1-RFI (Req for Expressions of Interest) Traction Power Substation.pdf
PDF 13 MB Posted
- Attached to
- Traction Power Substation
- Solicitation number
- RFI Doc2159754403
- Issued by
- Harris County, Houston City, Texas
About this file
This is a Request for Expressions of Interest (RFI) issued by the Metropolitan Transit Authority (METRO) of Harris County, Texas, for Design-Build services related to Traction Power Substation hardware replacement and control system updates. METRO is seeking qualified firms to provide expressions of interest for a Progressive Design-Build (PDB) delivery model to integrate hardware manufacturers and installers into the design process, currently at approximately 30% completion. The RFI requires submission of completed Exhibit A (Responder Information), Exhibit B (RFI Questionnaire), and Exhibit C (Progress Drawing Exhibits) through METRO's Bonfire hub and one hardcopy submission to the Procurement Division at 1900 Main Street, Houston, Texas 77002. The deadline for submitting bidder questions is May 15, 2026 at 5:00 p.m. Central Standard Time, with responses published by May 20, 2026 at 5:00 p.m. RFI responses are due by May 28, 2026 at 2:00 p.m. Central Standard Time. The RFI was issued on April 30, 2026.
The RFI questionnaire addresses critical project delivery considerations including market interest in the PDB delivery method versus standard Design-Bid-Build approaches, optimal design completion levels for pricing, two-phase PDB structure preferences, off-ramp provisions allowing METRO to terminate after Phase 1 or convert to competitive procurement, risk allocation between owner and design-builder, and electrical/systems expertise availability. Respondents are asked to provide information on outage strategy recommendations, commissioning and testing duration, long-lead equipment identification, constructability field investigations, realistic schedule durations for preconstruction, procurement, installation, and commissioning phases, and resource requirements. The RFI includes detailed schematic and single-line diagrams of the traction power substation systems, including specifications for AC and DC panels, rectifier units, circuit breakers, transformers, and SCADA control systems. Prospective respondents must register as vendors in METRO's SAP Procurement System through the METRO Supplier Self-Registration Page to receive notifications of upcoming opportunities and facilitate payment processing through the Ariba system.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
METROPOLITAN TRANSIT AUTHORITY (METRO)
REQUEST FOR EXPRESSIONS OF INTEREST
FOR
TRACTION POWER SUBSTATION
RFI NO. Doc2159754403
The Metropolitan Transit Authority of Harris County, Texas, requests Expressions of Interest (RFI) submissions from firms interested in providing Design-Build Traction Power Substation Station
Please submit RFI Responses and questions regarding this RFI electronically through METRO’s Bonfire hub at https://ridemetro.bonfirehub.com AND one (1) hardcopy of the submittal to the address below no later than 2:00 p.m. local time, May 28, 2026 to
Metropolitan Transit Authority Procurement Division, 8th Floor
1900 Main Street Houston, Texas 77002 https://ridemetro.bonfirehub.com/
Doc2159754403
TABLE OF CONTENTS
BACKGROUND
RFI RESPONSE REQUIREMENTS
EXHIBITS
EXHIBIT A: RESPONDER INFORMATION
EXHIBIT B: RFI QUESTIONAIRE
EXHIBIT C: DRAWINGS 6
1.0 BACKGROUND:
The Metropolitan Transit Authority of Harris County (METRO) is conducting a Request for Information (RFI) from interested parties regarding Substation Hardware Replacement. Metro is evaluating procurement strategies for replacement of hardware within existing traction power substations. Current design is approximately 30% complete.
Due to the hardware and installation driven nature of the work, METRO is considering offering this contract as a Progressive Design-Build to integrate the hardware manufacturer and installer into the design process and have a single point of responsibility and delivery.
REGISTER TO BECOME A SUPPLIER WITH METROPOLITAN TRANSIT AUTHORITY OF HARRIS COUNTY:
METRO has recently migrated to Ariba, and your account needs to be set up with our AP department for payments and purchasing. Please register as a vendor in our SAP Procurement System at METRO Supplier Self-Registration Page to receive email notifications of upcoming METRO opportunities.
2.0 RFI RESPONSE REQUIREMENTS
Responder’s response must include a completed:
Exhibit A: Responder Information
Exhibit B: RFI Questionnaire
Exhibit C: Progress Drawing Exhibits for Reference in Request for Information (RFI)
2.1 Important Processing Dates
METRO anticipates carrying out the procurement process in accordance with the schedule set forth in the table below.
All times are in the central time zone, times unless otherwise indicated. The schedule is subject to modification at the sole discretion of METRO. Respondents will be notified of any changes to the due date for questions or due date for the RFI submittals by an amendment to this RFI.
PROCUREMENT SCHEDULE
Procurement Activity Date (subject to change)
Time-Central Standard
RFI issued 4/30/2026 4:00 p.m.
Deadline for submission of Bidder questions to METRO’s Bonfire Hub
5/15/2026 5:00 p.m.
Responses to Bidders Q&A published by METRO on Bonfire Hub 5/20/2026 5:00 p.m.
RFI Response Due Date 5/28/2026 2:00 p.m.
2.2 Questions
All written questions related to this RFI will be accepted until 5:00 PM Central Standard Time on Friday, May 15, 2026. Submit questions via Bonfire hub. Response to questions to be answered by 5:00PM Central Standard Time, Wednesday, May 20, 2026
2.3 Response Due Date
Responses to this RFI will be receive by METRO until 2:00PM Central Standard Time, Thursday, May 28, 2026.
