10-10-25_Soccer_Field_Plans_and_Specifications.pdf

PDF 3 MB Posted

Attached to
Rice Soccer Field Improvements
Solicitation number
2025-IFB-287
Issued by
New Haven County, Connecticut

About this file

This document is a set of plans and specifications prepared by the City of New Haven Department of Engineering for the Rice Soccer Field Improvements project, located on English Drive in New Haven, Connecticut. The project involves turf improvements to an existing soccer field, including grading, aeration, seeding, and hydroseeding operations across the site. The specifications detail two primary turf improvement areas (Turf Improvement A and Turf Improvement B) with specific work sequences: mowing existing turf to one inch or less, filling low areas with sandy loam, aerating using a Verti-Drain 7316 with ten-inch solid tines, rolling with 300 to 1,000-pound machinery in two directions, and hydroseeding with a seed mixture of 70% tall fescue, 20% perennial ryegrass, and 10% Kentucky bluegrass at seven pounds per 1,000 square feet. The field dimensions are 305 feet by 180 feet, and contractors must remove and reinstall detectable corner markers at the four corners of the proposed field.

The contractor is responsible for complying with the City of New Haven's General Conditions and all applicable federal, state, and local laws and codes. Additional contractor obligations include submitting a Call Before You Dig (CBYD) request for utility locating prior to work commencement, marking existing irrigation heads, and repairing any damage to existing park elements including the irrigation system during construction. The city will provide access to the existing irrigation controller. Site preparation work includes sod removal to one-inch depth, rough grading one inch below final grades, addition of one inch of sand per CTDOT specifications, and tilling to six inches depth. All work must avoid soil saturation during grading, aeration, and tilling operations. An eight-foot fence and two ten-foot gates are to be installed by others prior to field improvements beginning.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Revision/IssueNo. Date

Project Number

Designed By

Date

Sheet Number

Project Name and Address

Drawn By

Sheet Title

COVER SHEET

Professional Seal

21-116-09

C I T

Y

O

F

N

E W

H

A V

E N

D E

P A

R T

M E

N T

O

F

E

N G

I N

E E

R I N

G

T H

E

H

O N

O R

A B

L

J U

S T

I

I C

K E

R

M

A Y

O R

G I O

V A

N N

I

Z

I N

N

P

E

C

I T

Y

E

N G

I N

E E

R

12/7/23

CITY OF NEW HAVEN

DEPARTMENT OF ENGINEERING

RICE SOCCER FIELD

IMPROVEMENTS

PROJECT NUMBER 21-116-09

HONORABLE JUSTIN ELICKER,

MAYOR

GIOVANNI ZINN, P.E.

CITY ENGINEER

23 8

26 25

9 15

PROJECT LOCATION

KJ

KJ

Sheet List Table

Sheet Number Sheet Title

1 Cover Sheet

2 Site Plan

Rice Soccer Field

Improvements

English Drive, New

Haven

55.00

.0

.0

.0

.0

.0

53.00

54.00

Bull Pen

305'-0"

180'-0"

Revision/IssueNo. Date

Project Number

Designed By

Date

Sheet Number

Project Name and Address

Drawn By

12/7/23

KJ

Sheet Title

SITE PLAN

Professional Seal

21-116-09

Rice Soccer Field

Improvements

English Drive, New

Haven

KJ

C I T

Y

O

F

N

V

E N

D E

P A

R T

M E

E

N G

I N

E E

R I N

G

T H

E

H

O N

O R

A B

S T

I C

K E

R

M

A Y

O R

G I O

V A

N N

I

Z

I N

N

P

E

C

I T

Y

E

N G

I N

E E

R

NORTH

SCALE:

feet20 40 60

1" = 20'

Notes:

1. The Contractor is responsible for complying with the City of New Haven's General Conditions and all applicable federal/state/local laws and codes.

2. The Contractor is responsible for submitting a CBYD request and having utilities located prior to the start of work.

3. Rice Field has an existing irrigation system. The City of New Haven will provide access to the existing irrigation controller. The Contractor will be responsible for marking existing irrigation heads.

4. Contractor is responsible for repairing any damage that occurs to existing park elements including but not limited to the irrigation system in the course of construction.

5. Contractor will remove detectable corner markers from the four corners of the existing soccer field and re-install them at the four corners of the proposed soccer field.

8' fence to be installed by others before field improvements begin

10' gate to be installed by others before field improvements begin

10' gate to be installed by others before field improvements begin

Proposed soccer field

Site Plan

Remove existing detectable metal field corner markers

Remove existing detectable metal field corner markers

Reinstall detectable metal field corner markers at each of the four corners of proposed soccer field

Proposed soccer field does not overlap with existing clay infield

Turf improvements3

Revision/IssueNo. Date

Project Number

Designed By

Date

Sheet Number

Project Name and Address

Drawn By

12/7/23

KJ

Sheet Title

DETAILS

Professional Seal

21-116-09

Rice Soccer Field

Improvements

English Drive, New

Haven

KJ

C I T

Y

O

F

N

V

E N

D E

P A

R T

M E

E

N G

I N

E E

R I N

G

T H

E

H

O N

O R

A B

S T

I C

K E

R

M

A Y

O R

G I O

V A

N N

I

Z

I N

N

P

E

C

I T

Y

E

N G

I N

E E

RFIELD CORNER MARKER

Not to scale

1' -3

Finish Grade

Gun barrel or other piece of metal that can be detected by a metal detector

Concrete

6"

Note: A detectable corner marker like the one shown above is existing at each of the four corners of the existing soccer field. The contractor is responsible for locating the corner markers, removing them, and reinstalling at the corners of the proposed field.

