This is a Project Manual and bidding document for the Twin County Joint Municipal Authority (TCJMA) Wastewater Treatment Plant PLC and HMI Upgrade project located at 309 Mahanoy Street in Nuremberg, Schuylkill County, Pennsylvania. The project involves migrating legacy programmable logic controller (PLC) and human-machine interface (HMI) systems to modern hardware and software platforms, specifically replacing the existing SLC PLC with a programmable automation controller and recreating the existing PanelView HMI application. Sealed bids will be received online via the PennBid Program until Wednesday, September 2, 2026, at 2:00 P.M., with bid results published online at http://PennBid.bonfirehub.com following the bid opening. The entire project will be awarded to a single contractor. Work must be substantially completed within 180 days after the contract commencement date and fully completed and ready for final payment within 210 days. Liquidated damages are assessed at $500 per day after the substantial completion deadline and $250 per day following substantial completion until final completion.
Bidders must submit a certified check, bank draft, or satisfactory bid bond in the amount of 10 percent of the total bid with their proposals. The successful bidder will be required to furnish performance and payment bonds, each in the amount of 100 percent of the contract price with an approved corporate surety. The project is financed in part by a grant from the Commonwealth of Pennsylvania, Commonwealth Financing Authority. All bidding documents are available at no cost via the PennBid Program. Bidders must comply with prevailing wage requirements, Pennsylvania Human Relations Act provisions, and the Public Works Employment Verification Act. The contract award will be made to the lowest responsive and responsible bidder within 60 days of bid opening, or within 120 days if delayed by required approval from another government agency, bond sales closure, or grant awards. Progress payments will be made at 95 percent of completed work with 5 percent retainage, reducing to no additional retainage once work reaches 50 percent completion with satisfactory progress. Final payment will include six percent annual interest on amounts due after substantial completion, unless project bonds carry a lower interest rate.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 2-Documents to submit with bid.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PROJECT MANUAL
Wastewater Treatment Plant PLC and HMI Upgrade Twin County Joint Municipal Authority Schuylkill County, Pennsylvania
Prepared for
PO Box 636 Nuremberg, PA 18241
July 2026 Project No. 0326-609053.00
Copyright 2026, of Benesch. All rights reserved. This plan and design content is the property of Benesch. Use, reuse, reproduction or modification of this plan or design information, or any part thereof, is strictly prohibited, except by written permission of this firm.
TCJMA – WWTP – PLC and HMI Upgrades – Project No. 0326-609053.00
TABLE OF CONTENTS
TABLE OF CONTENTS Page 1
Division .......Section Title ............................................................................................. ................................................. Pages
SERIES 00 – BIDDING REQUIREMENTS AND CONTRACT FORMS
001000 .........ADVERTISEMENT FOR BIDS
002000 .........INSTRUCTIONS TO BIDDERS
004100 .........BID FORM
004100 .........BID FORM – EXHIBIT A
005200 .........FORM OF AGREEMENT BETWEEN OWNER AND CONTRACTOR
007000 .........GENERAL CONDITIONS
008000 .........SUPPLEMENTARY CONDITIONS
008300 .........WAGE DETERMINATION SCHEDULE
DIVISION 01 – GENERAL REQUIREMENTS
010600 .........MOBILIZATION/DEMOBILIZATION
011000 .........SUMMARY
012200 .........UNIT PRICES
012500 .........SUBSTITUTION PROCEDURES
012600 .........CONTRACT MODIFICATION PROCEDURES
012900 .........PAYMENT PROCEDURES
013100 .........PROJECT MANAGEMENT AND COORDINATION
013200 .........CONSTRUCTION PROGRESS DOCUMENTATION
013233 .........PHOTOGRAPHIC DOCUMENTATION
013300 .........SUBMITTAL PROCEDURES
014000 .........QUALITY REQUIREMENTS
014200 .........REFERENCES
015730 .........TEMPORARY BYPASS PUMPING
016000 .........PRODUCT REQUIREMENTS
017300 .........EXECUTION
017419 .........CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL
017700 .........CLOSEOUT PROCEDURES
017823 .........OPERATION AND MAINTENANCE DATA
017833 .........WARRANTIES AND BONDS
017839 .........PROJECT RECORD DOCUMENTS
017900 .........DEMONSTRATION AND TRAINING
DIVISION 13 – SPECIAL CONSTRUCTION
130010 .........SPECIAL CONSTRUCTION
TABLE OF CONTENTS Page 2
APPENDICES
BID/CONSTRUCTION/BONDING REQUIREMENTS
BID BOND
PERFORMANCE BOND
PAYMENT BOND
STATEMENT OF BIDDER’S QUALIFICATIONS FORM
AGREEMENT OF SURETY FORM
PSATS CDL PROGRAM CONTRACTOR’S STATEMENT OF COMPLIANCE FORM
NON-COLLUSION AFFIDAVIT FORM
NONDISCRIMINATION/SEXUAL HARASSMENT CLAUSE
STATE REQUIREMENTS
BIDDER CERTIFICATION OF PREQUALIFICATION CLASSIFICATION AND WORK
CAPACITY FORM
CERTIFICATION OF NON-SEGREGATED FACILITIES
COMPLIANCE ILLEGAL ALIEN LABOR ACT
COMPLIANCE WITH THE STATE CONTRACTOR RESPONSIBILITY PROGRAM
CONTRACT PROVISION RIGHT TO KNOW LAW
CONTRACTOR INTEGRITY PROVISION
PROVISIONS CONCERNING THE AMERICANS WITH DISABILITIES ACT
PUBLIC WORKS EMPLOYMENT VERIFICATION FORM
STOP-CALL BEFORE YOU DIG
TCJMA| WWTP-PLC and HMI Upgrades | Project Manual
SERIES 0 – BIDDING REQUIREMENTS AND
CONTRACT FORMS
ADVERTISEMENT FOR BIDS Section 001000
ADVERTISEMENT FOR BIDS Section 001000 – Page 1
ADVERTISEMENT FOR BIDS
Sealed Bids for the Twin County Joint Municipal Authority (TCJMA – Wastewater Treatment Plant PLC and HMI Upgrades Project will be received online via the PennBid Program by TCJMA until Wednesday, September 2, 2026, at 2:00 P.M. (prevailing time). Bid results will be available online at http://PennBid.bonfirehub.com following the bid opening.