The Response must be submitted as follows:
ONE (1) ELECTRONIC SUBMITTAL, in PDF format, submitted via Bonfire hub at https://ridemetro.bonfirehub.com and
ONE (1) HARD COPY SUBMITTAL, in a sealed envelope bearing the name and address of the Responder and the identification RFI No. Doc2159754403 delivered to:
METROPOLITAN TRANSIT AUTHORITY OF HARRIS COUNTY, TEXAS
Attn: Je rome Sco t t
3.0 EXHIBITS
EXHIBIT A: RESPONDER INFORMATION
Instructions: Please complete this form and include it with the Response.
Company Name: _____________________________________
Date of Incorporation: _____________________________________
Mailing Address: _____________________________________
Company Phone Number: _____________________________________
Company Web Site: _____________________________________
Approx. Number of Employees: _________________________________
Person responsible for the information contained in RFI Response
Name: ______________________________________
Title: ______________________________________
Direct Phone Number: ______________________________________
Email: ______________________________________
Required Detailed Response:
Company Experience, Information about the contractor's experience with similar roofing projects.
Company Qualifications: Details about the contractor's qualifications, licenses, and insurance.
Methodology: Describe how your company will approach the project?
EXHIBIT B: RFI QUESTIONNAIRE
Instructions: Provide a response to the questions Exhibit B and include it in the Response. A response to each question is requested but not mandatory. Please do not renumber or reorder the questions.
Metropolitan Transit Authority of Harris County Rail Operations + Maintenance of Way Rail Vehicle Maintenance Division Infrastructure Improvements
Request for Information Substation Hardware Replacement
Substation Hardware Replacement
INTRODUCTION Exhibits B Houston METRO is evaluating procurement strategies for replacement of hardware within existing traction power substations. Current design is approximately 30% complete. Due to the hardware and installation driven nature of the work, METRO is considering offering this contract as a Progressive Design-Build to integrate the hardware manufacturer and installer into the design process and have a single point of responsibility and delivery.
SECTION 1 – Delivery Method (Progressive Design-Build)
1. Market Interest Is your firm interested in pursuing this project under a Progressive Design-Build (PDB) delivery model?
☐ YES
☐ NO
Would you prefer PDB over standard Design-Bid-Build, either Invitation for Bid (IFB) or Competitive Sealed Proposal (CSP)? Why?
2. Standard Structure What level of design completion do you believe is optimal to be able to price the work as a standard Design- Bid-Build?
Given design is currently approximately 30% [referenced here], what additional information would you require to price risk appropriately?
Rail Vehicle Maintenance Division Infrastructure Improvements
Request for Information Substation Hardware Replacement
3. Progressive Structure Do you support a two-phase PDB approach (Pre-construction Phase + GMP Phase)?
☐ YES
☐ NO
Are you comfortable setting a Guaranteed Maximum Price (GMP) at approximately 90% design?
☐ YES
☐ NO
What level of design completion do you believe is optimal before establishing GMP for substation hardware replacement?
4. Off-Ramp Language Would your firm accept an “Off-Ramp” provision allowing METRO to:
• Terminate after Phase 1 if GMP is not accepted?
• Convert to competitive procurement if negotiations fail?
• What contractual protections would you request if off-ramps are included?
5. Risk Allocation What risks do you believe are best managed by the Owner vs. the Design-Builder for:
• Unknown existing conditions inside substations
• Utility coordination
• Long-lead electrical equipment
• Commissioning and integration
How should escalation and supply chain volatility be handled in a PDB structure?
Are there any other major risks that you think that METRO should address in the contract language?
Rail Vehicle Maintenance Division Infrastructure Improvements
Request for Information Substation Hardware
6. Electrical / Systems Expertise Does your firm self-perform traction power / substation design, or rely on specialty subcontractors?
Does your firm self-perform traction power / substation installation & integration, or rely on specialty subcontractors?
SECTION 2 – Shutdown / Outage Strategy
1. Outage Preference From a constructability and risk standpoint, do you recommend:
☐ A single extended shutdown per substation, or
☐ Multiple incremental outages?
Why:
2. Commissioning & Testing What duration should be assumed for commissioning and burn-in testing?
Rail Vehicle Maintenance Division Infrastructure Improvements
Request for Information Substation Hardware
SECTION 3 – Technical & Execution Risk
1. Long-Lead Equipment What equipment items (breakers, transformers, relays, SCADA components, protection panels, etc.) are currently long-lead?
Should procurement of major electrical equipment be advanced separately?
2. Constructability What field investigations are recommended prior to final pricing?
Note that when METRO bids this project out, regardless of structure, bidders will be offered 3D LiDAR (Point Cloud) and 360 Imagery Scans of every substation.
3. Schedule What is a realistic duration for:
• Phase 1 (Preconstruction)
• Procurement
• Installation
• Commissioning
4. Resources What are the levels of resources from your firm and or subcontractors needed for this work and how does the resource availability impact phasing and vice versa.
