11-2N2384 Apply Methacrylate_ Place Polyester Concrete Overlay and Joint Seals.pdf

PDF 1 MB Posted

Attached to
11-2N2384 Apply Methacrylate, Place Polyester Concrete Overlay and Joint Seals
Solicitation number
11-2N2384
Issued by
San Diego County, San Diego City, California

About this file

This is a Notice to Bidders and Special Provisions for Construction document issued by the California Department of Transportation (Caltrans) for Contract No. 11-2N2384, a state highway construction project in San Diego County. The work involves applying methacrylate, placing polyester concrete overlay, and installing joint seals at various locations on Routes 8 and 125. The project includes 47 bid items encompassing traffic control systems, bridge deck treatment, asphalt and concrete work, pavement markings, and related construction activities. The estimated project cost is $4,910,000 with a contract duration of 100 working days. Bids opened on Wednesday, December 2, 2026, submitted electronically via Bid Express with a 2:00 p.m. deadline. Contractors must hold either a Class A license or a combination of Class C licenses (C-8, C-12, C-32). Specific closure restrictions apply to multiple freeway connectors, ramps, and city streets, with detailed lane requirement charts and time-of-day restrictions provided for Routes 8, 125, and connector routes throughout the La Mesa and surrounding San Diego County areas.

The contract includes a 3 percent Disabled Veteran Business Enterprise (DVBE) participation goal and a 5 percent Small Business Enterprise (SBE) participation goal. Bidders must submit on a unit price basis with bidder's security equal to at least 10 percent of the bid. Prevailing wages are required per California Department of Industrial Relations standards. The project involves multiple specialized submittals including environmental product declarations for hot mix asphalt and concrete materials, local material work plans with lead and pH testing for noncommercial sources, safety representative certifications and qualifications, and prompt payment monitoring through Caltrans' system. Liquidated damages apply for late lane reopenings, ranging from $1,000 to $2,150 per 10-minute interval depending on facility type and time period. Special closure restrictions apply during designated holidays, special shopping seasons, and major events throughout San Diego County, with complete details provided in charts M1 through M6 and J1 through J6. The contract requires coordination with coincident adjacent contracts and incorporation of professionally facilitated project partnering and safety oversight requirements.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Bids open Wednesday, December 2, 2026

Dated October 26, 2026 OSD

STATE OF CALIFORNIA

DEPARTMENT OF TRANSPORTATION

NOTICE TO BIDDERS

AND

SPECIAL PROVISIONS

FOR CONSTRUCTION ON STATE HIGHWAY IN SAN DIEGO COUNTY AT

VARIOUS LOCATIONS

In District 11 On Route 8, 125

Under

Bid book dated October 26, 2026 Standard Specifications dated 2025

Project plans approved June 30, 2026 Standard Plans dated 2025

Identified by

Contract No. 11-2N2384

11-SD-8, 125-Var

Project ID 1124000371

SPECIAL NOTICES

See sections 2 and 3 for contractors' registration requirements.

The Department advises bidders that potential claim records must be submitted by the contractor using the Department's Internet potential claim system.

See section 2 for submittal requirements for DVBE quotes and Non–Small Business

Subcontractor Preference.

For work plan for local material from (1) a noncommercial source or (2) a source not regulated under California jurisdiction, see section 6-1.03B(2).

See section 7-1.02K(3) for the requirements for electronic submittal of certified payroll records using LCPtracker Pro.

The flagging and temporary traffic control requirements have been revised. See sections 7-

1.03, 7-1.04, and 12.

See sections 2-1.11 and 2-1.33B for in-use off-road diesel-fueled vehicle requirements regarding Certificate of Reported Compliance submittals.

See section 14-11.14 for changes to the management of treated wood waste.

See sections 1-1.06, 1-1.07B, 2-1.23, 2-1.24, 2-1.33B(3), 5-1.13D, and 5-1.13F for “Small

Business Enterprise Participation Goal Requirement” and “Small Business and Non-Small Business Subcontractor Preferences.”

See section 6-1.08 for the requirements for environmental product declarations for hot mix asphalt and concrete materials and products.

Contract No. 11-2N2384 i

TABLE OF CONTENTS

NOTICE TO BIDDERS

BID ITEM LIST

SPECIAL PROVISIONS

ORGANIZATION

DIVISION I GENERAL PROVISIONS

1 GENERAL

2 BIDDING

5 CONTROL OF WORK

6 CONTROL OF MATERIALS

7 LEGAL RELATIONS AND RESPONSIBILITY TO THE PUBLIC

8 PROSECUTION AND PROGRESS

9 PAYMENT

DIVISION II GENERAL CONSTRUCTION

11 WELDING

12 TEMPORARY TRAFFIC CONTROL

13 WATER POLLUTION CONTROL

14 ENVIRONMENTAL STEWARDSHIP

DIVISION V SURFACINGS AND PAVEMENTS

36 GENERAL

39 ASPHALT CONCRETE

DIVISION VI STRUCTURES

48 TEMPORARY STRUCTURES

51 CONCRETE STRUCTURES

60 EXISTING STRUCTURES

DIVISION VIII MISCELLANEOUS CONSTRUCTION

75 MISCELLANEOUS METAL

DIVISION IX TRAFFIC CONTROL DEVICES

83 RAILINGS AND BARRIERS

84 MARKINGS

DIVISION XI MATERIALS

90 CONCRETE

ii

STANDARD PLANS LIST

The standard plan sheets applicable to this Contract include those listed below. The applicable revised standard plans (RSPs) listed below are included in the project plans.

