About this file
This document is a Request for Qualification (RFQ) issued by the City of Georgetown, South Carolina, seeking engineering consulting services for the Black River Road Widening Project (Project No. 1933). The RFQ aims to create a shortlist of three highly qualified electrical and distribution engineering consultants to develop comprehensive plans for relocating electrical infrastructure along Black River Road. The project involves identifying power line poles and associated equipment within the city's right-of-way. Key dates include a release date of September 10, 2025, with qualifications due by October 9, 2025 at 2:00 PM EST. A non-mandatory site visit can be arranged with the Electric Department Director, and proposals must be submitted electronically through the city's website.
The evaluation process will score submissions across six criteria totaling 100 points, including firm personnel qualifications (25 points), related project experience (25 points), project understanding and approach (20 points), pre-proposal interviews (20 points), reference letters (5 points), and local vendor preference (5 points). The selected consultant will be required to prepare a 10-year Capital Improvement Plan, provide final conclusions and recommendations, and maintain $1,000,000 in various insurance coverages. The city will cooperate by providing record drawings, reviewing submittals, and paying for services based on monthly work completion. The procurement process is designed to ensure transparency and fair selection of the most qualified engineering consultant for the project.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| EXHIBI A.pdf | ||
| EXHIBIT B LOCAL VENDOR SUBMITTAL FORM.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Page 1 of 15 _______ Initials
REQUEST FOR QUALIFICATION (RFQ)
LEADING TO A REQUEST FOR PROPOSAL (RFP)
FOR
ENGINEERING CONSULTING SERVICES
REQUESTOR: City of Georgetown
1134 North Fraser Street
Georgetown, SC 29440
Contact: Nereo Parreno, Purchasing Agent
Email: purchasing@georgetownsc.gov
Phone: 843.545.4046
PROJECT: Black River Road Widening Project
PROJECT NO: 1933
RELEASE DATE: Wednesday, September 10, 2025
DUE DATE: On or before 2:00 PM EST (local time) Thursday, October 9, 2025
Proposals must be submitted electronically through the City’s website, www.georgetownsc.gov.
The City will not accept Proposals by hard copy, fax, or email.
For instructions on how to submit your proposal electronically, please refer to the City’s website, under “Business”, or click here for a direct link.
http://www.georgetownsc.gov/ https://www.georgetownsc.gov/governmental_services/departments/finance/bids__rfps.php
Page 2 of 15 _______ Initials
TABLE OF CONTENTS
Topic Page
Important hyperlinks and email address 3
Background 3
Purpose 4
Project Description 4
Site Visit 4
Scope of Services 4
Process 5
Evaluation Criteria………...……………………………………………………………5
Intent to Award 7
Protest Procedure 7
Questions 8
Schedule of Events 9
Submittal Instructions 10
General Contractual Requirements 13
Exhibits 15
Page 3 of 15 _______ Initials
Important hyperlinks and email addresses:
1. City of Georgetown website
2. City of Georgetown Public Facebook
3. City of Georgetown Purchasing Ordinance in its entirety.
4. All available project documents
5. All questions must be submitted directly through Bidnet:
https://www.bidnetdirect.com/south-carolina/cityofgeorgetown
Communication
It is the policy of the City of Georgetown to commit to transparency, ensure impartiality, and complete procurement processes free of internal and external influences. To accomplish this policy, ex parte communication about the bid, between the time of commencement of preparation of the solicitation document and the bid award (written or oral), is prohibited. Therefore, potential respondents and/or respondents submitting proposals, bids, qualifications, Proposals, etc. shall not engage in communication with any City employee, including elected officials, except the City official(s) designated as the contact in the Solicitation Document.
Any communication outside the one between the designated City contact in the Solicitation
Document and respondents shall be considered ex parte communication and shall not be relied upon. The City shall disqualify any potential respondent and/or respondent’s proposal if the City discovers that potential respondent and/or respondent engaged in ex parte communication.
City employees and/or elected officials shall neither initiate nor engage in ex parte communication with potential respondent and/or respondents.
