This file is a Questions and Answers (Q&A) document for a Request for Information (RFI) regarding a Cislunar Space System (CSS) acquisition. The Government is seeking market research information to develop an acquisition strategy for up to five space vehicles capable of operating throughout cislunar space, including Earth-Moon transfers, libration point orbits, resonant orbits, and low-energy transfers to Sun-Earth L1/L2. Each space vehicle must accommodate a Government-provided payload (up to 2,000 kg, 3m × 1m × 1m envelope, 1–3 kW power), operate autonomously for at least 72 hours, maintain a design life of 3–5 years with 0.6 reliability threshold, and comply with orbital debris mitigation standards. The CSS will include spacecraft buses, integration and testing, ground segment operations (mission management, telemetry, tracking, control, and communications), space launch integration, and operations and maintenance support.
The Government anticipates awarding up to five Firm Fixed Price preliminary design study contracts following evaluation of RFI responses and intends notional procurement of the five space vehicles in late Calendar Year 2029, with Initial On-orbit Capability (IOC) defined as successful launch, initialization, and checkout of a minimum of one mission-ready cislunar space vehicle with its operational ground segment by Calendar Year 2031. Key uncertainties addressed in this Q&A include delta-V requirements for cislunar orbit transfers, injection orbit specifications, payload data processing scope, ground segment security and hosting models, autonomous operations definitions, positioning/navigation/timing requirements, end-of-life disposal methods compliant with Orbital Debris Mitigation Standard Practices, bus qualification heritage standards, and the distinction between artificial intelligence and "super intelligence" capabilities. The Government repeatedly declines to provide specific technical performance details, directing respondents to state reasonable assumptions. Launch services and cryptographic requirements will be provided as Government-furnished items. Respondents may serve as prime contractors on one response and as subcontractors on others, and they are encouraged to propose scalable platform variants and alternative launch approaches including commercial rideshare options.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| CSS_401.2.20261119 - RFI Questions Responses Batch 2.xlsx | XLSX spreadsheet | |
| (U) CSS RFI_2026_11_03_Final v2.pdf | ||
| (U) CSS RFI_2026_10_30 Final.pdf | ||
| Atch 1 to CSS RFI_Summary Response Template.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| Question | Question | Proposed Response |
| Q-001 | Can you provide estimated delta-Vs required for the host spacecraft? |
| Or perhaps clarify an example cislunar orbit transfer per following requirement to define max dV expected “Propulsive maneuverability to support cislunar orbit transfer, orbit insertions, and orbit station keeping.” | The intent of the RFI is to explore industry's capabilities and inform the Government's acquisition strategy. The Government does not intend to provide any additional details at this time regarding the Technical Performance Objectives documented in the RFI. Respondents are encouraged to state their assumptions regarding information that, while not provided in the RFI, may be relevant to understanding their RFI response. | ||
| Q-002 | Regarding the subject RFI, are you interested in reviewing non-compliant responses? | Although the Government will review all responses submitted by industry, as stated in the RFI our primary interest is in respondents that have experience developing integrated systems capable of operating in the cislunar environment. | |
| Q-003 | Can clarification be provided on the 6-DOF thruster requirement? Are there reference maneuvers or slews that drive the 6 DOF thruster requirement outside of standard momentum management or attitude control, and if so could they be provided? | The intent of the RFI is to explore industry's capabilities and inform the Government's acquisition strategy. The Government does not intend to provide any additional details at this time regarding the Technical Performance Objectives documented in the RFI. Respondents are encouraged to state their assumptions regarding information that, while not provided in the RFI, may be relevant to understanding their RFI response. | |
| Q-004 | Can clarification be provided on the preferred end of life disposal method? ODMSP does not specify preferred cislunar disposal method, though recent guidance has suggested either heliocentric or deep space disposal is preferred over lunar disposal. | The intent of the RFI is to explore industry's capabilities and inform the Government's acquisition strategy. The Government does not intend to provide any additional details at this time regarding the Technical Performance Objectives documented in the RFI. Respondents are encouraged to state their assumptions regarding information that, while not provided in the RFI, may be relevant to understanding their RFI response. | |
| Q-005 | Can clarification be provided on an estimated per vehicle payload mission data downlink per day requirement that can be used for ground system performance evaluation? | The intent of the RFI is to explore industry's capabilities and inform the Government's acquisition strategy. The Government does not intend to provide any additional details at this time regarding the Technical Performance Objectives documented in the RFI. Respondents are encouraged to state their assumptions regarding information that, while not provided in the RFI, may be relevant to understanding their RFI response. | |
| Q-006 | Can clarification be provided on what is meant by IOC in CY31? Does this mean all five satellites need to arrive at the target orbits and be fully activated by the beginning of CY31, or just a subset? | IOC is defined as successful launch, initialization and on-orbit checkout of a minimum of one (1) mission ready cislunar SV with its operational Ground Segment. | |
| Q-007 | Does the DAF provide concurrence that launch services and crypto will be provided as GFX for the CSS? | Respondents may assume that launch services and cryptographical requirements will be provided as GFX. | |
