This is a Statement of Work for ceiling grid removal and installation services at United States Coast Guard Sector Charleston, located at 196 Tradd Street, Charleston, South Carolina 29401, with a performance period of 30 calendar days commencing in March 2026.

The contractor shall furnish all labor, tools, equipment, and materials to remove existing ceiling grids and install new ceiling systems across approximately 2,270 square feet in five areas: office rooms 102 (201 sq ft) and 106 (157 sq ft), wardroom area (800 sq ft), galley serving line (112 sq ft), and messdeck area (1,000 sq ft) in the barracks building. Rooms 102 and the wardroom require 24-inch by 24-inch mineral fiber ceiling tiles with white, lightly textured surfaces and Class A fire-rating (Armstrong Model #607A or equivalent), while the galley serving line, messdeck, and room 106 require 24-inch by 24-inch mineral fiber tiles with white, fissured surfaces (Armstrong Model #673 or equivalent). The new grid materials must be galvanized or aluminum with corrosion resistance and white coloring. The contractor must also remove, replace, and reinstall all associated fixtures including smoke/heat detectors, lights, sprinkler heads, and speakers. Key deliverables include a detailed electronic materials list, manufacturer's installation instructions, 5% attic stock of replacement tiles from the same lot in original packaging, and manufacturer's maintenance materials and guidelines.

The contractor must provide qualified personnel with a minimum of five years' experience in commercial false ceiling system installation, be financially sound with verified references, and provide on-site project manager supervision. Work shall be performed Monday through Friday from 7:00 a.m. to 3:00 p.m., with the contractor required to notify the Government at least 21 days prior to mobilization. The contractor must submit a personnel roster for security approval, coordinate all staging and laydown areas with the Coast Guard, and comply with all federal environmental regulations, safety requirements, and underground utility verification procedures. The contractor shall provide a 12-month warranty for all parts and labor from the date of project completion, in addition to the manufacturer's minimum 20-year commercial wear warranty. All waste materials and construction debris must be removed from Government property with landfill disposal receipts submitted within 10 working days. The Government will provide utility services including electricity and water at existing outlets and sinks.

View the file

Other files

File Type Posted
Davis-Bacon Act WD SC20260023.pdf PDF
Construction Clauses and Provisions.pdf PDF
SF-1442 70Z03626Q0016.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONTRACT SPECIFICATIONS

TRADD_Ceiling Grid Removal & Install

AT

UNITED STATES COAST GUARD

SECTOR CHARLESTON

196 TRADD ST, CHARLESTON, SC 29401

MAR 2026

Section 01 11 00

SECTION 01 11 00

SUMMARY OF WORK

1) GENERAL

The United States Coast Guard (USCG) is seeking a qualified contractor to remove and install ceiling grid and tiles in two (2) office spaces, wardroom area, the galley serving line and the messdeck area in the barracks building at USCG SECTOR Charleston, 196 Tradd St, Charleston, SC 29401.

Sector Charleston is a working Coast Guard unit and will remain in operation during the project.

Bidders are responsible for visiting the site to field verify existing conditions and determine actual dimensions and the nature of the work required. Failure to visit the site does not relinquish the bidder from determining the extent and scope of the work required and estimating the difficulty and cost to complete the project.

The USCG Sector Charleston Onsite Representative is CWO Cody Wood for this project.

General Work Requirements

a) Furnish all labor, tools, equipment, and materials to install new ceiling grid in rooms 102 (approx. 201 sqft), 106 (approx. 157 sqft), wardroom area (approx. 800 sqft), the galley serving line (approx. 112 sqft), and the messdeck area (approx. 1000 sqft)in the barracks building located in the barracks building at U.S. Coast Guard Sector Charleston.

b) The Base Bid work generally includes, but is not limited to, the following:

c) Contractor shall prep area for installation of ceiling grid.

d) Install new ceiling grid and ceiling tiles where existing ceiling grid was originally.

e) Contractor shall re-install all fixtures associated with the ceiling.

i) Incidental work items not listed in this scope, but necessary to complete the project shall be included. Examples include, but are not limited to: removal, replacement, and installation of smoke/heat detectors, lights, sprinkler heads, speakers, etc.

f) Contractor shall provide a detailed electronic list of all materials and quantities used.