The project involves the migration of legacy programmable logic controller (PLC) and human-machine interface (HMI) systems at the Nuremberg WWTP to modern hardware and software platforms. The upgrade will replace the existing SLC PLC with a programmable automation controller and recreate the existing PanelView HMI application. The particular items of work for the contract are identified more specifically in the Bid Format, Contract Specifications and Contract Documents. The entire project will be awarded to one (1) Contractor. This Project is financed in part by a grant from the Commonwealth of Pennsylvania, Commonwealth Financing Authority.
All Bidding Documents are available at no cost at http://PennBid.bonfirehub.com
A certified check or bank draft, payable to the order of the Twin County Joint Municipal Authority or a satisfactory Bid Bond executed by the Bidder and acceptable surety in the amount of 10% of the Total Bid shall be submitted with each bid.
THE SUCCESSFUL BIDDER will be required to furnish and pay for satisfactory Performance and Payment Bonds, each in the amount of one hundred percent (100%) of the Contract Price with a corporate surety approved by the Owner.
Attention is called to the fact that no less than the minimum salaries and wages as set forth in the Contract Documents must be paid on this project and that the Contractor must ensure that employees and applicants for employment are not discriminated against because of their race, age, color, religion, sex, ancestry, national origin, or handicap.
The Contractor will be required to comply with the Provisions of the Pennsylvania Human Relations Act in providing equal employment opportunities in connection with all work.
This bid is for a public works contract and bidder is therefore subject to the provisions, duties, obligations, and penalties of the Public Works Employment Verification Act, 43 P.S. 167.1-167.11. All submitted bids shall be accompanied with the Public Works Employment Verification Form.
The Owner reserves the right to waive any informality or to reject any or all items or portions thereof or to waive any technicalities and informalities in the bid for the best interest of the Owner.
Bids may be held by the Owner for a period not to exceed 60 days from the date of opening bids for the purpose of reviewing the bids and investigating the qualifications of bidders, prior to awarding the contract.
However, the award of the contracts may be delayed by required approval of another government agency or closing on the project funding loans. Owner shall reject all bids or award to the lowest responsive and responsible bidder within 120 days of the bid opening.
TWIN COUNTY JOINT MUNICIPAL AUTHORITY
http://pennbid.bonfirehub.com/
ADVERTISEMENT FOR BIDS Section 001000
ADVERTISEMENT FOR BIDS Section 001000 – Page 2
TO: STANDARD SPEAKER
HAZLETON, PA
legals@scrantontimes.com
PLEASE PUBLISH ON:
1. Thursday, July 30, 2026
PLEASE SEND INVOICE AND PROOF OF PUBLICATION TO:
Twin County Joint Municipal Authority (TCJMA) PO Box 636 Nuremburg, PA 18241 tamiabindas@gmail.com
PLEASE SEND PROOF OF PUBLICATION TO:
Cheryl Bolich Benesch cbolich@benesch.com mailto:legals@scrantontimes.com mailto:tamiabindas@gmail.com mailto:cbolich@benesch.com
MABR – WWTP - UV Disinfection Installation Project – Project No. 32082.20 INSTRUCTIONS TO BIDDERS Section 002000
INSTRUCTION TO BIDDERS Section 002000 – Page 1
INSTRUCTIONS TO BIDDERS
TABLE OF CONTENTS
Page
ARTICLE 1 – DEFINED TERMS
ARTICLE 2 – COPIES OF BIDDING DOCUMENTS
ARTICLE 3 – QUALIFICATIONS OF BIDDERS
ARTICLE 4 – EXAMINATION OF BIDDING DOCUMENTS, OTHER RELATED DATA,
AND SITE
ARTICLE 5 – PRE-BID CONFERENCE
ARTICLE 6 – SITE AND OTHER AREAS
ARTICLE 7 – INTERPRETATIONS AND ADDENDA
ARTICLE 8 – BID SECURITY
ARTICLE 9 – CONTRACT TIMES
ARTICLE 10 – LIQUIDATED DAMAGES
ARTICLE 11 – SUBSTITUTE AND “OR-EQUAL” ITEMS
ARTICLE 12 – SUBCONTRACTORS, SUPPLIERS AND OTHERS
ARTICLE 13 – PREPARATION OF BID
ARTICLE 14 – SUBMITTAL OF BID
ARTICLE 15 – MODIFICATION AND WITHDRAWAL OF BID
ARTICLE 16 – OPENING OF BIDS
ARTICLE 17 – BIDS TO REMAIN SUBJECT TO ACCEPTANCE
ARTICLE 18 – EVALUATION OF BIDS AND AWARD OF CONTRACT
ARTICLE 19 – CONTRACT SECURITY AND INSURANCE
ARTICLE 20 – SIGNING OF AGREEMENT
ARTICLE 21 – RETAINAGE
ARTICLE 22 – NON-COLLUSION AFFIDAVIT
ARTICLE 23 – PENNBID
Section 002000 – Page 2 INSTRUCTION TO BIDDERS
ARTICLE 1 – DEFINED TERMS
1.01 Terms used in these Instructions to
Bidders have the meanings indicated in the General Conditions and Supplementary Conditions. Additional terms used in these Instructions to Bidders have the meanings indicated below:
A. Issuing Office – The office from which the Bidding Documents are to be issued and where the bidding procedures are to be administered.
B. Bidder - one who submits a Bid directly to the Owner as distinct from a sub-bidder, who submits a bid to a Bidder.
C. Successful Bidder - the lowest, responsible and responsive Bidder to whom Owner (on the basis of Owner's evaluation as hereinafter provided) makes an award.
D. PennBid Program – Online document and sealed bid management system available at http://PennBid.bonfirehub.com
ARTICLE 2 – COPIES OF BIDDING
DOCUMENTS
2.01 Complete set of Bidding Documents
may be obtained online at no cost via the PennBid Program (http://PennBid.bonfirehub.com)
2.02 Complete sets of Bidding Documents
shall be used in preparing Bids; neither Owner nor Engineer assumes any responsibility for errors or misinterpretations resulting from the use of incomplete sets of Bidding Documents.
