1) SOW_RIPIT_2.0_Replace Industrial Bldg Boiler.pdf
PDF 291 KB Posted
- Attached to
- USCG Base Charleston - Boiler Replacement
- Solicitation number
- 70Z036-P2600-00018
About this file
This is a Contract Specifications document for the replacement of an industrial building boiler at United States Coast Guard Base Charleston, located at 196 Tradd Street, Charleston, South Carolina 29401. The project number is listed as TBD with a target date of December 2025. The specification calls for the furnishing of all labor, materials, and equipment necessary to replace the hydronic heating boiler in the Industrial Building. The work includes complete demolition and removal of the existing boiler system, including all piping and flue connections; installation of one floor-mount, high-efficiency commercial water boiler rated at 725,000 BTU/hr, natural gas-fired, specifically a Lochinvar FTX725N fire tube condensing boiler with modulating burner (10:1 turndown ratio), variable flow capability (20-150 GPM), and advanced LED display control system; installation of new isolation valves, pressure relief valves, air vent valves, and backflow prevention devices; provision and installation of PVC vent piping and combustion air intake with proper securing and fire-stopping; installation of condensate drainage lines with neutralizer kits and condensate pump if required; and complete start-up, testing, and commissioning per manufacturer procedures including system training for unit personnel.
The total contract performance period is 60 calendar days, with the contractor required to notify the government at least 10 days prior to mobilization with all equipment and parts on hand. Work hours are Monday through Friday, 7:00 a.m. to 3:00 p.m., unless otherwise approved. The contractor must be a qualified installer with verifiable familiarity with the specified equipment, five years of documented commercial HVAC installation experience, and proof of financial stability with positive references. The contractor is responsible for site visits to verify existing conditions, all staging and laydown coordination with the Coast Guard, environmental compliance, safety program implementation, and proper disposal of all waste materials and hazardous substances. Deliverables include a detailed electronic materials list, line drawings with equipment schedules, operation and maintenance manuals, product data sheets, manufacturer's warranties (minimum 20-year commercial wear warranty), and a 12-month contractor warranty covering parts and labor. The Coast Guard Base Charleston Onsite Representative is CWO Cody Wood, and arrangements for site visits may be made by contacting cody.a.wood@uscg.mil.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 1) SOW_RIPIT_2.0_Replace Industrial Bldg Boiler REV.4-2-2026.pdf | ||
| SF-1442.pdf | ||
| Construction Clauses and Provisions.pdf | ||
| sc59.txt | TXT text file |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CONTRACT SPECIFICATIONS
Replace Industrial Bldg Boiler
AT
UNITED STATES COAST GUARD
BASE CHARLESTON
196 TRADD ST, CHARLESTON, SC 29401
PROJECT NUMBER TBD
DEC 2025
Section 01 11 00
SECTION 01 11 00
SUMMARY OF WORK
1) GENERAL
The United States Coast Guard (USCG) is seeking a qualified contractor to provide all labor, materials and equipment as required to replace the hydronic heating boiler in Industrial Building at USCG BASE Charleston, 196 Tradd St, Charleston, SC 29401.
Base Charleston is a working Coast Guard unit and will remain in operation during the project.
Bidders are responsible for visiting the site to field verify existing conditions and determine actual dimensions and the nature of the work required. Failure to visit the site does not relinquish the bidder from determining the extent and scope of the work required and estimating the difficulty and cost to complete the project.
The USCG Base Charleston Onsite Representative is CWO Cody Wood for this project.
General Work Requirements
The Base Bid work generally includes; furnish all labor, tools, equipment, and materials for the replacement of the hydronic heating boiler in the Industrial Bldg., but is not limited to, the following:
a) Demolition & Removal
i) Disconnect and remove existing boiler, including flue connections and piping (domestic water, gas, and hydronic as needed).
ii) Recover and properly dispose of all removed equipment and associated materials in compliance with local regulations.
iii) Cap or modify existing connections to prepare for new system installation.
b) Equipment Installation
i) Furnish and install one (1) Floor-Mount High-Efficiency Commercial
Water Boiler for hydronic heating systems.