3/25/2026001 PROGRESS PRINT SET FOR RFI
METROPOLITAN TRANSIT AUTHORITY OF HARRIS COUNTY, TEXAS
TRACTION POWER
SUBSTATION STATION
HARDWARE REPLACEMENT/UPGRADE
& CONTROL SYSTEM UPDATE
PROGRESS DRAWING EXHIBITS FOR
REFERENCE IN REQUEST FOR INFORMATION
Y-YELLOW, BL-BLUE
METER W/POWER SUPPLY
ANALOG / DIGITAL
PO
W
ER
SU
PP
LY
A
CIRCUIT BREAKER
DRAWOUT VT WITH FUSE
TEST BLOCK
COUNTER
LED
RESISTORRES
VARIABLE RESISTOR
or or
SCHEMATIC DIAGRAM SYMBOLS
MICRO SWITCH
(S01, S02, 33)
K
SELECTOR SWITCH
(CS, 43, S1, S3)
MANUAL SWITCH
KEY OPERATED
(S2, S4, S5, S6, S7)
OPTO ISOLATOR
DEVICE OPERATION
SHIELDED CABLE
INDICATOR, G-GREEN, R-RED,
R
TWISTED PAIR
JUMPER
Q0.1
PLC INPUT
PLC OUTPUT
QUANTITY AND SIZE OF CONDUCTOR
TEFLON INSULATED CONDUCTOR>2KV
BATTERY
GROUND CONNECTION
CONDUCTOR CONNECTION
POWER RECTIFIER OR DIODE
6-1/c 500kCMIL (kCMIL SAME AS MCM)
AUXILIARY RELAY COILK
w/ SERIES TRIP DEVICE
DRAW-OUT TYPE
ABOVE LINE AND
FRAME SIZE INDICATED
LINE IN AMPS
3-POLE, DRAW-OUT TYPE
15kV CIRCUIT BREAKER, ISOLATING DEVICE (TYPICAL) a c
(3Ø MADE UP NEUTRAL)
TERMINATION
SINGLE LINE DIAGRAM SYMBOLS SCHEMATIC DIAGRAM SYMBOLS
CHASSIS CONNECTION
PANEL CIRCUIT BREAKER,
TRIP VALUE BELOW
DC CIRCUIT BREAKER72
VOLTMETER
AMMETER
VT
K
CT
TRANSFORMER
3 PHASE, DELTA,
VOLTAGE TRANSDUCER
KEY INTERLOCK
TEST TERMINALS
VOLTAGE OR CURRENT
TRANSDUCER
ANSI DEVICE NUMBER
SINGLE LINE DIAGRAM SYMBOLS
CURRENT TRANSDUCER
MOTORIZED, NO-LOAD BREAK TYPE
EQUIPMENT ENCLOSURE OUTLINE
MANUAL PUSHBUTTON SWITCH -
MANUAL PUSHBUTTON SWITCH -
CLOSED WHEN ACTUATING DEVICE IS
DEVICE AUXILIARY SWITCH CONTACT -
OPEN WHEN ACTUATING DEVICE IS
DEVICE AUXILIARY SWITCH CONTACT -
RELAY INFLUENCE LINE
DIRECTION OF CONTROL OR
NORMALLY OPEN
NORMALLY CLOSED
CURRENT TRANSFORMER600/200-5
(TYPICAL FOR ANSI-
12 PULSE
(TYPICAL FOR IEEE 1653.2
CIRCUIT No. 31)
INTERPHASE TRANSFORMER
CONNECTED ON THE 200:5 TAPMR
TRANSFORMER
M
NUMBER DENOTES QUANTITY
VOLTAGE TRANSFORMER,
NUMBER INDICATES QUANTITY
CURRENT TRANSFORMER,
TERMINAL BLOCK
MULTI-RATIO 600:5
RECTIFIER TRANSFORMER,
CIRCUIT No. 31) DISCONNECT SWITCH
DISCONNECT SWITCH
MANUAL, NO-LOAD BREAK TYPE
THERMOCOUPLE
DC SHUNT
CONNECTION
FUSE
SA
CABLE STRESS
SURGE ARRESTOR
LIGHTNING OR
TRANSFORMER
3 PHASE, WYE,
w/ GROUND CONNECTION
CONE TERMINATION
CONNECTION
NON-OPERATED OR DE-ENERGIZED STATE
NON-OPERATED OR DE-ENERGIZED STATE
FLEXIBLE Cu CONDUCTOR (OR) BRAID >120mm
A
V
NEGATIVE GROUNDING DEVICE57
148 INCOMPLETE SEQUENCE RELAY
72-0 DC MAIN BREAKERF0
72-1 FEEDER BREAKERF1
F2 72-2 FEEDER BREAKER
F3 72-3 FEEDER BREAKER
DC PANELDP1
DC CONTACTORDCC
ST SHUNT TRIP
LOCAL - OFF - REMOTE
AUXILIARY RELAY FOR SHUNT TRIPKST
DS DOOR SWITCH
ELECTRONIC TEMPERATURE MONITORETM
E DC CIRCUIT BREAKER OPERATING SOLENOID
DC CIRCUIT BREAKER TRUCKBT
ALARMAL
S-A SCADA - ANALOG
95X TRANSFORMER TEMPERATURE AUXILIARY RELAY
UVTDS
UVTDC
CS/CL
CS/TR
LOR
AC PANEL
72-4 FEEDER BREAKER
RECTIFIER
NEGATIVE DISCONNECT SWITCHN
F4 R
EQUIPMENT
API
SA SURGE ARRESTOR
85TX TRANSFER TRIP TRANSMIT
SCADA LOCAL / REMOTE SWITCH43L/R
AUXILIARY POWER STATION
AMPERE
DESCRIPTION
BUFFER AMPLIFIER
COUNTER, CONTROL
DIGITAL PROTECTION UNIT
FUSE, CIRCUIT BREAKER
FIBER OPTIC
FEEDER MONITORING RELAY
INDICATOR
CURRENT (EUROPEAN SYMBOL)