2.03 Owner and Engineer, in making copies of
Bidding Documents available on the above terms, do so only for the purpose of obtaining Bids for the Work and do not authorize or confer a license for any other use.
ARTICLE 3 – QUALIFICATIONS OF
BIDDERS
3.01 To demonstrate Bidder’s qualifications
to perform the Work, within 14 days of Owner’s request, Bidder shall submit written evidence such as financial data, previous experience, present commitments, and such other data as may be called for below.
A. Evidence of Bidder’s authority to do business in the state where the Project is located.
3.02 Bidder is advised to carefully review
those portions of the Bid Form requiring Bidder’s representations and certifications.
3.03 Firms debarred from work in the
Commonwealth of Pennsylvania and/or the Federal Government are not eligible to bid.
ARTICLE 4 – EXAMINATION OF
BIDDING DOCUMENTS, OTHER
RELATED DATA, AND SITE
4.01 Subsurface and Physical Conditions
A. The Supplementary Conditions identify:
1. Those reports known to Owner of explorations and tests of subsurface conditions at or contiguous to the Site.
2. Those drawings known to Owner of physical conditions relating to existing surface or subsurface structures at the Site (except Underground Facilities).
B. Copies of reports and drawings referenced in Paragraph 4.01.A will be made available by Owner to any Bidder on request. Those reports and drawings are not part of the Contract Documents, but the “technical data” contained therein upon which Bidder is entitled to rely as provided in
INSTRUCTION TO BIDDERS Section 002000
INSTRUCTIONS TO BIDDERS Section 002000 – Page 3
Paragraph 4.02 of the General Conditions has been identified and established in Paragraph 4.02 of the Supplementary Conditions. Bidder is responsible for any interpretation or conclusion Bidder draws from any “technical data” or any other data, interpretations, opinions, or information contained in such reports or shown or indicated in such drawings.
4.02 Underground Facilities
A. Information and data shown or indicated in the Bidding Documents with respect to existing Underground Facilities at or contiguous to the Site is based upon information and data furnished to Owner and Engineer by owners of such Underground Facilities, including Owner, or others.
4.03 Hazardous Environmental Condition
A. The Supplementary Conditions identify any reports and drawings known to Owner relating to a Hazardous Environmental Condition identified at the Site.
B. Copies of reports and drawings referenced in Paragraph 4.03.A will be made available by Owner to any Bidder on request. Those reports and drawings are not part of the Contract Documents, but the “technical data” contained therein upon which Bidder is entitled to rely as provided in Paragraph 4.06 of the General Conditions has been identified and established in Paragraph 4.06 of the Supplementary Conditions. Bidder is responsible for any interpretation or conclusion Bidder draws from any “technical data” or any other data, interpretations, opinions, or information contained in such reports or shown or indicated in such drawings.
4.04 Provisions concerning responsibilities
for the adequacy of data furnished to prospective Bidders with respect to subsurface conditions, other physical conditions, and Underground Facilities, and possible changes in the Bidding Documents due to differing or unanticipated subsurface or physical conditions appear in Paragraphs 4.02, 4.03, and 4.04 of the General Conditions.
Provisions concerning responsibilities for the adequacy of data furnished to prospective Bidders with respect to a Hazardous Environmental Condition at the Site, if any, and possible changes in the Contract Documents due to any Hazardous Environmental Condition uncovered or revealed at the Site which was not shown or indicated in the Drawings or Specifications or identified in the Contract Documents to be within the scope of the Work, appear in Paragraph 4.06 of the General Conditions.
4.05 On request, Owner will provide Bidder
access to the Site to conduct such examinations, investigations, explorations, tests, and studies as Bidder deems necessary for submission of a Bid.
Bidder shall fill all holes and clean up and restore the Site to its former condition upon completion of such explorations, investigations, tests, and studies. Bidder shall comply with all applicable Laws and Regulations relative to excavation and utility locates.
4.06 A. Reference is made to Article 7 of the
Supplementary Conditions for the identification of the general nature of other work that is to be performed at the Site by Owner or others (such as utilities and other prime contractors) that relates to the Work contemplated by these Bidding Documents. On request, Owner will provide to each Bidder for examination access to or copies of contract documents (other than portions thereof related to price) for such other work.
B. Paragraph 6.13.C of the General Conditions indicates that if an Owner safety program exists, it will be noted in the Supplementary Conditions.
Section 002000 – Page 4 INSTRUCTION TO BIDDERS
4.07 It is the responsibility of each Bidder
before submitting a Bid to:
A. examine and carefully study the Bidding Documents, and the other related data identified in the Bidding Documents;
B. visit the Site and become familiar with and satisfy Bidder as to the general, local, and Site conditions that may affect cost, progress, and performance of the Work;
C. become familiar with and satisfy Bidder as to all federal, state, and local Laws and Regulations that may affect cost, progress, and performance of the Work;
D. carefully study all: (1) reports of explorations and tests of subsurface conditions at or contiguous to the Site and all drawings of physical conditions relating to existing surface or subsurface structures at the Site (except Underground Facilities) that have been identified in Paragraph
4.02 of the Supplementary Conditions as containing reliable "technical data," and (2) reports and drawings of Hazardous Environmental Conditions, if any, at the Site that have been identified in the Paragraph
4.06 of the Supplementary Conditions as containing reliable "technical data";
E. consider the information known to Bidder; information commonly known to contractors doing business in the locality of the Site; information and observations obtained from visits to the Site; the Bidding Documents;
and the Site-related reports and drawings identified in the Bidding Documents, with respect to the effect of such information, observations, and documents on (1) the cost, progress, and performance of the Work; (2) the means, methods, techniques, sequences, and procedures of construction to be employed by Bidder, including applying any specific means, methods, techniques, sequences, and procedures of construction expressly required by the Bidding Documents;
and (3) Bidder’s safety precautions and programs;
F. agree at the time of submitting its Bid that no further examinations, investigations, explorations, tests, studies, or data are necessary for the determination of its Bid for performance of the Work at the price(s) bid and within the times required, and in accordance with the other terms and conditions of the Bidding Documents;
G. become aware of the general nature of the work to be performed by Owner and others at the Site that relates to the Work as indicated in the Bidding Documents;
H. promptly give Engineer written notice of all conflicts, errors, ambiguities, or discrepancies that Bidder discovers in the Bidding Documents and confirm that the written resolution thereof by Engineer is acceptable to Bidder; and
I. determine that the Bidding Documents are generally sufficient to indicate and convey understanding of all terms and conditions for the performance of the Work.