Background
The Georgetown Electric Utility Department offers a range of services to the residents and businesses of Georgetown, including the provision of purchased power, distribution, metering, street lighting, and security lighting. The department acquires wholesale power from Santee
Cooper and the Southeastern Power Administration, which is subsequently distributed to customers through a 12,470-volt distribution system. This system comprises eight circuits originating from two substations: Georgetown and Maryville.
https://www.georgetownsc.gov/ https://www.facebook.com/cityofgtown/ https://cms7files.revize.com/georgetownsc/Document%20Center/Government/Department/Finance%20Documents/Forms/Procurement%20Policy.pdf https://vrapp.vendorregistry.com/Bids/View/BidsList?BuyerId=4a9920b8-7411-40a3-b333-0d07f00f270c https://www.bidnetdirect.com/south-carolina/cityofgeorgetown
Page 4 of 15 _______ Initials
Purpose
The purpose of this Request for Qualifications (RFQ) is to seek statements of qualification from electrical and distribution engineering consultants to create a shortlist of highly qualified firms for the relocation of the electrical equipment on Black River Road. The RFQ selection will lead to a
Request for Proposal (RFP) from top three (3) engineering firms. The words engineer, consultant, or consulting firm are meant to be synonymous with this RFQ.
Project Description
The Department of Transportation is in the process of widening the road to enhance access to the hospital entrance. Due to the presence of electrical equipment, including power lines and poles, within the right-of-way managed by the City of Georgetown, it will be necessary to relocate these utilities as part of this project.
Site Visit
Please refer to the exhibit map for the project's location, which will be provided to the selected consultant at a later date.
The site is situated at the 500-600 block of Black River Rd, Georgetown, South Carolina 29440.
For arrangements regarding a site visit, please contact Ryan Courtemanche, the Electric
Department Director, at 843-545-4600. Our standard business hours are from 8:30 AM to 5:00
PM.
While a site visit is not mandatory, it is strongly encouraged prior to submitting a proposal. Failure to visit the site shall in no way relieve any bidder from any obligation in respect to their bid.
Scope of Services
The selected firm(s) may be required to deliver the following services:
The engineering consultant is expected to develop comprehensive plans and provide detailed locations for the electrical infrastructure along the Black River Road. This includes identifying power line poles and any associated equipment mounted on those poles.
Safety and Environmental Concerns
Understanding the National Electrical Safety Code (NESC) is essential for anyone working in the electric utility sector. This standard outlines the crucial rules and guidelines for the installation, operation, and maintenance of electric supply and communication lines, safeguarding both utility workers and the public. Professionals in the field should be well-versed in the NESC, as it impacts every aspect of an electric utility system, from design to construction, operation, and maintenance.
By being knowledgeable about these regulations, they can ensure compliance with public power safety standards and contribute to economically viable practices. It's important for individuals to
Page 5 of 15 _______ Initials actively engage in the revision process and provide valuable feedback, as this helps maintain the integrity and safety of public power systems.
Capital Improvement Plan
The consultant shall prepare a 10-year CIP in order of priority with cost estimates prorated for inflation.
Final Conclusions and Recommendations
Provide all necessary conclusions and recommendations in this section.
The city will:
1. Cooperate with the consultant on a timely basis.
2. Provide the appropriate record drawings and information.
3. Review the consultant's draft submittals in a timely fashion.
4. Pay for all services rendered based on a percentage of work completed at the end of the month.
Process
The City will conduct the selection of qualified Engineering Consultant in the following manner:
1. The RFQ and Qualification Form documents will be available on our website.
Qualification will be received and evaluated as described in this RFQ.
2. The best qualified, responsible, and responsive Engineering Consultant will be presented to the City Administrator for approval, as required.
3. After the Administrator's approval, the City will issue an Intent to Award Notice.
4. The Submittal Listing of Qualification received will be published on the City’s website within forty-eight (48) hours of opening. Click here for a direct link.