| Q-008 | Can clarification be provided on what ground data processing is expected? | The intent of the RFI is to explore industry's capabilities and inform the Government's acquisition strategy. The Government does not intend to provide any additional details at this time regarding the Technical Performance Objectives documented in the RFI. Respondents are encouraged to state their assumptions regarding information that, while not provided in the RFI, may be relevant to understanding their RFI response. | |
| Q-009 | Are there expected frequency bands that will be approved for usage for this mission? | The intent of the RFI is to explore industry's capabilities and inform the Government's acquisition strategy. The Government does not intend to provide any additional details at this time regarding the Technical Performance Objectives documented in the RFI. Respondents are encouraged to state their assumptions regarding information that, while not provided in the RFI, may be relevant to understanding their RFI response. | |
| Q-010 | Is there a preference for a type of propulsion? | The intent of the RFI is to explore industry's capabilities and inform the Government's acquisition strategy. The Government does not intend to provide any additional details at this time regarding the Technical Performance Objectives documented in the RFI. Respondents are encouraged to state their assumptions regarding information that, while not provided in the RFI, may be relevant to understanding their RFI response. | |
| Q-011 | Can more intention for autonomous operations be shared. i.e. is the ask for the system to be able to execute loaded commands for 72 hours or something else? | The intent of the RFI is to explore industry's capabilities and inform the Government's acquisition strategy. The Government does not intend to provide any additional details at this time regarding the Technical Performance Objectives documented in the RFI. Respondents are encouraged to state their assumptions regarding information that, while not provided in the RFI, may be relevant to understanding their RFI response. | |
| Q-012 | 1. Cislunar Tug Capability: Is a LEO-to-LLO cislunar transportation capability within the intended scope of this RFI? |
2. Reusability: While not specifically identified in the RFI, is vehicle reusability considered a desirable attribute for proposed solutions?
3. Refuelability: Similarly, is on-orbit refueling capability of interest, even though it is not explicitly addressed in the RFI?
4. Platform Variants: May the five requested vehicles be structured as scalable platform variants?
5. Payload Delivery: Should payload delivery capability be assessed on a wet-mass basis, dry-mass basis, or both?
6. Mission Timeline: Is there a preferred or target mission execution timeframe (days, months, or years) that respondents should optimize against?
7. Power Levels: For a potential Orbital Transfer Vehicle (OTV) solution, would a 300 kWe platform be considered responsive to the RFI?
8. Qualification Requirements: Regarding Section 6.A.2, would flight heritage gained through integration on a prime contractor's previously qualified spacecraft platform satisfy the intent of the qualification criteria, or are there additional requirements that should be considered?
| 9. Relevant Experience: With respect to the requested description of cislunar-domain expertise and experience supporting classified government space systems, are there any limitations, preferences, or additional guidance regarding the level of detail respondents should provide? | The intent of the RFI is to explore industry's capabilities and inform the Government's acquisition strategy. The Government does not intend to provide any additional details at this time regarding the Technical Performance Objectives documented in the RFI. Respondents are encouraged to state their assumptions regarding information that, while not provided in the RFI, may be relevant to understanding their RFI response. | |
| Q-013 | Bus heritage and NRE |
a. Recent cislunar and deep-space spacecraft procured by NASA, NOAA, and AFRL (for example CAPSTONE, SWFO-L1, and Oracle-M) used commercial bus product lines that were adapted for their first flight beyond GEO, rather than buses with prior cislunar flight. Will the Government apply a comparable standard for this effort, accepting product-line or subsystem flight heritage plus cislunar-specific adaptation and qualification? If so, how will it treat subsystem flight history, TRL, or completion of system AI&T within 24 months? Must the heritage be demonstrated at the time of the RFI response or by a later milestone such as PDR?
b. Given the payload class (up to 2,000 kg, 1–3 kW), does the Government anticipate some NRE to scale a design that is already in place? How, in that case, should respondents characterize “minimal NRE”? a. The Government is not applying standards, it is assessing current marketplace capabilities to inform its acquisition strategy. There is no current requirement for demonstration of heritage. The Government is assessing the current and planned maturity of the marketplace.
b. The RFI states that the Government is looking for industry's "ability to provide a rapid, low-risk (minimal non-recurring engineering (NRE)) solution." This means that there is not an expectation of zero NRE. In the context of a low risk solution, respondents should interpret less NRE as being lower risk than more NRE.
| Q-014 | Security | |
| What is the anticipated classification level of the program and payload, and what facility clearance level will be required at the preliminary design study award? | The Government does not currently have a predetermined classification level for the program/payload. The Government is exploring the market place for existing, low-risk capabilities. | |
| Q-015 | Mission and launch |
a. What injection orbit should respondents assume from the Government-provided NSSL booster? Will the Government consider approaches in which SVs are delivered to LEO or GTO and perform their own transfer to cislunar space?
b. What operational orbits are envisioned for the initial SVs?
c. Should respondents assume all SVs launch on a single Government-provided NSSL mission or may respondents propose alternative or self-procured launch, for example rideshare or a dedicated commercial launch?