(1) Specifications:
(a) BTU/hr: 725000
(b) Fuel Type: Natural Gas
(c) Fire Tube Condensing Boiler
(d) Advanced control system with an LED display
(e) Maximum Pressure
(f) Modulating Burner: Turndown Ratio 10:1
(g) Durable Heat Exchanger
(h) Variable Flow: 20 to 150 GPM
ii) Set new unit in same location as existing (or nearest code-compliant accessible location).
iii) Connect to existing domestic water, gas, and hydronic piping systems.
iv) Install new isolation valves, pressure relief valves, air vent valves, and backflow prevention devices as required.
v) New pipe insulation for all new piping and any existing insulation that was damaged or disturbed in this scope.
c) Exhaust Flue
i) Provide and install PVC vent piping and combustion air intake for appliance.
ii) Secure and support piping per code and manufacturer requirements
(e.g., minimum pitch, maximum spacing, fire-stopping if applicable).
iii) Ensure vent and intake separation meets clearance specifications.
d) Condensate Drainage
i) Install condensate lines with neutralizer kits (if required).
ii) Route condensate to approved drain with air gap.
iii) Include condensate pump if gravity drainage is not feasible.
e) Start-Up & Commissioning
i) Start and test each appliance per manufacturer start-up procedures.
ii) Check all connections for leaks, proper combustion, and safe operation.
iii) Confirm thermostat and control function, water temperature, and system pressure.
iv) Provide owner/operator basic system training.
f) Incidental Work Items
i) Incidental work items not listed in this scope, but necessary to complete the project shall be included. Examples include, but are not limited to: removal, replacement, and installation of smoke/heat detectors, lights, sprinkler heads, speakers, etc.
g) Closeout
i) Start and test each appliance per manufacturer start-up procedures.
ii) Check all connections for leaks, proper combustion, and safe operation.
iii) Confirm thermostat and control function, water temperature, and system pressure.
iv) Provide owner/operator basic system training.
v) Contractor shall provide a detailed electronic list of all materials and quantities used.
vi) Contractor shall provide line drawings of new equipment installed with a schedule of parts and equipment installed.
2) SPECIFIC WORK REQUIREMENTS
a) Install Lochinvar FTX725N Fire Tube Floor-Mount High-Efficiency Natural
Gas Commercial Water Boiler 725000 BTU, for reference it is the same boiler as the Barracks Bldg. A
b) All equipment must be installed in strict compliance with manufacturer's guidelines and all applicable industry standards.
3) Qualifications
a) The Contractor shall provide qualified personnel to perform all requirements specified in this SOW.
b) The installer must meet the following minimum qualifications:
i) Verifiable familiarity with the specified equipment.
ii) Five years of documented experience in commercial HVAC installation.
iii) Proof of financial stability and a positive project history with references.
4) SPECIAL WORK REQUIREMENTS
a) The contractor is responsible for getting appropriate calculations for the spaces in this scope.
b) Coordinate all staging and laydown areas with the Coast Guard prior to work starting.
5) TEMPORARY FACILITIES OR UTILITIES
a) None required.
6) PROJECT PERFORMANCE PERIOD
a) The total contract performance period shall include not only the time needed to complete the base bid and approved option items, but it also includes the time needed to submit, review, and approve all material submittals, and complete all project record (closeout) documents. After work begins at the site, perform the work continuously during normal working hours and show daily progress until all work is complete.
b) Contractor shall notify the Government at least 10 days prior to mobilizing and have all equipment and parts on hand.
c) The total contract performance period is 60 calendar days.
7) LOCATION
a) The work is located at:
U.S. Coast Guard Base Charleston
196 Tradd St, Charleston, SC 29401
8) SITE VISITS
a) Arrangements for visiting the site may be made by contacting:
CWO Cody Wood
Email: cody.a.wood@uscg.mil
9) DRAWINGS ACCOMPANYING SPECIFICATION
a) There are no drawings accompanying this specification.
10) WORK HOURS
a) Normal Working Hours
b) Perform all work at the site from Monday through Friday from 7:00am to
3:00 pm, unless otherwise approved. This project requires a special schedule to prevent operational interruptions during the installation process. Please refer to the scope section for detailed coordination of working hours. The contractor shall plan a schedule to minimize disruptions to building operations.
mailto:cody.a.wood@uscg.mil
c) Performing the work beyond the listed working hours is at the discretion of the Coast Guard unit and the contractor must gain prior approval.
11) SPECIFIC ENVIRONMENTAL REQUIREMENTS
a) All contractors working on CG Base Charleston shall abide by all federal environmental regulations as published by the Environmental
Protection Agency, 40 CFR (series). Contractor written environmental management and pollution prevention programs shall be reviewed by the
Environmental Protection Specialist, Jeff Wachowski ((803) 465-1908 or
Michael.J.Wachowski@uscg.mil) prior to starting work and must be in accordance with ICSPORTSVA INSTM5090.2, the Unit Environmental Guide.
b) Written notification must be provided to the Environmental Protection Specialist of any activity that could potentially cause a permit violation on Base Charleston. Some examples of qualifying activities are: any activity that could result in a spill or discharge into a waterway or introducing a hazardous material into the environment.
c) Copies of the following must be provided to the Environmental Protection Specialist prior to starting work in affected areas:
Material Safety Data Sheets, permits, and notices of intent.
d) Hazardous materials used by a contractor are required to be disposed of by that contractor. Disposal must be in accordance with federal, state, and local guidelines.