RSP A3A Abbreviations (Sheet 1 of 3)

RSP A3B Abbreviations (Sheet 2 of 3)

RSP A3C Abbreviations (Sheet 3 of 3)

A10A Legend - Lines and Symbols (Sheet 1 of 5)

A10B Legend - Lines and Symbols (Sheet 2 of 5)

A10C Legend - Lines and Symbols (Sheet 3 of 5)

A10D Legend - Lines and Symbols (Sheet 4 of 5)

A10E Legend - Lines and Symbols (Sheet 5 of 5)

A20A Pavement Markers and Traffic Lines - Typical Details

A20B Pavement Markers and Traffic Lines - Typical Details

A20C Pavement Markers and Traffic Lines - Typical Details

A20D Pavement Markers and Traffic Lines - Typical Details

A20E Traffic Lines - Typical Details for Contrast Striping

A20F Pavement Markers and Traffic Lines - Typical Details

A20G Exit Ramp with Enhanced Pavement Markers for Wrong Way Details

A24A Pavement Markings - Arrows

A24B Pavement Markings - Arrows and Symbols

A24C Pavement Markings - Symbols and Numerals

A24D Pavement Markings - Words

A24E Pavement Markings - Words

A24F Pavement Markings - Crosswalks

A24G Pavement Markings - Yield Lines, Limit Lines, and Wrong Way Details

A24H Pavement Markings - Arrows

T1A Temporary Crash Cushion - Sand Filled (Unidirectional)

T1A1 Temporary Crash Cushion - Sand Filled (Unidirectional)

T1B Temporary Crash Cushion - Sand Filled (Bidirectional)

T2 Temporary Crash Cushion - Sand Filled (Shoulder Installations)

RSP T3A Temporary Railing (Type K)

T3B Temporary Railing (Type K)

T3C Temporary Barrier System (Cross Bolt)

T3D Temporary Barrier System (Cross Bolt) iii

T3E Temporary Barrier System (Cross Bolt)

T3F Temporary Barrier System (Cal F-23)

T3F2 Temporary Barrier System (Cal F-23)

T3G Temporary Barrier System (Staking or Anchoring)

T3G2 Temporary Barrier System (Staking or Anchoring)

T9 Traffic Control System Tables for Lane and Ramp Closures

T10 Traffic Control System for Lane Closure on Freeways and Expressways

T10A Traffic Control System for Lane Closure on Freeways and Expressways

RSP T11 Traffic Control System for Lane Closure on Multilane Conventional Highways

RSP T12 Traffic Control System for Half Road Closure on Multilane Conventional Highways and Expressways

RSP T13 Traffic Control System with Reversible Control on Two Lane Conventional Highways

T14 Traffic Control System for Ramp Closure

T18 Traffic Control System - Construction Work Zone Speed Limit Reduction on Freeways and Expressways

T20 Traffic Control System - Construction Work Zone Speed Limit Reduction Details

T30 Temporary Pedestrian Access Routes - Typical Sidewalk Closure and Pedestrian Detour

T32 Temporary Pedestrian Access Routes - Typical Sidewalk/Crosswalk Closure and Pedestrian Detour

T59 Temporary Water Pollution Control Details (Temporary Concrete Washout Facility)

B6-21 Joint Seals (Maximum Movement Range = 2")

RS1 Roadside Signs - Typical Installation Details No. 1

RS2 Roadside Signs - Wood Post - Typical Installation Details No. 2

RS4 Roadside Signs - Typical Installation Details No. 4

S93 Framing Details for Framed Single Sheet Aluminum Signs, Rectangular Shape

S94 Roadside Framed Single Sheet Aluminum Signs, Rectangular Shape

S95 Roadside Single Sheet Aluminum Signs, Diamond Shape

CANCELED STANDARD PLANS LIST

The 2025 standard plan sheets listed below are canceled and not applicable to this contract.

Plan No.

Date

Canceled Plan No.

Date Canceled

Plan No.

Date

Canceled

P8 04-20-26

NOTICE TO BIDDERS

Bids open Wednesday, December 2, 2026

Dated October 26, 2026

General work description: Apply methacrylate, place polyester concrete overlay and joint seals.

The Department will receive electronically sealed bids for the following work: CONSTRUCTION ON

STATE HIGHWAY IN SAN DIEGO COUNTY AT VARIOUS LOCATIONS.

District-County-Route-Post Mile: 11-SD-8, 125-Var

Contract No. 11-2N2384

The Contractor must have either a Class A license or any combination of the following Class C licenses which constitutes a majority of the work: C-8, C-12, C-32.

The DVBE Contract goal is 3 percent.

The SBE Contract goal is 5 percent.

Bids must be on a unit price basis.

Complete the work within 100 working days.

The estimated cost of the project is $4,910,000.

The Department will receive bids until 2:00 p.m. on the bid open date via Bid Express website. Bids received after this time will not be accepted. For more information refer to the Electronic Bidding Guide at the Office Engineer's website.

The Department will open and publicly read the bids through webcast/teleconference services immediately after the specified closing time.

For bid results go to:

https://ppmoe.dot.ca.gov/cc

Select Electronic Bidding under the Bidding tab.

District office addresses are provided in the Standard Specifications.

Present bidders' inquiries to the Department and view the Department's responses at:

https://ppmoe.dot.ca.gov/cc?id=cc_bidinquiries

Questions about alleged patent ambiguity of the plans, specifications, or estimate must be asked before bid opening. After bid opening, the Department does not consider these questions as bid protests.

Submit your bid with bidder's security equal to at least 10 percent of the bid.

Under Govt Code § 14835 et seq. and 2 CA Code of Regs § 1896 et seq., the Department gives preference to certified small businesses and non–small businesses who commit to 25 percent certified small business participation.

Under Pub Cont Code § 6107, the Department gives preference to a "California company," as defined, for bid comparison purposes over a nonresident contractor from any state that gives or requires a preference to be given to contractors from that state on its public entity construction contracts.

Prevailing wages are required on this Contract. The Director of the California Department of Industrial Relations determines the general prevailing wage rates. Obtain the wage rates at the DIR website, http://www.dir.ca.gov, or from the Department's Labor Compliance Office of the district in which the work is located.

The Department has made available Notices of Suspension and Proposed Debarment from the Federal Highway Administration. For a copy of the notices, go to https://www.dir.ca.gov/dlse/debar.html.

Additional information is provided in the Excluded Parties List System at https://sam.gov/content/home.

Caltrans and the Construction Industry are committed to making partnering the way we do business. For more information, go to https://dot.ca.gov/programs/construction/partnering.

Department of Transportation

BID ITEM LIST

Item No.