| d. Are there reference payloads, or an expected range of payload mass, power, and volume, that respondents should design to? Should respondents baseline the 2,000 kg upper limit, and will all SVs host the same payload type? | The intent of the RFI is to explore industry's capabilities and inform the Government's acquisition strategy. The Government does not intend to provide any additional details at this time regarding the Technical Performance Objectives documented in the RFI. Respondents are encouraged to state their assumptions regarding information that, while not provided in the RFI, may be relevant to understanding their RFI response. | |
| Q-016 | Collaboration with others |
| Under “one approach per company,” may a company serve as prime on one response and as a subcontractor or supplier on other teams’ responses? | Yes | ||
| Q-017 | Is there an opportunity to schedule a brief discussion with the TPOC to clarify requirements, or is engagement limited to written questions and answers? | No | |
| Q-018 | The RFI specifies a maximum payload mass of 2,000 kg and a maximum payload envelope of 3 × 1 × 1 m. Would the government consider smaller spacecraft buses with more limited payload capacities, such as 50 kg? | The intent of the RFI is to explore industry's capabilities and inform the Government's acquisition strategy. The Government does not intend to provide any additional details at this time regarding the Technical Performance Objectives documented in the RFI. Respondents are encouraged to state their assumptions regarding information that, while not provided in the RFI, may be relevant to understanding their RFI response. | |
| Q-019 | If smaller spacecraft are eligible, would the government consider solutions that meet the lower end of the specified power range, proportional to their smaller payload capacity? | The intent of the RFI is to explore industry's capabilities and inform the Government's acquisition strategy. The Government does not intend to provide any additional details at this time regarding the Technical Performance Objectives documented in the RFI. Respondents are encouraged to state their assumptions regarding information that, while not provided in the RFI, may be relevant to understanding their RFI response. | |
| Q-020 | The Cislunar Coordination Office is currently partnering with SpaceWERX to mature cislunar SDA capabilities through its Direct-to-Phase II challenge. Are performers from this effort anticipated to be a source of government-furnished payloads for the CSS program, or have other payloads already been identified? | The Government does not have specific payloads in mind for purposes of this market research. | |
| Q-021 | At what stage does the government anticipate identifying and pairing government-furnished payloads with spacecraft providers? | The Government is using this RFI to help develop its acquisition strategy. | |
| Q-022 | Could you clarify the anticipated scope and deliverables of the preliminary design study contracts? | No. The Government is using this RFI to help develop its acquisition strategy. | |
| Q-023 | Payload |
a. Is the 2,000 kg not-to-exceed (NTE) value a mandatory payload accommodation capability for every space vehicle (SV), or an upper bound across possible payloads?
b. What actual payload masses, margins, and centers of gravity should respondents assume for the first five vehicles?
c. Are there jitter, pointing, or other spacecraft design considerations for the envisioned payload(s)?
d. Is the total payload mass envisioned as multiple different payloads, sensors, or instruments per
| spacecraft? | The intent of the RFI is to explore industry's capabilities and inform the Government's acquisition strategy. The Government does not intend to provide any additional details at this time regarding the Technical Performance Objectives documented in the RFI. Respondents are encouraged to state their assumptions regarding information that, while not provided in the RFI, may be relevant to understanding their RFI response. | |
| Q-024 | Simultaneous Payload Limits |
a. Must each SV simultaneously accommodate a 2,000 kg payload, dimensions of 3 m × 1 m × 1 m, and the 3 kW power objective, or are these independent maxima?
b. Is 1 kW the acceptable design threshold for payload power?
c. Are there threshold and/or objective payload thermal-management requirements? For example, a payload requiring 1 kW of input power may require approximately 0.5–1 kW of heat rejection
| through spacecraft radiators. | The intent of the RFI is to explore industry's capabilities and inform the Government's acquisition strategy. The Government does not intend to provide any additional details at this time regarding the Technical Performance Objectives documented in the RFI. Respondents are encouraged to state their assumptions regarding information that, while not provided in the RFI, may be relevant to understanding their RFI response. | |
| Q-025 | Launch Quantity / Campaign |
a. Does the Government envision one NSSL launch for all five SVs or multiple Government-provided launches?
| b. May industry propose one, two, or more spacecraft per launch and a phased fleet deployment? | The intent of the RFI is to explore industry's capabilities and inform the Government's acquisition strategy. The Government does not intend to provide any additional details at this time regarding the Technical Performance Objectives documented in the RFI. Respondents are encouraged to state their assumptions regarding information that, while not provided in the RFI, may be relevant to understanding their RFI response. | |
| Q-026 | Injection Performance |
a. What Government-provided National Security Space Launch (NSSL) booster and launch configuration should be assumed?
b. Please provide mission-specific net delivered mass to translunar injection (TLI) at the reference C3, including treatment of adapters and margins, fairing constraints, and separation conditions.
c. Which transfers and orbit insertions must be performed by the SV?
d. Are any transfers or orbit insertions envisioned to use an orbital transfer vehicle (OTV) to reduce
| spacecraft propellant consumption? | The intent of the RFI is to explore industry's capabilities and inform the Government's acquisition strategy. The Government does not intend to provide any additional details at this time regarding the Technical Performance Objectives documented in the RFI. Respondents are encouraged to state their assumptions regarding information that, while not provided in the RFI, may be relevant to understanding their RFI response. | |
| Q-027 | Deployment Sequence |
a. Does late CY2029 refer to first launch or delivery of all five vehicles?
b. What capability and fleet quantity are required for initial on-orbit operations in CY2031?