2) SPECIFIC WORK REQUIREMENTS

a) AREA/OFFICE PREPARATION

i) Contractor assumes all responsibility for preparation of area to ensure the grid is properly installed IAW manufacturers specifications.

b) NEW CEILING GRID INSTALLATION

i) The new grid materials must be galvanized or aluminum to ensure there is corrosion resistance and meet the specifications of the ceiling tiles to be installed. The grid shall be white in color and match as closely as possible to existing rooms and hallways.

ii) The new tiles in rooms 102 and Wardroom shall be 24-inch by 24-inch squares, made of mineral fiber with a white, lightly textured surface, square edges, compatible with standard suspended ceiling grids, sound-absorbing, Class A fire-rated, and resistant to sagging, staining, fading, mildew, mold, soil, and fire. Armstrong Model #607A, 24” x 24”, or equivalent, may be used as an example of acceptable quality and performance.

iii) The new tiles in the galley serving line, the Messdeck, and room 106 shall be 24-inch by 24-inch squares, made of mineral fiber with a white, fissured surface, square edges, compatible with standard suspended ceiling grids, and resistant to fire, mildew, mold, sagging, and soil. Armstrong Model #673, 24” x 24”, or equivalent, may be used as an example of acceptable quality and performance.

iv) Isolate area of installation from rest of building. Perform all work by manufacturer's approved installers, in accordance with the manufacturer's printed instructions.

v) Quality Assurance: Contractor shall assure the product is appropriate for the application and environment in which it is to be installed, and that the product is merchantable for service, free of any visible and latent defects, and will perform for the purpose for which it is intended without compromise.

vi) If practicable reuse any removed ceiling fixtures.

vii) New grid and tiles shall be installed as soon as practicable i.e., long delays due to supply chain, scheduling, or other issues are not acceptable.

viii) Attic Stock: Contractor shall provide a minimum of 5% total quantity of each of new types of tiles to the local maintenance staff for future replacement or patching. Attic stock shall be from the same lot and in original packaging with exact matching type, size, pattern, and color.

ix) Maintenance: Contractor shall provide manufacturer’s maintenance materials, information, and guidelines for product after installation.

3) Qualifications

a) The Contractor shall provide qualified personnel to perform all requirements specified in this SOW.

b) The installer must have a minimum of 5 years’ experience in the installation of commercial false ceiling systems, be financially sound, have references and a sound history, and provide on-site project manager supervision. The ceiling grid and tiles must be installed in strict compliance with the manufacturer’s installation guidelines and industry standards.

4) SPECIAL WORK REQUIREMENTS

a) The contractor is responsible for getting appropriate calculations for the spaces in this scope.

b) Coordinate all staging and laydown areas with the Coast Guard prior to work starting.

5) TEMPORARY FACILITIES OR UTILITIES

a) None required.

6) PROJECT PERFORMANCE PERIOD

a) The total contract performance period shall include not only the time needed to complete the base bid and approved option items, but it also includes the time needed to submit, review, and approve all material submittals, and complete all project record (closeout) documents. After work begins at the site, perform the work continuously during normal working hours and show daily progress until all work is complete.

b) Contractor shall notify the Government at least 21 days prior to mobilizing.

c) The total contract performance period is 30 calendar days.

7) LOCATION

a) The work is located at:

United States Coast Guard Sector Charleston 196 Tradd St, Charleston, SC 29401

8) DRAWINGS ACCOMPANYING SPECIFICATION

a) There are no drawings accompanying this specification.

9) WORK HOURS

a) Normal Working Hours

b) Perform all work at the site from Monday through Friday from 7:00am to

3:00 pm, unless otherwise approved. This project requires a special schedule to prevent operational interruptions during the installation process. Please refer to the scope section for detailed coordination of working hours. The contractor shall plan a schedule to minimize disruptions to building operations.

c) Performing the work beyond the listed working hours is at the discretion of the Coast Guard unit and the contractor must gain prior approval.

10) SPECIFIC ENVIRONMENTAL REQUIREMENTS

a) All contractors working on CG Sector Charleston shall abide by all federal environmental regulations as published by the Environmental Protection Agency, 40 CFR (series). Contractor written environmental management and pollution prevention programs shall be reviewed by the Environmental Protection Specialist, Jeff Wachowski ((803) 465-1908 or Michael.J.Wachowski@uscg.mil) prior to starting work and must be in accordance with ICSPORTSVA INSTM5090.2, the Unit Environmental Guide.

b) Written notification must be provided to the Environmental Protection Specialist of any activity that could potentially cause a permit violation on Sector Charleston. Some examples of qualifying activities are: any activity that could result in a spill or discharge into a waterway or introducing a hazardous material into the environment.

mailto:Michael.J.Wachowski@uscg.mil

c) Copies of the following must be provided to the Environmental Protection Specialist prior to starting work in affected areas:

Material Safety Data Sheets, permits, and notices of intent.

d) Hazardous materials used by a contractor are required to be disposed of by that contractor. Disposal must be in accordance with federal, state, and local guidelines.