Item Code Item Description Unit of Measure Estimated Quantity

0001 070030 LEAD COMPLIANCE PLAN LS LUMP SUM

0002 090100 TIME-RELATED OVERHEAD (WDAY) WDAY 100

0003 090200 DISPUTE RESOLUTION ADVISOR ON-SITE

MEETING

EA 3

0004 090207 HOURLY OFF-SITE DISPUTE-RESOLUTION-

ADVISOR-RELATED TASKS

HR 30

0005 120090 CONSTRUCTION AREA SIGNS LS LUMP SUM

0006 120100 TRAFFIC CONTROL SYSTEM LS LUMP SUM

0007 120103 STATIONARY IMPACT ATTENUATOR VEHICLE DAY 100

0008 120207 PORTABLE RADAR SPEED FEEDBACK SIGN

SYSTEM

DAY 100

0009 128651 PORTABLE CHANGEABLE MESSAGE SIGN (EA) EA 6

0010 130100 JOB SITE MANAGEMENT LS LUMP SUM

0011 130201 WATER POLLUTION CONTROL PROGRAM LS LUMP SUM

0012 038275 MANAGE SOLID WASTE GENERATED BY THE

PUBLIC

HR 80

0013 390132 HOT MIX ASPHALT (TYPE A) TON 58

0014 397005 TACK COAT TON 0.3

0015 398200 COLD PLANE ASPHALT CONCRETE PAVEMENT SQYD 590

0016 480400 TEMPORARY DECKING LS LUMP SUM

0017 046491 STRUCTURAL CONCRETE, BRIDGE (RSC) CY 3.1

0018 511118 CLEAN EXPANSION JOINT LF 1,581

0019 519081 JOINT SEAL (MR 1/2") LF 1,076

0020 519088 JOINT SEAL (MR 1") LF 140

Item No.

Item Code Item Description Unit of Measure Estimated Quantity

0021 519091 JOINT SEAL (MR 1 1/2") LF 314

0022 519204 STRIP JOINT SEAL ASSEMBLY (MR 2 1/2") LF 51

0023 520102 (F) - BAR REINFORCING STEEL (BRIDGE) LB 694

0024 600001 PUBLIC SAFETY PLAN LS LUMP SUM

0025 600011 RAPID SETTING CONCRETE (PATCH) CF 683

0026 600029 REMOVE ASPHALT CONCRETE SURFACING SQFT 9,430

0027 600031 REMOVE CONCRETE DECK SURFACE SQFT 13,157

0028 600033 REMOVE UNSOUND CONCRETE CF 683

0029 600037 PREPARE CONCRETE BRIDGE DECK SURFACE SQFT 237,591

0030 600041 FURNISH POLYESTER CONCRETE OVERLAY CF 9,196

0031 600043 (F) - PLACE POLYESTER CONCRETE OVERLAY SQFT 82,526

0032 600045 (F) - TREAT BRIDGE DECK SQFT 155,065

0033 600047 FURNISH BRIDGE DECK TREATMENT MATERIAL GAL 1,723

0034 600114 BRIDGE REMOVAL (PORTION) LS LUMP SUM

0035 600200 PAINT BRIDGE IDENTIFICATION EA 2

0036 810230 PAVEMENT MARKER (RETROREFLECTIVE) EA 710

0037 048969 RECONSTRUCT STEEL PLATE BARRIER EA 2

0038 840516 THERMOPLASTIC PAVEMENT MARKING

(ENHANCED WET NIGHT VISIBILITY)

SQFT 1,670

0039 846033 REMOVE TRAFFIC STRIPE LF 22,300

0040 846035 REMOVE THERMOPLASTIC PAVEMENT

MARKING

SQFT 1,670

Item No.

Item Code Item Description Unit of Measure Estimated Quantity

0041 847068 6" TRAFFIC STRIPE TAPE (BROKEN 17-7) LF 340

0042 847077 8" TRAFFIC STRIPE TAPE WITH CONTRAST

(WARRANTY) (BROKEN 12-3)

LF 410

0043 847105 12" TRAFFIC STRIPE TAPE WITH CONTRAST

(WARRANTY)

LF 1,790

0044 847218 6" TRAFFIC STRIPE TAPE WITH CONTRAST

(WARRANTY)

LF 11,900

0045 847222 6" TRAFFIC STRIPE TAPE WITH CONTRAST

(WARRANTY) (BROKEN 36-12)

LF 7,230

0046 847224 8" TRAFFIC STRIPE TAPE WITH CONTRAST

(WARRANTY)

LF 650

0047 999990 MOBILIZATION LS LUMP SUM

SPECIAL PROVISIONS

ORGANIZATION

Special provisions are under headings that correspond with the main-section headings of the Standard Specifications. A main-section heading is a heading shown in the table of contents of the Standard Specifications.

Each special provision begins with a revision clause that describes or introduces a revision to the Standard Specifications.

Any paragraph added or deleted by a revision clause does not change the paragraph numbering of the Standard Specifications for any other reference to a paragraph of the Standard Specifications.

DIVISION I GENERAL PROVISIONS

1 GENERAL

Add to section 1-1.01:

Bid Items and Applicable Sections

Item code

Item description Applicable section

038275 MANAGE SOLID WASTE GENERATED BY THE PUBLIC 14

046491 STRUCTURAL CONCRETE, BRIDGE (RSC) 51

048969 RECONSTRUCT STEEL PLATE BARRIER 83

Add to the table in the 1st paragraph of section 1-1.06:

SBE Small Business Enterprise

Add to section 1-1.07B:

small business enterprise: Small business or small business for the purpose of public works, as certified by the Department of General Services, Office of Small Business and DVBE Services, and as defined in Govt Code § 14835 et seq. and 2 CA Code of Regs § 1896 et seq.

2 BIDDING

Add between the 1st and 2nd paragraphs of section 2-1.06B:

The Department makes the following supplemental project information available:

Supplemental Project Information

Means Description Included in the Information Handout Final Report – Utilization of Small Business Enterprises

Form (DOT OCR-0003) Available as specified in the Standard Specifications

Bridge as-built drawings.