Evaluation Criteria
The selection of the consultant is based on professional qualifications and competitive fees. Fee proposals may be subject to negotiation for fair and reasonable compensation.
All qualifications will be reviewed for purposes of determining professional qualifications, experience, project understanding, responsiveness and responsibility. The submission of a qualification for review does not necessarily qualify the proposer or proposal as being responsive or responsible. Failure to provide specific information, as requested, for use in the evaluation will cause your qualification to be non- responsive.
The Project Review Committee (PRC), consisting of members appointed by the City Administrator or his/her designee will review and independently score the qualifications submitted by all firms.
In its review, the PRC will consider all elements of the RFQ. Firms shall be ranked from the most highly qualified to least qualified based on the information provided by each firm and the evaluation criteria. The RFQ selection process will result in a Request for Proposals (RFP) being issued to the top three (3) firms.
Page 6 of 15 _______ Initials
Offers will be consistently evaluated using only the criteria stated below
Items no. Evaluation Criteria Maximum Points
1 Experience & Qualifications of Firm
Personnel
• Key personnel experience in Electrical
Utilities and distribution systems
• Asset management experience
• RIA and SRF experience
2 Related Experience of Similar Past Projects
• Consultants’ ability to deliver a quality work product on budget and on schedule on similar types of projects
3 Project Understanding and Approach –
• Description/understanding of required services
• Overall plan of project execution, including timeline
• Explain how the firm will ensure excellent communication from the
Project Manager to City staff, including dealing with plant field personnel.
4 Pre-Proposal Meeting Interviews 20
5 Reference letters from other Electrical
Utilities (Three)
6 Local Vendor Preference 5
Total 100
Page 7 of 15 _______ Initials
Intent to Award
Submission of a proposal indicates acceptance by the Engineering Consultant of the conditions contained in this RFQ. The City shall have the sole discretion in determining the best qualified, responsive and responsible Engineering Consultant(s).
A. The ability, capacity, and skill of the Engineering Consultant to perform the contract to provide the service required;
B. Whether the Consultant can perform or provide the service promptly, or within the time specified, without delay or interference;
C. The character, integrity, reputation, judgment, experience, and efficiency of the
Consultant;
D. The quality of performance of previous contracts or services similar to services being sought in this RFQ;
E. The previous and existing compliance by the Consultant with laws and ordinances relating to the contract or services;
F. The ability of the Consultant to perform or provide the service;
G. The quality, availability, and adaptability of the consultant services to the particular use required;
H. The ability of the Consultant to provide services for the nature of the requirements of an awarded contract as required in the RFQ; and
I. Whether the Consultant has met the criteria of the terms and conditions of the RFQ.
Protest Procedure
In accordance with the City’s Procurement Ordinance, any protest or objection to this RFQ award process must be submitted in writing to the City of Georgetown, Attn: Nereo Parreno, Purchasing Agent, PO Drawer 939, Georgetown, SC 29440, within ten (10) calendar days of the notification of award posted to the City’s website.
Page 8 of 15 _______ Initials
Questions
No answers will be given over the phone.
All questions regarding this Request for Proposals must be submitted directly through our procurement platform, Bidnet, no later than 2:00 PM EST (local time) on Wednesday, September
24, 2025.
Please note - if you do not receive an online confirmation from Bidnet that your questions submission was successful, it is the bidder's sole responsibility to contact the Purchasing Agent at
843.545.4046.
No questions will be accepted after the deadline mentioned above. All submittals shall include the following in the subject line: Black River Road Widening Engineering Services
Answers to questions or Addenda will be posted on the City’s website as an Addendum no later than 2:00 PM EST (local time), Wednesday, October 1, 2025.
Page 9 of 15 _______ Initials
Schedule of Events
When the Procurement Division is closed due to force majeure, proposal openings will be postponed to the same time on the next official business day. The vendor is responsible for obtaining information regarding proposal submittals directly from the City’s website.
Procurement procedures are subject to the City’s procurement policies as outlined in Section 2-
188 of the City’s Municipal Code (Chapter (Administration), Article IV (Procurement)). The
City’s Procurement Ordinance can be found in its entirety on the City’s website.