AUXILIARY RELAY
LOCAL ANNUNCIATOR PANEL
OVERHEAD CONTACT SYSTEM
OPERATOR
PLUG (CONNECTOR)
PROGRAMABLE LOGIC CONTROLLER
PANEL METER
COMPONENT IDENTIFICATION
MECHANISM OPERATED CELL SWITCH (BREAKER STATUS)
JACK (CONNECTOR)
RESISTOR
SWITCH
SUPERVISORY CONTROL AND DATA ACQUISTION
SCADA TRIP & CLOSE
VOLTAGE (EUROPEAN SYMBOL)
VOLTAGE
VOLTAGE DIVIDER
WIRE NUMBER
TERMINAL BLOCK OR DC BREAKER DISCONNECT DEVICE
TRUCK OPERATED CELL SWITCH (TRUCK POSITION)
TRACTION POWER TRANSFORMER
HV INTERUPTING DEVICE
RECTIFIER DIODE OVERTEMPERATURE, ALARM
RECTIFIER DIODE OVERTEMPERATURE, TRIP
TRANSFORMER WINDING OVERTEMPERATURE, ALARM
TRANSFORMER WINDING OVERTEMPERATURE, TRIP
50/51 PHASE FAULT TIME OVERCURRENT RELAY
50/51 N
WITH INSTANTANEOUS ELEMENT
GROUND FAULT TIME OVERCURRENT RELAY
WITH INSTANTANEOUS ELEMENT
AC CIRCUIT BREAKER
FRAME FAULT RELAY
AC OVERVOLTAGE RELAY
DC FEEDER BREAKER
DC FEEDER DIRECT ACTING TRIP DEVICE76
ANSI DEVICE TABLE
NUMBER
26R2
49T2
EMERGENCY STOP PUSHBUTTON
AC SUPPLY UNDERVOLTAGE
REVERSE CURRENT INSTANTANEOUS RELAY
DC EQUIPMENT DOOR INTERLOCK DEVICE
NEGATIVE SEQUENCE VOLTAGE
RECTIFIER OVERLOAD RELAY
ANNUNCIATOR
51A
49T1
DESCRIPTION
26R1
APS
A
BA
F
H
K
OP
P
PM
J
150R
186H
LINE TEST RECLOSING RELAY
DC LOCKOUT RELAY, HAND RESET
AC LOCKOUT RELAY, HAND RESET
POSITIVE DISCONNECT SWITCH
NEGATIVE DISCONNECT SWITCH
DC FEEDER RATE OF RISE RELAY
89N
86H 89P
TRANSFER TRIP RECEIVE85RX
DIODE FUSE MONITOR ALARM98-1
98-2 DIODE FUSE MONITOR TRIP
EMERGENCY TRIP SWITCHETS
SHORT CIRCUIT DEVICESCD
S03 COMPONENT IDENTIFICATION
R S
U
V
VD
X
TRANSFORMER OIL LEVEL TRIP71Q2
71Q1 TRANSFORMER OIL LEVEL ALARM
63-1 TRANSFORMER SUDDEN PRESSURE ALARM
TRANSFORMER OIL TEMPERATURE ALARM26Q1
TRANSFORMER OIL TEMPERATURE TRIP26Q2
DC FEEDER LOAD MEASURING FOR LINE TEST182
Q
DIAGRAM, DEVICE TABLE
NUMBER
CTR
DPU
F/O
FMR
LAP
MOC
OCS
PLC
SCADA
S-T & C
K03
TOC
WN
TPT
186 DC LOCKOUT RELAY
DC UNDERVOLTAGE127
150 DC INSTANTANEOUS OVERCURRENT RELAY
151 DC LONG TIME OVERCURRENT RELAY
159 DC OVERVOLTAGE RELAY
MAINTENANCE MODE SWITCH43MM
TRANSFER TRIP SWITCH43TT
CONTROL CONTROL / CLOSE
CONTROL CONTROL / TRIP
INTELLIGENT TEMPERATURE MONITORITM
FIRE ALARMFA
UNDERVOLTAGE TRIP DEVICE COIL
UNDERVOLTAGE TRIP DEVICE SOLENOID
63-2 TRANSFORMER SUDDEN PRESSURE TRIP
S-ETS SCADA - EMERGENCY TRIP SHUTDOWN
12.47TRUXILLO60
PIERCE
FRANKLIN80
34.5
34.5
VOLTAGE
YARD
BELLFORT
EL PASEO
BRAYS
WICHITA
TMC40
YD
12.47
12.47
34.5
12.47
12.47
12.47
(kV)
NAME
TABLE 1
No.
UTILITY
85RX85TX
FEEDER 1
(NOTE 2)
FEEDER
FEEDER
FEEDER
TO OCS
DC POSITIVE BUS, 750Vdc, 2000A
176176
172-4172-3
176176
172-2 2000A 172-1
182150R
SA
V
89N64L64G
DC NEGATIVE BUS, 2000A
(NOTE 4)
S-T&C (NOTE 1) 2000A
S-T&C
1200A
27A
SA
150KVA
AC PANEL AP1
SWARTZ
600AF
500AT
TABLE 1 / 208-120
1087KVA
TABLE 1 / 2X587
(NOTE 8)
72-0
K
K
SA
SA
T13
SA
SA
T24
S4S3S2S1
NGD
AUXILIARY POWER
TRANSFORMER
12.47 KV
34.5 KV
INCOMING UTILITY FEEDER, 3PH, 3W
(SEE TABLE 1)
PT 3
51N 50/ A 51A 51
50/
59 47 V27
AC
MFPR
186H 32
64G
64L 33N 33R 4949
R2
T1 T2
33T
R1
-2-15
FA
HVAC
-1
49H
AMB
HVAC
-2
TPT
SIGNALSRECTIFIER
CUBICLE
SIGNALS
NEGATIVE
CUBICLE
SIGNALS
MAIN DC
CUBICLE
SIGNALS
BUILDING
SIGNALS
L/R
186H
IEEE 1653.2
CIRCUIT NO 31
RECTIFIER UNIT
1MW
A V
159150148
VT
NEG.
