.
4. Dual-Path Campus Connectivity & School ID Odd/Even Traffic Engineering Policy The District's 47 remote school campuses utilize a dual-homed single-mode fiber architecture connecting across two distinct hub sites to provide active, simultaneous connectivity to both the ESC and LDZ Data Centers. The preferred plan is to reuse the existing optics from the current infrastructure in the new equipment. To prevent core link saturation and ensure balanced Data Center utilization, active traffic steering is governed by the District's School ID Odd/Even policy:
Campus Cluster Distribution:
Palo Duro / Caprock: 11 Schools; Caprock / AHS : 14 Schools; LDZ DC / Palo Duro: 10 Schools; LDZ DC / Tascosa: 5 Schools; Tascosa / ESC DC: 3 Schools; ESC DC / Amarillo: 4 Schools.
ODD School ID Policy (ESC Data Center Egress):
Campuses assigned an ODD School ID must have their Layer 3 OSPF routing engineered to actively utilize both Data Center paths—routing default egress traffic through the ESC Data Center while maintaining direct, active Layer 3 reachability to hosted services at the LDZ Data Center. Both ESC and LDZ are active core nodes on the ring.
EVEN School ID Policy (LDZ Data Center Egress):
Campuses assigned an EVEN School ID must have their Layer 3 OSPF routing engineered to actively utilize both Data Center paths—routing default egress traffic through the LDZ (De Zavala) Data Center while maintaining direct, active Layer 3 reachability to hosted services at the ESC Data Center. Both ESC and LDZ are active core nodes on the ring.
OSPF Metric Engineering, Fast Convergence:
The Contractor must achieve deterministic traffic steering and balanced bandwidth utilization across the optical ring via tuned OSPF cost metrics, stub/NSSA boundary summarization, and strict prefix controls. To ensure deterministic traffic engineering and sub-50ms dynamic routing convergence, the architecture must implement two complementary mechanisms:
Sub-50ms Dynamic Path Convergence: Core ring paths must implement Loop-Free Alternate (LFA / TI-LFA) or platform-equivalent pre-computed alternate forwarding paths to maintain continuous data-plane forwarding within ≤ 50 ms during single-link or optical transceiver transitions.
Convergence Acceptance Testing: Dynamic routing convergence will be validated during scheduled post-installation maintenance windows. The Contractor and District engineering team will inject line-rate bidirectional test traffic (via RFC 2544 / ITU-T Y.1564 traffic generation or high-rate active probing) and simulate link-state transitions by administratively shutting ports and disconnecting optical jumpers at diverse points across the ring. Traffic reconvergence on LFA-protected core paths must measure under 50 ms total frame loss; paths relying on full OSPF SPF recalculation must reconverge within 500 ms.
5. Parallel 'On Top' Staging & Dark Fiber Cutover Strategy
Zero interruption to school day operations is a mandatory condition of contract. All deployment activities must follow a structured parallel-staging methodology:
Parallel 'On Top' Deployment: All new RON routers, aggregation switches, and optics must be racked, powered, and fully operationalized 'on top of' (in parallel with) active production equipment prior to moving any physical fiber.
Interim NCS 2006 Optical Grooming: Where dark fiber pairs cannot be doubled, the vendor must plan, configure, and verify interim optical circuits, transponder pass-throughs, or temporary wavelengths across the existing NCS 2006 DWDM infrastructure to validate connectivity before executing final cuts.
Systematic Dark Fiber Swing: Dark fiber pairs will be sequentially moved from the legacy NCS 2006 transponders directly to the new 400G RON router optics during approved evening maintenance windows (6:00 PM – 5:00 AM CST). Each span cut must be optically and logically verified prior to proceeding to the next segment.
6. Detailed Phased Statement of Work
Phase 1: Secure Pre-Staging Lab:
Receive, inspect, and asset tag all chassis; flash golden operating system images (IOS-XR / IOS-XE or equivalent); bind smart licenses; apply baseline District hardening templates; execute 48-hour continuous burn-in load testing.
Phase 2: Optical Characterization:
Perform bidirectional OTDR traces, optical return loss (ORL) measurements, and power level validation across all ring spans currently terminating on NCS transponders. Validate unamplified 400G Bright ZR+ link budgets.
Clean and scope all fiber bulkheads to IEC 61300-3-35 standards.
Phase 3: Parallel Installation:
Mount equipment into designated MDF racks at 6 Hub Sites and 47 School MDFs. Connect dual power supplies to independent UPS/utility feeds. Pre-run and label new LC-LC and MPO-12 patch jumpers.
Phase 4: Dynamic OSPF & Core Routing:
Configure DWDM grid frequencies, TX power, pre-FEC BER telemetry, OSPFv2/OSPFv3 multi-area routing, and Odd/Even School ID traffic engineering policies.