11) SAFETY PROGRAM

a) The Contractor is wholly responsible for work site safety. Implement a safety program that protects the lives and health of personnel in the construction area, prevents damage to property and avoids work interruptions. Provide appropriate safety measures including but not limited to barricades, signs and signal lights as well as complying with the requirements of all applicable federal, State and local safety laws, rules and regulations.

b) Written notification must be provided to the Base Safety Officer, John Difranceso ((843) 610-8177 or John.DiFrancesco2@uscg.mil), in their capacity as Base Fire Marshal of any activity that could potentially cause fire or explosion or that changes or reduces the capability of fighting a fire or explosion. Some examples of qualifying activities are: a fire hydrant or fire suppression system that must be taken out of service for any reason, electrical work that affects fire alarm systems, introduction of hazardous or flammable material onto the Base, and blocking of any egress routes or emergency vehicle routes.

Inclusion of this information in the contract constitutes written notification as long as the outsource review sheet is signed by Base Safety Officer. The alternat POC is CWO Cody Wood.

c) Copies of the following must be provided to the Base Safety Officer prior to starting work in affected areas: Confined Space Entry Permits, Hot Work Chits, and Dig Chits. Confined space clearance must be conducted by a certified marine chemist and permit required spaces will have a copy of the permit posted on site during work. Hot work will only be conducted with permission and a fire watch must be posted during work. A facility dig chit is required in addition to a Miss Utility dig chit. The systems on Sector Charleston are not limited to what the City of Charleston has on file. In order to ensure electrical safety and integrity of systems, a facility chit is required.

d) Lock Out/Tag Out requires notification and coordination with facilities and will not be conducted by a contractor on Sector Charleston. A Facilities Division representative is required for all contractors Lock Out/Tag Out needs.

12) AVAILABILITY OF UTILITY SERVICES

a) The Government will provide all utility services required in the performance of this contract, including reasonable amounts of electricity and water. Electrical power is provided at existing outlets for the Contractor to operate equipment necessary in the performance of work. Hot and cold water is provided at existing sinks and outlets limited to the normal water capacity of the building. No special heating or cooling of water will be provided.

b) The Government will not furnish any other resources to the Contractor in support of this contract.

mailto:John.DiFrancesco2@uscg.mil

13) UNDERGROUND AND CONCEALED UTILITIES

a) Any utility locations provided are diagrammatic, not exact.

b) Physically verify the location and elevation of the existing underground and concealed utilities local to the work area. Employ techniques to scan the construction site including electromagnetic and sonic equipment prior to commencing the work. Mark the surface of the ground where existing underground utilities are discovered.

14) UTILITY OUTAGES

a) Identify the utility, reason for interruption, proposed time of interruption, and duration of interruption. Do not interrupt utilities until authorized by the Contracting Officer’s Representative (COR).

15) CONTRACTOR USE OF PREMISES

a) The work shall be performed on a Coast Guard operational military installation. Become familiar with and obey station fire, traffic, and security regulations. Personnel shall not stray from the immediate area of work or direct avenues of ingress and egress unless authorized in advance by the COR. Isolate each construction area with temporary partitions and dust controls. Provide movable high-visibility safety fencing about all work areas and equipment laydown areas located outdoors. Provide temporary covers on excavations that remain open overnight.

16) CLEANUP

a) The Contractor shall keep the work area, including the laydown and storage area, free from accumulations of waste materials on a daily basis and comply with all federal, state, and local regulations pertaining to the storage, transport, and disposal of wastes. The Contractor shall not use Coast Guard waste disposal facilities including garbage cans, trash piles, or dumpsters.

17) ENVIRONMENTAL

a) Protection of the Environment

b) The Contractor shall comply with all applicable federal, state, and local laws and regulations for the protection of the environment, including but not limited to the Endangered Species Act (ESA), Bald and Golden Eagle Protection Act (BGEPA), the Migratory Bird Treaty Act (MBTA), National Historic Preservation Act (NHPA), the Resource Conservation and Recovery Act (RCRA), and Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA).

c) Generated Waste

d) Any waste generated because of the project shall either be recycled or be disposed of in accordance with RCRA requirements.

e) Any hazardous waste shall be manifested off site with the Coast Guard unit listed as the Generator and signatory. Any hazardous waste shall be analyzed, characterized, stored, and disposed of in accordance with RCRA and all applicable federal, state, and local laws and ordinances.

f) Hazardous waste shall be properly transported and delivered to an appropriate facility. The Contractor shall submit for COR approval the proposed disposal facility, qualifications of the transporters, and the draft hazardous waste manifest.

18) DISPOSITION OF MATERIALS

a) All materials including construction debris and equipment shall be removed from Government property. The Government will not be responsible for the condition or loss of, or damage to, such property after notice to proceed. Materials and equipment shall not be viewed by prospective purchasers or sold on the site.

b) The Contractor shall submit the disposal receipt from the landfill within 10 working days of disposal.

19) STORM PROTECTION

a) The Contractor shall take every practicable precaution to minimize danger from storms to personnel, the work, and to adjacent property.

Precautions shall include, but not be limited to, closing all opening, removing all loose materials, tools, and equipment from exposed locations, and removing or securing scaffolding and other temporary work.

20) RECEIPT OF MATERIALS

a) The Contractor is responsible to receive all equipment, materials, and supplies.

21) DELIVERY AND STORAGE

a) The Contractor is responsible for the proper transport and storage of all equipment and materials.

22) SECURITY

a) Submit a list of the names of all personnel working on the project site prior to the preconstruction conference for approval. The roster shall be submitted via email, and at a minimum, include the first name, last name, job description, and company of employment.

b) Immediately submit a new list upon a change in on-site project personnel. Refer to the paragraph titled, Special Notice Prior Notification, for notification requirements. Only personnel on the approved list are allowed onto the project site.

c) All approved personnel shall carry a valid, Government-issued identification while on Government property in conformance with the Real ID Act of 2005. Non-compliant personnel shall be escorted off Government property.

23) FINAL INSPECTION AND ACCEPTANCE

a) Electronically submit a written request for final acceptance to the

Coast Guard.

24) WARRANTIES

a) Provide manufacturer's standard performance guarantees or warranties including minimum twenty-year commercial wear warranty. In addition to any manufacturer’s warranty for the ceiling grid and tiles, the Contractor shall provide a written warranty for all parts and labor for a period of 12 months from the date of project completion/USCG acceptance of work. The Contractor shall, at no additional cost to the government, make necessary replacements and/or repairs due to defective installation or unsatisfactory workmanship that becomes apparent within 12 months of the installation completion date.

25) TRAINING

a) The Contractor shall provide training to unit personnel in the operation of the equipment. The Operation and Maintenance Manuals shall be approved and provided to the unit prior to the training.

26) SUBMITTALS

The Contractor shall provide the Onsite Representative with:

a) ROSTER OF PERSONNEL

b) PROJECT SCHEDULE

c) Prepare a Construction Progress Schedule. It shall include all major milestones and events for the entire duration of the construction contract.

d) One copy of the manufacturer's printed Installation instructions for the grid and tiles, including surface preparation, and recommended adhesives to the Onsite Representative.

e) Attic Stock: Contractor shall provide a minimum of 5% total quantity of new tiles to the local maintenance staff for future replacement or patching. Attic stock shall be from the same lot and in original packaging with exact matching type, size, pattern, and color.

f) Manufacturer’s maintenance materials, information, and guidelines for product after installation.

g) Signed and fully executed originals of all hazardous waste profiles, test results, hazardous waste manifests and/or other shipping papers, and all other required documentation. The Contractor shall submit a copy of the waste shipment records within one day of the shipment leaving the project site.

h) Copies of the manufacturer’s warranties

i) Copies of Contractor’s written warranty.

27) SAFETY PLAN

a) The Contractor is wholly responsible for work site safety. The Contractor shall implement a safety program that protects the lives and health of personnel in the construction area and adjacent areas, prevents damage to property, and avoids work interruptions. The Contractor shall provide appropriate safety barricades, signs, signal lights, etc. as well as complying with the requirements of all applicable Federal, State and Local safety laws, rules, and regulations.

28) PRODUCT DATA

a) Submit the product data sheet for each manufactured item. It shall include the manufacturer's descriptive literature of cataloged products, equipment drawings, diagrams, performance and characteristic curves and catalog cuts. Submit complete descriptive data for each type of material. Clearly mark data to indicate the type of material to be provided.

29) OPERATION AND MAINTENANCE MANUALS

a) Submit electronically and provide the following:

b) Contact information for the prime contractor, sub-contractor, and major equipment vendor/supplier; Warranty information; Test procedures;

Results of all testing and commissioning procedures; Performance data;

c) A control sequence describing start-up, operation and shut-down instructions;

d) Installation instructions;

e) Maintenance instructions;

f) Operating instructions;

g) Parts list.

30) Documentation

a) None.

-- End of Section –