P-RI-01

IRGN

IRGN

IRGN

IRGN

IRGN

IRGN

IRGN

IRGN

IRGN

IRGN

52.14

55.26

52.1452.16 52.13

54.49

52.69

55.22 55.2155.24

58.68

IRGN

IRGN

IRGN

IRGN

IRGN

IRGN

IRGN

IRGN

IRGN

IRGN

IRGN

IRGN

IRGN

IRGN

IRGN

IRGN

IRGN

52.29

52.50

IRGN

IRGN

IRGN

IRGN

TREE 184752.04TREE 184852.03

TREE184954.17

TREE185055.82

TREE185155.15

BASES 55.36

BASES 55.24

BASES57.08

BASES55.61

BASES55.89

55.25

54.34

50.66

51.10

51.32

53.46

55.26

55.17

52.07

55.1755.1655.18

44.39

55.2455.2355.25

52.36

51.91

51.80

51.27

50.92

51.09

50.37

TREE209149.95

TREE209250.36

TREE 209350.23

TREE 209450.60

TREE 209550.69

TREE209650.72

TREE209750.69

TREE 209850.79

TREE209950.66

TREE 210050.34

TREE 210149.98

TREE210249.52

52.67

52.77

53.2353.23

53.20

53.18

53.25

52.94

53.09

52.0052.0352.0252.04

44.06

IRGN

IRGN

IRGN

IRGN

IRGN

IRGN

IRGN

IRGN

IRGN

IRGN

52.14

55.26

52.1452.16 52.13

54.49

52.69

55.22 55.2155.24

58.68

IRGN

IRGN

IRGN

IRGN

IRGN

IRGN

IRGN

IRGN

IRGN

IRGN

IRGN

IRGN

IRGN

IRGN

IRGN

IRGN

IRGN

IRGN

52.29

52.50

IRGN

IRGN

IRGN

IRGN

TREE 270752.04TREE 270852.03

TREE270954.17

TREE271055.82

TREE271155.15

BASES 55.36

BASES 55.24

BASES57.08

BASES55.61

BASES55.89

55.25

54.34

50.66

51.10

51.32

53.46

55.26

55.17

52.07

55.1755.1655.18

55.2455.2355.25

52.36

51.91

51.80

51.27

50.92

51.09

50.37

TREE295149.95

TREE295250.36

TREE 295350.23

TREE 295450.60

TREE 295550.69

TREE295650.72

TREE295750.69

TREE 295850.79

TREE295950.66

TREE 296050.34

TREE 296149.98

TREE296249.52

52.67

52.77

53.2353.23

53.20

53.18

53.25

52.94

53.09

52.0052.0352.0252.04

44.06

51.89

53.31

51.92 51.90

51.10

51.28

50.50

52.6552.59

50.5050.50

51.6951.8951.89

52.83

55.00

51.00

52.00

53.00

54.00

52.00

53.00

54.00

305'-0"

180'-0"

Tu rf

Im pro ve m en t A

Turf Improvement A

Turf Improvement B

Mow all turf in the area of work to 1" tall or less.

Fill in low areas with sandy loam per USDA Soil Survey

Manual

Aerate using a kicking/shattering cultivator such as Verti-Drain 7316.

Use 10" long solid tines with angle adjusted for maximum kick action. Do not aerate while soil is saturated.

Roll with a 300LB-1000LB machine in two directions. Do not roll while soil is saturated.

Hydroseed Seed: 70% tall fescue, 20% perennial ryegrass, and 10% Kentucky Bluegrass.

7 LBS/1,000 SF.

Limestone: 50 LBS per 1,000 SF.

Fertilizer: 32-0-4 with 50% slow release nitrogen, 5 LBS per 1,000 SF.

Mulch: 50-50 paper and wood mulch, 100% recycled material

Cut sod to 1" depth. Remove and dispose of material off site.

Rough grade to 1" below grades shown on site plan. Do not grade while soil is saturated.

Add 1" depth of sand per CTDOT form 818 M.05.02-1 to achieve grades shown on site plan.

Till to 6" depth to incorporate sand into existing soil. Do not till while soil is saturated.

Turf Im provem ent B

TURF IMPROVEMENTS

1" = 50'

P-RI-04

Existing grade

Proposed grade

SECTION B

3/32" = 1'-0"

P-RI-06

Sheets and Views
Soccer Field-Cover Sheet
Soccer Field-Site Plan
Soccer Field-Details