c.Review structural damage expected to be found during removal of architectural finishes.
Incorporate recommendations into interactive pdf and REVIT Model.
d.Meet with Design/Build Engineer and the GSA Structural Engineer to advise on extent of repairs needed at unobservable locations. Advise on best methods to maintain permanent access points to provide for ability to inspect and make repairs in the future. Responsibility for implementation of the actual repairs shall lie with the Design/Build Team.
e.Provide construction observation and reports to verify that the work as constructed in Building 7 meets the intent of the Report.
4. Technical and Requirements Certification:
I certify the data under my cognizance which are included in this J&A are accurate and complete to the best of my knowledge and belief.
10/12/2012
X William Garrott
Project Manager, GSA R10 PBS GPSSC
X Pete Blakely, PE, SE ...
GSA Region 10 PBS Structural Engineer
5. Contracting Officer Decision: This exemption to the fair opportunity process is approved, in accordance with FAR Subsection 16.505(b)(2)(i)(C)), in the interest of economy and efficiency because it is a logical follow-on to order GS-P-10-12-XB-0010 already issued under the contract.
X Dwayne Cannon, SR. Contracting Officer