4.08 The submission of a Bid will constitute
an incontrovertible representation by Bidder that Bidder has complied with every requirement of this Article 4, that without exception the Bid is premised upon performing and furnishing the Work required by the Bidding Documents and applying any specific means, methods, techniques, sequences, and procedures of construction that may be shown or indicated or expressly required by the Bidding Documents, that Bidder has given Engineer written notice of all conflicts, errors, ambiguities, and discrepancies that Bidder has discovered
INSTRUCTIONS TO BIDDERS Section 002000 – Page 5 in the Bidding Documents and the written resolutions thereof by Engineer are acceptable to Bidder, and that the Bidding Documents are generally sufficient to indicate and convey understanding of all terms and conditions for performing and furnishing the Work.
ARTICLE 5 – PRE-BID CONFERENCE
5.01 A pre-Bid conference (if required) will
be outlined in Section 001000, Advertisement For Bids.
ARTICLE 6 – SITE AND OTHER AREAS
6.01 The Site is identified in the Bidding
Documents. Easements for permanent structures or permanent changes in existing facilities are to be obtained and paid for by Owner unless otherwise provided in the Bidding Documents. All additional lands and access thereto required for temporary construction facilities, construction equipment, or storage of materials and equipment to be incorporated in the Work are to be obtained and paid for by Contractor.
ARTICLE 7 – INTERPRETATIONS AND
ADDENDA
7.01 Bidder shall submit all questions about
the meaning or intent of the Bidding Documents via the “Messages/Vendor Discussions” feature in PennBid.
Interpretations or clarifications considered necessary by Engineer in response to such questions will be issued by Addenda posted to PennBid to all parties recorded by Engineer as having received the Bidding Documents.
Questions received less than ten days prior to the date for opening of Bids may not be answered. Only questions answered by Addenda will be binding.
Oral and other interpretations or clarifications will be without legal effect.
7.02 Addenda may be issued to clarify, correct, or change the Bidding
Documents as deemed advisable by Owner or Engineer.
ARTICLE 8 – BID SECURITY
8.01 A Bid must be accompanied by Bid
security made payable to Owner in an amount of 10 percent of Bidder’s maximum Bid price and in the form of a certified check, bank money order, or a Bid bond (on the form attached) issued by a surety meeting the requirements of Paragraphs 5.01 and 5.02 of the General Conditions.
8.02 If a surety Bid Bond is utilized, it shall be
mandatory that the Bid Bond specifically identify the Bid, and the date of the Bid which it accompanies; additionally, it shall be mandatory that the power of attorney accompanying a Bid Bond evidencing the authority of the person signing on behalf of the surety company to sign the Bid Bond shall be dated the same date as the Bid Bond; further, it shall be mandatory that the Bid Bond itself be dated the same date as the Bid, as well as signed by the principal bidder and the surety company through its authorized representatives. Failure to comply with any of the aforesaid positions shall result in the disqualification of the Bid, which Bid shall not thereafter be considered.
8.03 As soon as each of the Bids received has
been reviewed and the Bids have been compared, Owner will return the Bid security of all Bidders except the three apparent lowest responsive and responsible Bidders. Bid security provided by Bidders who are not among the apparent three lowest responsive and responsible Bidders will be returned within ten (10) calendar days following the date of Bid opening. When the Agreement has been executed by the successful Bidder, the Bid security of the other Bidders will also be returned. The Bidder to whom the Notice of Award is given will be required to submit to Owner the required Bonds within ten
(10) calendar days from the date of
Section 002000 – Page 6 INSTRUCTION TO BIDDERS receipt of the Notice of Award. In case of a failure of Bidder to whom a Notice of Award has been given to execute and deliver in a timely manner the required Bonds, Owner may at its option consider such Bidder in default, in which case the Bid security accompanying the proposal shall become the property of Owner. The successful Bidder to whom a Notice of Award is given will be required to execute the Agreement and deliver it, together with the required evidence of insurance coverages, to the Owner within ten (10) calendar days from the date when the Notice of Award is delivered to the successful Bidder. In case of failure of the successful Bidder to execute the Agreement, or to submit the required evidence of insurance coverages in accordance with the Contract Documents, Owner may consider the successful Bidder in default, in which case the Bid security accompanying the Bid shall become the property of Owner.
ARTICLE 9 – CONTRACT TIMES
9.01 The number of days within which, or the
dates by which, Milestones are to be achieved and the Work is to be substantially completed and ready for final payment are set forth in the Agreement.
ARTICLE 10 – LIQUIDATED DAMAGES
10.01 Provisions for liquidated damages, if
any, are set forth in the Agreement.
ARTICLE 11 – SUBSTITUTE AND “OR-
EQUAL” ITEMS
11.01 The Contract, if awarded, will be on the
basis of materials and equipment specified or described in the Bidding Documents without consideration of possible substitute or “or-equal” items.
Whenever it is specified or described in the Bidding Documents that a substitute or “or-equal” item of material or equipment may be furnished or used by Contractor if acceptable to Engineer, application for such acceptance will not be considered by Engineer until after the Effective Date of the Agreement. The procedure for submission of any such application by Contractor and consideration by Engineer is set forth in Paragraph 6.05 of the General Conditions and may be supplemented in the Supplemental Conditions.
