10-26-22 ADDENDUM NO 2.pdf
PDF 402 KB Posted
- Attached to
- Park Center Roof Replacement
- Solicitation number
- 26-22
- Issued by
- Salt Lake County, Utah
About this file
This is Addendum No. 2 to a sealed bid solicitation issued by Murray City, Utah for roof replacement services at the Murray Park Center. The addendum, issued on September 23, 2026, clarifies that Section 5 of a previously uploaded cost area diagram should be removed from all proposals. The original roof plan, dimensions, specifications, and scope of work remain unchanged, and bidders must rely on the original project drawings and solicitation documents for all construction requirements. A revised bid form without a line item for Section 5 has been provided to ensure formulas are not affected by this modification. Bidders are required to sign and attach Addendum No. 2 to their proposals.
The project involves complete replacement of the existing roof system at Murray Park Center, including removal and disposal of existing roofing materials, deck and substrate repairs, insulation, installation of a new 60 mil TPO roofing system, drainage improvements, flashings, coping and parapet work, and related accessories. Qualified roofing contractors must provide all labor, materials, equipment, permits, supervision, site protection, cleanup, and coordination necessary to complete the work. No specific pricing terms, contract duration, or award information is provided in this addendum document.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ADDENDUM NO. 2
Issue Date: September 23, 2026
The map that was uploaded created section 5 and does not match the original drawing of the roof.
Clarification:
Please remove section five from your proposals. I have uploaded a new bid form with no line for section five so that no formulas will be affected by this change.
Cost Area Diagram Only. Roof Areas 1–9 are provided solely to organize bid pricing. This diagram does not modify the original roof plan, dimensions, specifications, or scope of work. Bidders shall rely on the original project drawings and solicitation documents for construction requirements.
Please sign and attach addendum #2 to your proposal/bid.
Authorized Signature: ______________________________________ Date: _____________
Amandah Maudsley, Purchasing Agent