The City reserves the right to change the project schedule as it deems necessary. In the event of a major date change, the City will post notice of such on the City’s website and notify known participants. The City reserves the right to issue addenda to this RFQ up to two (2) days before the RFQ due date as needed to clarify the City’s desires or to make corrections or changes to the
RFQ document or submittal process.
The City reserves the right to request additional information from any and all prospective contractors or individuals deemed necessary by the City to evaluate the Proposals. However, this process may not be used as an opportunity to submit missing documentation, missing information, or to make substantive revisions to the original proposal.
No. MILESTONE EVENT DATE TIME (EST)
1 Request for Qualifications (RFQ): Engineering Wednesday, September 10, 2025
Non mandatory site visit 500-600 Block of Black
River By arrangement with Electric Department Director
Deadline for written questions - Submitted via
Bidnet Wednesday, September 24, 2025 2:00 PM
Deadline for addenda to be posted to the City's website, www.georgetownsc.gov Wednesday, October 1, 2025 2:00 PM
5 Engineering Qualification due date Wednesday, October 9, 2025 2:00 PM
6 Inteview Schedule for Firms October 13 - November 7, 2025
6 RFQ Statement Evaluations Nov-25
7 RFQ Notice of Award (tentative) Nov-25
8 Request for Proposal to Shortlisted Firms (tentative) December, 2025
9 RFP Award Jan-26
Page 10 of 15 _______ Initials
The City reserves the right to cancel or reissue the RFQ and/or revise the schedule at any time.
The City also reserves the right to accept or reject any or all Proposals deemed in its best interest and to accept all or part of the scope of work herein as its project timeline and/or budget allows.
Once a final determination is made, the City is not required to furnish a statement of the reason(s) a proposal was not selected.
All information will be updated and posted on the City’s website.
It is the Consultant’s sole responsibility to obtain the information directly from the City’s website regarding this project.
The Consultant will acknowledge receipt of all issued addenda in their submittals, if applicable.
No: __________________Dated:______________
Submittal Instructions
By initialing the bottom of each page of this RFQ document, the Consultant represents that (1) their representatives have read and understood the solicitation and (2) their proposal is made in compliance with this solicitation. The Consultant’s s representatives are expected to examine this
RFQ thoroughly and request an explanation of any ambiguities, discrepancies, errors, omissions, or conflicting statements. Failure to do so will be at their risk.
All procurement procedures are subject to the City’s procurement policies as outlined in Section
2-188 of the City’s municipal code.
The City’s Purchasing Ordinance can be found in its entirety on the City’s website.
It is the sole responsibility of the Consultant’s to have their Qualification delivered to the City before the closing hour and date. The City assumes no responsibility for technological failure in submitting Proposals electronically. It is the sole responsibility of the Contractor to confirm that their proposal was submitted on time, and that their PDF file/files are not corrupt.
Page 11 of 15 _______ Initials
Submittals may be rejected if deemed non-responsive. To be considered, interested parties must submit the following no later than the aforementioned deadline:
1. Submit proposal electronically through the City’s website, www.georgetownsc.gov.
Click here to submit electronically.
Submittal package must include all of the following items.
1. Companies Statement of Qualification (NTE 5 pages)
2. Complete initialed copy of this RFQ document
3. Complete Mandatory Local Vendor Submittal Form (Page 10)
4. List of three (3) references letters
2. The City reserves the right to waive any minor informalities and irregularities of submittals that do not affect price, quantity, quality, or delivery. Minor informalities to include:
failing to initial the proposal, failing to acknowledge addenda, or not submitting the Local
Vendor Preference Option Form, will not, by themselves result in a submittal being deemed non-responsive. The City will request that any and all Consultant correct the minor informality or irregularity within the same specified time.
3. Electronic proposal must be received electronically through the City’s website, www.georgetownsc.gov, no later than the aforementioned deadline. . Bids will be publicly opened and read aloud via the City’s public Facebook page, https://www.facebook.com/Cityofgtown/. No proposal will be accepted after such time.