c. Please define Operational Initial On-orbit Capability in CY2031, including the required number of operational spacecraft.
d. Please define Full Operational Capability.
| e. Are target orbit assignments available? | The intent of the RFI is to explore industry's capabilities and inform the Government's acquisition strategy. The Government does not intend to provide any additional details at this time regarding the Technical Performance Objectives documented in the RFI. Respondents are encouraged to state their assumptions regarding information that, while not provided in the RFI, may be relevant to understanding their RFI response. | |
| Q-028 | Bus Qualification / Heritage |
a. How will the Government evaluate an “existing cislunar qualified bus design”?
b. Is completion of system-level assembly, integration, and test (AI&T) within the next 24 months an acceptable alternative to recent flight of the proposed design?
| c. How will the Government evaluate heritage for a derivative bus? | The intent of the RFI is to explore industry's capabilities and inform the Government's acquisition strategy. The Government does not intend to provide any additional details at this time regarding the Technical Performance Objectives documented in the RFI. Respondents are encouraged to state their assumptions regarding information that, while not provided in the RFI, may be relevant to understanding their RFI response. | |
| Q-029 | Mission Data / Communications / PNT |
a. Can the DAF provide expected mission-data volumes, latency and tasking timelines, Earth-contact or coverage requirements, positioning, navigation, and timing (PNT) performance needs, and any mandated Government communications interfaces?
b. Are all communications links envisioned as direct-to-Earth, or may communication-relay satellites be used
| The intent of the RFI is to explore industry's capabilities and inform the Government's acquisition strategy. The Government does not intend to provide any additional details at this time regarding the Technical Performance Objectives documented in the RFI. Respondents are encouraged to state their assumptions regarding information that, while not provided in the RFI, may be relevant to understanding their RFI response. | |
| Q-030 | Payload / Cyber Interfaces |
a. Will payload interface-control data and any classified handling requirements be made available?
b. What are the assumed NSA Type-I cryptographic boundary, key-management responsibilities, and Government-furnished payload/interface provisions?
| The intent of the RFI is to explore industry's capabilities and inform the Government's acquisition strategy. The Government does not intend to provide any additional details at this time regarding the Technical Performance Objectives documented in the RFI. Respondents are encouraged to state their assumptions regarding information that, while not provided in the RFI, may be relevant to understanding their RFI response. | |
| Q-031 | Super Intelligence |
a. Please define “Super Intelligence” (SI), including the expected demonstration, onboard
| compute/storage capability, or autonomy standard beyond the stated 72-hour autonomous operation requirement. | The intent of the RFI is to explore industry's capabilities and inform the Government's acquisition strategy. The Government does not intend to provide any additional details at this time regarding the Technical Performance Objectives documented in the RFI. Respondents are encouraged to state their assumptions regarding information that, while not provided in the RFI, may be relevant to understanding their RFI response. | |
| Q-032 | Mission Operations |
a. Will the DAF provide design reference mission (DRM) scenarios?
b. Will each payload or spacecraft have a different DRM?
c. Please clarify the Orbital Debris Mitigation Standard Practices (ODMSP) end-of-life disposal criteria applicable to the envisioned operating regimes, including libration-point orbits, resonant orbits,
| and low-energy transfer trajectories to Sun–Earth L1/L2. | The intent of the RFI is to explore industry's capabilities and inform the Government's acquisition strategy. The Government does not intend to provide any additional details at this time regarding the Technical Performance Objectives documented in the RFI. Respondents are encouraged to state their assumptions regarding information that, while not provided in the RFI, may be relevant to understanding their RFI response. | ||
| Q-033 | The RFI uses the term “system.” Would a company such as XXXXX, which specializes in ground systems, be able to submit a response focused solely on the ground system, or is the Government seeking turnkey systems that include the space vehicle, ground segment, communications, and launch integration? | Although the Government will review all responses submitted by industry, as stated in the RFI our primary interest is in respondents that have experience developing integrated systems capable of operating in the cislunar environment. | |
| Q-034 | Is there a preference for a type of propulsion? | The intent of the RFI is to explore industry's capabilities and inform the Government's acquisition strategy. The Government does not intend to provide any additional details at this time regarding the Technical Performance Objectives documented in the RFI. Respondents are encouraged to state their assumptions regarding information that, while not provided in the RFI, may be relevant to understanding their RFI response. | |
| Q-035 | Can more intention for autonomous operations be shared. i.e. is the ask for the system to be able to execute loaded commands for 72 hours or something else? | The intent of the RFI is to explore industry's capabilities and inform the Government's acquisition strategy. The Government does not intend to provide any additional details at this time regarding the Technical Performance Objectives documented in the RFI. Respondents are encouraged to state their assumptions regarding information that, while not provided in the RFI, may be relevant to understanding their RFI response. | |