ARTICLE 12 – SUBCONTRACTORS,
SUPPLIERS AND OTHERS
12.01 If the Supplementary Conditions require
the identity of certain Subcontractors, Suppliers, individuals, or entities to be submitted to Owner in advance of a specified date prior to the Effective Date of the Agreement, the apparent Successful Bidder, and any other Bidder so requested, shall within five days after Bid opening, submit to Owner a list of all such Subcontractors, Suppliers, individuals, or entities proposed for those portions of the Work for which such identification is required. Such list shall be accompanied by an experience statement with pertinent information regarding similar projects and other evidence of qualification for each such Subcontractor, Supplier, individual, or entity if requested by Owner. If Owner or Engineer, after due investigation, has reasonable objection to any proposed Subcontractor, Supplier, individual, or entity, Owner may, before the Notice of Award is given, request apparent Successful Bidder to submit a substitute, without an increase in the Bid.
12.02 If apparent Successful Bidder declines to
make any such substitution, Owner may award the Contract to the next lowest Bidder that proposes to use acceptable Subcontractors, Suppliers, individuals, or entities. Declining to make requested substitutions will not constitute grounds for forfeiture of the Bid security of any Bidder. Any Subcontractor, Supplier, individual, or entity so listed and against which Owner or Engineer makes no written objection prior to the giving of the Notice of Award will be deemed acceptable to Owner and Engineer
INSTRUCTIONS TO BIDDERS Section 002000 – Page 7 subject to revocation of such acceptance after the Effective Date of the Agreement as provided in Paragraph 6.06 of the General Conditions.
ARTICLE 13 – PREPARATION OF BID
13.01 The Bid Form (Exhibit A) is included
with the Bidding Documents for Reference. Bidders shall complete the electronic bid form within PennBid (“Requested Information” tab).
13.02 All blanks on the PennBid Bid Table
shall be completed. A Bid price shall be indicated for each section, Bid item, alternative, adjustment unit price item, and unit price item] listed therein. In the case of optional alternatives the words “No Bid,” “No Change,” or “Not Applicable” may be entered.
13.03 A Bid by a corporation shall be executed
in the corporate name by the president or a vice-president or other corporate officer accompanied by evidence of authority to sign. The corporate seal shall be affixed and attested by the secretary or an assistant secretary. The corporate address and state of incorporation shall be shown.
13.04 A Bid by a partnership shall be executed
in the partnership name and signed by a partner (whose title must appear under the signature), accompanied by evidence of authority to sign. The official address of the partnership shall be shown.
13.05 A Bid by a limited liability company
shall be executed in the name of the firm by a member and accompanied by evidence of authority to sign. The state of formation of the firm and the official address of the firm shall be shown.
13.06 A Bid by an individual shall show the
Bidder’s name and official address.
13.07 A Bid by a joint venture shall be executed
by each joint venturer in the manner indicated on the Bid Form. The official address of the joint venture shall be shown.
13.08 All names shall be printed in ink below
the signatures.
13.09 The Bid shall contain an
acknowledgment of receipt of all Addenda, the numbers of which shall be filled in on the Bid Form.
13.10 Postal and e-mail addresses and
telephone number for communications regarding the Bid shall be shown.
13.11 The Bid shall contain evidence of
Bidder’s authority and qualification to do business in the state where the Project is located, or Bidder shall covenant in writing to obtain such authority and qualification prior to award of the Contract and attach such covenant to the Bid. Bidder’s state contractor license number, if any, shall also be shown on the Bid Form.
ARTICLE 14 – SUBMITTAL OF BID
14.01 Sealed Bids shall be submitted online
via the PennBid Program (http://PennBid.bonfirehub.com) by the date and time indicated in the Advertisement for Bids. Sealed bid should be accompanied by the Bid security, Non-Collusion Affidavit, Certification of Bidder Regarding Equal Employment Opportunity and other required documents.
ARTICLE 15 – MODIFICATION AND
WITHDRAWAL OF BID
15.01 A Bid may be withdrawn or modified at
any time within PennBid prior to the due date and time identified in the Invitation for Bids.
15.02 If within 2 days after Bids are opened any
Bidder files a duly signed written notice with Owner and promptly thereafter demonstrates to the reasonable satisfaction of Owner that there was a material and substantial mistake in the preparation of its Bid, that Bidder may withdraw its Bid, and the Bid security will be returned. Thereafter, if the Work
Section 002000 – Page 8 INSTRUCTION TO BIDDERS is rebid, that Bidder will be disqualified from further bidding on the Work.
15.03 After the commencement of opening of
Bids, no Bid may be withdrawn during the period specified for the holding of Bids as set forth in “Bids to remain subject to acceptance” below, except as provided in Pennsylvania Act 4 of 1974, P.L. 9, relating to withdrawal of a bid in the event of a mistake.
ARTICLE 16 – OPENING OF BIDS
16.01 Bids will be announced at the time and
place indicated in the Advertisement or Invitation to Bid and, unless obviously non-responsive, read aloud publicly. An abstract of the amounts of the base Bids and major alternates, if any, will be made available to Bidders after the opening of Bids.
ARTICLE 17 – BIDS TO REMAIN
SUBJECT TO ACCEPTANCE
17.01 Owner shall award the contract to the
lowest responsive and responsible Bidder or shall reject all Bids within sixty (60) days of the date of the Bid opening, and no Bidder may withdraw his Bid before the expiration of such sixty (60) day period; provided, however, if the award of contracts is delayed by required approval of another government agency, the sale of bonds closing on project loans or the award of a grant or grants, Owner shall reject all Bids or award the contract to the lowest responsive and responsible Bidder within one hundred twenty (120) days of the date of Bid opening, and in such event no Bidder may withdraw his Bid before the expiration of such one hundred twenty (120) day period.
Extensions of the date for the award of the contract may be made by the mutual written consent of Owner and the lowest responsive and responsible Bidder.
ARTICLE 18 – EVALUATION OF BIDS
AND AWARD OF CONTRACT
18.01 Owner reserves the right to reject any or
all Bids, including without limitation, nonconforming, nonresponsive, unbalanced, or conditional Bids. Owner further reserves the right to reject the Bid of any Bidder whom it finds, after reasonable inquiry and evaluation, to not be responsible. Owner may also reject the Bid of any Bidder if Owner believes that it would not be in the best interest of the Project to make an award to that Bidder. Owner also reserves the right to waive all informalities not involving price, time, or changes in the Work and to negotiate contract terms with the Successful Bidder. Discrepancies between the unit price and the corresponding extended total will be resolved in favor of the unit price, provided that the BIDDER agrees to the correction of the extended total and subsequent correction of the base bid price. Discrepancies between the indicated sum of any column of figures and the correct sum thereof will be resolved in favor of the correct sum.