REF.
TRANSFER TRIP SEND / RECEIVE
TO / FROM ADJACENT TPSS
VT
A
V
NEGATIVE
RETURN
CABLES TO
RUNNING
RAILS OR
IMPENDENCE
BONDS
PROVISION FOR NEGATIVE
DRAINAGE CABLES
DC SWGR
ENCLOSURE
FO
DC
MFPR
SCALE
0-1000V
COMMUNICATIONS
POWER SUPPLY
LOCATED IN SIGNAL &
COM. BUILDING
SUBSTATION
POWER
SUPPLY
STATION CONTROL CABINET PLC
NOTES:
1. KEY INTERLOCK PREVENTS OPENING OF 89N DEVICE UNLESS
MAIN DC BREAKER IS OPEN.
2. PROTECTIVE DEVICES AND INSTRUMENTS FOR FEEDER
BREAKERS ARE IDENTICAL TO FEEDER 1.
3. CURRENT AND POTENTIAL TRANSFORMERS AND UTILITY
METERING PROVIDED BY THE UTILITY.
4. DEVICE 32 FUNCTION IS PART OF DC MFPR
PROGRAM SEQUENCE:
- ENERGIZE AC LOCKOUT ~ 86H
- TRIP & LOCKOUT AC BREAKER
- OPEN MAIN DC BREAKER
5. 186H HAND RESET LOCKOUT RELAY LOCATED IN 72-0 CUBICLE.
6. 86 ENERGIZED FOR:
- REV CURRENT (32)
- DC EQUIPMENT DOOR OPEN (33N, 33R)
- RECTIFIER TRIP FUNCTIONS (26-R2, 98-2)
- XFMR TRIP FUNCTIONS (33T, 49-T2)
- DC LOCKOUT (186H)
7. 186H ENERGIZED FOR:
- ETS & FIRE (5, FA)
- DC EQUIPMENT DOOR OPEN (33N, 33R)
- FRAME FAULT (64L)
- INCOMPLETE SEQUENCE (148)
8. KEY INTERLOCK PREVENTS TO FUSES UNLESS PNL AP1 MAIN
ACCESS BREAKER IS OPEN.
9. 43 L/R LOCATED ON EACH AC AND DC BREAKER CUBICLE.
10. TRANSFORMER OIL HIGH TEMPERATURE (26Q1) AND HIGH
PRESSURE (71Q1) ALARMS ARE FOR YARD TPSS ONLY.
11. NEGATIVE GROUNDING DEVICE IS FOR MAIN LINE TPSS ONLY.
12. 43MM AND 43TT LOCATED ON SCC.
(NOTE 5)
AA V
DC MFPR
VT
S-T&C
TT
MM
49L
AMB
Q1
Q1
(SEE NOTE 10)
(SEE NOTE 11)
NOTE 12
NOTE 12
NOTE 9
Q2
Q2
-1
-2
S-ETS
S-ETS
A1
RELAY
COMP.
CONTROL
POWER
COMPARTMENT
REAR
CABLE
COMP.
LOAD SIDE
TERMINALS
TERMINALS
LINE SIDE
38"
38"
90"
48"
BARRIER
BARRIER
TOP VIEW
FRONT VIEW SIDE VIEW
TB2
TB1
RE
S1 S2
1/4" GLASTIC
FROM TOP
(CABLE ENTRY
CABLE
SUPPORT
CABLE
SUPPORT
SUPPORT
FOR BUS
FROM TOP)
(CABLE ENTRY
CT WIRING
AMMETER VOLTMETER
1.50
0.56 DIA. HOLES (2)
(TWO NEMA
2 HOLE 250MCM LUGS)
LINE/LOAD TERMINAL DETAIL
1/4" GLASTIC
LOAD & LINE
SIDE TERMINALS
SUPPORT FOR BUS
SUPPORT
FOR CT'S
2.5
7.5
20.0
30.0
20.0
7.5
TYPICAL BOLTDOWN
HOLE PROVISION
2.234
.50 DIA.
48"
1.75 .633.125
11 1/8"
13 1/2"
NEW POWER
MONITOR
18'
LV section
HV section
Contactor Pnl
Contactor Pnl
Rectifier
DC BKR
FDR #1
B a tt e ry
Charger
3'-3
" 1'-11
5'
D C
P n l
Grounding
Bar
AC Switchgear
Transformr
Rectifier
4'-6"
Front
3'-2"
BREAKER
REMOVAL
AREA
7' 2'-8
NEW BATTERY
CHARGER
NEW TEMP.