12) SAFETY PROGRAM
a) The Contractor is wholly responsible for work site safety. Implement a safety program that protects the lives and health of personnel in the construction area, prevents damage to property and avoids work interruptions. Provide appropriate safety measures including but not limited to barricades, signs and signal lights as well as complying with the requirements of all applicable federal, State and local safety laws, rules and regulations.
b) Written notification must be provided to the Base Safety Officer, John
Difranceso ((843) 610-8177 or John.DiFrancesco2@uscg.mil) in their capacity as Base Fire Marshal of any activity that could potentially cause fire or explosion or that changes or reduces the capability of fighting a fire or explosion. Some examples of qualifying activities are: a fire hydrant or fire suppression system that must be taken out of service for any reason, electrical work that affects fire alarm systems, introduction of hazardous or flammable material onto the Base, and blocking of any egress routes or emergency vehicle routes.
Inclusion of this information in the contract constitutes written notification as long as the outsource review sheet is signed by Base
Safety Officer.
c) Copies of the following must be provided to the Base Safety Officer prior to starting work in affected areas: Confined Space Entry Permits, Hot Work Chits, and Dig Chits. Confined space clearance must be conducted by a certified marine chemist and permit required spaces will have a copy of the permit posted on site during work. Hot work will only be conducted with permission and a fire watch must be posted during work. A facility dig chit is required in addition to a Miss
Utility dig chit. The systems on Base Charleston are not limited to what the City of Charleston has on file. In order to ensure electrical safety and integrity of systems, a facility chit is required.
d) Lock Out/Tag Out requires notification and coordination with facilities and will not be conducted by a contractor on Base Charleston. A
Facilities Division representative is required for all contractor Lock
Out/Tag Out needs.
13) AVAILABILITY OF UTILITY SERVICES
a) The Government will provide all utility services required in the performance of this contract, including reasonable amounts of electricity and water. Electrical power is provided at existing outlets for the Contractor to operate equipment necessary in the performance of work. Hot and cold water is provided at existing sinks and outlets limited to the normal water capacity of the building. No special heating or cooling of water will be provided..
b) The Government will not furnish any other resources to the Contractor in support of this contract.
14) UNDERGROUND AND CONCEALED UTILITIES
a) Any utility locations provided are diagrammatic, not exact.
b) Physically verify the location and elevation of the existing underground and concealed utilities local to the work area. Employ techniques to scan the construction site including electromagnetic and sonic equipment prior to commencing the work. Mark the surface of the ground where existing underground utilities are discovered.
15) UTILITY OUTAGES
a) Identify the utility, reason for interruption, proposed time of interruption, and duration of interruption. Do not interrupt utilities until authorized by the Contracting Officer’s Representative (COR).
16) CONTRACTOR USE OF PREMISES
a) The work shall be performed on a Coast Guard operational military installation. Become familiar with and obey station fire, traffic, and security regulations. Personnel shall not stray from the immediate area of work or direct avenues of ingress and egress unless authorized in advance by the COR. Isolate each construction area with temporary partitions and dust controls. Provide movable high-visibility safety fencing about all work areas and equipment laydown areas located outdoors. Provide temporary covers on excavations that remain open overnight.
17) CLEANUP
a) The Contractor shall keep the work area, including the laydown and storage area, free from accumulations of waste materials on a daily basis and comply with all federal, state, and local regulations pertaining to the storage, transport, and disposal of wastes. The
Contractor shall not use Coast Guard waste disposal facilities including garbage cans, trash piles, or dumpsters.
18) ENVIRONMENTAL
a) Protection of the Environment
b) The Contractor shall comply with all applicable federal, state, and local laws and regulations for the protection of the environment, including but not limited to the Endangered Species Act (ESA), Bald and
Golden Eagle Protection Act (BGEPA), the Migratory Bird Treaty Act
(MBTA), National Historic Preservation Act (NHPA), the Resource
Conservation and Recovery Act (RCRA), and Comprehensive Environmental
Response, Compensation, and Liability Act (CERCLA).
c) Generated Waste
d) Any waste generated because of the project shall either be recycled or be disposed of in accordance with RCRA requirements.
e) Any hazardous waste shall be manifested off site with the Coast Guard unit listed as the Generator and signatory. Any hazardous waste shall be analyzed, characterized, stored, and disposed of in accordance with
RCRA and all applicable federal, state, and local laws and ordinances.
f) Hazardous waste shall be properly transported and delivered to an appropriate facility. The Contractor shall submit for COR approval the proposed disposal facility, qualifications of the transporters, and the draft hazardous waste manifest.