Discrepancies between words and figures will be resolved in favor of the words.
18.02 More than one Bid for the same Work
from an individual or entity under the same or different names will not be considered. Reasonable grounds for believing that any Bidder has an interest in more than one Bid for the Work may be cause for disqualification of that Bidder and the rejection of all Bids in which that Bidder has an interest.
18.03 In evaluating Bids, Owner will consider
whether or not the Bids comply with the prescribed requirements, and such alternates, unit prices and other data, as may be requested in the Bid Form or prior to the Notice of Award.
18.04 In evaluating Bidders, Owner will
consider the qualifications of Bidders and may consider the qualifications and experience of Subcontractors, Suppliers, INSTRUCTIONS TO BIDDERS Section 002000 – Page 9 and other individuals or entities proposed for those portions of the Work for which the identity of Subcontractors, Suppliers, and other individuals or entities must be submitted as provided in the Supplementary Conditions.
18.05 Owner may conduct such investigations
as Owner deems necessary to establish the responsibility, qualifications, and financial ability of Bidders, proposed Subcontractors, Suppliers, individuals, or entities proposed for those portions of the Work in accordance with the Contract Documents.
18.06 If the contract is to be awarded, it will be
awarded to the lowest responsive and responsible Bidder or shall reject all Bids within sixty (60) days of the date of the Bid opening, and no Bidder may withdraw his Bid before the expiration of such sixty (60) day period; provided, however, if the award of contracts is delayed by required approval of another government agency, the sale of bonds closing on project loans or the award of a grant or grants, Owner shall reject all Bids or award the contract to the lowest responsive and responsible Bidder within one hundred twenty (120) days of the date of Bid opening, and in such event no Bidder may withdraw his Bid before the expiration of such one hundred twenty
(120) day period. Thirty (30) day extensions of the date for the award of the contract may be made by the mutual written consent of Owner and the lowest responsive and responsible Bidder.
ARTICLE 19 – CONTRACT SECURITY
AND INSURANCE
19.01 Article 5 of the General Conditions and
the Supplementary Conditions set forth Owner's requirements as to performance and payment Bonds. The Bidder, as required by 8 P.S. §193, shall submit its Bonds prior to the Owner issuing a Notice of Award. If the Bonds fail to become binding upon the award of the contract to Bidder, Owner may consider the bidder in default, in which case the
Bid security accompanying the Bid shall become the property of the Owner.
ARTICLE 20 – SIGNING OF AGREEMENT
20.01 When Owner issues a Notice of Award to
the Successful Bidder, it shall be accompanied by the required number of unsigned counterparts of the Agreement along with the other Contract Documents which are identified in the Agreement as attached thereto. Within 15 days thereafter, Successful Bidder shall sign and deliver the required number of counterparts of the Agreement and attached documents to Owner. Within thirty days thereafter, Owner shall deliver one fully signed counterpart to Successful Bidder with a complete set of the Drawings with appropriate identification.
ARTICLE 21 – RETAINAGE
21.01 Provisions concerning Contractor’s
rights to deposit securities in lieu of retainage are set forth in the Agreement.
ARTICLE 22 – NON-COLLUSION
AFFIDAVIT
22.01 All bidders must complete and execute
the enclosed Non-Collusion Affidavit.
This Affidavit is material to any contract awarded pursuant to this Project and is in accordance with Pennsylvania Antibid- Rigging Act, 73 P.S. S.S.1611 et seq.
The Affidavit should be executed by an officer or the person approved to sign the bid. In the case of joint ventures, all parties must execute separately. Failure to file an Affidavit in compliance with these instructions may result in disqualification of the Bid.
ARTICLE 23 – PENNBID
23.01 Bidder obtained bidding documents via
the PennBid program, are to satisfy the applicable fees of the program. Notice to Proceed may be delayed or retainage may be withheld until fee has been paid.
BID FORM Section 004100
BID FORM Section 004100 – Page 1
SECTION 004100 - BID FORM
ARTICLE 1 – BID RECIPIENT
1.01 This Bid is submitted to:
Owner: Twin County Joint Municipal Authority (TCJMA)
Project No.: 0326-609053.00
1.01 The undersigned Bidder proposes and agrees, if this Bid is accepted, to enter into an Agreement with
Owner in the form included in the Bidding Documents to perform all Work as specified or indicated in the Bidding Documents for the prices and within the times indicated in this Bid and in accordance with the other terms and conditions of the Bidding Documents.
ARTICLE 2 – BIDDER’S ACKNOWLEDGEMENTS
2.01 Bidder accepts all of the terms and conditions set forth in the Instructions to Bidders, which are incorporated herein by reference, including without limitation those terms and conditions regarding the disposition of Bid security. After the commencement of opening of Bids, no Bid may be withdrawn during the period specified for the holding of Bids as hereinafter set forth, except as provided in Pennsylvania Act 4 of 1974, P.L. 9, relating to withdrawal of a Bid in the event of a mistake. The Owner shall award the Contract to the lowest responsive and responsible Bidder, or shall reject all Bids within sixty (60) days of the date of Bid opening, and no Bidder may withdraw his Bid before the expiration of such sixty (60) day period; provided however, if the award of the Contract is delayed by required approval of another government agency, the sale of bonds, closing on project loans or the award of a grant or grants, the Owner shall reject all Bids or award the Contract to the lowest responsible Bidder within one hundred twenty (120) days of the date of Bid opening, and in such event no Bidder may withdraw his Bid before the expiration of such one hundred twenty
(120) day period. Extensions of the date for the award of the Contract may be made by the mutual written consent of the Owner and lowest responsible Bidder.