| Q-036 | Section 4, item 2 identifies the operating regime as "throughout cislunar space to include Earth-Moon transfers, libration point orbits, resonant orbits, and low energy transfers to Sun-Earth L1/L2." Will the Government provide a design reference mission or a bounding orbit set for the space vehicle? These regimes do not share a thermal, plasma or illumination environment: a low lunar orbit vehicle sees up to approximately 1,250 W/m2 of lunar long-wave radiance and on the order of 4,460 eclipses per year, while a near-rectilinear halo orbit avoids eclipse by design and is thermally gentler than geosynchronous orbit. Radiator sizing, battery capacity, battery cycle life and orbit-maintenance propellant cannot be bounded without this. Additionally, is each space vehicle to be qualified for all listed regimes, or is a regime assigned per vehicle across the five-vehicle set? | The intent of the RFI is to explore industry's capabilities and inform the Government's acquisition strategy. The Government does not intend to provide any additional details at this time regarding the Technical Performance Objectives documented in the RFI. Respondents are encouraged to state their assumptions regarding information that, while not provided in the RFI, may be relevant to understanding their RFI response. | |
| Q-037 | Section 6.B, item 7 requires an "existing cislunar qualified bus design." Will the Government credit a geosynchronous qualification pedigree in the environments where the geosynchronous case demonstrably envelopes the cislunar case? Per SLS-SPEC-159 Rev I, total ionizing dose at geosynchronous orbit exceeds the cislunar case at every shielding depth; worst-case surface charging electron temperature is three to seven times higher at geosynchronous orbit; internal dielectric charging from trapped relativistic electrons has no cislunar analogue; and GEO/cislunar regimes are assigned identical single event effects environment. Any thermal or power differences are based on orbits, which is asked in the question above | The intent of the RFI is to explore industry's capabilities and inform the Government's acquisition strategy. The Government does not intend to provide any additional details at this time regarding the Technical Performance Objectives documented in the RFI. Respondents are encouraged to state their assumptions regarding information that, while not provided in the RFI, may be relevant to understanding their RFI response. | |
| Q-038 | Section 6.A, item 5.f directs respondents to state assumptions regarding use of their own command media and commercial standards. Does the Government intend that direction to extend to the natural environment specification and the qualification test standard, or will the Government specify them? If specified, respondents request identification of the governing documents and revisions. | The intent of the RFI is to explore industry's capabilities and inform the Government's acquisition strategy. The Government does not intend to provide any additional details at this time regarding the Technical Performance Objectives documented in the RFI. Respondents are encouraged to state their assumptions regarding information that, while not provided in the RFI, may be relevant to understanding their RFI response. | |
| Q-039 | Section 6.E, item 18 states that space vehicle integration is onto a Government-provided National Security Space Launch booster. What injection state will the booster deliver, a trans-lunar injection or an Earth parking orbit from which the space vehicle performs its own transfer? The answer sets both the space vehicle delta-V requirement and the transit radiation dose. A single trans-lunar injection pass through the trapped belts is approximately 2.9 krad(Si) behind 2.5 mm of aluminum and is negligible against the mission budget, whereas a low-thrust spiral transfer accrues dose over months and can rival or exceed the operational-orbit dose. This question therefore bears on bus class, propellant load and parts selection simultaneously. | The intent of the RFI is to explore industry's capabilities and inform the Government's acquisition strategy. The Government does not intend to provide any additional details at this time regarding the Technical Performance Objectives documented in the RFI. Respondents are encouraged to state their assumptions regarding information that, while not provided in the RFI, may be relevant to understanding their RFI response. | |
| Q-040 | Section 4, item 8 states that the system may leverage existing Government or commercial communication capabilities. Will the Government provide access to the Deep Space Network or an equivalent cislunar-capable ground network as a Government Furnished item, and if so will the owning organization confirm willingness to provide it as Section 6.A, item 5.e requires? Free-space path loss in lunar orbit is approximately 20.6 dB greater than at geosynchronous orbit, a factor of 115 in power, and one-way light time is approximately 1.28 seconds, so aperture availability and scheduling priority are first-order drivers of both the communication architecture and the recurring cost estimate. | The intent of the RFI is to explore industry's capabilities and inform the Government's acquisition strategy. The Government does not intend to provide any additional details at this time regarding the Technical Performance Objectives documented in the RFI. Respondents are encouraged to state their assumptions regarding information that, while not provided in the RFI, may be relevant to understanding their RFI response. | |
| Q-041 | Section 6.B, item 7 requires that the respondent or respondent team has integrated the proposed bus and has either flown it "within the past three (3) years" or has taken or will take it through system-level Assembly, Integration and Test "within the next twenty-four (24) months." From what reference date do these two windows run, the RFI issue date or the assumed Authority to Proceed in 2QFY27? The difference is approximately six months of eligible flight history and materially affects which bus designs qualify. | The intent of the RFI is to explore industry's capabilities and inform the Government's acquisition strategy. The Government does not intend to provide any additional details at this time regarding the Technical Performance Objectives documented in the RFI. Respondents are encouraged to state their assumptions regarding information that, while not provided in the RFI, may be relevant to understanding their RFI response. | |