Late Proposals will not be accepted nor considered. The official clock shall be that of the
City’s Purchasing Agent, or designee. The City reserves the right to accept or reject any or all Proposals and to waive any informalities and technicalities in the proposal process.
No additional fees, costs, or any other reimbursable expenses will be allowed.
4. This solicitation does not commit the City to award a contract. The City reserves the right to waive any technicalities or informalities and to accept or reject any and/or all submissions as deemed by its sole judgment to be in its best interest. The City also reserves the right to terminate the selection process without notice, to waive any irregularities in any submittal, and to request additional information from any of the contractors submitting a proposal.
5. The Consultant may withdraw their proposal only by written request, at any time prior to the scheduled opening of responses. Partial or incomplete Proposals may be rejected.
6. All costs incurred in preparing the proposal, or costs incurred in any other manner by the
Contractor in responding to this RFQ, will be wholly the Consultants’ responsibility. All materials and documents submitted by the Consultant in response to this RFQ become the property of the City and will not be returned.
7. Any proprietary information contained in the proposal should be so indicated as follows:
Vendor Disclosure
Notice of SC Freedom of Information Act
“The parties acknowledge that all material submitted may be subject to release under the South Carolina Freedom of
Information Act (FOIA) and will be released to the public unless exempt from disclosure under the FOIA.”
http://www.georgetownsc.gov/ https://vrapp.vendorregistry.com/Bids/View/BidsList?BuyerId=4a9920b8-7411-40a3-b333-0d07f00f270c http://www.georgetownsc.gov/ https://www.facebook.com/cityofgtown/
Page 12 of 15 _______ Initials
We discourage you from including any information you consider propriety or trade secret, as this material is subject to the FOIA once it’s in the City’s possession. If you must include any such information in your submission, please identify it by color, labeling, and/or bold font as “PROPRIETARY INFORMATION” so that it can be readily recognized. In the event the City receives a request for this material, the City will notify those parties who have identified information they believe is proprietary or trade secret of the request. The
City has a ten (10) day deadline to respond to the request. This is your window to file an action challenging the release. Please be on notice that if the City is not served with such an action, the information will be released.
8. Proposals must be made in the official name of the company or individual under which business is conducted (showing official business address) and must be signed in ink by a person duly authorized to legally bind the person, partnership, company or corporation submitting the proposal. Proposals having any erasures or corrections must be initialed in ink by the vendor.
9. Disqualification and Rejection of Proposal – The City reserves the right to reject any proposal from a contractor who has failed to perform satisfactorily, or complete on time, or in a manner consistent with the RFQ documents, contract of similar nature, or to reject the proposal from a contractor who is not in a position to perform such a contract satisfactorily. The City expressly reserves the right to award the contract to the Contractor that best meets the requirements as set forth herein.
10. Assignment of Contract – Assignment to the selected Consultant of any contract to be entered into in accordance with this RFQ will not be recognized by the City unless such assignment has prior written approval of the City.
11. Insurance Provisions - The selected Consultant will be required to provide and maintain proof of insurance throughout the contract term in the amount of $1,000,000.00 and as required at the point of contract negotiation by the City’s Risk Manager as follows:
• Comprehensive General Liability (per occurrence);
• Comprehensive Auto Liability (per occurrence); and
• Workers’ Compensation Liability
• Automobile Liability
• Professional Liability
The City of Georgetown is to be named as “Additional Insured” on the above insurance coverage as respect to the City’s interest under the contract. Certificates showing proof of insurance shall be submitted to the City prior to commencement of services under the agreement. Further, it shall be an affirmative obligation upon the Consultant to advise the
City’s Risk Management Department within two (2) days of the cancellation herein at one of the following options below:
• Email – askidmore@georgetownsc.gov
• Fax - 843.527.6173
• Mailing address - PO Box 939, Georgetown, SC 29442
Failure to do so shall be construed to be a breach of the agreement:
12. Indemnification - The selected Consultant agrees to indemnify, defend and hold harmless the City and their authorized officers, employees, agents, and volunteers from any and all claims, actions, losses, damages, and/or liabilities arising from their acts, errors, or omissions and for any costs or expenses incurred by the City therefore under an agreement.