MONITOR
B a tt e ry
D is c o n n e c t
NEW POWER
METER
FRONT VIEW
7'-25 8"
AB
AB
SIEMENS FEEDER BREAKER TP-SHP
1'-115 8"
Y
AV
N5 N6
MFPR
N8N7
Y Y Y N1 N2 N3 N4
186H LOCKOUT
ENGRAVING
REC TEMP ALARM
OPEN / CLOSE
XFMR TEMP ALARM
REC DIODE FAIL
GROUP ALARM
N8
N5
N4
N3
N2
N1
ITEM
N6
N7
VOLTMETER
AMMETER
FEEDER BREAKER
SECTION
FAR #4
DC
BREAKER
FAR #3
DC
BREAKER
FAR #1
DC
BREAKER
FAR #2
DC
BREAKER
RECTIFIER
NEGATIVE
RETURN
SECTION
F2F3F4 F1 F0 R N
ACU1
ACU2
AP1DP1
BC
1" PVC CONDUIT
FOR (1) FIBER
OPTIC CABLE
1" EMT CONDUIT
FOR (1) FIBER
OPTIC CABLE
1" EMT CONDUIT
FOR (1) SHIELDED
COAXIAL CABLE
MAIN
DC BREAKERNON-METALIC
4"X4"WW
4' -3
1" EMT CONDUIT
FOR (1) SHIELDED
COAXIAL CABLE
AP1: 208/120 VAC DISTRIBUTION PANEL
BC: BATTERY CHARGER
F0: MAIN DC BREAKER
ACU1: AIR CONDITIONING UNIT #1
F1: FEEDER BREAKER #1
M: S7-PLC IN F0 CUBICLE
T: RECTIFIER TRANSFORMER
COMM: COMMUNICATIONS BLDG.
ACU2: AIR CONDITIONING UNIT #2
DP1: 125 VDC DISTRIBUTION PANEL
SAP: SCADA AND ANNUNCIATOR PANEL
ETS: EMERGENCY TRIP SWITCH
EL: EMERGENCY LIGHT
FA: FIRE ALARM
H1: AC BREAKER
LEGEND
HVAC
UNIT#1
15-TON
SPARE PARTS
CABINET
DOCUMENT
CABINET
HVAC
UNIT#2
15-TON
AC BREAKER
TEST BOX
AC
PANEL P1
6070 DOOR W/12"
TRANSOM
OCS DISCONNECT SWITCHES
(TYP 2)
DOOR
ACTIVE INACTIVE
FIELD INSTALLED SURGE
ARRESTOR BOXES (TYP 5)
TEMPERATURE
CONTROL
43'-11"
'-6
BU
IL
D
IN
G
BUILDING
MAIN
AC BREAKER
150KVA
AUXILIARY
TRANSFORMER
1,087KVA
RECTIFIER
TRANSFORMER
RT01
H V
LV
CONTROL ACCESS
PANEL
DC
PANEL P2
BATTERY
DISCONNECT
FOLD DOWN
TABLE TOP
BATTERY RACK
W/COMPOSITION
BOARD FOLD DOWN
TABLE
WALL MOUNTED
TELEPHONE
DEVICE
NEW TEMP.
MONITOR
NEW BATTERY
CHARGER
NEW NEGATIVE
GROUNDING
DEVICE (NGD)
NEW TEMP.
MONITOR
NEW DC BREAKER
TEST BOX
REPLACE EXISTING PLC & SCADA
INTERFACE CABINET WITH NEW
STATION CONTROL CABINET (SCC)
EPOXY
17'-11"
36'-0"
FIRE
EXTINGUISHER
(TYP 2)
'-3
6"3" 1'-8"
6" 2'-0"
2'-6"
[25#] EACH
DC
PANEL P2DOCUMENT
CABINET
[200#]
[100#]
SPARE PARTS
CABINET
(FLOOR MOUNTED)
[200#]
3'-7"
6" 1'-5"
6" 1'-9"
BATTERY RACK
WITH COMPOSITION
BOARD FOLD DOWN
TABLE
1' -8
BATTERY
DISC
[47#]
BATTERY
CHARGER
[460#]
1' -9
[1,000#]
3' -0
2"
3' -0
7"
1'-11 5/8" 1'-11 5/8"
[500#]
1'-11 5/8"
FDR #2
DC
BREAKER
15'-5 7/16"
OCS DISCONNECT SWITCHES
(TYP 2)
HVAC
UNIT#1
10-TON
[960#]
[500#]
FDR #3
DC
BREAKER
[500#]
FDR #4
DC
BREAKER
INSULATED
BARRIER
2'-11 7/16"
[500#]
FDR #1
DC
BREAKER
[500#]
MAIN
DC
BREAKER
1'-11 5/8"
[1,500#]
RECTIFIER
NEGATIVE
RETURN
SECTION
[1,000#]
1'-10 9/16"
NO EPOXY
3"
6"
2'-6"
6" 8"
6" 8"
3" 1'-8"
[10#]
WALL MOUNTED
TELEPHONE
AC BREAKER
TEST BOX
[200#] [50#]
AC
PANEL
P1
3" 7'
-1 1"
HVAC
UNIT#2
10-TON
HIGH VOLTAGE
[5,000#]
150KVA
AUXILIARY
TRANSFORMER
WITH FUSE
MAIN
AC BREAKER
[3,400#]
[12,000#]
1,087KVA
RECTIFIER
TRANSFORMER
RT01
LV
H
V
EMERGENCY
PUSH BUTTOMS
(TYP 4)
[960#]
2-30" DOORS
2'-7 11/16"
6"7"
1'-6"
2-3070
DOORS
2" 9'-8"
18'-1"
3' -4
12.5KV DELTA
208Y/120V
LOW VOLTAGE
BREAKER
REMOVAL
AREA
2'-4"
4' -0
BREAKER
REMOVAL
AREA (TYP.)
1'-11 5/8"7"
4' -1
0"
5' -0
6' -4
2'-0"
DOOR
PANIC BUTTON
(TYP 4)
9"
3'-0" 4'-6" 9"
2'-6" 2'-5" 2'-5" 2'-6" 3'-0" 2'-4" 2'-4" 8"
DEVICE
1' -2
1'
-7
1/
2'-0"
TEMPERATURE
CONTROL (TYP 2)
REPLACE EXISTING PLC &
SCADA INTERFACE CABINET
WITH NEW STATION
CONTROL CABINET (SCC)
NEW NEGATIVE
GROUNDING
DEVICE (NGD)
NEW BATTERY
CHARGER
NEW TEMP.