ARTICLE 3 – BIDDER’S REPRESENTATIONS
3.01 In submitting this Bid, Bidder represents that:
A. Bidder has examined and carefully studied the Bidding Documents, other related data identified in the Bidding Documents, and the following Addenda, receipt of which is hereby acknowledged:
Addendum No. Addendum Date
B. Bidder has visited the Site and become familiar with and is satisfied as to the general, local, and
Site conditions that may affect cost, progress, and performance of the Work.
C. Bidder is familiar with and is satisfied as to all Laws and Regulations that may affect cost, progress, and performance of the Work.
D. Bidder has carefully studied all: (1) reports of explorations and tests of subsurface conditions at or contiguous to the Site and all drawings of physical conditions relating to existing surface or
BID FORM Section 004100 – Page 2 subsurface structures at the Site (except Underground Facilities) that have been identified in SC-
4.02 as containing reliable "technical data," and (2) reports and drawings of Hazardous Environmental Conditions, if any, at the Site that have been identified in SC-4.06 as containing reliable "technical data."
E. Bidder has considered the information known to Bidder; information commonly known to contractors doing business in the locality of the Site; information and observations obtained from visits to the Site; the Bidding Documents; and the Site-related reports and drawings identified in the Bidding Documents, with respect to the effect of such information, observations, and documents on (1) the cost, progress, and performance of the Work; (2) the means, methods, techniques, sequences, and procedures of construction to be employed by Bidder, including applying the specific means, methods, techniques, sequences, and procedures of construction expressly required by the Bidding Documents; and (3) Bidder’s safety precautions and programs.
F. Based on the information and observations referred to in Paragraph 3.01.E above, Bidder does not consider that further examinations, investigations, explorations, tests, studies, or data are necessary for the determination of this Bid for performance of the Work at the price(s) bid and within the times required, and in accordance with the other terms and conditions of the Bidding Documents.
G. Bidder is aware of the general nature of work to be performed by Owner and others at the Site that relates to the Work as indicated in the Bidding Documents.
H. Bidder has given Engineer written notice of all conflicts, errors, ambiguities, or discrepancies that Bidder has discovered in the Bidding Documents, and the written resolution thereof by Engineer is acceptable to Bidder.
I. The Bidding Documents are generally sufficient to indicate and convey understanding of all terms and conditions for the performance of the Work for which this Bid is submitted.
ARTICLE 4 – BIDDER’S CERTIFICATION
4.01 Bidder certifies that:
A. This Bid is genuine and not made in the interest of or on behalf of any undisclosed individual or entity and is not submitted in conformity with any collusive agreement or rules of any group, association, organization, or corporation;
B. Bidder has not directly or indirectly induced or solicited any other Bidder to submit a false or sham Bid;
C. Bidder has not solicited or induced any individual or entity to refrain from bidding; and
D. Bidder has not engaged in corrupt, fraudulent, collusive, or coercive practices in competing for the Contract. For the purposes of this Paragraph 4.01.D:
1. “corrupt practice” means the offering, giving, receiving, or soliciting of any thing of value likely to influence the action of a public official in the bidding process;
2. “fraudulent practice” means an intentional misrepresentation of facts made (a) to influence the bidding process to the detriment of Owner, (b) to establish bid prices at artificial non-competitive levels, or (c) to deprive Owner of the benefits of free and open competition;
BID FORM Section 004100 – Page 3
3. “collusive practice” means a scheme or arrangement between two or more Bidders, with or without the knowledge of Owner, a purpose of which is to establish bid prices at artificial, non-competitive levels; and
4. “coercive practice” means harming or threatening to harm, directly or indirectly, persons or their property to influence their participation in the bidding process or affect the execution of the Contract.
ARTICLE 5 – BASIS OF BID
5.01 Bidder will complete the Work in accordance with the Contract Documents for the following price(s) as included in Exhibit A.
5.02 Unit Prices have been computed in accordance with Paragraph 11.03.B of the General Conditions.
5.03 Bidder acknowledges that estimated quantities are not guaranteed, and are solely for the purpose of comparison of Bids, and final payment for all unit price Bid items will be based on actual quantities, determined as provided in the Contract Documents
5.04 All specifications sections are considered incidental to ALL the unit price items unless otherwise noted.
ARTICLE 6 – TIME OF COMPLETION
6.01 Bidder agrees that the Work will be substantially complete and will be completed and ready for final payment on or before the dates or within the number of calendar days indicated in the Agreement.
6.02 Bidder accepts the provisions of the Agreement as to liquidated damages.
6.03 The terms used in this Bid which are defined in the General Conditions of the construction contract included as part of the Contract Documents have the meaning assigned to them in the General Conditions
6.04 Bidder understands that the OWNER reserves the right to reject any or all bids, reject any or all items, and further reserves the right to delete any item or parts of items
6.05 Bidder understands that the OWNER shall award the contract on the basis of the lowest total sum bid submitted, which total sum bid shall include the total of the base bid plus any alternates selected by the OWNER.
BID FORM Section 004100 – Page 4
ARTICLE 7 – ATTACHMENTS TO THIS BID
7.01 The following documents are submitted with and made a condition of this Bid:
A. Required Bid Security;
B. Bid Form (Section 004100);
C. Electronic PennBid Bid Table Form;
D. Agreement of Surety Form;
E. PSATS CDL Program Contractor’s Statement of Compliance Form;
F. Non-Collusion Affidavit Form;
G. Nondiscrimination/Sexual Harassment Clause;
H. Certification of Bidder Regarding Equal Employment Opportunity;
I. Bidder Certification of Prequalification Classification and Work Capacity Form
J. Certification of Non-Segregated Facilities
K. Compliance Illegal Alien Labor Act;
L. Compliance with The State Contractor Responsibility Program;
M. Contract Provision Right to Know Law;
N. Contractor Integrity Provision;
O. Provisions Concerning the Americans With Disabilities Act;
P. Public Works Employment Verification Form;
Q. Stop-Call Before You Dig;
R. Evidence of authority to do business in the state of the Project; or a written covenant to obtain such license within the time for acceptance of Bids; and
S. Required Bidder Qualification Statement with Supporting Data.
BID FORM Section 004100 – Page 5
ARTICLE 8 – DEFINED TERMS
8.01 The terms used in this Bid with initial capital letters have the meanings stated in the Instructions to Bidders, the General Conditions, and the Supplementary Conditions.