| Q-042 | Section 4, item 4 gives a total payload mass not to exceed 2,000 kg and payload dimensions not to exceed 3 m by 1 m by 1 m. Is this a single monolithic payload, or an aggregate allocation across multiple Government-provided payloads on one space vehicle? The answer drives the modular payload-to-bus interface approach requested at Section 6.F, item 20, the primary structure design, and the concept drawings requested at Section 6.E, item 19. | The intent of the RFI is to explore industry's capabilities and inform the Government's acquisition strategy. The Government does not intend to provide any additional details at this time regarding the Technical Performance Objectives documented in the RFI. Respondents are encouraged to state their assumptions regarding information that, while not provided in the RFI, may be relevant to understanding their RFI response. | |
| Q-043 | Section 4, item 5 specifies payload power of 1 kW threshold and 3 kW objective. Are these values orbit-average continuous power or peak power, and are they required concurrently with full bus operation including propulsive maneuvering and communication? Solar array area, battery capacity and thermal rejection sizing differ substantially between the continuous and peak interpretations. | The intent of the RFI is to explore industry's capabilities and inform the Government's acquisition strategy. The Government does not intend to provide any additional details at this time regarding the Technical Performance Objectives documented in the RFI. Respondents are encouraged to state their assumptions regarding information that, while not provided in the RFI, may be relevant to understanding their RFI response. | |
| Q-044 | Section 4, item 1 specifies a design life including on-orbit checkout of 3 years threshold and 5 years objective. Does the design life clock start at launch, at completion of on-orbit checkout, or at arrival in the operational orbit? For a cislunar mission the transfer and commissioning phase can consume a material fraction of a three-year life, and the Section 5 schedule objective separates Initial Launch Capability in late CY29 from Operational Initial On-orbit Capability in CY31. | The intent of the RFI is to explore industry's capabilities and inform the Government's acquisition strategy. The Government does not intend to provide any additional details at this time regarding the Technical Performance Objectives documented in the RFI. Respondents are encouraged to state their assumptions regarding information that, while not provided in the RFI, may be relevant to understanding their RFI response. | |
| Q-045 | Does the Government require survival of a lunar eclipse? SLS-SPEC-159 Rev I Table 3.3.9.1.4-1 gives a bounding case of 233 minutes of zero solar flux at 100 km circular lunar orbit, including 188 minutes of totality during which incident flux falls to between 0.03 percent and zero of nominal. Whether this class of event is a required survival case or an accepted risk within the design life drives battery capacity and survival heater sizing directly. | The intent of the RFI is to explore industry's capabilities and inform the Government's acquisition strategy. The Government does not intend to provide any additional details at this time regarding the Technical Performance Objectives documented in the RFI. Respondents are encouraged to state their assumptions regarding information that, while not provided in the RFI, may be relevant to understanding their RFI response. | |
| Q-046 | Section 4, item 1 specifies 0.6 reliability at three years threshold and five years objective, with "adequate expendables/wear-out resources to support five years of mission." Against what environment and what failure-rate data basis is reliability to be computed? No fielded cislunar population exists from which to derive mean time between failures at this production quantity; will the Government accept a parent-program failure modes, effects and criticality analysis and reliability prediction in lieu? Separately, the expendables and wear-out statement cannot be sized without the operating regime, since battery cycle count varies by approximately a factor of fifty between low lunar orbit and a halo orbit and orbit-maintenance propellant varies with gravity field exposure. | The intent of the RFI is to explore industry's capabilities and inform the Government's acquisition strategy. The Government does not intend to provide any additional details at this time regarding the Technical Performance Objectives documented in the RFI. Respondents are encouraged to state their assumptions regarding information that, while not provided in the RFI, may be relevant to understanding their RFI response. | |
| Q-047 | Section 4, item 3.d requires end-of-life disposal capability compliant with the Orbital Debris Mitigation Standard Practices (ODMSP). A full-text review of the November 2019 ODMSP finds no occurrence of cislunar, libration, Lagrange, resonant orbit or Earth-Moon anywhere in the document; its disposal practices are defined solely for two protected regions, low Earth orbit by atmospheric reentry and geosynchronous orbit by transfer to a graveyard orbit above GEO. No disposal pathway is defined for a vehicle that is in neither region at end of mission, which is the case for every regime in Section 4, item 2. Respondents request the Government's required disposal end state for each regime, and confirmation of whether an analogized extension of geosynchronous graveyarding, justified by rationale in a disposal assessment, is an acceptable compliance approach. | The intent of the RFI is to explore industry's capabilities and inform the Government's acquisition strategy. The Government does not intend to provide any additional details at this time regarding the Techncial Performance Objectives documented in the RFI. Respondents are encouraged to state their assumptions regarding information that, while not provided in the RFI, may be relevant to understanding their RFI response. | |