MONITOR
NEW TEMP.
MONITOR
NEW DC BREAKER
TEST BOX
EPOXY
17'-11"
36'-0"
FIRE
EXTINGUISHER
(TYP 2)
'-3
6"3" 1'-8"
6" 2'-0"
2'-6"
[25#] EACH
DC
PANEL P2DOCUMENT
CABINET
[200#]
[100#]
SPARE PARTS
CABINET
(FLOOR MOUNTED)
[200#]
3'-7"
6" 1'-5"
6" 1'-9"
BATTERY RACK
WITH COMPOSITION
BOARD FOLD DOWN
TABLE
1' -8
BATTERY
DISC
[47#]
BATTERY
CHARGER
[460#]
1' -9
[1,000#]
3' -0
2"
3' -0
7"
1'-11 5/8" 1'-11 5/8"
[500#]
1'-11 5/8"
FDR #2
DC
BREAKER
15'-5 7/16"
OCS DISCONNECT SWITCHES
(TYP 2)
HVAC
UNIT#1
10-TON
[960#]
[500#]
FDR #3
DC
BREAKER
[500#]
FDR #4
DC
BREAKER
INSULATED
BARRIER
2'-11 7/16"
[500#]
FDR #1
DC
BREAKER
[500#]
MAIN
DC
BREAKER
1'-11 5/8"
[1,500#]
RECTIFIER
NEGATIVE
RETURN
SECTION
[1,000#]
1'-10 9/16"
NO EPOXY
3"
6"
2'-6"
6" 8"
6" 8"
3" 1'-8"
[10#]
WALL MOUNTED
TELEPHONE
AC BREAKER
TEST BOX
[200#] [50#]
AC
PANEL
P1
3" 7'
-1 1"
HVAC
UNIT#2
10-TON
HIGH VOLTAGE
[5,000#]
150KVA
AUXILIARY
TRANSFORMER
WITH FUSE
MAIN
AC BREAKER
[3,400#]
EMERGENCY
PUSH BUTTOMS
(TYP 4)
[960#]
2'-7 11/16"
6"7"
1'-6"
2-3070
DOORS
2" 9'-8"
18'-1"
3' -4
12.5KV DELTA
208Y/120V
LOW VOLTAGE
2'-4"
4' -0
BREAKER
REMOVAL
AREA (TYP.)
1'-11 5/8"7"
4' -1
0"
6' -4
2'-0"
DOOR
PANIC BUTTON
(TYP 4)
9"
3'-0" 4'-6" 9"
3'-0" 2'-4" 2'-4" 8"
NEW BATTERY
CHARGER
NEW TEMP.
MONITOR
EXISTING CABLES IN
CONDUITS FROM
OUTDOOR RECTIFIER
TRANSFORMER
BREAKER
REMOVAL
AREA
TEMPERATURE
CONTROL (TYP 2)
REPLACE EXISTING PLC &
SCADA INTERFACE CABINET
WITH NEW STATION
CONTROL CABINET (SCC)
55'-4"
2'-8"
18'-0"
14'-8"
55'-4"
2'-0"
'-0
'-8
8"
2"
M.
O.
3'- 4"
3'- 4" 2'-
8" 4'-
0" M.
O.
25'-2"
4'- 0"
M.
O.
2'- 8"
5'-8"
22'-0"
5'- 4"
7'-8"
M.O.
18'-8"
7'-4"10'-8"1'-4"8'-0" M.O.
6'-10"
8"
6'-10"
9'-4" 1'-4" 4'-4"8" 1'-4" M.O. M.O.
3'-2" 1'-4"
3'-2" M.O.
3'-2"
M.O. M.O.
1'-4"
'-8
BATTERY
CHARGER
DC
PANEL P2
BATTERY
DISCONNECT
AC
PANEL
P1
MAIN
DC
BREAKER
RECTIFIER
NEG.RET.
SECTION
LO
W
V O
LT
AG
E
RECTIFIER
TRANSFORMER
RT01
[14,500#]H
IG
H
V O
LT
AG
E
[5 ,0
LO
W
V O
LT
AG
E
8Y /1
V
AU
XI
LI
AR
Y
PO
W
ER
TR
AN
SF
O
R M
ER
H
IG
H V
O
LT
AG
E
.5
KV
D
EL
TA
RECTIFIER
AC BREAKER
12.5KV
INCOMING 12.5 KV
AUXILIARY
TRANSFORMER FUSES
EPB
BATTERY RACK
EPB
GB
GB
SURGE
ARRESTOR
NEG.
RETURN
NEW BATTERY CHARGER
NEW NEGATIVE
GROUNDING
DEVICE (NGD)
NEW TEMP.
MONITOR
NEW TEMP.