BID SUBMITTAL
9.01 This Bid is submitted by:
If Bidder is:
An Individual
Name (typed or printed):
By:
(Individual’s signature)
Doing business as:
A Partnership
Partnership Name:
By:
(Signature of general partner -- attach evidence of authority to sign)
Name (typed or printed):
A Corporation
Corporation Name:
(SEAL)
State of Incorporation:
Type (General Business, Professional, Service, Limited Liability):_______
By:
(Signature -- attach evidence of authority to sign)
Name (typed or printed):
Title:
(CORPORATE SEAL)
Attest
Date of Qualification to do business in PA is ____/____/____.
A Joint Venture
BID FORM Section 004100 – Page 6
Name of Joint Venture:
First Joint Venturer Name:
(SEAL)
By:
(Signature of first joint venture partner -- attach evidence of authority to sign)
Name (typed or printed):
Title:
Second Joint Venturer Name: (SEAL)
By:
(Signature of second joint venture partner -- attach evidence of authority to sign)
Name (typed or printed):
Title:
(Each joint venturer must sign. The manner of signing for each individual, partnership, and corporation that is a party to the joint venture should be in the manner indicated above.)
Bidder's Business Address
Phone No. _____________________________________ Fax No.
E-mail ______________________________ _______
SUBMITTED on , 20____.
State Contractor License No. . [If applicable]
Contractor Federal ID No.
Contractor UEI No.
Exhibit A PLC and HMI Upgrades Twin County Joint Municipal Authority Wastewater Treatment Plant
Project No. 0326-609053.00
Bid Form
Item No. Title Unit Price in Words - Material Supply Unit Price ($) Total Amount ($)
A 1.00 LS Mobilization/Demobilization
B 1.00 LS PLC and HMI Upgrades
BASE BID - FOR INFORMATIONAL PURPOSES ONLY
COMPLETE BID ELECTRONICALLY ON PENNBID ELECTRONIC SYSTEM
Quantity
FORM OF AGREEMENT Section 005200
FORM OF AGREEMENT Section 005200 – Page 1
FORM OF AGREEMENT
BETWEEN OWNER AND CONTRACTOR
THIS AGREEMENT is by and between
Twin County Joint Municipal Authority (TCJMA) (“Owner”) and
(“Contractor”).
Owner and Contractor hereby agree as follows:
ARTICLE 1 – WORK (CONTRACT A)
1.01 Contractor shall complete all Work as specified or indicated in the Contract Documents.
The Work is generally described as follows:
Project: TCJMA – Wastewater Treatment Plant PLC and HMI Upgrade Project
Contract Number: 0326-609053.00
ARTICLE 2 – THE PROJECT
2.01 The Project for which the Work under the Contract Documents may be the whole or only a part is generally described as follows:
The PLC and HMI Upgrade Project Project is located at 309 Mahanoy Street in the Nuremburg, Schuylkill County, Pennsylvania 18241. The project includes the migration of legacy programmable logic controller (PLC) and human-machine interface (HMI) systems to modern hardware and software platforms. The upgrade will replace the existing SLC PLC with a programmable automation controller and recreate the existing PanelView HMI application. Refer to Contract Documents for specifics.
ARTICLE 3 – ENGINEER
3.01 The Project is being administered by Alfred Benesch & Company (Engineer), which is to act as Owner’s representative, assume all duties and responsibilities, and have the rights
FORM OF AGREEMENT Section 005200 – Page 2 and authority assigned to Engineer in the Contract Documents in connection with the completion of the Work in accordance with the Contract Documents.
ARTICLE 4 – CONTRACT TIMES
4.01 Time of the Essence
A. All time limits for Milestones, if any, Substantial Completion, and completion and readiness for final payment as stated in the Contract Documents are of the essence of the Contract.
4.02 Dates for Substantial Completion and Final Payment
A. The Work will be substantially completed within 180 days after the date when the Contract times commences to run as approved in Paragraph 2.03 of the General Conditions and completed and ready for final payment in accordance with Paragraph
14.07 of the General Conditions within 210 days after the date when the contract time commence to run.
4.03 Liquidated Damages
A. Contractor and Owner recognize that time is of the essence as stated in Paragraph 4.01 above and that Owner will suffer financial loss if the Work is not completed within the times specified in Paragraph 4.02 above, plus any extensions thereof allowed in accordance with Article 12 of the General Conditions. The parties also recognize the delays, expense, and difficulties involved in proving in a legal or arbitration proceeding the actual loss suffered by Owner if the Work is not completed on time. Accordingly, instead of requiring any such proof, Owner and Contractor agree that as liquidated damages for delay (but not as a penalty), Contractor shall pay Owner $500 for each day that expires after the time specified in Paragraph 4.02 above for Substantial Completion until the Work is substantially complete. After Substantial Completion, if Contractor shall neglect, refuse, or fail to complete the remaining Work within the Contract Time or any proper extension thereof granted by Owner, Contractor shall pay Owner $250 for each day that expires after the time specified in Paragraph 4.02 above for completion and readiness for final payment until the Work is completed and ready for final payment.
ARTICLE 5 – CONTRACT PRICE
5.01 Owner shall pay Contractor for completion of the Work in accordance with the Contract Documents an amount in current funds equal to the sum of the amounts determined pursuant to Paragraphs below:
A. For all Unit Price Work, an amount equal to the sum of the established unit price for each separately identified item of Unit Price Work times the actual quantity of that item in Accordance with Attached Unit price Schedule, See Exhibit A.
Total of all Bid Prices (Unit Price Work)
FORM OF AGREEMENT Section 005200 – Page 3
Total of all Base Price (words):
The Bid prices for Unit Price Work set forth as of the Effective Date of the Agreement are based on estimated quantities. As provided in Paragraph 11.03 of the General Conditions, estimated quantities are not guaranteed, and determinations of actual quantities and classifications are to be made by Engineer as provided in Paragraph 9.07 of the General Conditions.
B. For all Work, at the prices stated in Contractor’s Bid,…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .