1 SOW - Overhaul two condensate pumps in Pit No 5.doc

DOC document 50 KB Posted

Attached to
J043--Overhaul Two Condensate Pumps at Northport VA Medical Center
Solicitation number
36C24220Q0700
Issued by

View the file

Other files

File Type Posted
36C24220Q0700_1.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

1.

Title of Project:

Overhaul two (2) steam condensate pumps in Pit No. 5 at Building 5 2.

Scope of Work:

Provide all labor, materials, and supervision to remove, rebuild & reinstall condensate pump no. 1 and no. 2 and to replace two (2) starters and one (1) float switch located in Pit No. 5 at Building 5

Specific tasks are:

Remove, Rebuild & Reinstall Condensate Pump No. 1 located in Pit No. 5 at Building 5:

· Set up equipment to enter confined space

· Isolate condensate pump no. 1

· Disconnect electric

· Pull and remove condensate pump no. 1 from pit

· Rig condensate pump no. 1 to truck

· Transport condensate pump no. 1 to the vendor’s repair facility for evaluation

· Overhaul pump at vendor’s repair facility; Overhaul to include new gaskets, new high temperature viton seal, new assorted brass hardware, new motor, repair thread on impeller, balance the impeller and shaft, sandblast, paint, and bench test

· Set up equipment to enter confined space

· Reinstall pump

· Reconnect electric to pump

· Test for proper operation

Remove, Rebuild & Reinstall Condensate Pump No. 2 located in Pit No. 5 at Building 5:

· Set up equipment to enter confined space

· Isolate condensate pump no. 2

· Disconnect electric

· Pull and remove condensate pump no. 2 from pit

· Rig condensate pump no. 2 to truck

· Transport condensate pump no. 2 to the vendor’s repair facility for evaluation

· Overhaul pump at vendor’s repair facility; Overhaul to include new gaskets, new high temperature viton seal, new assorted brass hardware, new motor, balance the impeller and shaft, sandblast, paint, and bench test

· Set up equipment to enter confined space

· Reinstall pump

· Reconnect electric to pump

· Test for proper operation

Starters:

· Set up equipment to enter confined space

· Furnish and install two new starters and two new selector switches

· Rewire

· Test for proper operation Float Switch Pit No. 5, located in Pit No. 5:

· Set up equipment to enter confined space

· Furnish and install one new float switch

· Rewire

· Test for proper operation

3.

Background:

On Friday, 5/15/2020, steam leaks were found in Pit No. 5 at the Northport VAMC, 79 Middleville Road Northport, NY 11768. The steam leaks have been caused by two (2) failed condensate pumps that are beyond economic repair.

4.

Performance Period:

Ten days 5.

Inspection

The Plumbing Shop Supervisor will perform an inspection in the presence of the contractor and prior to the contractor leaving the facility. This inspection is to ensure that all work is complete per the terms of this Statement of Work.