Phase 5: Phased Evening Cutover:
Execute overnight cuts (6:00 PM – 5:00 AM CST), swing dark fiber spans sequentially, verify OSPF convergence, and swing school uplinks.
7. Required Vendor Deliverables
D1: Low-Level Design (LLD) & NIP:
Detailed engineering design document containing OSPF area mapping, Odd/Even cost metric tables, optical power budgets, port assignment matrices, and rollback runbooks.
D2: Pre-Staging & Burn-In Certification:
Lab audit report certifying 48-hour zero-defect burn-in completion, serial-to-MAC mapping, and asset tag logs.
D3: Optical Test & Cleanliness Certification:
Bidirectional OTDR traces, optical loss logs, and digital end-face inspection photos for every migrated fiber strand.
D4: Interim NCS Configuration Playbook:
Documented configuration procedures for temporary circuits/wavelengths deployed across the NCS 2006 system.
D5: As-Built Documentation & Knowledge Transfer:
Final updated Visio topology schematics, gold configuration backups, and an 8-hour hands-on technical training workshop for District engineering staff.
D6: Final System Acceptance, Stability Period, & Milestone Release Final System Acceptance is the formal milestone confirming the network meets all contractual, architectural, and operational performance standards prior to contract closeout and final retainer disbursement.
Designated Approver: All test plans, test results, deliverable sign-offs, and the Certificate of Final Acceptance must be formally approved in writing by the AISD Chief Technology Officer.
Approvals from field engineers, project managers, or contractors do not constitute final acceptance.
Acceptance Gate Criteria & Required Verification Testing: Before entering the 14-day Operational Stability Period, the Contractor must complete and document the following acceptance test procedures in an AISD-approved Network Acceptance Testing (NAT) log:
- Throughput & Latency Validation: Full-duplex RFC 2544 / ITU-T Y.1564 synthetic line-rate testing across all provisioned Routed Optical links at 100% committed information rate (CIR) with zero packet drop and frame loss ratio (FLR) ≤ 10^-6.
- Automated Link/Route Failover Testing: Simulation of planned and unplanned outages (physical fiber pulls and administrative interface shutdowns) across all ring spans. Traffic restoration on core paths utilizing BFD and TI-LFA / FRR must restore data flow within ≤ 50 ms total frame loss; unprotected SPF reconvergence must complete within ≤ 500 ms.
- Optical Health & Margin Audit: Digital scope inspection showing zero end-face contamination and bidirectional optical power readings confirming receiver margins meet or exceed design thresholds specified in D1 (Low-Level Design).
- Deliverable Sign-Off: Complete delivery and formal AISD engineering sign-off on deliverables D1 through D5, including updated Visio topology diagrams, gold configuration backups, and completion of the mandatory 8-hour hands-on technical training workshop.
Additionally, the Contractor must submit a finalized asset inventory report to the District documenting the exact physical installation location of all deployed equipment by serial number and AISD asset tag.
14-Day Operational Stability Period: Following the successful completion and AISD sign-off of the verification testing above, all live production traffic will be migrated to the new Routed Optical Network, initiating a mandatory 14 consecutive calendar day Operational Stability Period:
- Commencement Trigger: The stability clock begins at 00:01 AM on the first calendar day following 100% production cutover and AISD’s written approval of the NAT test report.
- Pass / Success Criteria: The stability period is deemed successful if the network operates for 14 continuous days without a Severity 1 (Critical) or Severity 2 (Major) network outage or degradation attributable to hardware defects, software instability, vendor configuration defects, or optical link flaps.
- Clock Reset for Significant Faults: Any Severity 1 incident (e.g., loss of connectivity across a hub site, core ring partition, or service-impacting hardware failure) will immediately abort the test, require root-cause remediation by the Contractor, and fully restart the 14-day clock at Day 1. Any Severity 2 incident (e.g., loss of link redundancy, recurring interface flapping, or memory/CPU leak) will pause the stability clock; if corrective action is not completed within 24 hours, the clock resets to Day 1.
Carrier/third-party fiber cuts outside contractor control pause the clock for the duration of the event rather than resetting it.
Milestone Payments: Final Acceptance and contract billing are phased to protect District operations:
- Conditional Acceptance (In-Service): Upon successful completion of Verification Testing and migration of live production traffic, the Contractor achieves Conditional Acceptance.
- Final Acceptance & Retainage Release: AISD will withhold ten percent (10%) of each approved progress payment as retainage, totaling ten percent (10%) of the final contract price. Retainage becomes payable upon successful completion of the required 14-day operational stability period, correction of outstanding deficiencies, site cleanup, and delivery of all required documentation and training. Following written approval by the AISD Chief Technology Officer, the contractor may invoice for the final retained balance.