| Q-048 | The RFI and its attachment use different terms for the same item. Section 6.B, item 11 requests experience using "Super Intelligence (SI) to manage autonomous SV operations over extended durations." Attachment 1, Summary Response Template, RFI Responses tab, item 11 requests experience using "Artificial Intelligence to manage autonomous SV operations over extended durations" and refers to "an AI managed autonomous operations capability." Which term governs? If Artificial Intelligence is intended, respondents request confirmation. If Super Intelligence is intended as a distinct capability class, respondents request the Government's definition, since the term is not defined in the RFI and the on-board compute and storage answer depends on it. | Any references to AI in RFI documents should be interpreted as SI. | |
| Q-049 | Section 4, item 3.a requires autonomous operation for at least 72 hours. Does this mean 72 hours with no ground contact available, or 72 hours with no operator intervention while scheduled contacts continue? The first interpretation sizes on-board data storage, autonomous fault management authority and on-board orbit determination; the second is principally a ground automation requirement. | The intent of the RFI is to explore industry's capabilities and inform the Government's acquisition strategy. The Government does not intend to provide any additional details at this time regarding the Technical Performance Objectives documented in the RFI. Respondents are encouraged to state their assumptions regarding information that, while not provided in the RFI, may be relevant to understanding their RFI response. | |
| Q-050 | Section 6.B, item 8 requests the planned approach for cislunar Positioning, Navigation and Timing. Does the Government baseline a particular lunar gravity model for orbit determination and payload geolocation, for example a GRAIL-derived model, and does the Government intend to make any cislunar navigation or relay service available during the period of performance? Orbit determination accuracy claims and any geolocation accuracy derived from them depend on the assumed model and on whether a navigation service exists. | The intent of the RFI is to explore industry's capabilities and inform the Government's acquisition strategy. The Government does not intend to provide any additional details at this time regarding the Technical Performance Objectives documented in the RFI. Respondents are encouraged to state their assumptions regarding information that, while not provided in the RFI, may be relevant to understanding their RFI response. | |
| Q-051 | Section 6.C, item 13 requests a description of any cloud hosting requirements for the ground segment. Will the Government furnish an accredited hosting environment and Authority to Operate, and at what classification levels, or is the respondent to propose and accredit its own hosting environment? Accreditation timelines are a principal schedule driver for a ground segment supporting an Initial Launch Capability in late CY29, and the answer determines whether accreditation is Government-furnished scope or respondent scope. | The intent of the RFI is to explore industry's capabilities and inform the Government's acquisition strategy. The Government does not intend to provide any additional details at this time regarding the Technical Performance Objectives documented in the RFI. Respondents are encouraged to state their assumptions regarding information that, while not provided in the RFI, may be relevant to understanding their RFI response. | |
| Q-052 | Do the payload-capacity requirements represent accommodation of a single payload or a multi-payload suite? If multiple payloads are contemplated, are there Government expectations for payload allocation, interfaces, and concurrent operations? | The intent of the RFI is to explore industry's capabilities and inform the Government's acquisition strategy. The Government does not intend to provide any additional details at this time regarding the Technical Performance Objectives documented in the RFI. Respondents are encouraged to state their assumptions regarding information that, while not provided in the RFI, may be relevant to understanding their RFI response. | |
| Q-053 | Please clarify the required security and hosting model for the ground segment. Are contractor-hosted, accredited facilities and/or cloud environments acceptable for C2 and MPS? If a classified environment is required, please identify the anticipated environment, applicable cybersecurity/control framework, ATO process, and accrediting authority. | The intent of the RFI is to explore industry's capabilities and inform the Government's acquisition strategy. The Government does not intend to provide any additional details at this time regarding the Technical Performance Objectives documented in the RFI. Respondents are encouraged to state their assumptions regarding information that, while not provided in the RFI, may be relevant to understanding their RFI response. | |
| Q-054 | Does the RFI’s reference to onboard autonomy/Super Intelligence contemplate a complementary ground-based autonomy or decision-support capability? If so, please describe the intended role and any applicable interfaces or performance expectations. | The intent of the RFI is to explore industry's capabilities and inform the Government's acquisition strategy. The Government does not intend to provide any additional details at this time regarding the Technical Performance Objectives documented in the RFI. Respondents are encouraged to state their assumptions regarding information that, while not provided in the RFI, may be relevant to understanding their RFI response. | |
| Q-055 | Please define “Super Intelligence (SI)” and the intended onboard-autonomy scope. Does the 72-hour autonomous-operation requirement assume a communications-denied condition, or only the absence of active ground commanding? | "Super Intelligence" is equivalent to the term "Artificial Intelligence" commonly used in industry. |
The intent of the RFI is to explore industry's capabilities and inform the Government's acquisition strategy. The Government does not intend to provide any additional details at this time regarding the Technical Performance Objectives documented in the RFI. Respondents are encouraged to state their assumptions regarding information that, while not provided in the RFI, may be relevant to understanding their RFI response.