MONITOR
2'-2"
5'- 8" H
VA
C
NEW DC
BREAKER
TEST BOX
REPLACE EXISTING PLC & SCADA
INTERFACE CABINET WITH NEW
STATION CONTROL CABINET (SCC)
EXISTING
PANEL AND
TELEPHONE
SYSTEM
NEW EPOXY FLOORING
LOW VOLTAGE
2'-9"
(NO EPOXY)
43'-11"
10'-8"
5' -0
'-6
FIRE
EXTINGUISHER
(TYP 2)
'-6
PANIC BUTTON
(TYP 4)
H
VA
C U
N
IT
BATTERY RACK
WITH COMPOSITION
BOARD FOLD DOWN
TABLE
3'-11"
WALL MOUNTED
TELEPHONE
3"
1'-1 1/2"
4"
1'-4 1/2"
3"1'-0"
[2,90#]
BATTERY
CHARGER
BATTERY
DISCONNECT
DC
PANEL P2
1'-8" 3"
[100#] [25# EACH][50#]
[460#]
6" 6"
7"
3"
2'-6"
[10#]
AC
PANEL
P1
1'-8"
[200#]
3' -0
3'
-0
2"
[1,800#]
HVAC
UNIT#1
15-TON
TYP.(2)
2'-7 11/16"
[500#]
15'-5 7/16"
FDR #1
DC
BREAKER
OCS DISCONNECT SWITCHES
(TYP 2)
[500#]
FDR #4
DC
BREAKER
[500#]
FDR #2
DC
BREAKER
[500#]
FDR #3
DC
BREAKER
LO
W
V O
LT
AG
E
(EPOXY)
[1000#] [500#]
MAIN
DC
BREAKER [1,500#]
RECTIFIER
1'-11 5/8"1'-11 5/8"
1'-11 5/8"
2'-11 7/16"
1'-11 5/8"
INCOMING 34.5 KV
AUXILIARY
TRANSFORMER FUSES
AUXILIARY POWER
TRANSFORMER
208Y/120V
[5,000#]
34.5KV
HIGH VOLTAGE
[12,080#]
3"
H
IG
H V
O
LT
AG
E
6' -0
RECTIFIER
TRANSFORMER
RT01
[14,500#]
RECTIFIER
AC BREAKER
34.5KV
[1,200#]
DOCUMENT
CABINETSPARE PARTS
CABINET
AC BREAKER
TEST BOX
[50#]
2'-8"2'-8" 2'-9"
3"
2'-0"
1"
2'-0"
11"
1'-8"
4'-0" 4'-0"
3' -4
AREA
REMOVAL
BREAKER
6' -0
2'-6"
1'-3"
BREAKER
REMOVAL
AREA (TYP.)
1'-11 5/8"
1'-5 9/16"
NEGATIVE
RETURN
SECTION
4"
INSULATED
BARRIER
DOOR
1'-1" 4'-6"
'-1
0"
2-3070
DOORS
5' -0
2'-6"
[1,800#]
HVAC
UNIT#1
15-TON
TYP.(2)
7' -1
0"
1'-5"4'-0" 4'-0"
15'-9"
1' -2
1' -7
1/
1'-11 5/8"
DEVICE
NEW TEMP.
MONITOR
NEW BATTERY
CHARGER
NEW NEGATIVE
GROUNDING
DEVICE (NGD)
NEW TEMP.
MONITOR
REPLACE EXISTING PLC
& SCADA INTERFACE
CABINET WITH NEW
STATION CONTROL
CABINET (SCC)
1'-115 8" 1'-115
8" 1'-115 8" 1'-115
8"
15'-513 16"
15'-5 7 16"
2'-71 2"2'-11 7
16"1'-115 8"
SIEMENSFEEDER BREAKER #4 SIEMENS SIEMENS SIEMENS SIEMENS SIEMENS
MFPR
AV
G R
N11
N2N1
B
N6 N7
MFPRMFPR MFPR MFPR
Y W
RECTIFIERFEEDER 4 FEEDER 3 FEEDER F2 FEEDER F1 MAIN BREAKER NEGATIVE RETURN
SECTION
(WITH SIDE PANELS)
(FRAMES)
N1 G
N2 R
31'-615 32"
BY W
N1 G
N2
RBY W
N1 G
N2
RBY W
N1 G
N2
RBY W
N1 G
N2 R
64G
N3 N4 N5 N3 N4 N5 N3 N4 N5 N3 N4 N5 N3 N4 N5
N10
186H LOCKOUT
REMOTE
LOCAL
ENGRAVING
GROUP ALARM
OPEN / CLOSE
LOCAL / REMOTE
64G/64L - FRAME FAULT
CLOSED
OPEN
N11
N10
N9
N8
N5
N4
N3
N2
N1
ITEM
FRONT VIEW
N6
N7
VOLTMETER
AMMETER
N9N8 N9N8 N9N8 N9N8N9N8
FEEDER BREAKER #3 FEEDER BREAKER #2 FEEDER BREAKER #1 MAIN BREAKER RECTIFIER NEGATIVE SWITCH
HMI SCREEN
FURNISH AND INSTALL ADDITIONAL HMI
SCREEN ON NEGATIVE RETURN CUBICLE
AT TEXAS MEDICAL CENTER
SUBSTATION ONLY
| 1: |
| Market Interest -Y: Off |
| Market Interest -N: Off |
| Market Interest: |
| 2: |
| Standard Structure A: |
| Standard Structure B: |
| 1 Outage A: Off |
| 1 Outage B: Off |
| 1 Outage C: |
| 2 Comissioning: |
| 3: |
| PDB Support -Y: Off |
| PDB Support -N: Off |
| GMP at 90% -Y: Off |
| GMP at 90% -N: Off |
| LOD: |
| 1 Equipment A: |
| 1 Equipment B: |
| 2 Constructability: |
| 3 Schedule: |
| 4 Resources: |
| 4: |
| Offramp A: |
| Offramp B: |
| Offramp C: |
| 5: |
| Risk A: |
| Risk B: |
| Risk C: |
| 6: |
| Systems A: |
| Systems B: |
File details come from the government source that posted it. Updated .