mailto:askidmore@georgetownsc.gov
Page 13 of 15 _______ Initials
13. Compliance With Law – The selected Consultant and its agents and employees shall be bound and comply with all federal, state and local laws, ordinance rules and regulations, as well as all other governing bodies having legal jurisdiction with respect to the area where such work is performed.
14. City Business License and Permits - The selected Consultant shall be required to obtain all applicable City permits and business licenses prior to work commencing. Contact the
Finance Department at 843.545.4041 for business license information. Contact the
Planning & Community Development Department at 843.545.4017 for construction permit information. These expenses shall be included in the total proposal cost.
15. Payment terms - A monthly itemized billing statement must be submitted in a form specified by the City for services performed. The City will remit full payment on all undisputed invoices within thirty (30) days from receipt of the invoice by the appropriate person(s) (to be designated at the time of contract).
General Contractual Requirements- As Applicable
1. Force Majeure - The Contractor shall not be liable for any excess costs if the failure to perform the contract arises out of causes beyond the control and without the fault or negligence of the Contractor. Such causes may include, but are not limited to acts of God or of the public enemy, acts of Governments in either its sovereign or contractual capacity, fires, floods, epidemics, quarantine restriction, strikes, freight embargoes, and unusually severe weather; but in every case the failure to perform must be beyond the control and without the fault or negligence of the Contractor.
2. Governing Law - Except to the extent that this agreement may be governed by any federal law, including federal bankruptcy law, this agreement shall be governed by, constructed and interpreted under, and enforced exclusively in accordance with the laws of the State of
South Carolina, and the courts in the State of South Carolina shall have jurisdiction with respect to any dispute arising hereunder.
3. Contractor Qualifications - Contractor must, upon request of the City, furnish satisfactory evidence of its ability to furnish products and/or services in accordance with the terms and conditions of this RFQ. The City reserves the right to make the final determination as to the Contractor’s ability to provide the services herein.
4. Contractor Responsibility – Each Contractor shall fully acquaint him/herself with conditions relating to the scope and restrictions attending the execution of the work under the conditions of this RFQ. It is expected that this will sometimes require on-site observation. The failure or omission of the Contractor to acquaint him/herself with existing conditions shall in no way relieve him/her of any obligation with respect to this RFQ or to a contract.
5. Affirmative Action - The Contractor will take affirmative action in complying with all federal and state requirements concerning fair employment and employment of the handicapped, and concerning the treatment of all employees without regard or discrimination by reason of race, color, religion, sex, national origin or physical handicap.
6. Women and Minority Business Enterprise (WMBE) Statement - It is the policy of the City to provide minorities and women equal opportunity for participating in all aspects of the
City’s contracting and procurement programs, including but not limited to employment, Page 14 of 15 _______ Initials construction projects, and lease agreements consistent with the laws of the State of South
Carolina. It is the policy of the City to prohibit discrimination against any person or business in pursuit of these opportunities on the basis of race, color, national origin, religion, sex, age, handicap, or veteran status. It is further the policy of the City to conduct its contracting and procurement programs so as to prevent such discrimination and to resolve any and all claims of such discrimination.
7. Termination - Subject to the following provisions, any contract resulting from this request for Proposals may be terminated by the City provided a thirty (30) day advance notice in writing by the City Administrator, or his designee, is given to the Contractor:
7.1 Non-Appropriations - Funds for this contract are payable from local appropriations. If the sufficient appropriations are not made to pay the charges under the contract it shall terminate without any obligation to the City.
7.2. Convenience - In the event that a contract is terminated or canceled upon request and for the convenience of the City without the required thirty (30) day advance written notice, then the City shall negotiate reasonable termination costs, if applicable.