| Q-056 | Please define the scope of “data processing” for CSS. Does it include only decommutation and handling of data, C2/MPS data processing, or processing raw payload data into defined data products? If payload-data processing is required, please identify expected product levels, formats, and Government interfaces. | The intent of the RFI is to explore industry's capabilities and inform the Government's acquisition strategy. The Government does not intend to provide any additional details at this time regarding the Technical Performance Objectives documented in the RFI. Respondents are encouraged to state their assumptions regarding information that, while not provided in the RFI, may be relevant to understanding their RFI response. |
| Q-057 | For purposes of Section 6.C.12(b), does “ground infrastructure” include both ground entry points and physical mission-operations-center and/or SCIF spaces? | The intent of the RFI is to explore industry's capabilities and inform the Government's acquisition strategy. The Government does not intend to provide any additional details at this time regarding the Technical Performance Objectives documented in the RFI. Respondents are encouraged to state their assumptions regarding information that, while not provided in the RFI, may be relevant to understanding their RFI response. |
| Q-058 | Will the Government exclude the cover page, front matter, and table of contents from the 15-page response limit? | No |
| Q-059 | The RFI specifies a minimum 12-point proportional font. May respondents use a smaller, legible font for tables, figure captions, graphics, and callouts while retaining a minimum 12-point font for body text and headings? | Yes |
| Q-060 | Please provide a quantitative definition of “operationally responsive” tasking and delivery timelines. Does the Government anticipate acquiring communications services through the Joint Antenna Marketplace, through a contractor-provided commercial model, or either? Please also identify any preferred Government or commercial relay networks. | The intent of the RFI is to explore industry's capabilities and inform the Government's acquisition strategy. The Government does not intend to provide any additional details at this time regarding the Technical Performance Objectives documented in the RFI. Respondents are encouraged to state their assumptions regarding information that, while not provided in the RFI, may be relevant to understanding their RFI response. |
| Q-061 | Are there mandated Government ground architectures, frameworks, standards, or data formats with which CSS must comply, such as a DAF common-ground architecture? | The intent of the RFI is to explore industry's capabilities and inform the Government's acquisition strategy. The Government does not intend to provide any additional details at this time regarding the Technical Performance Objectives documented in the RFI. Respondents are encouraged to state their assumptions regarding information that, while not provided in the RFI, may be relevant to understanding their RFI response. |
| Q-062 | Please define the intended ground-system operational model and acceptance approach: contractor-operated, Government-operated, or hybrid; expected O&M duration and level of effort; required training, procedures, and technical-data deliverables; key performance parameters, including availability and C2/data-delivery latency; and expected ORR, end-to-end-test, and operational-readiness criteria. | The intent of the RFI is to explore industry's capabilities and inform the Government's acquisition strategy. The Government does not intend to provide any additional details at this time regarding the Technical Performance Objectives documented in the RFI. Respondents are encouraged to state their assumptions regarding information that, while not provided in the RFI, may be relevant to understanding their RFI response. |
| Q-063 | Is there a mandatory Government Mission Planning and Scheduling system with which CSS must integrate? | The intent of the RFI is to explore industry's capabilities and inform the Government's acquisition strategy. The Government does not intend to provide any additional details at this time regarding the Technical Performance Objectives documented in the RFI. Respondents are encouraged to state their assumptions regarding information that, while not provided in the RFI, may be relevant to understanding their RFI response. |
| Q-064 | What pointing, navigation, and timing accuracy requirements apply to the space vehicle throughout its cislunar operating regime? | The intent of the RFI is to explore industry's capabilities and inform the Government's acquisition strategy. The Government does not intend to provide any additional details at this time regarding the Technical Performance Objectives documented in the RFI. Respondents are encouraged to state their assumptions regarding information that, while not provided in the RFI, may be relevant to understanding their RFI response. |
| Q-065 | What are the expected duration and specific success criteria for the on-orbit checkout and payload-calibration/initialization phase? | The intent of the RFI is to explore industry's capabilities and inform the Government's acquisition strategy. The Government does not intend to provide any additional details at this time regarding the Technical Performance Objectives documented in the RFI. Respondents are encouraged to state their assumptions regarding information that, while not provided in the RFI, may be relevant to understanding their RFI response. |
| Q-066 | What are the Government’s expectations for contractor ground support during the launch campaign, including any required use of specific launch-site network infrastructure or ground support equipment? | The intent of the RFI is to explore industry's capabilities and inform the Government's acquisition strategy. The Government does not intend to provide any additional details at this time regarding the Technical Performance Objectives documented in the RFI. Respondents are encouraged to state their assumptions regarding information that, while not provided in the RFI, may be relevant to understanding their RFI response. |
| Q-067 | Because the initial five SVs may serve as seed vehicles for a future constellation, should the proposed ground architecture incorporate specific scalability features? Will scalability be an evaluation consideration? | The intent of the RFI is to explore industry's capabilities and inform the Government's acquisition strategy. The Government does not intend to provide any additional details at this time regarding the Technical Performance Objectives documented in the RFI. Respondents are encouraged to state their assumptions regarding information that, while not provided in the RFI, may be relevant to understanding their RFI response. |
| Q-068 | Does the Government intend to host separable payloads? If so, are there specific payload-separation-system, interface, safety, or operational requirements respondents should address? | The intent of the RFI is to explore industry's capabilities and inform the Government's acquisition strategy. The Government does not intend to provide any additional details at this time regarding the Technical Performance Objectives documented in the RFI. Respondents are encouraged to state their assumptions regarding information that, while not provided in the RFI, may be relevant to understanding their RFI response. |
| Q-069 | The RFI seeks to maximize SVs per launch. Would a single larger SV per launch be considered non-compliant, or evaluated as higher risk? Please identify any target number of SVs per launch. In addition, please provide target orbit(s), intended orbit mix across the five SVs, and any planning-level Delta-V or station-keeping/propellant assumptions needed to assess five-year expendables and design-life compliance. | The intent of the RFI is to explore industry's capabilities and inform the Government's acquisition strategy. The Government does not intend to provide any additional details at this time regarding the Technical Performance Objectives documented in the RFI. Respondents are encouraged to state their assumptions regarding information that, while not provided in the RFI, may be relevant to understanding their RFI response. |
| Q-070 | Is an opportunity for a brief discussion on this Cislunar RFI on/or before 11/17 | The Government does not intend to conduct any discussions with industry prior to receipt of RFI responses. |