19) DISPOSITION OF MATERIALS
a) All materials including construction debris and equipment shall be removed from Government property. The Government will not be responsible for the condition or loss of, or damage to, such property after notice to proceed. Materials and equipment shall not be viewed by prospective purchasers or sold on the site.
b) The Contractor shall submit the disposal receipt from the landfill within 10 working days of disposal, if applicable.
20) STORM PROTECTION
a) The Contractor shall take every practicable precaution to minimize danger from storms to personnel, the work, and to adjacent property.
Precautions shall include, but not be limited to, closing all opening, removing all loose materials, tools, and equipment from exposed locations, and removing or securing scaffolding and other temporary work.
21) RECEIPT OF MATERIALS
a) The Contractor is responsible to receive all equipment, materials, and supplies.
22) DELIVERY AND STORAGE
a) The Contractor is responsible for the proper transport and storage of all equipment and materials.
23) SECURITY
a) Submit a list of the names of all personnel working on the project site prior to the preconstruction conference for approval. The roster shall be submitted via email, and at a minimum, include the first name, last name, job description, and company of employment.
b) Immediately submit a new list upon a change in on-site project personnel. Refer to the paragraph titled, Special Notice Prior
Notification, for notification requirements. Only personnel on the approved list are allowed onto the project site.
c) All approved personnel shall carry a valid, Government-issued identification while on Government property in conformance with the
Real ID Act of 2005. Non-compliant personnel shall be escorted off
Government property.
24) FINAL INSPECTION AND ACCEPTANCE
a) Electronically submit a written request for final acceptance to the
Coast Guard.
25) WARRANTIES
a) Provide manufacturer's standard performance guarantees or warranties including minimum twenty-year commercial wear warranty. In addition to any manufacturer’s warranty for the ceiling grid and tiles, the
Contractor shall provide a written warranty for all parts and labor for a period of 12 months from the date of project completion/USCG acceptance of work. The Contractor shall, at no additional cost to the government, make necessary replacements and/or repairs due to defective installation or unsatisfactory workmanship that becomes apparent within
12 months of the installation completion date.
26) TRAINING
a) The Contractor shall provide training to unit personnel in the operation of the equipment. The Operation and Maintenance Manuals shall be approved and provided to the unit prior to the training.
27) SUBMITTALS
The Contractor shall provide the Onsite Representative with:
a) ROSTER OF PERSONNEL
b) PROJECT SCHEDULE
c) Prepare a Construction Progress Schedule. It shall include all major milestones and events for the entire duration of the construction contract.
d) One copy of the manufacturer's printed Installation instructions for the grid and tiles, including surface preparation, and recommended adhesives to the Onsite Representative.
e) Manufacturer’s maintenance materials, information, and guidelines for product after installation.
f) 60Copies of the manufacturer’s warranties
g) Copies of Contractor’s written warranty.
28) SAFETY PLAN
a) The Contractor is wholly responsible for work site safety. The
Contractor shall implement a safety program that protects the lives and health of personnel in the construction area and adjacent areas, prevents damage to property, and avoids work interruptions. The
Contractor shall provide appropriate safety barricades, signs, signal lights, etc. as well as complying with the requirements of all applicable Federal, State and Local safety laws, rules, and regulations.
29) PRODUCT DATA
a) Submit the product data sheet for each manufactured item. It shall include the manufacturer's descriptive literature of cataloged products, equipment drawings, diagrams, performance and characteristic curves and catalog cuts. Submit complete descriptive data for each type of material. Clearly mark data to indicate the type of material to be provided.
30) OPERATION AND MAINTENANCE MANUALS
a) Submit electronically and provide the following:
b) Contact information for the prime contractor, sub-contractor, and major equipment vendor/supplier; Warranty information; Test procedures;
Results of all testing and commissioning procedures; Performance data;
c) A control sequence describing start-up, operation and shut-down instructions;
d) Installation instructions;
e) Maintenance instructions;
f) Operating instructions;
g) Parts list.
31) Documentation
a) None.
-- End of Section –