Replace section 2-1.23 with:

2-1.23 SMALL BUSINESS ENTERPRISE PARTICIPATION GOAL REQUIREMENT

2-1.23A General

Section 2-1.23 applies if an SBE participation goal requirement is shown on the Notice to Bidders.

The SBE participation goal requirement is in addition to any DVBE goal shown on the Notice to Bidders and the DVBE requirements in section 2-1.22.

Make work available to SBEs and select work parts consistent with the available SBEs, including subcontractors, suppliers, service providers, and truckers.

Meet the SBE participation goal requirement shown on the Notice to Bidders. A bid that demonstrates an SBE participation commitment less than the SBE participation goal requirement is nonresponsive.

Each listed SBE must be certified as a small business or small business for the purpose of public works by 5:00 p.m. on the bid opening date. The complete application and any required substantiating documentation must be received by the Department of General Services by 5:00 p.m. on the bid opening date.

The Department of General Services determines whether an SBE was certified on the bid opening date.

The Department of Transportation confirms an SBE’s certification status.

2-1.23B SBE Submittals

Submit SBE information under section 2-1.33.

For the SBE participation goal requirement, submit the following:

1. Completed Small Business Enterprise – Commitment form. Failure to submit the completed form by 4 p.m. on the 4th business day after bid opening may result in a nonresponsive bid.

2. Copy of the quote for each SBE shown on the Small Business Enterprise – Commitment form that describes the type and dollar amount of work shown on the form. Quotes are not required for work that will be completed by SBE prime bidders. Failure to submit a copy of the quote for each SBE listed on the Commitment form by 4 p.m. on the 4th business day after bid opening may result in disallowance of the SBE’s participation.

3. Completed Small Business Enterprise – Confirmation form from each SBE listed on the Commitment form. The form for each SBE is required to establish that the SBE will be participating in the Contract for the type and dollar amount of work shown on the form. Failure to submit completed Confirmation forms for each SBE listed on the Commitment form by 4 p.m. on the 4th business day after bid opening may result in disallowance of the SBE’s participation.

4. If an SBE is participating as a joint venture partner, submit a copy of the joint venture agreement.

The Department may contact you and SBEs to clarify quotes and supporting documentation.

If you elect, at time of bid, to pursue the optional small business or non-small business preference, see section 2-1.24 for the requirements arising from your request for the preference. SBE participation listed to meet the SBE participation goal requirement should not be listed for the preference.

Replace section 2-1.24 with:

2-1.24 SMALL BUSINESS AND NON–SMALL BUSINESS SUBCONTRACTOR PREFERENCES

2-1.24A General

Section 2-1.24 applies to a non-federal-aid contract.

The Department applies small business preferences and non–small business preferences under Govt Code § 14835 et seq. and 2 CA Code of Regs § 1896 et seq.

Any contractor, subcontractor, supplier, or service provider who qualifies as a small business or small business for the purpose of public works is encouraged to apply for certification as an SBE by submitting its application to the Department of General Services, Office of Small Business and DVBE Services.

The Department of General Services determines whether an SBE was certified on the bid opening date.

The Department of Transportation confirms an SBE’s certification status before applying the small business or non-small business preference.

Contract award is based on the total bid, not the reduced bid.

Pursuant to Govt Code § 14838, SBE participation listed on the Small Business Enterprise – Commitment form used to meet the SBE participation goal requirement should not be listed on the Certified Small Business Listing for the Non-Small Business Preference form. Listing the same SBE participation on both the Small Business Enterprise – Commitment form and on the Certified Small Business Listing for the Non-Small Business Preference form may result in disallowance of the SBE’s participation toward the small business or non-small business preference.

2-1.24B Small Business Preference

The Department allows a bidder certified as an SBE by the Department of General Services, Office of Small Business and DVBE Services, a preference if:

1. Bidder submitted a completed Request for Small Business Preference or Non–Small Business Preference form with its bid

2. Low bidder did not request the preference or is not certified as a small business

The Bidder's signature on the Request for Small Business Preference or Non–Small Business Preference form certifies that the Bidder is certified as an SBE at the date and time of bid or has submitted a complete application to the Department of General Services. The complete application and any required substantiating documentation must be received by the Department of General Services by 5:00 p.m. on the bid opening date.

The small business preference is a reduction for bid comparison in the total bid submitted by the small business contractor by the lesser of the following amounts:

1. 5 percent of the verified total bid of the low bidder

2. $50,000

If the Department determines that a certified small business bidder is the low bidder after the application of the small business preference, the Department does not consider a request for non–small business preference.

2-1.24C Non–Small Business Subcontractor Preference

At time of bid, the Department allows a bidder not certified as an SBE by the Department of General Services, Office of Small Business and DVBE Services, the option of requesting the non-small business subcontractor preference. If a bidder elects to pursue that option at the time of bid, the bidder is required to meet the corresponding commitment.

For the non-small business subcontractor preference, submit the following:

1. Completed Request for Small Business Preference or Non–Small Business Preference form with your bid

2. Completed Certified Small Business Listing for the Non–Small Business Preference form which shows you are subcontracting at least 25 percent to certified SBEs

Each listed SBE must be certified as a small business or small business for the purpose of public works by 5:00 p.m. on the bid opening date. The complete application and any required substantiating documentation must be received by the Department of General Services by 5:00 p.m. on the bid opening date.

Failure to submit a completed Certified Small Business Listing for the Non–Small Business Preference form by 4 p.m. on the 4th business day after bid opening will result in a nonresponsive bid.

The non–small business subcontractor preference is a reduction for bid comparison in the total bid submitted by the non–small business contractor requesting the preference by the lesser of the following amounts:

1. 5 percent of the verified total bid of the low bidder

2. $50,000

Delete section 2-1.33B(2)(b).

Replace the table in the 1st paragraph of section 2-1.33B(3)(b)(ii) with:

Bid Form Submittal Schedule for a Non-Federal-Aid Contract with a DVBE Goal Form Submittal deadline

Bid to the Department of Transportation Time of bid except for the public works contractor registration number for a joint-venture contract

For a joint-venture contract, copy of the Bid to the Department of Transportation as submitted at the time of bid with the public works contractor registration number

10 days after bid opening

Subcontractor List Time of bid In-Use Off-Road Diesel-Fueled Vehicle List 10 days after bid opening Small Business/DVBE/DBE Certification Status Time of bid Opt Out of Payment Adjustments for Price Index Fluctuationsa

Time of bid

Certified DVBE Summary No later than 4 p.m. on the 4th business day after bid opening

California Company Preference Time of bid

Small Business Enterprise – Commitment No later than 4 p.m. on the 4th business day after bid opening

Small Business Enterprise – Confirmation No later than 4 p.m. on the 4th business day after bid opening

Request for Small Business Preference or Non– Small Business Preferencea

Time of bid

Certified Small Business Listing for the Non– Small Business Preferencea

No later than 4 p.m. on the 4th business day after bid opening aSubmit only if you choose the option or preference.

Replace the table in the 1st paragraph of section 2-1.33B(3)(c)(ii) with:

Bid Form Submittal Schedule for a Non-Federal-Aid Contract without a DVBE Goal Form Submittal deadline

Bid to the Department of Transportation Time of bid except for the public works contractor registration number for a joint-venture contract

For a joint-venture contract, copy of the Bid to the Department of Transportation as submitted at the time of bid with the public works contractor registration number

10 days after bid opening

Subcontractor List Time of bid In-Use Off-Road Diesel-Fueled Vehicle List 10 days after bid opening Small Business/DVBE/DBE Certification Status Time of bid Opt Out of Payment Adjustments for Price Index Fluctuationsa

Time of bid

California Company Preference Time of bid

Certified DVBE Summaryb No later than 4 p.m. on the 4th business day after bid opening

Small Business Enterprise – Commitment No later than 4 p.m. on the 4th business day after bid opening

Small Business Enterprise – Confirmation No later than 4 p.m. on the 4th business day after bid opening

Request for Small Business Preference or Non– Small Business Preferencea

Time of bid

Certified Small Business Listing for the Non– Small Business Preferencea

No later than 4 p.m. on the 4th business day after bid opening aSubmit only if you choose the option or preference.

bSubmit only if you obtain DVBE participation or you are the apparent low bidder, 2nd low bidder, or 3rd low bidder and you choose to receive the specified incentive.

5 CONTROL OF WORK

Replace the 2nd and 3rd paragraphs of section 5-1.09A with:

For a contract with a total bid over $1 million and 100 or more working days, professionally facilitated project partnering is required.

Replace the 1st paragraph of section 5-1.09C with:

For a contract with a total bid over $1 million and 100 or more working days, training in partnering skills development is required.

Replace the 10th paragraph of section 5-1.13C with:

For the purpose of determining compliance with Pub Cont Code § 10115 et seq.:

1. At monthly periods, complete and submit a Monthly Report - Utilization of Disabled Veteran Business Enterprise (DVBE) State Funded Projects Only form

1.1. Submit the first report when determined by you and the Engineer but not later than 30 calendar days after the contract time starts.

1.2. Space subsequent report submittals 30 calendar days apart

1.3. If the thirtieth calendar day falls on a Saturday or holiday, submit the report on the following working day

2. Upon work completion, complete and submit Final Report - Utilization of Disabled Veteran Business

Enterprises (DVBE) State Funded Projects Only form

3. Upon reasonable notice and during normal business hours, permit access to its premises for the purposes of:

3.1. Interviewing employees

3.2. Inspecting and copying books, records, accounts and other material that may be relevant to a matter under investigation

The Monthly Report - Utilization of Disabled Veteran Business Enterprise (DVBE) State Funded Projects Only form, search number 11CON001, is available at:

https://forms.dot.ca.gov/

Replace section 5-1.13D with:

5-1.13D Non-Small Business Preference

5-1.13D(1) General

Section 5-1.13D applies to a non-federal-aid contract when you have obtained a non-small business subcontractor preference under section 2-1.24.

Use each SBE as shown on the Certified Small Business Listing for the Non-Small Business Preference form unless you receive authorization for a substitution under section 5-1.13D(3).

Maintain records of subcontracts and agreements made with each SBE. Include in the records:

1. SBE subcontract or agreement

2. Name and business address of each business

3. Proof of each payment made to an SBE

Upon reasonable notice and during normal business hours, permit access to the SBE premises for the purpose of:

1. Interviewing employees.

2. Inspecting and copying books, records, accounts, and other material that may be relevant to a matter under investigation.

Upon work completion, complete a Final Report – Utilization of Small Business Enterprise form and submit within 10 days of Contract acceptance. The Department withholds the greater of 10 percent of the SBE work amount or $10,000 until the form is submitted. The Department releases the withhold upon submission of the completed form. If additional payments are made to an SBE after submittal of the completed form, submit an updated form to reflect such payments.

5-1.13D(2) Commercially Useful Function

SBEs must perform a commercially useful function under 2 CA Code Regs § 1896.15 when performing tasks listed on the Certified Small Business Listing for the Non-Small Business Preference form and as a Department authorized substitute SBE. The SBE’s value of work will only count toward the non-small business preference if the SBE performs a commercially useful function under 2 CA Code Regs § 1896.15.

Provide written notification to the Engineer at least 15 days in advance of each SBE’s initial performance of work on the Contract. Include the SBE’s name, contract work to be performed, and the location, date, and time of where the SBE’s work will take place.

Monitor each SBE’s performance of a commercially useful function throughout their duration of work on the Contract. Maintain supporting documentation of commercially useful function related records. Provide copies of the following to the Department within 5 business days of a specific SBE request:

1. Subcontract or agreement with the SBE

2. Purchase orders

3. Bills of lading

4. Invoices

5. Proof of payment

You and your SBEs must submit any commercially useful function related records and documents within 5 business days of Department request such as:

1. Proof of ownership or lease and rental agreements for equipment

2. Tax records

3. Employee rosters

4. Certified payroll records

5. Inventory rosters

Notify the Engineer immediately if you believe an SBE may not be performing a commercially useful function.

Failure to submit requested records and documents, or failure of an SBE to perform a commercially useful function, will be a violation of these specifications. Such violations will result in referral to the Department of General Services, and you may be subject to sanctions under Govt Code § 14842 et seq.

5-1.13D(3) Substitutions

Substitution of an SBE may be requested for the reasons listed in Pub Cont Code § 4107. The Department will consider your SBE substitution request under 2 CA Code Regs § 1896.10. The substitute must be another SBE.

The requirement that an SBE be certified by the bid opening date does not apply to SBE substitutions after contract award.

Include in your substitution request:

1. Copy of the written notice issued to the SBE with proof of delivery

2. Copy of the SBE response to the notice

3. Your explanation of the reason for the substitution request

4. Names and certification numbers of the listed SBE and the proposed substitute SBE

5. Description of the work to be performed including dollar amount or percentage of overall contract the proposed substitute SBE will perform

6. If an SBE substitution cannot occur, written justification and the steps that were taken to try to acquire a new SBE and how that non-small business preference portion of the Contract will be fulfilled

Upon receipt of the substitution request, the listed SBE will be notified by the Department of the substitution request. The listed SBE will have 5 business days to respond. Where the listed SBE objects to the substitution, the Department will schedule a hearing.

If the Department authorizes your SBE substitution request, it will do so in writing.

Work performed by a firm other than the listed SBE or authorized substitute will be a violation of these specifications. Such violations will result in notification of the Department of General Services, and you may be subject to sanctions under Govt Code § 14842 et seq.

Replace section 5-1.13E with:

5-1.13E Prompt Payment

Section 5-1.13E applies to all contracts.

Pay your subcontractors within 7 days of receipt of each progress payment under Pub Cont Code §§ 10262 and 10262.5. Pay duly authorized motor carriers of property in dump trucks for transportation charges under Bus & Prof Code § 7108.6. Pay other entities, such as material suppliers, within 30 days of receipt of each progress payment.

Each month, after the 15th and prior to 20th, submit the following payment information through the Department’s prompt payment monitoring system at https://caltrans.dbesystem.com:

1. Subcontractor’s or entity’s business name

2. Description of work performed

2.1. Bid item numbers or change order numbers

2.2. Written narrative of work performed

3. Value of work performed

4. Amount paid to subcontractor or entity

5. Withhold amount, if applicable

6. Explanation of withhold reasoning, if applicable

Your subcontractors and other entities may validate payments received using the prompt payment monitoring system.

If a subcontractor’s or other entity’s work is in dispute, provide a written withhold notification to the subcontractor or entity and the Engineer no later than 7 days after receipt of the corresponding progress payment that includes the following:

1. Value of the disputed work

2. Amount of the withhold being taken

3. Bid item numbers or change order numbers associated with the disputed work

4. Explanation of the deficiencies of the disputed work and how the corresponding value was calculated

5. Corrective actions to be taken for release of withheld amount

The Department may request additional documentation from you to evaluate whether you applied the withhold in good faith. Submit requested documents within 10 days of receipt of request.

The Department may withhold the same amount of your withhold from a future progress pay estimate if the Department determines any of the following has occurred:

1. Withhold was not applied in good faith

2. Requested additional withhold documentation records were not provided

3. Payment information was not submitted through the prompt payment monitoring system

4. Required withhold notification was not provided

The Department may also apply a 2 percent penalty on the withhold amount for every month payment is not made.

Replace section 5-1.13F with:

5-1.13F Small Business Enterprise Participation Goal Requirement

5-1.13F(1) General

Section 5-1.13F applies to a non-federal-aid contract if an SBE participation goal requirement is shown on the Notice to Bidders.

Use each SBE as shown on the Small Business Enterprise – Commitment form unless you receive authorization for a substitution under section 5-1.13F(3).

Maintain records of subcontracts and agreements made with each SBE. Include in the records:

1. SBE subcontract or agreement

2. Name and business address of each business

3. Proof of each payment made to an SBE

Upon reasonable notice and during normal business hours, permit access to the SBE premises for the purpose of:

1. Interviewing employees.

2. Inspecting and copying books, records, accounts, and other material that may be relevant to a matter under investigation.

Upon work completion, complete a Final Report – Utilization of Small Business Enterprise form and submit within 10 days of Contract acceptance. The Department withholds the greater of 10 percent of the

SBE work amount or $10,000 until the form is submitted. The Department releases the withhold upon submission of the completed form. If additional payments are made to an SBE after submittal of the completed form, submit an updated form to reflect such payments.

5-1.13F(2) Commercially Useful Function

SBEs must perform a commercially useful function under 2 CA Code Regs § 1896.15 when performing tasks listed on the Small Business Enterprise – Commitment form and as a Department authorized substitute SBE. The SBE’s value of work will only count toward the SBE participation goal requirement if the SBE performs a commercially useful function under 2 CA Code Regs § 1896.15.

Provide written notification to the Engineer at least 15 days in advance of each SBE’s initial performance of work on the Contract. Include the SBE’s name, contract work to be performed, and the location, date, and time of where the SBE’s work will take place.

Monitor each SBE’s performance of a commercially useful function throughout their duration of work on the Contract. Maintain supporting documentation of commercially useful function related records. Provide copies of the following to the Department within 5 business days of a specific SBE request:

1. Subcontract or agreement with the SBE

2. Purchase orders

3. Bills of lading

4. Invoices

5. Proof of payment

You and your SBEs must submit any commercially useful function related records and documents within 5 business days of Department request such as:

1. Proof of ownership or lease and rental agreements for equipment

2. Tax records

3. Employee rosters

4. Certified payroll records

5. Inventory rosters

Notify the Engineer immediately if you believe an SBE may not be performing a commercially useful function.

Failure to submit requested records and documents, or failure of an SBE to perform a commercially useful function, will be a violation of these specifications. Such violations will result in referral to the Department of General Services, and you may be subject to sanctions under Govt Code § 14842 et seq.

5-1.13F(3) Substitutions

Substitution of an SBE may be requested for the reasons listed in Pub Cont Code § 4107. The Department will consider your SBE substitution request under 2 CA Code Regs § 1896.10. The substitute must be another SBE.

The requirement that an SBE be certified by the bid opening date does not apply to SBE substitutions after contract award.

Include in your substitution request:

1. Copy of the written notice issued to the SBE with proof of delivery

2. Copy of the SBE response to the notice

3. Your explanation of the reason for the substitution request

4. Names and certification numbers of the listed SBE and the proposed substitute SBE

5. Description of the work to be performed including dollar amount or percentage of overall contract the proposed substitute SBE will perform

6. If an SBE substitution cannot occur, written justification and the steps that were taken to try to acquire a new SBE and how that SBE participation goal requirement portion of the Contract will be fulfilled

Upon receipt of the substitution request, the listed SBE will be notified by the Department of the substitution request. The listed SBE will have 5 business days to respond. Where the listed SBE objects to the substitution, the Department will schedule a hearing.

If the Department authorizes your SBE substitution request, it will do so in writing.

Work performed by a firm other than the listed SBE or authorized substitute will be a violation of these specifications. Such violations will result in notification of the Department of General Services, and you may be subject to sanctions under Govt Code § 14842 et seq.

Replace section 5-1.15 with:

5-1.15 SAFETY REPRESENTATIVE

5-1.15A General

Designate an on-site safety representative to superintend project safety for the duration of this Contract.

The safety representative may perform other non-safety related work if safety responsibilities are fulfilled.

The safety representative must be available after work hours as needed. The safety representative is not required to be on-site during plant establishment period, erosion control establishment period, or temporary suspensions when no other Contract work is being performed.

Develop a written site-specific safety program (SSSP) that incorporates known hazards associated with the project.

5-1.15B Submittals

Submit a resume of the safety representative before starting work on the project, including education, completed safety training, and safety experience in heavy construction, heavy industrial, or oil and energy industry.

Submit a copy of the safety representative's certificate for the Cal/OSHA 30-hour – Cal/OSHA Standards for the Construction Industry or OSHA 510 - OSHA Standards for the Construction Industry training course as an informational submittal. The certificate must include:

1. Name of the entity providing certification

2. Name of the individual receiving certification

3. Date when the certification was provided

4. Expiration date, if applicable

Submit a copy of the SSSP as an informational submittal:

1. At least 15 days before starting work

2. At least 48 hours before starting work whenever a revision is made to the SSSP

5-1.15C Certifications

The safety representative must have completed training and received a certificate of completion for the Cal/OSHA 30-hour - Cal/OSHA Standards for the Construction Industry or OSHA 510 – OSHA Standards for the Construction Industry training course.

The safety representative must have one of the following certifications:

1. Certified Safety Professional from the Board of Certified Safety Professionals

2. Construction Health and Safety Technician from the Board of Certified Safety Professionals

3. Occupational Hygiene and Safety Technician from the Board of Certified Safety Professionals

4. Safety Trained Supervisor from the Board of Certified Safety Professionals

5. Safety Trained Supervisor Construction from the Board of Certified Safety Professionals

6. Associate Safety Professional from the Board of Certified Safety Professionals

7. Master Safety Professional from the National Association of Safety Professionals

8. Certified Safety Director from the National Association of Safety Professionals

5-1.15D Qualifications

The safety representative must be a competent and qualified person, as defined by Cal/OSHA, and must provide safety oversight on the project. The safety representative must have:

1. At least 3 years of safety experience in heavy construction, heavy industrial, or oil and energy industry

2. Knowledge in the area of safety procedure for all types of work being performed on this project

3. Knowledge of Department specifications and plans, Cal/OSHA policy and procedures, and 8 CA

Code of Regs safety requirements

The safety representative must have completed safety training and maintain valid certifications for:

1. First aid

2. Cardiopulmonary resuscitation

5-1.15E Duties and Responsibilities

The safety representative must be available by:

1. Cellular telephone

2. Two-way radio

3. Mobile internet access

The safety representative must:

1. Develop the SSSP

2. Conduct the on-site new project orientation for each worker assigned to the project

3. Review the construction work plans for each subcontractor before starting work

4. Conduct or attend pre-planning sessions for high hazard work such as excavations, demolition, confined space entry, falsework, crane hoisting, high-risk utilities such as high-pressure pipelines with fuel or natural gas, and tunneling or boring

5. Conduct weekly job site safety meetings

6. Review work schedules, including subcontractors' work schedules, to ensure adequacy of job hazard analyses and address all safety concerns and issues

7. Ensure safety data sheets are available on-site for all materials and have a hazard communication program for informing workers of material hazards

8. Verify compliance with hazardous waste requirements under section 14-11, including spill prevention and control measures

9. Conduct daily safety inspections of the job site for hazards and compliance with safety requirements in the specifications and 8 CA Code of Regs

10. Report all incidents to the Engineer immediately, including the investigation of any close calls

When monitoring the job site, including work zones with certified flaggers or traffic control technicians, take immediate corrective action and notify the Engineer if an imminent danger is identified.

If the Engineer determines the safety representative is not meeting the intended duties and responsibilities, you must replace the safety representative within 30 days of written notice from the Engineer. If you need to replace the safety representative, notify the Engineer and provide replacement safety representative resume and required certifications at least 15 days before the replacement.

You may submit a secondary safety representative to act on behalf of the designated safety representative during extended shifts, continuous operations, or short-term absences that will not exceed 14 days in duration. The secondary safety representative must meet the same required qualifications and certifications as the designated safety representative.

Add to the end of section 5-1.20A:

During the progress of the work under this Contract, work under the following contracts may be in progress at or near the job site of this Contract:

Coincident or Adjacent Contracts

Contract no. County–Route–Post Mile Location Type of work 11-2N2974 SD-8-14.6/R21.6 San Diego County PCC Slab replacement 11-432834 SD-125-9.6/15.4 San Diego County Install Trash Treatment

Systems

Coordinate lane closures and traffic handling with the Engineer and with contractors of coincident or adjacent projects. Potential conflicts may not be limited to the contracts listed above.

Add to the end of section 5-1.32:

Personal vehicles of your employees must not be parked on the traveled way or shoulders, including sections closed to traffic.

Add between the 6th and 7th paragraph of section 5-1.43E(1)(a):

DRA and DRB meetings may be held either virtually or on-site at the job location upon mutual agreement by the Contractor, the Department, and the DRA or DRB.

DRA and DRB meetings include:

1. Initial project meeting

2. Progress meetings

3. Dispute meetings

On-site meetings are held at a physical location and include on-site time, travel time, transportation, lodging, and incidentals for each day or portion thereof.

Virtual meeting includes virtual meeting time, equipment, and incidentals for each hour or portion thereof, either all or part of the DRA and DRB members, with the following requirements:

1. Obtain authorization for virtual meeting 14 days before the meeting

2. Use of Webex, Zoom or MS Teams virtual platforms

Obtain authorization for DRA or DRB members before spending any time on DRA- or DRB- related tasks.

Hourly off-site DRA and DRB related tasks include reviewing the plans, specifications, evaluating positions, preparing recommendations, completing forms, or performing any other off-site DRA- or DRB-related tasks.

Replace section 5-1.43E(1)(i) with:

5-1.43E(1)(i) Payment

Pay the DRA or each DRB member for meeting participation as follows:

1. $250 per hour for agreed hourly off-site DRA- or DRB-related tasks

2. For attending a virtual off-site meeting with a limit of $1,000 per meeting at hourly off-site DRA-or

DRB-related tasks rate

3. $2,500 per day for each on-site meeting

Department does not pay for (1) DRA- or DRB-work performed after Contract acceptance or (2) cost of preparing for or attending ADR meetings.

The Department pays:

1. $250 per hour for agreed off-site DRA- or DRB-related tasks

2. For each DRA or DRB member attending a virtual off-site meeting with a limit of $1,000 per meeting at hourly off-site DRA-or DRB-related tasks rate

3. $2,500 per DRA on-site meeting

4. Up to $7,500 per DRB on-site meeting

Payment is full compensation for each meeting and off-site DRA- or DRB-related tasks.

The Department does not adjust the unit price for an increase or decrease in the quantity of:

1. DRA on site meeting

2. DRB on site meeting

3. Hourly off-site DRA- or DRB-related task

Within 60 days of receipt of Department's payment, submit copies of associated invoices and supporting documents in the form of a canceled check or bank statement for DRA- or DRB-payment verification.

6 CONTROL OF MATERIALS

Replace section 6-1.03B with:

6-1.03B Submittals

6-1.03B(1) General

Not Used

6-1.03B(2) Work Plan

For local material, such as rock, gravel, earth, structure backfill, pervious backfill, imported borrow, and culvert bedding, obtained from a (1) noncommercial source, or (2) source not regulated under California jurisdiction, submit a local material plan for each material at least 60 days before placing the material. The local material plan must include:

1. Certification signed by you and an engineer who is registered as a civil engineer in the State or a professional geologist licensed as a professional geologist by the State stating:

I am aware local material from a noncommercial source or a source not regulated under CA jurisdiction must be sampled and analyzed for pH and lead and may require sampling and analysis under section 6-1.03B(3) for other constituents of concern based on the land use history. I am aware that local material sources must not contain ADL at concentrations greater than 80 mg/kg total lead or equal to or greater than 5 mg/L soluble lead as determined by the Waste Extraction Test (WET) Procedures, 22 CA Code of Regs § 66261.24(a)(2) App II. I am aware that a maximum quantity of material may be excavated at the site based on the minimum number of samples taken before excavating at the site under section 6-1.03B(3).

2. Land use history of the local material location and surrounding property

3. Sampling protocol

4. Number of samples per volume of local material

5. QA and QC requirements and procedures

6. Qualifications of sampling personnel

7. Stockpile history

8. Name and address of the analytical laboratory that will perform the chemical analyses

9. Analyses that will be performed for lead and pH

10. Other analyses that will be performed for possible hazardous constituents based on:

10.1. Source property history

10.2. Land use adjacent to source property

10.3. Constituents of concern in the ground water basin where the job site is located

The plan must be sealed and signed by an engineer who is registered as a civil engineer in the State or a professional geologist licensed as a professional geologist by the State.

If the plan requires revisions, the Engineer provides comments. Submit a revised plan within 7 days of receiving comments. Allow 7 days for the review.

6-1.03B(3) Analytical Test Results

At least 15 days before placing local material, submit analytical test results for each local material obtained from a noncommercial source or a source not regulated under CA jurisdiction. The analytical test results must include:

1. Certification signed by an engineer who is registered as a civil engineer in the State or a professional geologist licensed as a professional geologist by the State stating:

The analytical testing described in the local material plan has been performed. I performed a statistical analysis of the test results using the US EPA's ProUCL software with the applicable 95 percent upper confidence limit. I certify that the material from the local material source is suitable for unrestricted use at the job site, it has a pH above 5.0, does not contain soluble lead in concentrations equal to or greater than 5mg/l as determined by the Waste Extraction Test (WET) Procedures, 22 CA Code of Regs § 66261.24(a)(2) App II, does not contain lead in concentrations above 80 mg/kg total lead, is free from all other contaminants identified in the local material plan, and will comply with the job site's basin plan and water quality objectives of the RWQCB.

2. Chain of custody of samples

3. Analytical results no older than 1 year

4. Statistical analysis of the data using US EPA’s ProUCL software with a 95 percent upper confidence limit

5. Comparison of sample results to hazardous waste concentration thresholds and the RWQCB's basin plan requirements and water quality objectives for the job site location

6-1.03B(4) Sample and Analysis

Sample and analyze local material from a (1) noncommercial source or (2) a source not regulated under CA jurisdiction:

1. Before bringing the local material to the job site

2. As described in the local material plan

3. Under US EPA Test Methods for Evaluating Solid Waste, Physical/Chemical Methods (SW-846)

The sample collection must be designed to generate a data set representative of the entire volume of proposed local material.

Before excavating at the (1) noncommercial material source or (2) a source not regulated under CA jurisdiction, collect the minimum number of samples and perform the minimum number of analytical tests for the corresponding maximum volume of local material as shown in the following table:

Minimum Number of Samples and Analytical Tests for Local Material

Maximum volume of imported borrow (cu yd)

Minimum number of samples and analytical tests

< 5,000 8

5,000–10,000 12…

This is the start of the file's text. The full file is on GovTribe.