7.3 Cause - Termination by the City for the cause, default or negligence on part of the
Contractor, shall be excluded from the foregoing provisions; termination costs, if any shall not apply. The thirty (30) day advance notice requirement is waived and the default provision herein shall apply.
7.4 Default – In case of default by the Contractor, the City reserves the right to purchase any and all items/services in default in open market, charging Contractor with any excessive costs. SHOULD SUCH CHARGE BE ASSESSED, NO SUBSEQUENT
PROPOSALS OF THE DEFAULTING CONTRACTOR WILL BE CONSIDERED
UNTIL THE ASSESSED CHARGE HAS BEEN SATISFIED.
8. Prime Contractor Responsibilities - The Contractor will be required to assume sole responsibility for the complete effort as required by this RFQ. The City will consider the
Contractor to be the sole point of contact with regard to all contractual matters.
9. Subcontracting - If any part of the work covered by this RFQ is to be subcontracted, the
Contractor shall identify the subcontracting organization and the contractual arrangements made therewith at the time of the offer. All subcontractors must be approved by the City.
The successful Contractor will also furnish the corporate or company name and the names of the officers of any subcontractors engaged by the Contractor.
10. Ownership of Material – All materials and documents submitted by the Contractor in response to this specification become the property of the City and will not be returned to the Contractor.
11. Compliance with State and Federal Requirements – State and Federal requirements that are more restrictive than these set forth herein shall be followed by the Contractor.
12. Contract Amendments - Amendments to any agreement between the City and the
Contractor must be reviewed and approved in writing by the City Administrator or his designee.
13. Assignment - No contract or its provisions may be assigned, sublet, or transferred without the written consent of the City Finance Department.
14. Records Retention and Right to Audit – The City shall have the right to audit the books and records of the Contractor as they pertain to this contract. Such books and records shall be maintained for a period of three (3) years from the date of final payment under contract.
Page 15 of 15 _______ Initials
15. The City may conduct performance audits of the Contractor, as determined necessary by the City. Pertaining to all audits, the Contractor shall make available to the City access to its computer files containing the history of the contract performance and all other documents related to the audit. Additionally, any software used by the Contractor shall be made available for auditing purposes at no cost to the City.
16. Independent Contractor Status - The parties hereby agree that the Contractor is an independent contractor of the City and that nothing in an agreement with the City shall be deemed to place the parties in a relationship of employer/employee, partners, or joint ventures. Neither party shall have the right to obligate or bind the other in any manner.
Each party agrees and acknowledges that it will not hold itself out as an authorized agent with the power to bind the other party in any manner. Each party shall only be responsible for any withholding taxes, payroll taxes, disability insurance payments, unemployment taxes, or other similar taxes or charges with respect to its activities in relation to the performance of its obligations of an agreement.
17. Representations of Contractor - Contractor represents, warrants, and covenants that:
(a) In providing the services contractor shall utilize the care and skill used by members of the Contractor’s profession practicing under similar circumstances at the same time and in the same locality.
(b) All employees provided by the Contractor to the City shall have the qualifications, skills, and experience necessary to perform his/her job in accordance with the requirements of the agreement. The City may request the removal of any employee for a good cause.
(c) Contractor is a business validly existing and in good standing under the laws of the
State of South Carolina.
18. Indemnity Provisions - Contractor agrees to and shall indemnify and hold the City harmless from and against all liability, loss, damages or injury, and all costs and expenses
(Including attorney fees and costs of any suit related thereto) suffered or incurred by the
City, arising from or related to the terms of this project, or Contractor’s performance thereunder.
19. City Business License and permits - The selected Contractor shall be required to obtain all applicable City permits and business licenses prior to work commencing. Contact the
Finance Department at 843.545.4041 for business license information. Contact the
Planning & Community Development Department at 843.545.4017 for permitting information. These expenses shall be included in the total proposal cost.
Exhibits Available
A) GIS layout of the location
B) Mandatory Local Vendor Submittal Form
File details come from the government source that posted it. Updated .